BAILII is celebrating 24 years of free online access to the law! Would you
consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it
will have a significant impact on BAILII's ability to continue providing free
access to the law.
Thank you very much for your support!
[New search]
[Printable RTF version]
[Buy ICLR report: [1999] 1 WLR 1646]
[Help]
IN
THE SUPREME COURT OF JUDICATURE
CHANF 98/1130/3
COURT
OF APPEAL (CIVIL DIVISION)
ON
APPEAL FROM THE HIGH COURT OF JUSTICE
CHANCERY
DIVISION
(Mr.
Justice Rattee)
Royal
Courts of Justice
Strand
London
WC2A 2LL
Thursday,
25th February 1999
B
e f o r e :
LORD
JUSTICE HIRST
LORD
JUSTICE MUMMERY
LORD
JUSTICE BUXTON
-
- - - - - - -
MATRA
COMMUNICATION SAS
Appellant
-
v -
HOME
OFFICE
Respondent
-
- - - - - - -
(Handed
down transcript of
Smith
Bernal Reporting Limited
180
Fleet Street, London EC4A 2HD
Tel:
0171 421 4040 Fax: 404 1424
Official
Shorthand Writers to the Court)
-
- - - - - - -
MR.
D. VAUGHAN Q.C. and MR. M. BREALEY
(instructed by Messrs Nabarro Nathanson, London, W1) appeared on behalf of the
Appellant.
MR.
C. FLINT Q.C. and MR. A. LEWIS
(instructed by The Treasury Solicitor) appeared on behalf of the Respondent.
-
- - - - - - -
J
U D G M E N T
(As
approved by the Court)
Crown
Copyright
BUXTON
LJ:
Introduction
This
appeal from a judgment of Rattee J delivered on 31 July 1998 turns on the
compatibility with Community law of the three month time-limit for bringing
claims that is imposed by regulation 32(4)(b) of the Public Services Contracts
Regulations 1993 [the Regulations]. Other issues were considered by the judge
and were ventilated before us, but as will become apparent the issue just set
out is the main point of substance in the appeal.
The
facts
The
plaintiff, Matra Communication SAS [Matra], is a French company that
specialises in the design of the type of mobile radio telephone systems that
are used by limited groups on a secure basis. The system that it offers for
this purpose is called TETRAPOL: the nature of which it is fortunately not
necessary for the purposes of this judgment for me to explicate further. The
main rival system, offered by a consortium called Quadrant, of which BT plc is
a member, is based on technology called TETRA.
In
July 1995 the Home Office issued a consultation document that set out what
were likely to be the requirements for a new secure radio system for the police
service; but envisaging that the selected system was likely to be attractive
also to other public service users, such as the fire service. This project,
called in this case a project for a national PSRCS, was obviously potentially
of the greatest interest to providers such as Matra since its likely value as
stated in the project notice referred to below would be £1.5 billion over
15 years. Matra however learned that Home Office policy was to require TETRA
systems for the project. That excluded Matra, as Matra pointed out to the Home
Office in a letter dated 29 September 1995. That requirement on the part of
the Home Office was confirmed in the notice of the PSRCS project published in
accordance with Community requirements in the Official Journal on 23 January
1996. That set out the terms of the project and invited expressions of
interest from contractors who were willing to take part in more detailed
project definition studies. The notice said specifically that
Subject
to its adoption by the European Union, Tetra will be the technical standard
specified for the mobile radio service.
After
the publication of that notice Matra sought without success to persuade the
Home Office to change its announced policy. In a letter to the Home Office
dated 30 May 1996 Matra acknowledged that, whatever the position about the
adoption of TETRA as a European Standard, that system had been adopted by the
Home Office, and therefore Matra could not pursue the project further. On 9
August 1996 the Home Office issued a formal invitation to tender, which
specified TETRA. Some considerable time later, in June 1997, Matra reopened
the correspondence, and sought the extension of the project to include
TETRAPOL; but the Home Office made clear, for instance in a letter of 18 July
1997, that they would not interrupt the procurement process. Matra then sent a
solicitors' letter dated 12 September 1997 threatening proceedings. The
contract was awarded, to Quadrant, on 10 October 1997. Matra issued these
proceedings on 13 October 1997.
The
action
Matra
complains that the specification of TETRA prevents it, in the context of the
PSRCS project, from supplying goods and services within the United Kingdom, and
thus entails a breach of the directly effective provisions of Articles 30 and
59 of the EU Treaty. Further, Article 3.2 of Council Directive 92/50/EEC,
relating to the coordination of procedures for the award of public service
contracts, provides that contracting authorities shall ensure that there is no
discrimination between different service providers. Matra allege that the
effect of specifying TETRA is to breach that requirement.
