BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just Β£1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales Court of Appeal (Civil Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales Court of Appeal (Civil Division) Decisions >> BMBF (No 12) Ltd v Harland & Wolff Shipbuilding & Heavy Industries Ltd [2001] EWCA Civ 862 (8 June 2001) URL: http://www.bailii.org/ew/cases/EWCA/Civ/2001/862.html Cite as: [2001] 2 Lloyd's Rep 227, [2001] EWCA Civ 862, [2001] CLC 1552, [2001] 2 All ER (Comm) 385, [2001] 2 LLR 227 |
[New search] [Printable RTF version] [Help]
COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM QUEEN'S BENCH DIVISION
COMMERCIAL COURT
(MR JUSTICE TOMLINSON)
Strand, London, WC2A 2LL Friday 8th June 2001 |
||
B e f o r e :
LORD JUSTICE CLARKE
and
SIR MARTIN NOURSE
____________________
BMBF (NO. 12) LIMITED |
Respondent |
|
- and - |
||
HARLAND AND WOLFF SHIPBUILDING AND HEAVY INDUSTRIES LIMITED |
Appellant |
____________________
Smith Bernal Reporting Limited, 190 Fleet Street
London EC4A 2AG
Tel No: 020 7421 4040, Fax No: 020 7831 8838
Official Shorthand Writers to the Court)
Andrew Popplewell QC and Sean O'Sullivan Esquire (instructed by Ince & Co, London, for the respondent)
____________________
Crown Copyright ©
LORD JUSTICE POTTER:
INTRODUCTION
THE RELEVANT TERMS OF THE CONRACT.
The Builder will construct, complete and deliver to the Owner the Vessel described herein and the Owner shall duly pay the Builder therefore all in accordance with the following clauses in this contract.
To install same and provide the necessary foundations, wiring, piping and successfully tested and commissioned interface connections to ensure the Owner Furnished Equipment functions as complete operational systems.
The total cost for Drill-Ship No. 1740 shall be [US$ 260,068,234] comprised as follows:
A. [US$ 153,859,234] (the "Contract Price") for detailed design, procurement (exclusive of OFE, see below), construction, installation of all equipment, commissioning and setting to work of the total drill-ship, all according to this Contract.
B. [US$ 106,209,000] for OFE. Unless otherwise mutually agreed the Owner shall be responsible for all payments due in respect of OFE to Owner Suppliers and Owner Sub-contractors.
Builder shall provide the Parent Company Guarantee and the Letter of Credit [in forms Schedule 2 of the Contract] to Owner at the date of signature of this Contract. Further with reference to the Letter of Credit the 'First Letter') issued by Builder to Owner in conjunction with the Shipbuilding Contract relating to Hull No: 1739, Builder hereby agrees to:
(i) amend said First Letter to refer to and also apply to this Contract; and
(ii) extend the Expiry Date of the first Letter to 10 August 2000.
8.3.5 Twenty per cent (20%) of the Contract Price, plus or minus any increases or decreases occasioned in accordance with the provisions of this Contract or any Amendment thereof which have not previously been accounted for by adjustment of this or any earlier instalments, at Delivery of the Vessel, estimated to be February 10, 2000.
[Clause 8.3.5 was subsequently amended by the Novation Agreement later referred to, but such amendments are not relevant for the purposes of this appeal].
"Any amounts for bonuses or liquidated damages under Clause 12 shall be calculated and determined on or before Delivery of the vessel and shall be payable on the Delivery Date, and Owner shall be entitled to net-off such amount(s) against the instalment referred to in Clause 8.3.5 above." [i.e. the instalment payable on Delivery]
the Vessel, as it is constructed, and all machinery, equipment and materials from time to time appropriated or intended for it shall become and remain the absolute property of the Owner but the Builder shall at all times have a lien thereon for any part of the Contract Price which is unpaid ... provided that such lien shall not continue or be enforceable by or on behalf of the Builder in any of the circumstances described in clauses 15.1 or 15.2.
12.1 The Vessel shall be delivered to the Owner by the Builder at the Builder's Yard on or before the Contract Delivery Date.
12.2 Provided that:
(i) the Vessel is in compliance with the requirements of the contract and the Specifications; and
(ii) all the Certificates referred to below are tendered
then Delivery of the Vessel shall be forthwith effected by the concurrent signature by the Owner and the Builder of a Certificate of Delivery acknowledging delivery of the Vessel by the builder and acceptance by the Owner.
