BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales Court of Appeal (Civil Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales Court of Appeal (Civil Division) Decisions >> Cenargo Ltd v Izar Construcciones Navales SA [2002] EWCA Civ 524 (26 March 2002) URL: http://www.bailii.org/ew/cases/EWCA/Civ/2002/524.html Cite as: [2002] EWCA Civ 524, [2002] CLC 1151 |
[New search] [Printable RTF version] [Help]
COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
COMMERCIAL COURT
(Mr Justice Andrew Smith)
Strand London WC2 |
||
B e f o r e :
LORD JUSTICE LONGMORE
and
SIR MARTIN NOURSE
____________________
CENARGO LIMITED | Appellant | |
-v- | ||
IZAR CONSTRUCCIONES NAVALES SA | ||
(formerly EMPRESA NACIONAL BAZAN DE CONSTRUCCIONES | ||
NAVALES MILITARES SA | Respondent | |
and | ||
IZAR CONSTRUCCIONES NAVALES SA | ||
(formerly EMPRESA NACIONAL BAZAN DE CONSTRUCCIONES | ||
NAVALES MILITARES SA | Appellant | |
-v- | ||
CENARGO LIMITED | Respondent |
____________________
Smith Bernal Reporting Limited
190 Fleet Street London EC4A 2AG
Tel: 020 7421 4040 Fax: 020 7831 8838
(Official Shorthand Writers to the Court)
Mr D Kendrick QC and Mr R Waller (instructed by Messrs Sinclair Roche Temperley, London EC2) appeared on behalf of Izar Construcciones Navales SA (Builders).
____________________
Crown Copyright ©
(A)The true construction of the contractual terms relating to trailer carrying capacity.
(B)Whether on their true construction there was a breach of these terms and, if so, in what respect.
(C)Whether any breach gave rise to a right to recover liquidated damages as provided by the contract.
(D)Whether the right to invoke the liquidated damages clause had been lost.
"ARTICLE I - DESCRIPTION AND CLASS
1.VESSEL'S DESCRIPTION
The Builder undertakes to build at the Builder's yard at Seville and to properly install all Buyer's supplied items and to deliver to the Buyer, who hereby orders and undertakes to accept delivery of one Roll-on Roll-off Cargo Passenger Vessel of approximately 6,300 metric tons deadweight in sea water of specific gravity of 1,025 on a draft of 6.5 metres, the Vessel, which shall have, for the purpose of identification only, the Builder's Hull Number 287 subject to and in accordance with this Contract and relevant Specification No. 56.118 dated 25/01/96 (`the Specification') and Plan No. 6118/001/01 (`the Plan') signed by both parties, which form an integral part of this Contract.
The Specification and the Plan are intended to explain each other and anything shown on the Plan and not stipulated in the Specification and anything stipulated in the Specification and not shown on the Plan shall be deemed to be contained in both.
In the event of any conflict between this Contract and the Specification and/or the Plan, the provisions of this Contract shall prevail. In the event of any conflict between the Specification and the Plan the provisions of the Specification shall prevail.
4.CAPACITY
The Vessel shall have a RoRo freight capacity of at least 146, 13 metre slots.
ARTICLE II - PRICE AND TERMS OF PAYMENT
2.TERMS OF PAYMENT
Not later than delivery of the Vessel, any variations in the Contract Price ... but excluding any damages payable in accordance with Article III, will be calculated and the payment due upon delivery of the Vessel will be varied accordingly. At the same time and as a condition thereof the Builder will pay the Buyer any amount payable under Article III of this Contract.
5.PAYMENT FOR LIQUIDATED DAMAGES
Any amounts for liquidated damages under Article III shall be calculated and determined on delivery of the Vessel and shall be paid by the Builder to the Buyer on the Vessel's delivery.
ARTICLE III - DAMAGES
5.DEFICIENCY IN TRAILER CARRYING CAPACITY
In this Clause 5 `trailers' refers to fully laden trailers with a mean carrying capacity of thirty (30) mt.
(a)If the actual trailer carrying capacity of the Vessel is less than 146 Units of 13 metres each the Builder shall pay to the Buyer as liquidated damages One hundred and fifty thousand United States Dollars ($150,000) for each trailer unit by which the Vessel is deficient but excluding the first one (1) in respect of which deficiency no liquidated damages shall be payable. If the deficiency in trailer carrying capacity is ten (10) or more the Buyer as an alternative to receiving the aforementioned liquidated damages may rescind the Contract.
(b)In the event of deficiency in a deadweight and trailer carrying capacity the Buyer may elect whether to claim under sub clause 4 or sub clause 5 of this Article III.