The
Home Office denies those claims, fundamentally on the ground that European
procurement rules required them to specify TETRA, as being the approved
standard. That very important question is not in issue in this appeal. The
Home Office however successfully contended before the Judge that the action
should be, in effect, struck out, because it had not been brought within the
three month time-limit that the Home Office argued to be applicable to this
claim. In order to understand that point it is necessary first to set out the
legislative provisions relevant to that issue.
The
time-limits
This
matter is addressed in Community legislation in Council Directive 89/665/EEC on
the coordination of laws relating to the application of review procedures to
the award of public supply contracts [Directive 89/665]. In its recitals the
Directive 89/665 observes that the extant Directives on public procurement "do
not contain any specific provisions ensuring their effective application" (a
matter to which I shall have to return), and then says, inter alia
Whereas
the existing arrangements at both national and Community levels for ensuring
their application are not always adequate to ensure compliance with the
relevant Community provisions particularly at a stage when infringements can be
corrected.
Whereas
the opening-up of public procurement to Community competition necessitates a
substantial increase in the guarantees of transparency and non-discrimination;
whereas, for it to have tangible effects, effective and rapid remedies must be
available in the case of infringements of Community law in the field of public
procurement or national rules implementing that law;
Whereas
it is necessary to ensure that adequate procedures exist in all the Member
States to permit the setting aside of decisions taken unlawfully and
compensation of persons harmed by an infringement.
The
relevant legislative provisions then follow:
Article
1
1.
The Member States shall take the measures necessary to ensure that, as regards
contract award procedures falling within the scope of Directives 71/305/EEC and
77/62/EEC, decisions taken by the contracting authorities may be reviewed
effectively and, in particular, as rapidly as possible in accordance with the
conditions set out in the following Articles.... on the grounds that such
decisions have infringed Community law in the field of public procurement or
national rules implementing that law...
3.
The Member states shall ensure that the review procedures are available, under
detailed rules which the Member States may establish, at least to any person
having or having had an interest in obtaining a particular public supply or
public works contract and who has been or risks being harmed by an alleged
infringement. In particular, the Member States may require that the person
seeking the review must have previously notified the contracting authority of
the alleged infringement and of his intention to seek review.
Article
2
1.
The Member States shall ensure that the measures taken concerning the review
procedures specified in Article 1 include provision for the powers to:-
(a)
take, at the earliest opportunity and by way of interlocutory procedures,
interim measures with the aim of correcting the alleged infringement or
preventing further damage to the interests concerned, including measures to
suspend or to ensure the suspension of the procedure for the award of a public
contract or the implementation of any decision taken by the contracting
authority;
(b)
either set aside or ensure the setting aside of decisions taken unlawfully,
including the removal of discriminatory technical, economic or financial
specifications in the invitation to tender, the contract documents or in any
other document relating to contract award procedure;
(c)
award damages to persons harmed by an infringement.
It
was agreed before us that the provisions of Article 2 had been properly
transposed into regulation 32 of the 1993 Regulations. The relevant parts of
regulation 32 are as follows:
(3)
Proceedings under this regulation shall be brought in England and Wales and in
Northern Ireland in the High Court and, in Scotland, before the Court of Session.
(4)
Proceedings under this regulation may not be brought unless-
(a) the
services provider bringing the proceedings has informed the contracting
authority of the breach or apprehended breach of the duty owed to him pursuant
to paragraph (1) above by the contracting authority and of his intention to
bring proceedings under this regulation in respect of it; and
(b) they
are brought promptly and in any event within 3 months from the date when
grounds for the bringing of the proceedings first arose unless the Court
considers that there is good reason for extending the period within which
proceedings may be brought.
(5)
Subject to paragraph (6) below, but otherwise without prejudice to any other
powers of the Court, in proceedings brought under this regulation the Court may-
(a) by
interim order suspend the procedure leading to the award of the contract in
relation to which the breach of the duty owed pursuant to paragraph (1) above
is alleged, or suspend the implementation of any decision or action taken by
the contracting authority in the course of following such procedure; and
(b) if
satisfied that a decision or action taken by a contracting authority was in
breach of the duty owed pursuant to paragraph (1) above-
(i) order
the setting aside of the decision or action or order the contracting authority
to amend any documents; or
(ii) award
damages to a services provider who has suffered loss or damage as a consequence
of the breach, or
(iii)
do both of those things.
The
claims made by Matra
The
substantive claims made by Matra in its statement of claim are:
1.
A Declaration that the Defendant is in breach of Article 30 and/or Article 59
and/or Article 3(2) of Directive 92/50 and/or Regulation 8 of [the Regulations]
by excluding from consideration TETRAPOL based systems in the evaluation of the
Public Safety Radio communications Project as advertised in the Contract Notice
published in the Official Journal of the European communities on 23 January 1996
2.