Upon Delivery of the Vessel the Builder shall hand to the Owner, the Builder's Certificate, the Certificate of the Classification Society, all other Certificates required to enable the Owner to operate the Vessel and all other Certificates, Provisional Certificates and Protocols .
12.4 Upon Delivery of the Vessel, the following shall occur:
12.4.1 If Delivery occurs on or before fifteen (15) days prior to the Contract Delivery Date, Owner shall pay to Builder the sum of United States Dollars Three Million (USD $3,000,000) as a bonus for early delivery;
12.4.2 If Delivery occurs between the period of fourteen (14) days prior to Contract Delivery Date and fifteen (15)days after Contract Delivery Date, the bonus referred to in Section 12.5.1, above, shall be reduced by the sum of United States Dollars One Hundred Thousand (USD $100,000) per day such that no bonus may be earned by the Builder after the expiry of such thirty (30) days.
12.4.3 There shall be a grace period of fifteen (15) days from the sixteenth (16th ) through the thirtieth (30th ) day after the Contract Delivery Date where no bonus may be earned by the Builder and no liquidated damages shall become due and payable to the Owner.
12.4.4 If Delivery occurs on or after the thirty-first day after the Contract Delivery Date, Builder shall pay to the Owner as liquidated damages, but not as a penalty, the sum of United States Dollars Fifty Thousand (USD $50,000) per day for a period not to exceed fifteen (15) days.
12.4.5 If Delivery occurs on or after the forty-sixth day after the Contract Delivery Date, Builder shall pay to the Owner as liquidated damages, but not as a penalty, the sum of United States Dollars Seventy Five Thousand (USD $75,000) per day for a period not to exceed fifteen (15) days.
12.4.6 If Delivery occurs on or after the sixty-first (61st) day after the Contract Delivery Date, Builder shall pay to Owner as liquidated damages, but not as a penalty, the sum of United States Dollars One Hundred Thousand (USD $100,000) per day for a period not to exceed thirty (30) days.
12.4.7 If Delivery has not occurred within the period of ninety (90) days after the Contact Delivery Date, no further or other liquidated damages shall be payable by Builder and Builder's liability to pay liquidated damages under this Clause 12.5 shall be limited to the aggregate amount of United States Dollars, Four Million, Eight Hundred Seventy Five Hundred Thousand (USD $4,875,000), payable under clauses 12.4.4, 12.4.5, and 12.4.6, respectively, the liquidated damages payable thereunder being, for the avoidance of doubt, cumulative. In this event, Owner shall be entitled to exercise the rights and remedies available to it under Clause 15.
[Clause 12.4 was amended by Contract Amendment No 2 dated 5 October 1998 but that amendment is immaterial to the construction of the contract.]
12.5 If any items on the Vessel are incomplete when the Vessel is otherwise ready for Delivery and the Owner and the Builder agree that such items:
(i) do not materially affect the operation of the Vessel;
(ii) are not likely to cause damage or deterioration; and
(iii) do not constitute such a number that whilst not individually giving rise to such material effect, nor likely to cause damage or deterioration, are in aggregate material to the condition of the Vessel;
then the Owner will take Delivery of the Vessel. Owner shall in any event have such items completed in a manner to be mutually agreed upon between the Builder and the Owner. Dispatch to the Vessel by sea freight, or if practicable by air freight in the case of emergency, of items completed and/or received at the Builder's Yard subsequent to departure of the Vessel therefrom shall be at the expense of the Builder excepting items of Owner Furnished Equipment the cost of dispatch of which shall be at the expense of the Owner.
Contract Delivery Date shall mean 10th February 2000 as from time to time extended pursuant to this Contract by Permissible Delay.
It is not necessary to refer to the definition of Permissible Delay.
15.1 Upon the occurrence of any of the following events the Builder shall be in default:
15.1.1 the Vessel becomes a total loss in accordance with Clause 10.4; or
15.1.2 the Vessel is requisitioned by the British Government; or
15.1.3 the Builder without just cause refuses to proceed with the construction of the Vessel; or
15.1.4 an order is made or an effective resolution is passed for the winding up of the Builder (otherwise than a members' voluntary winding up for the purposes of amalgamation or reconstruction) or a receiver or administrator is appointed of the whole or any part of the undertaking of the Builder; or
15.1.5 if at any time during this Contract, following receipt of request to do so from Owner, the Builder, utilising the Primavera level 3 critical path project schedule, is unable to demonstrate to the Owner's satisfaction that it has sufficient additional capacity, including sub-contracted labour, and/or materials, and/or has developed a recovery plan that would enable him to deliver the Vessel within ninety (90) days following the Contract Delivery Date and that the Builder is implementing such plan and/or utilizing such additional capacity and exercising all necessary due diligence to achieve Delivery within such period; or
15.1.6 if at any time during this Contract, the Builder is placed into default under the "Shipbuilding Contract relating to Hull No:1739.