Damages
Particulars
of the loss and damage alleged were given in paragraphs 29 and 30 of the
statement of claim as follows:
29
(ii) Matra had a real chance of being awarded the contract for the provision of
the PSRCS due to lower cost and due to the fact that a TETRAPOL based system
was better suited to the provision of PSRCS.
(iii)
Matra claims as damages the profit that it would have made on the PSRCS
contract and consequential loss due to damage to its reputation.
30.
Pending further discovery, in particular discovery of the terms and conditions
of the contract to Quadrant, Matra estimates its claim at £100,000,000 in
respect of equipment and subsequent support in relation to the provision of
spares and materials.
It
is important at this stage to note that the damages claimed are not what Mr
Vaughan described before the Judge, and which for purposes of identification
only I will continue to refer to, as
Norbrook
damages; that name being taken from Case C-127/95
Norbrook
Laboratories v Ministry of Agriculture
,
2 April 1998. In Case C-127/95 the European Court of Justice restated the
conditions imposed by Community law on the recovery of damages for a breach of
Community law by a member state. The Court of Justice said, at paragraphs
106-107 of its ruling, that
It
must be remembered, first, that as the Court has held repeatedly, the principle
of State liability for loss and damage caused to individuals as a result of
breaches of Community law for which the State can be held responsible is
inherent in the system of the Treaty (Joined Cases C-6/90 and C-9/90 Francovich
and Others v. Italian Republic
[1991] ECR I-5357, paragraph 35; Joined Cases
C-46/93 and C-48/93 The Queen v. H.M. Treasury, ex parte British
Telecommunications [1996] I-1631, paragraph 38; Case C-5/94 The Queen v. MAFF,
ex parte Hedley Lomas
[1996] ECR I-2553, paragraph 24; and Joined Cases
C-178/94, C-179/94, C-188/94, C-189/94 and C-190/94 Dillenkofer and others v.
Germany
[1996] ECR I-4845, paragraph 20).
It
is clear from the above case-law that three conditions must be satisfied for a
Member State to be required to compensate for damage thus caused: the rule of
law infringed must have been intended to confer rights on individuals; the
breach must be sufficiently serious; and there must be a direct causal link
between the breach of the obligation resting on the State and the damage
sustained by the injured parties (Brasserie du Pecheur and Factortame paragraph
51; British Telecommunications, paragraph 39; Hedley Lomas, paragraph 25; and
Dillenkofer and others, paragraph 24, all cited above).
It
is clear that the damages claim in our case is not a
Norbrook
claim not only because Mr Vaughan so said; but also because no attempt is made
in the statement of claim to plead, much less to establish, that the breach on
which the claim is based was "sufficiently serious" in
Norbrook
terms.
The
issue
s
The
case proceeded below on a series of preliminary points relating to whether the
claim complied with regulation 32(4)(b) of the Regulations, which it will be
seen is in effect a limitation provision. Although there was no formal claim
to strike the action out, the effect of the Judge's findings was that the
action could not proceed further, since he held that it had not been brought
within the time limited by regulation 32(4)(b), and that no grounds existed
for extending that time.
Rather
than simply set out the preliminary points it will be more convenient to list
the issues that arise on the appeal, not least because they fall conveniently
into, and were argued before us in, a somewhat different order from that
adopted before the Judge. The issues in the appeal are:
I.
Was this action brought promptly and in any event within three months from the
date when grounds for the bringing of the action first arose, as required by
regulation 32(4)(b)?
II
Is that requirement of regulation 32(4)(b) in conformity with Community law?
III
If yes, was the Judge correct in refusing to extend the time limited by
regulation 32(4)(b)?
I
deal with these questions in turn. They are however all affected by a general
issue as to the effect and status of Directive 89/665, transposed as it is into
the Regulations. I deal with that matter first.
Directive
89/665
Both
parties recognised that their respective cases turned on a proper understanding
of the juristic nature and effect of Directive 89/665. Matra contended in
particular that the requirement of Article 2.1(c) that member states should put
in place procedures for the award of damages to persons harmed by an
infringement of, inter alia, Directive 92/50 was a separate and free-standing
provision, not necessarily linked to or dependent on the requirements in
Articles 2.1 (a) and (b) for procedures to correct infringements or set aside
decisions. The importance of this contention was that Mr Vaughan argued, inter
alia, that the damages claim made by Matra should be treated as a claim
entirely separate from any claim that might have been made, but in the event
was not, under regulations 32(5) (a) or (b)(i) of the Regulations. Thus, for
instance, the appropriate event from which time started to run under the
Regulations in respect of a damages claim might be different from the
appropriate event relevant to a claim to set aside or have altered a contract
procedure. Each separate right of recourse had to be evaluated according to
the rules of domestic law relevant to that type of recourse. By contrast, Mr
Flint QC for the Home Office in effect argued that Directive 89/665 provided a
complete and separate statement of the ability of the persons protected by it
to assert their rights, and of the limitations on that ability. The recourse
provided by the Regulations under the Directive had to be looked at as a whole.