For the avoidance of doubt, the Builder will not be placed into default under the provisions of Clause 15.1.5 where there is a dispute regarding the Contract Delivery Date which arises out of Clause 6.11.
15.2 In circumstances of Builder's default as described in Clause 15.1 or in the circumstances set out in Clauses 12.4.6 or 13.4, the Owner, without prejudice to its rights under the Parent Company Guarantee, shall be entitled by Notice to the Builder EITHER:
(i) to cancel this Contract in which event Builder shall forthwith refund to the Owner (a) the aggregate amount of all sums paid pursuant to Clause 8, (b) any amount reasonably and properly paid by Owner to any Owner Subcontractors and (c) any and all amounts reasonably and properly paid by Owner for Owner Furnished Equipment which has been incorporated in the Vessel, all together with interest thereon at the rate of two (2%) percent over one-month LIBOR from time to time for the particular currency, calculated in each case from the date of payment by Owner to the date such refund is made.
However, the proceeds of any insurance claim previously received by Owner shall be deducted from the amount to be refunded under this sub-clause (i). Upon such refund as aforesaid being made in full, all the obligations, duties and liabilities of each of the parties hereto to the other under this Contract shall forthwith be completely discharged and title to the Vessel shall be vested in Builder;
OR
(ii) to take possession of the Vessel in its unfinished state and complete the Vessel in accordance with this Contract and the Specifications either at the Builder's Yard or elsewhere, at Owner's sole option. In the event that Owner decides to complete the Vessel at Builder's Yard, Owner and its agents or Owner Subcontractors shall be entitled to use Builder's Yard, building, plant, machinery, tools and implements and all materials appropriated to or ordered for the Vessel and shall not be liable for breakage or damage thereto. In this case, in the event that the cost of completing the Vessel is more than the amount of the outstanding instalments, Builder shall pay to Owner on demand an amount equal to the amount of such excess from the time of demand with interest thereon at two (2) % per cent over one month LIBOR from time to time for the particular currency calculated from the date of demand until the date of refund.
15.3 In the circumstances set out in Clause 15.2:
(i) Owner shall be entitled, in the event that it elects to cancel this Contract pursuant to Clause 15.2(i) above, and no refund is made in full by Builder within five (5) days of receipt of Notice of such cancellation, to make demand under the Letter of Credit and/or the Parent Company Guarantee, in Owner's sole option; and
(ii) Owner shall be entitled, in the event that it elects to take possession pursuant to Clause 15.2(ii), then or at any time thereafter to make demand under the Letter of Credit for the full amount thereof and to utilise the same for the purposes of completing the Vessel (in accordance with the terms of this Contract and the Specifications) and shall account to Builder for any unutilised amounts following such completion, and/or to make demand under the Parent Company Guarantee and to utilise all sums from time to time received thereunder for the purposes of completing the Vessel (in accordance with the terms of this Contract and the Specifications).
15.4 Subject always to the provisions of Clause 15.2(ii), 15.3 and 15.5, in the event of the cancellation, rescission or termination of this Contract by the Owner, the property in the Vessel and all its materials, machinery and equipment shall, following receipt by the Owner of the full amount of all instalments paid up to the date of such cancellation, rescission or termination of the Contract and all other amounts payable by the Builder to the Owner hereunder, be transferred to and vest in the Builder.
15.5 In the event that the Owner elects to take possession of the Vessel pursuant to Clause 15.2(ii), the Builder shall assign (or procure the assignment of) the Subcontracts, Supplier contracts and/or any rights arising thereunder to the Owner and shall do and execute such assurances, acts and documentation required or desirable for vesting the Subcontracts and/or any rights arising thereunder in the Owner.
15.6 All items of Owner's Furnished Equipment not incorporated in the Vessel shall be made available to Owner
15.7 In the event that Owner elects to take possession of the Vessel pursuant to Clause 15.2(ii), any sums due from Builder to Owner by way of liquidated damages already incurred at the date of Notice shall be set off against any remaining instalments due from Owner to Builder.
16.1 the Builder for the whole of the Guarantee Period guarantees the Works against all defects which are due to defective design .., defective material, poor workmanship and/or the Works not having been performed in accordance with the Contract the Guarantee Period shall be for a period of twelve (12) months from Delivery of the Vessel provided always that, in respect of any repairs or replacements or such additional works as are referred to in Clause 16.6, the Guarantee Period shall be twelve (12) months after completion of such repairs, replacements and additional works. The Guarantee Period shall not in any event exceed twenty-four (24) months in total Delivery.
..
16.6 the Builder shall remedy at his own expense any defect arising during the guarantee Period against which the Works are guaranteed under this Contract and which is Notified by Owner to Builder in accordance with Clause 16.2, by making all necessary repairs and replacements by performing such additional works as may be required to remedy such defect
.
16.9 the guarantees and remedies contained in this Clause 16 concerning the defects which are covered by this Clause 16 are the sole and exclusive guarantees and remedies in favor of the Owner concerning such matters. All guarantees and remedies concerning such matters which would otherwise be implied by law (whether under the Sale of Goods Act or otherwise) and all remedies in tort, (including but not limited to negligence), are expressly excluded
THE BACKGROUND AND HISTORY OF THE DISPUTE
"Contract Amendment No 3 dated 19 November 1999.11. Hull No. 1740 was the second of two, effectively identical, Vessels which the Builder agreed to build for the Owner. By November 1999, disputes had arisen between them with regard to both Vessels. The Builder alleged, but the Owner denied, that substantial extra cost and delays had been and were being incurred by reason of changes to the design and specification, for which the Owner was responsible. The Owner believed that the Builder was inefficient and was not entitled to any additional payment or extension of time, so far as Hull No. 1740 was concerned, under the Modifications and Change Orders provisions of Clause 6. In the background was what the Owner saw as the parlous financial condition of the Builder, whom it believed might be forced into liquidation. The Builder is and was a subsidiary of Harland and Wolff Holdings Ltd, which is owned or majority owned by a Norwegian company, Fred Olsen Energy ASA.
12. The commercial pressures by November 1999 were very great and the stakes were high. The situation as it was then is described in the third Recital to Contract Amendment No 3
"(C) The Builder has made claims in excess of £130 million under the Shipbuilding Contract and the equivalent contract for Hull No. 1739 in respect of (i) certain alleged breaches by the Owner and the Owner of Hull 1739, (ii) the costs associated with alleged changes to the Specifications to the Shipbuilding Contract and the equivalent contract for Hull No. 1739, and (iii) increases in the steel weight of the Vessel and Hull No. 1739, all of which claims are denied by the Owner, the owner of Hull 1739 and GMIDC [the "Old Owner" as it had then become]".13. Amendment No 3 to the Shipbuilding Contract was accompanied by the FOE Agreement, to which Fred Olsen Energy ASA ("FOE") and the Owner were parties, the latter on its own behalf and on behalf of the Claimants as the "New Owner" of Hull No 1740.
14. The overall effect of these November agreements can be stated briefly as follows. The Owner agreed to pay £28 million on account of the Builder's claims in respect of Hull No. 1740. An arbitration was to follow pursuant to clause 20 of the Shipbuilding Contract. That amount was to be taken into account in a final settlement of accounts following the arbitration Award. The Owner agreed to make a further payment not exceeding £8 million, which was to be matched by an equivalent payment by FOE. The Owner also agreed to release a Letter of Credit in the sum of $40 million which the Builder had procured pursuant to clause 8.2 of the Contract, as amended. This allowed the Builder to acquire the use of funds which it had provided as security for the Credit. Further, Contract Amendment No 3 included the following undertakings by the Owner-
2.4 The Owner agrees:(a) that there shall be no further requests for adjustments or variations to the Specifications or changes in the scope of works remaining to be undertaken in respect of the Vessel;(b) not to exercise its rights under Clause 15.2 of the Shipbuilding Contract unless(i) FOE is in breach of its obligations under the FOE Agreement; and/or(ii) Delivery of the Vessel has not taken place by 31st July 2000 as such date shall be extended by all periods of Permissible Delay or Owner's default under the Shipbuilding Contract arising after the date of this Agreement, such circumstance being deemed to be a Builder's default under Clause 15.1 (it being understood that this provision shall not alter the Contract Delivery Date under the Shipbuilding Contract), and(c) that the delivery instalment for (sic) the Contract Price for the Vessel shall be paid in full in accordance with the Contract and without deduction in respect of liquidated damages for late delivery (but without prejudice to the Owner's right to bring the Builder's liability for liquidated damages into account in arbitration proceedings)."Recent History
16. Sea trials took place by mid-July 2000. After their completion, the Builder contended that the vessel was ready for delivery, or alternatively was ready apart from OFE items for which the Owner was responsible. The Owner denied this and produced a 'punch list' of items which it said needed rectification by the Builder before the vessel could be in a deliverable state in accordance with the Shipbuilding Contract. On and after 24 July, until 1 August 2000, the Builder tendered Delivery under the Contract, but the tenders were refused.