Some
of the more detailed implications of this dispute will have to be taken up in
addressing the individual issues in the appeal. In more general terms,
however, I am of opinion that:
1.
The "damages" referred to in Article 2.1(c) are not
Norbrook
damages. As already noted that is conceded in this case, but the point needs
to be underlined. At the date of Directive 89/665, not only did the Directives
to which it was subsidiary not contain provisions to ensure their effective
application in the member states, as the recitals to Directive 89/665
acknowledged in terms, but also it was uncertain whether, in at least a number
of member states, there could be any, or at least any general, recourse to
damages as a remedy for infringement of directly effective Community rights:
for example, see the position in 1989 in the United Kingdom as set out in the
judgments in this court in
Bourgoin
SA v Ministry of Agriculture
[1986] 1 QB 716. The right to damages that the member states are obliged by
Article 2.1(c) to create must therefore be, in Community terms, sui generis,
and must find its origins and limits in the specific provisions of Directive
89/665 rather than in more general principles of Community law.
2.
That Directive 89/665 creates its own limited code of remedies is underlined
by the fact that it only applies, because the underlying Directive 92/50 only
applies, to contracts of a value in excess of ECU 200,000: Directive 92/50,
Article 7.1. If the remedies envisaged by Directive 89/665 were general
remedies already available in member states through the requirements of
Community law, rather than being remedies imposed on the member states by
Directive 89/665 itself, not only would there have been no need for Directive
89/665 at all, but also the exclusion from contracts of a certain size of the
Directive 89/665 remedies would equally beat the air.
3.
Once the obligation of the member state to provide that remedy in damages has
been discharged by the United Kingdom by the terms of regulation 32(5)(b)(ii)
those damages provided by domestic law remain damages on the basis envisaged by
Directive 89/665; but regulation 32(5)(b)(ii) nonetheless thereby creates a
private law, non-discretionary, remedy, because within the national legal order
any remedy in damages necessarily has those qualities.
4.
The obligation under Article 2.1(c) arises in the context of a scheme of
remedies that are intended, as the recitals to Directive 89/665 state, to be
effective and rapid.
5.
The "review" required by Article 1, and elsewhere in Directive 89/665, is the
whole scheme of remedies that the member state is required to make available.
That is of some importance in connexion with point 4 above, because under
Article 2.1 "the review procedures specified in Article 1" include the power to
award damages under Article 2.1(c); it is therefore that whole range of
remedies, including damages, that are required by Article 1 to be provided
"effectively and, in particular, as rapidly as possible".
I
revert to some of these considerations when addressing the particular issues in
this case, to which I now turn.
I.
Was this action brought promptly and in any event within three months from the
date when grounds for the bringing of the action first arose, as required by
regulation 32(4)(b)?
As
a matter of logic, issue II is the first issue to be considered, because if
regulation 32(4)(b) is not in conformity with Community law it must be
disapplied or ignored, and thus it does not matter whether or not the action
was brought within the time limited by it. However, certain of the matters
addressed under issue II overlap with issue I; and the analysis of the
requirements of regulation 32(4)(b) forced on us by issue I illuminates the
terms and nature of that regulation in a manner that is of value when
considering issue II.
The
Judge answered this question in the negative, and was plainly right to do so.
The issue is when "grounds for the bringing of the proceedings" first arose.
By regulation 32(2), breaches of duty under the Regulations are actionable by
any services provider (which expression includes Matra) who in consequence of
the breach "suffers or risks suffering" loss or damage. By its pleading, and
in particular by the terms of the declaration that it seeks, Matra alleges that
the breach was committed by the terms of the Official Journal notice of 23
January 1996. Even if, as Matra now contends, there was some uncertainty at
that stage as to whether TETRA was to be adopted as a European Union standard,
it was quite clear to Matra by June 1996 that it had been excluded from the
PSRCS project. Matra so stated in its letter of 30 May 1996, a letter that
Matra's solicitors subsequently adopted in their own letter before action of 12
September 1997. On any sensible view of the facts, therefore, it was plain to
Matra some fifteen months before they issued their writ that they were
suffering, or at least risked suffering, damage by reason of the configuration
of the PSRCS project.
Mr
Vaughan sought to meet this point by arguing that the damages claim had to be
viewed separately from the other relief provided by the Regulations. While
Matra might well have been under an obligation to seek an injunction, or public
law relief, in January or at least in May 1996, a damages claim did not arise
and therefore could not be pleaded until it was clear that damages were going
to be suffered. That was not clear until the contract was actually awarded, to
someone else. Matra had acted very promptly on that latter event.