17. On 27 July 2000, according to the Owner's evidence, the Builder refused access to the vessel to all Owner's personnel and made it clear that no further work of any type would be permitted on the vessel until the Owner took Delivery (first statement of Robert Dawson, dated 2 August 2000).
18. On 1 August 2000 the Owner gave notice to the Builder under clause 15.2 (ii) to take possession of the vessel in what the Owner alleged was its unfinished state. On the same day, the Owner applied to the Commercial Court in London for an interim mandatory injunction entitling it to take possession against the provision of security. On 11 August, following a two-day hearing at which both parties were represented, the Deputy Judge made an Order substantially in the terms sought by the Owner. The Order included, however, an undertaking by the Owner to permit the Builder to place up to three observers on the vessel (undertaking (d)), and in paragraph 4 it stated "This Order may be varied in whole or in part by the Arbitrators".
19. The Owner took possession of the vessel immediately and caused it to proceed, first to the Clyde, and then across the Atlantic towards Galveston, Texas, where arrangements were made for further work to be done to prepare it for delivery to Exxon under a three-year time charter. It is contemplated that delivery to Exxon will take place in October.
20. When the hearing took place before us on 5-7 September 2000, the vessel was nearing the end of its trans-Atlantic voyage but it had not reached U.S. coastal waters.
This application
21. The Commercial Court's Order (by undertaking (e)) foreshadowed an application to the arbitration Tribunal by the Builder on 5 September. By letter dated 14 August the Builder's solicitors called upon the Owner to pay sums totalling about $36 million against invoices already sent, which they alleged were due because the vessel was in a deliverable state under the Shipbuilding Contract, or alternatively would become due "at latest on completion of the vessel". The Letter then indicated, without prejudice to the Builder's principal position, that they would accept payment of all sums due "save for $2,000,000", which their client was willing to have paid into an escrow account "pending final resolution by the arbitrators".
22. No payment was forthcoming and by letter dated 16 August 2000 the Builder's solicitors gave notice of an application for (sic) the Tribunal "for an Order requesting your clients to pay the delivery instalment" (a reference to clause 8.3.5 of the shipbuilding contract, as amended). The letter added:-
"In the event that this issue cannot be resolved in the time available....then please note that our clients will be requesting the tribunal to exercise their rights pursuant to section 39 of the Arbitration Act 1996 to grant provisional relief and provide for payment".23. Further correspondence between the solicitors failed to achieve agreement as to the scope of the hearing - which in our view was regrettable - and in the event Leading Counsel made oral submissions and on the final day produced written formulations of the issues they asked the Tribunal to decide.
The issues
24. In truth, there was little if any difference between the parties as to what the issues were, which we are asked to decide. The Builder sought payment of the delivery instalment and other sums which it alleged were due, following the Owner's taking possession of the vessel (as authorised by the Court Order), but without prejudice to its underlying submission that the vessel was in a deliverable state and the Owner was wrong to refuse delivery under the shipbuilding contract, as it had done before 31 July. The Owner denied this and contended that it was entitled to exercise its right to take possession by notice under clause 15.2 (ii), as it had done pursuant to the Court Order, and that no sum was payable under the terms of the Shipbuilding Contract or should be ordered to be paid by way of interim relief.
25. The central issue we were called upon to consider, therefore, was the legal consequences of the Owner's exercise or purported exercise of the right to take possession of the vessel under clause 15.2 (ii). It was common ground between the parties that we could not hear evidence to decide whether the vessel was, in fact, in a deliverable state on or before 31 July and therefore whether the Owner had been entitled to refuse delivery then.