There
are a number of serious objections to that argument. First, it is not correct
as a matter of fact. Matra's claim is, as stated in paragraph 29(ii) of its
statement of claim, for loss of the chance to obtain the PSRCS contract. It
lost that chance, and therefore suffered damage, whether or not the contract
was awarded to anyone else. Quantification of that loss would of course be
difficult, and be affected by whether in the event the contract was awarded at
all, and the extent to which Matra's absence from the field of contenders
contributed to any failure to make the award. But those are indeed issues of
quantification, not of liability. To that extent, therefore, Matra's argument
confuses liability for loss or damage with the assessment of damages. The
latter task may well not yet be possible when the action is brought, or when
liability first arises; but that does not affect the fact that in this case
liability arose when Matra in its pleading said it did.
Second,
however, and more fundamentally, Matra's argument is inconsistent both with the
normal English practice and with the scheme of the Directive 89/665. As to
the former, questions of limitation are determined, as regulation 32(4) says,
according to when the
proceedings
are brought; it is unheard of to have a single limitation period which however
commences at different dates according to the nature of the
remedy
sought. As to Directive 89/665, I have pointed out above that the whole range
of remedies envisaged by Directive 89/665 is required to be provided rapidly,
and no distinction is made in that respect between damages and other remedies.
Although the present issue is one of construction of the Regulations, the
approach of the Regulations in submitting all remedies to the same rules is
consistent with the approach of the Directive.
II
Is that requirement of regulation 32(4)(b) in conformity with Community law?
This
is the central issue in the appeal. The Judge answered this question in the
affirmative. My reasons for holding that he was right to do so differ in some
details from the grounds adopted by him, but the arguments appear to have been
put to us in some respects in terms that had not been ventilated before the
Judge.
The
Community jurisprudence
As
already indicated, it is accepted that the Regulations correctly transpose the
substance of Directive 89/665. The latter, however, while generally supporting
promptitude, neither lays down nor specifically permits any particular period
of limitation. The question is therefore whether the limitation period
provided for the remedies under the Regulations causes the whole scheme of
those remedies, including their limitation period, to breach the United
Kingdom's obligation to provide remedies for breaches of Community provisions
that comply with the requirements of Community jurisprudence. In addressing
that question the Judge rightly referred to the principle adopted by the Court
of Justice in Cases C6/90 and C9/90 [1991] ECR 5357,
Francovich,
at paragraph 43 of that report, and expanded on in Case C261/95
[1997] ECR I-4025,
Palmisani,
at paragraph 27 of the judgment of the Court of Justice:
it
follows from consistent case-law since Francovich that...it is on the basis of
the rules of national law on liability that the State must make reparation for
the consequences of the loss or damage caused; further, the conditions, in
particular time-limits, for reparation of loss or damage laid down by national
law must not be less favourable than those relating to similar domestic claims
(principle of equivalence) and must not be so framed as to make it virtually
impossible or excessively difficult to obtain reparation (principle of
effectiveness).
It
was accepted before us that the domestic remedies, including the limitation
period, must be scrutinised according to those two tests. I deal later with
the principle of effectiveness. I turn first to the application of the
principle of equivalence.
The
principle of equivalence
The
operation and effect of this principle is of crucial importance in this case.
In
Palmisani
the complaint was of delay in transposing a Directive on the protection of
employees on the insolvency of their employers. The law of the member state in
question required an action for reparation for loss or damage suffered thereby
to be brought within one year of the Directive's eventual transposition. As
"similar domestic claims" under the principle of equivalence the parties
referred to actions for reparation for non-contractual loss under Article 2043
of the Civil Code (a five-year limitation period); and to claims for the actual
benefits provided on the basis of the Directive (a one-year limitation period).
As to the latter, the Court of Justice recorded,
[1997] ECR I-4025[34], that
the objective of providing employees with specific benefits was different from
the objective of compensating them for depriving them of those benefits by
failure to transpose the Directive that related to them. As to the comparison
with general non-contractual liability, the Court of Justice said, at paragraph
38 of the report,
As
far as the ordinary system of non-contractual liability is concerned it must be
pointed out that, unlike the procedures [for payment of benefits] that system
is on the whole, in terms of its objective, similar to that introduced [to
compensate for the belated transposition] inasmuch as it is intended to
guarantee reparation of the loss or damage sustained as a result of the conduct
of the perpetrator. However, in order to establish the comparability of the
two systems in question, the essential characteristics of the domestic system
of reference must be examined. In that regard the Court does not have all the
information necessary to determine more specifically whether an action for
damages brought by an individual pursuant to Article 2043 of the Italian Civil
Code is capable of being directed against public authorities on the ground that
they have failed to act or have committed an unlawful act for which they can be
held responsible in the exercise of their powers. It falls therefore to the
national court to undertake that examination.
The
Court of Justice continued, at paragraph 39,
If
the ordinary Italian system of non-contractual liability were to prove
incapable of serving as a basis for an action against public authorities for
unlawful conduct for which they can be held responsible in the exercise of
their powers and the national court were unable to undertake any other relevant
comparison between the time limit at issue and the conditions relating to
similar claims of a domestic nature, the conclusion would have to be drawn, in
view of the foregoing, that Community law does not preclude a Member State from
requiring any action for reparation of the loss or damage sustained as a result
of the belated transposition of the Directive to be brought within a limitation
period of one year from the date of its transposition into national law.
Two
principles can be drawn from this part of the judgment. First, the principle
of "equivalence" really does mean what it says. The domestic court, in
applying the principle, must look not merely for a domestic action that is
similar to the claim asserting Community rights, but for one that is in
juristic structure very close to the Community claim. It does that, in the
words of the Court of Justice in Case C-326/96,
Levez,
[1999] IRLR 36 at paragraph 43, by considering "the purpose and the essential
characteristics of allegedly similar domestic actions". That approach was
demonstrated in
Palmisani
by the rejection of a claim for specific payments, as opposed to compensation,
as a relevant comparison. It was also demonstrated by the need to find in the
domestic law not merely a cause of action for reparation, but one for
reparation for conduct of a public authority in the exercise of its powers.
The narrowness of that comparison was underlined by Mr Advocate General Cosmas
in paragraphs 38 and 39 of his opinion:
The
claim in this case is for reparation on the ground that Directive 80/987 was
not transposed into Italian law within the prescribed period, and as a result
the persons concerned could not obtain the benefit of the guarantee provided
for by the Directive at the proper time. Only the national court is in a
position to know what similar claim may exist under the Italian legal system.
If,
however, it were necessary to provide the national court with some element of
comparison, it would in my opinion be the non-contractual liability of the
State arising from belated adoption of a regulatory act provided for by an
enabling statute.
Second,
as paragraph 39 of the judgment of the Court of Justice makes clear, if there
is no action in the domestic system that fulfils the requirements set out
above, then the national system is at liberty (subject always to the further
principle of effectiveness) to set whatever limitation period seems best to it
for the claim in relation to Community rights.
Mr
Vaughan accepted this latter principle, and that the task of the court was to
seek to identify a "comparator" in domestic procedure that met the
Palmisani
criteria. If there was such a valid comparator, the Community claimant was
entitled to the limitation period that applied to that comparator. If there
was no such comparator, the limitation period provided by regulation 32(4)(b)
was not, on this ground at least, open to objection in Community law. I will
therefore survey in turn the various comparators put before us and before the
Judge.
Action
for breach of statutory dut
y
Mr
Vaughan said, rightly, that the action for damages provided by the Regulations
was, in its domestic characterisation, one for breach of statutory duty. It
should therefore be subject to the same limitation period as domestic actions
for breach of statutory duty, which was (usually) six years. This argument was
plainly wrong. As Mr Flint put it, "breach of statutory duty" is simply too
wide a category to meet the
Palmisani
requirements of equivalence. If the approach here suggested were correct, then
the Court of Justice would in that case have accepted claims under Article 2043
of the Italian Civil Code as an appropriate comparator without further
investigation.
Action
for breach of other directly effective Community rights
This
was one of the comparators relied on before the Judge. He correctly held that
the comparison was wrong as a matter of Community law, because the comparator
must be concerned with similar rights derived wholly from domestic law: per the
Advocate-General in
Levez
at paragraphs 26-28 of his opinion. Further, and in any event, the claim in
respect of other directly effective Community rights will be for
Norbrook
damages. The essential characteristics of that claim are therefore different
from those of a claim under the Regulations.
Judicial
review
It
would appear that before the Judge Mr Flint supported this comparator with some
caution. He however succeeded in persuading the Judge that the comparison was
appropriate. The Judge referred, in my respectful view rightly, to the fact
that the whole purpose of Directive 89/665 was to secure the rapid
rectification of errors by public authorities, just as do judicial review
proceedings, and to the fact that the wording of Regulation 32(4)(b) had
clearly been taken more or less verbatim from RSC O53 r4(1). The Judge
continued, at p34C,
In
my judgment the only similar domestic action is an application for judicial
review. The procedure laid down by Article 32, including the time limit, is no
less favourable to a claimant than that laid down by Order 53 for judicial
review. Therefore, in my judgment, there is no breach of the principle of
equivalence.
Before
us, Mr Flint was even more restrained in his reliance on judicial review as an
appropriate comparator. He was justified in that diffidence.