26. Mr Hunter QC, for the Builders, raised one issue of fact (strictly, mixed fact and law) which he invited us to decide. He submitted that the Owner was not entitled to exercise the clause 15.2(ii) right to take possession of the vessel on 1 August when it had done so, because clause 2.4.(b) of the Contract Amendment No 3, by which the Owner agreed not to exercise the right until after 31 July, was itself liable to be extended "by all periods of Permissible Delay or Owner's default under the Shipbuilding Contract arising after the date of this agreement". Clearly, he submitted, the Builder will succeed in obtaining at least one day's extension when the matter is considered in due course, whether for Permissible Delay as defined or by reason of force majeure (clause 13). Therefore, the Owner's purported exercise of its clause 15.2 (ii) right was certainly premature.
27. Mr Popplewell QC for the Owner responded that the notice was repeated daily until 11 August. The latest notice was only premature if the Builder was entitled to at least 10 days' extension of the time limit, and he submitted that the arbitrators could not decide this without hearing evidence, which we could not do at this hearing.
28. We do not make any finding on this issue. We proceed on the basis suggested by Mr Popplewell, namely, that the Owner is arguably correct in contending that the time limit imposed by clause 2.4 (b) of Contract Amendment No 3 expired before, at latest, 11 August and that it was entitled to give the clause 15.2 (ii) notice on that day, if not earlier. Naturally, the Builder retains the right to argue that all the notices were premature. Our present concern is to consider the legal consequences of the exercise of the Owner's assumed right to take possession under the clause.
(i) Was the vessel complete and/or in a deliverable state as at 1 August 2000?
(ii) Had the deadline for delivery of 31 July 2000 been extended by any period of Permissible Delay?
(iii) What was the extent of the losses (if any) as a result of its inability to deliver the vessel into a charterparty concluded with Exxon?
[It is the case for the owner that, if the vessel had been constructed by the builder in conformity with the Contract and Specifications it would have been delivered into Exxon's service on or after the Contract Delivery Date, 10 February 2000, and that the owner's inability to deliver the vessel to Exxon has caused loss at a rate of US$200,000 per day.]
(iv) Is the owner entitled to recover all or part of the £28,000,000 which it provided on a without prejudice basis pursuant to the November 1999 Contract Amendment No. 3 plus a further £3.9 million matched by an equivalent amount from FOE (see paragraphs 13 and 14 of the award above)?
(v) Is the builder entitled to recover all or any of the £130,000,000 which it has asserted in claims against the owner and the owner of Hull No. 1739?
THE ARBITRATORS' DECISION
40. . When the Owner elects to take possession of the vessel under sub-clause (ii), it rejects the alternative right under sub-clause (i) to cancel the contract and recover the sums it has paid the Builder. The Vessel then remains with the Builder and becomes the property of the Builder. By way of contrast, Notice given under sub-clause (ii) does not cancel or terminate the contract, for the reasons we have indicated above, and the contract therefore remains in being. This being so, the Owner's obligation to pay the Contract sum against delivery of the completed Vessel remains in existence and binding upon the Owner.
41. The question thus arises whether "Delivery of the Vessel" which is the condition precedent to the payment obligation under Clause 8.3.5, can take place when the Owner takes the possession under Clause 15.2(ii). Mr Popplewell argues that the Owner is under no obligation to complete the Vessel either in accordance with the Contract and the Specification or at all, except possibly when the Vessel remains at the Builder's Yard, which it has not done here. The Owner, he submits, has liberty to complete there or elsewhere, but no obligation to do so. The concluding words of the first sentence of the sub-clause "at Owner's sole option", refer generally to the various alternatives open to the Owner (whether to exercise the right; whether to complete, or not; whether in accordance with the Contract and Specifications, or otherwise; whether at the Builder's Yard or elsewhere), not merely to the last of these, which is covered by the immediately preceding words "either at the Builder's Yard or elsewhere".
42. We accept Mr Popplewell's submission that the right to take possession may be exercised in appropriate circumstances at any stage of the life of the contract, and that regard must be had to its potential operation at each different stage.
43. We can express our conclusions shortly. Given that the contract remains in existence notwithstanding the Owner's exercise of the right to take possession of the unfinished Vessel, we do not see any insuperable difficulty either in principle or in practice in applying the contract terms to the period following the Notice when the contract work is being done by the Owner, its agents or sub-contractors, rather than by the Builder, whether at the Builder's Yard (using the Builder's plant etc) or elsewhere. We need not elaborate on this. The relevant question is whether "Delivery" can take place, as required by the Contract, when the Owner already has title (Clause 9.1) and Possession (Clause 15.2(ii) and in fact) of the Vessel. Delivery formalities remain (Clause 12.2) and there is no reason why these cannot be complied with when construction, trials, etc are complete.