First,
while as I have indicated I cannot accept arguments that are based on a need to
view the damages claim envisaged by Directive 89/665 in complete isolation from
the other provisions of that Directive, Mr Vaughan is nonetheless right in
saying that the damages claim envisaged by the Regulations must necessarily be
a claim in private law. While therefore there may be good reasons of policy
for the limitation period applied to the particular damages remedy provided by
the Regulations, those reasons are not to be found in, and the limitation
period cannot be justified by comparison with, the criteria applying to the
general public law remedies of Order 53. Second, whilst a damages claim can
now be joined in an Order 53 application, that is a matter of procedure, not of
substance, and only arises where there is a separate though linked right to
damages:
[RSC
O 53 r 7(1)] permitting a joinder of claims for damages for tort or breach of
contract was an entirely procedural reform, designed to prevent multiplicity
of proceedings, and did not affect the rule that there is no right to damages
for unlawful administrative action
per
se:
De
Smith, Woolf and Jowell,
Judicial
Review of Administrative Action
(5th edition), para 19-010.
That
means, as Mr Vaughan pointed out, that the effective limitation period for such
a claim is not the three months of Order 53, but whatever period would apply to
the claim if the plaintiff did not take advantage of the provisions of Order 53
rule 7(1). It is this consideration that, in my view, takes the damages claim
under the Regulations well away from any equivalence with procedure under Order
53.
Mr
Vaughan said that this was his strongest case. The right of action provided by
the 1988 Act was directly equivalent to the right to claim damages created by
the Regulations. It was, in the absence of any indication to the contrary,
subject to a six-year limitation period.
By
the 1988 Act local and other public authorities are forbidden to select the
persons with whom they contract on the basis of "non-commercial
considerations". Such considerations include, by
section 17(4), such matters
as the composition of and the terms of employment enjoyed by the contractors'
workforce; and the country of origin of supplies used by the contractors. By
section 19(7)(b) a failure to comply with that duty is actionable in damages by
any person who in consequence suffers loss or damage, though by
section 19(8)
any
action...by a person who has submitted a tender for a proposed public supply or
works contract arising out of the exercise of functions in relation to the
proposed contract the damages shall be limited to damages in respect of
expenditure reasonably incurred by him for the purpose of submitting the tender
Mr
Vaughan submitted that the purpose of both the Regulations and the 1988 Act was
the same, to provide tenderers with a right to compensation when they had been
unfairly treated. To implement that purpose, in both cases a damages remedy
was provided against a public authority when it had wrongly excluded a tenderer
from the contracting process.
I
agree that the 1988 Act comes closer as a comparator than any of the other
candidates surveyed, but it falls well short of satisfying the principle of
equivalence set out in
Palmisani
and
LEVEZ.
First, the purpose of the two legislative provisions, and thus of the actions
that they support, is different. The Regulations enforce the objectives of
Directive 92/50/EEC, which is aimed at the establishment of the internal
Community market and the general elimination of discrimination between
nationals of different member states. To cite one only of the recitals to that
Directive,
to
eliminate practices that restrict competition in general and participation in
contracts by other Member State's nationals in particular it is necessary to
improve the access of service providers to procedures for the award of contracts.
By
contrast, the 1988 Act has much more limited objectives. It does not address
competition in public supply in general, or indeed at all; that latter
objective is pursued by different provisions in Part I of the 1988 Act.
Rather, it prohibits very specific conditions in the procurement policy of
public authorities. The contrast is indeed to be seen in an authority shown to
us by Mr Vaughan, Case 31/87 [1988] ECR 4635,
Beentjes.
A condition of invitations to tender issued by the Dutch Ministry of
Agriculture was that contractors should employ long-term unemployed persons. A
complaint was raised under Directive 71/305/EEC, the predecessor of our
Directive 92/50. The Court of Justice held that
the
condition relating to the employment of long-term unemployed persons is
compatible with the directive if it has no direct or indirect discriminatory on
tenderers from other Member States of the Community. An additional specific
condition of this kind must be mentioned in the contract notice.
The
contrast with the 1988 Act is very striking. Under
section 17(5)(a) such a
condition would be absolutely prohibited as a condition relating to the
composition of the contractor's workforce. It would not be saved by any
publication of a specific notice; nor by appeal to an absence of actual
discriminatory effect, and much less to the absence of any discrimination
against nationals of other member states of the Community. And on the other
side of the coin, many contractual requirements prohibited under Directive
89/665 and the Regulations would not be open to objection under the 1988 Act:
including, significantly enough, as Mr Vaughan agreed, the specification of
TETRA that is complained of in this case.