44. In our view, Clause 15.2(ii) gives a limited right (to take possession of the Vessel in its unfinished state and complete [etc]), not the unqualified right, in effect to terminate the contract, for which the owner contends. If this is correct, then the Owner's obligation to pay the delivery instalment, and any other instalments as they become due under the contract remains. We therefore HOLD that if the owner gave a valid Notice under clause 15.2(ii), then its obligation to pay the delivery instalment in accordance with Clause 8.3.5 remains binding upon it.
45. More difficult is the question as to the time when payment of further instalment becomes due. Many variables have to be considered in this context, particularly the stage at which the right to take possession is exercised and whether the Vessel is completed at the Builder's Yard or moved elsewhere. The correct answer in principle, in our view, is that the instalment payment becomes due to the Builder when the appropriate stage of completion is reached by the Owner subject always to deduction of additional costs which the Owner has incurred. But we are concerned with a case where (1) the Vessel has been removed, and (2) completion will not be limited to what is repaired by the Contract and Specification, but will incorporate additional items of work and equipment required by the Owners for the purposes of the Exxon charterparty
50. We do not think that the Owner should be in a better position than if the Notice under Clause 15.2 (ii) was validly given. Yet that is the effect of the Deputy Judge's Order. The Owner has achieved possession as well as ownership of the vessel and in practical terms the ability to complete the Vessel otherwise than in accordance with the contract and specification. The Owner has not been required to pay the final instalment of the Contract Price, even after allowing for the estimated costs of completion at another Yard. That sum, in our view, either is already due or will shortly become due.
51. The Builder's claim that [the final instalment] is already due gains formidable support from the principle applied in Mackay v- Dick (1885) 7 App Cas 251. Where the Owner elects not to complete the Vessel "in accordance with the Contract and Specification" then it cannot rely upon its failure to do so as a defence to the Builder's claim for the delivery instalment of the Contract Price. But we need not form a concluded view, because the time difference is short and we may take account of pending as well as accrued obligations (which are assumed obligations, in any event).
THE JUDGMENT OF TOMLINSON J
"One cannot spell out of an express provision for recovery of the additional costs of construction, an implied provision for payment to the Builder of unpaid instalments or for a right of deduction therefrom in respect of the cost of construction."
THE GROUNDS OF APPEAL
DISCUSSION AND CONCLUSION
SUBSIDIARY ISSUES
Clause 7.6
"Owner shall be entitled to set-off all sums due to it pursuant to this clause against the installment of the Contract Price payable pursuant to Clause 8.3.5"
"This renders it unnecessary to deal with the Owner's subsidiary arguments concerning its alleged ability to set-off against the Delivery Instalment sums due to it under Clause 7.6 of the Contract These points no longer arise although had they fallen for consideration I would have been unable to resolve them without inviting the arbitrators to furnish further reasons. In that regard I should mention in all fairness that the Tribunal was plainly under great pressure to produce an early award and in such circumstances understandably directed only a small part of their reasons to these subsidiary issues."
Set-off against Builder's Quarterly Invoices
"For and including, but not limited to, additional services which are requested by Owner, but are not provided for in any Project Change Order and facilities usage for Owner's Subcontractors. Owner's Suppliers "
The owner was obliged to pay the undisputed portion within thirty days.
Provisional Assessment of Costs of Completion
"(7) On an appeal under this section the court may by order
(a) .
(b) ..
(c) remit the award to the tribunal, in whole or in part, for reconsideration in the light of the court's determination .."
"We do not consider that the sum otherwise due from the Owner should be reduced for this reason, in the circumstances of the present case."
CONCLUSION
LORD JUSTICE CLARKE:
i) Clause 15.2 is triggered in a number of different circumstances, not all of which involve actual default on the part of the builder. For example they include the force majeure circumstances set out in clause 13.4. They also include the "circumstances of Builder's default as described in Clause 15.1", not all of which involve actual default. Thus clause 15.2 may fairly be described as an events clause not confined to events of default. As I see it, its purpose is to provide for the consequences of such events in a way which is fair and equitable as between the parties.ii) Once triggered, clause 15.2 gives the owner a right to give a notice under the clause. If the owner chooses to give such a notice it must "EITHER" cancel the contract under clause 15.2(i) "OR" take the steps expressly provided by clause 15.2(ii).
iii) The steps expressly provided by clause 15.2(ii) were:
"to take possession of the Vessel in its unfinished state and complete the Vessel in accordance with this Contract and the Specifications either at the Builder's Yard or elsewhere, at Owner's sole option "iv) I entirely agree with Potter LJ and Sir Martin Nourse that the plain meaning of that provision is that if the owner chooses to take the action open to him under clause 15.2(ii) it must take possession "and complete the vessel in accordance with the contract and the Specifications" (my emphasis). There is to my mind no warrant for construing the word "and" disjunctively or for construing that phrase as if it read "and (if the Owner wishes) complete the Vessel ".
v) The phrase "at Owner's sole option" is governed by the expression "either at the Builder's Yard or elsewhere". Thus the option conferred by the clause is not a choice whether to complete the vessel or not. It simply allows the owner to choose whether to complete it at the builder's yard or elsewhere.
vi) The remaining part of the clause 15.2(ii) expressly provides for what is to happen if the cost of completing the vessel is more than the outstanding instalments, which must mean the outstanding instalments set out in clause 8 including of course the delivery instalment. In that event the builder must reimburse the owner for the extra cost together with interest. That is on the footing that the outstanding instalments remain at least notionally due and that the builder is notionally entitled to them, but that the owner does not have to pay them if the cost of completing the vessel exceeds them.
vii) What then if the cost of completing the vessel is less than the outstanding instalments? It must follow that the owner must pay them, including the delivery instalment, but that the owner may deduct the cost of completing the vessel and pay the balance, if any. That seems to me to follow from clause 15.2(ii) as a matter of construction, but, if that is wrong, by necessary implication. If the officious bystander were asked whether the owner could deduct the cost from the outstanding instalments he would say "of course".
viii) That solution seems to me to represent a fair balance between the interests of the parties. The owner ends up with a vessel completed in accordance with the contract. It pays the contract price but no more than the contract price because, if the vessel costs more to complete, the builder must reimburse the extra cost plus interest. Any other view would provide the owner with an unwarranted windfall where (as here) the cost of completing the vessel is less than the outstanding instalments.
ix) I can see nothing in the terms of the contract or the surrounding circumstances to lead to a different view. For example, while I recognize that, where the owner exercises its rights under clause 15.2(ii), clause 12.1 must be read subject to clause 15.2(ii), there is nothing in either clause 12 or clause 15 to prevent the delivery instalment becoming due. The delivery instalment is payable "at Delivery of the Vessel" as provided by clause 8.3.5. By clause 12.2 "Delivery of the Vessel" is different from delivery in the sense of transfer of possession and there is nothing in clause 8 or clause 12 to prevent "Delivery" being effected so as to make the delivery instalment due.
x) In these circumstances there is no reason for giving the clause other than its ordinary and natural meaning. I agree with Sir Martin Nourse that there is no basis upon which it would be appropriate for the court to interfere with or contradict the views of the arbitrators in paragraph 43 of the award which he has quoted. It follows that there is no reason to hold that the clause is unworkable if it is given its ordinary and natural meaning.
SIR MARTIN NOURSE:
"In circumstances of Builder's default . . . the Owner . . . shall be entitled by Notice to the Builder EITHER:
i) to cancel this Contract . . .OR
ii) to take possession of the Vessel in its unfinished state and complete the Vessel in accordance with this Contract and the Specifications either at the Builder's Yard or elsewhere, at Owner's sole option."
"The only sensible construction is in my view that the words 'at Owner's sole option' qualify or have as their subject matter the alternatives separated by the disjunctive 'and' as in 'to take possession of the Vessel in its unfinished state' and 'complete the Vessel in accordance with this Contract and the Specifications either at the Builder's Yard or elsewhere'. So understood, there is no obligation to complete the Vessel let alone to do so in accordance with the Contract and the Specifications. Indeed the language used is in any event the language of entitlement, not that of imposition of obligation."
"Given that the contract remains in existence notwithstanding the Owner's exercise of the right to take possession of the unfinished Vessel, we do not see any insuperable difficulty either in principle or in practice in applying the contract terms to the period following the Notice when the contract work is being done by the Owner . . . rather than by the Builder, whether at the Builder's Yard . . . or elsewhere. We need not elaborate on this."