Second,
the whole structure and approach of the two regimes is different. Directive
92/50, and thus the Regulations, lay down a very detailed code for the whole
tendering process; the 1988 Act merely prohibits certain specific conditions
from being included in invitations to tender that are otherwise not regulated
by it at all. And the essential conditions of the two actions that are
generated by those regimes are different. Damages under the Regulations are at
large, indeed in this case alleged to amount to loss of profits of
£100,000,000; under the 1988 Act they are confined to the tendering
expenses of persons who do submit tenders. That, as Mr Flint said, is not
merely a cap on the damages, but a limitation to a particular type of damages,
to one head of loss suffered by one class of plaintiff. Mr Flint summed up
this part of the case by pointing out that on the facts of our case Matra
would, mutatis mutandis, simply have had no claim under the 1988 Act, because
its complaint was nothing to do with irrelevant conditions, but rather with the
form of invitation to tender; its claim was for loss of a chance of profit and
loss of reputation and not for tendering expenses; and it could not claim in
any event because it had not been a tenderer.
All
these considerations confirm that the Judge was right in holding the 1988 Act
not to be an equivalent comparator under the
Palmisani
rule.
I
therefore conclude that Mr Flint was right in what was his primary case before
us, as in effect before the Judge, that there is no such comparator for the
claim under the Regulations. By the application of the second rule in
Palmisani,
therefore, the limitation period provided for that claim is not open to attack
under Community law.
Effectiveness
This
is very limited criterion. The remedy provided by the member state must not
make the Community right "virtually impossible or excessively difficult" to
exercise: Case C-312/93
[1995] ECR I-4599 [12]. Mr Vaughan in effect accepted
that it was impossible to attack this case on that basis. He had originally
submitted that a requirement to instigate proceedings for a damages remedy many
months before the actual conferring of the contract meant that time could
expire before the right accrued. That argument however rests on the
contention, which I have demonstrated above to be mistaken, that damage is not
suffered until damages are quantifiable or potentially quantifiable. I can see
no other reason for holding that the remedies granted by the Regulations are
not effective in the Community law sense.
The
Regulations not being invalid it is necessary to go on and consider the third
issue.
III
Was the Judge correct in refusing to extend the time limited by regulation
32(4)(b)?
Mr
Vaughan accepted that this was a matter of discretion, and that to disturb the
Judge's refusal to extend the time limit he had to show that there had been an
error in principle. That error was said to be the adoption by the Judge of an
approach based on the criteria appropriate to a public law claim under Order
53, rather than a private law damages claim, where the balance of prejudice,
not expressly considered by the Judge, should be taken into account.
I
leave aside the preliminary question, discussed above, as to whether it is
appropriate to analyse the damages claim under the Regulations, albeit a claim
in private law, in isolation from the general scheme of the Regulations,
because even on the basis advanced by Mr Vaughan the objections to the Judge's
approach are unfounded. First, as a matter of construction of the Regulations,
since those Regulations use the language of Order 53, and since (as I have
held) it is lawful for them to use that language, the Judge should not be
criticised if in applying that language he did indeed confine himself to
principles to be found in public law. Second, however, if prejudice is to be
taken into account, I am quite satisfied that the effect even of a damages
claim, and notably a claim for a huge amount, in a complex contracting process
such as the present will be to have an unsettling and disrupting effect on that
process. The damages claim cannot succeed unless Matra demonstrates that the
basis of the whole PSRCS project, the use of TETRA technology, is unlawful.
That that is indeed Matra's case is reinforced by the declaration to that
effect that Matra seeks in the action: which will apparently be an active claim
should this action continue. There is every reason in the public interest why
such claims should be made promptly. That consideration is only underlined by
the emphasis on speedy recourse of Directive 89/665 itself.
The
Judge reviewed other considerations advanced by Matra and rejected all of them.
He was clearly justified in that course, and in particular in not entering into
speculation about the strength of Matra's claim; and in concluding that Matra
had been well-informed throughout as to its rights, and had taken a conscious
decision, however commercially justified that might have been, not to assert
them at the appropriate time. There are no grounds for criticising his
conclusion on this point.
Conclusion
I
would accordingly declare, in much the same terms as the Judge, that
1.
The requirements of regulation 32(4)(b) of the Public Services Contracts
Regulations 1993 are not unlawful as being in breach of Community law
2.
The plaintiffs did not bring these proceedings within the time limited by that
sub-regulation
3.
There are no grounds for displacing the Judge's refusal to extend that time
and I would dismiss this appeal.
MUMMERY
LJ
:
I agree
HIRST
LJ
:
I also agree.
Order:
Appeal dismissed with costs.
-
- - - - - - -
BAILII:
Copyright Policy |
Disclaimers |
Privacy Policy |
Feedback |
Donate to BAILII
URL: http://www.bailii.org/ew/cases/EWCA/Civ/1999/860.html