ARTICLE X - WARRANTY QUALITY
1.GUARANTEE OF MATERIAL WORKMANSHIP AND DESIGN
The Builder for the period twelve (12) of months from the date of acceptance of delivery of the Vessel, guarantees the Vessel, her engines and accessories and all parts and equipment thereof, that are manufactured or furnished or supplied by the Builder or its Subcontractors under this Contract, against all defects which are due to faulty design (excluding matters of general arrangement and layout of accommodation or deck or machinery all insofar as operational convenience or ergonomics are concerned, defective material and/or poor workmanship and are not result of incompetence, mismanagement, negligence, accident or wilful neglect of the Buyer, or its agents and/or employees.
5.FRAME OF RESPONSIBILITY
The guarantees contained as herein above in this Article replace and exclude any other liability (and whether contractual or tortious, including liability for negligence), guarantee, warranty and/or condition imposed or implied by the law, customary, statutory, admiralty or otherwise, by reason of the construction and sale of the Vessel by the Builder for and to the Buyer."
"101 TYPE OF VESSEL
The vessel will be a RO-RO PASSENGER VESSEL designed and built for service in world wide traffic, carrying road trailers, cars and passengers as specified herebelow, with a capacity at least of 2,000 Lane meters, equivalent to 146 slots of 13m length, (width 3 meters), 47 Officers and Crewmen and 214 passengers, 114 in cabins and 100 in airline seats.
104 DESIGN CAPACITIES
(a)Cargo capacities
Lane meters (width 3m):
. On Upper Deck (8 lanes in breadth), about 1,075m
. On Main Deck (6 lanes in breadth), about875m
------
Total 2,000m (sic)
Road trailers (length: 13m; 30 t/trailer)
. On Upper Deck80 road trailers
. On Main Deck66 road trailers
----------
Total 146 road trailers
202 SCANTLING - GENERAL
Decks will be designed for the following deck loads:
Upper deck...(Trailers weight 45 t max)
Main deck... (Trailers weight 45 t max)"
(A)Trailer carrying capacity
(1)Since one of the purposes of a liquidated damages clause is to ease the calculation of damage, the builders were more likely to be correct. Any breach could be ascertained by a single act of measurement, whereas, on the buyers' construction, calculating the extent of the breach would be a complex operation. For the purpose of the trial, there had to be a practical exercise resulting in agreement between the experts that, on the basis of an extra length of 0.15 of a metre, ten fewer trailers could be loaded than, on the buyers' interpretation, the contract required.
(2)Nothing in the contract made any provision for the amount of extra space required for clearance and manoeuvrability purposes; it was unlikely that the builders would be intended to calculate this for themselves; it was only at trial that a figure of 0.15 of a metre had emerged, by way of agreement between the experts, after consideration of other figures.
(3)Since trailers of exactly 13 metres in length were rare and were on the evidence often greater or smaller in length, the figure of 13 metres could only have been intended to designate a notional average length. But the longer the trailer the more space would in fact be needed for clearance and manoeuvrability. The contract was, therefore, ambiguous as to whether the vessel was to accommodate any combination of trailers in the notionally extended space provided the overall average length was not more than 13 metres or whether it would suffice if at least one such combination could be accommodated.
(1)that the reference to 13 metre slots in Article I.4 of the contract was more naturally a reference to the length of the slot rather than the length of the trailer which was to fit into the slot;
(2)that the wording of the liquidated damages clause itself in Article III.5 specified payment of $150,000 "for each trailer unit by which the Vessel is deficient"; the word "unit" referred back to "146 Units of 13 metres each"; the trailer unit had, grammatically, to be a space since a vessel could correctly be said to be deficient in spaces but not to be deficient in trailers;
(3)that the absence of any reference in Article III.5 to the stipulated length being an average told against the buyers' contention;
(4)that Article V.1, in relation to the obligation of the builders to make requested modifications, was conditional on an agreement to any necessary adjustment of "the number of units of trailer carrying capacity"; in that clause also the word "units" had to refer to spaces rather than trailers;
(5)that the terms of paragraph 101 of the specification repeated the phrase "146 slots of 13m length" but this time in conjunction with the phrase "width 3 metres". There was no dispute that the width referred to the lanes in which trailers were to go and thus to the spaces in such lanes. What was true of width of spaces was also true for length of spaces.
(6)that, while paragraph 104 of the specification, if construed in isolation, lent some support to the buyers' contention, it had to be interpreted consistently with paragraph 101.
(1)The judge had excluded the phrase "freight capacity" from his consideration of Article I.4. Once that phrase was brought into the equation, it was clear that the slot measurement was a measurement of a unit of freight. The slot, therefore, had to accommodate a unit of freight of 13 metres; in other words, it had to accommodate a trailer of 13 metres.
(2)Likewise, the phrase "trailer unit by which the Vessel is deficient" in Article III.5 must refer to a trailer of 13 metres, especially since the clause took the trouble at its beginning to define the word "trailer", although the word did not appear in the clause itself.
(3)The same construction applied to Article V.1 if (which he denied) it was helpful to consider that clause at all.
(4)Paragraph 101 of the specification provided for a capacity of at least 2,000 lane meters which was said to be equivalent to 146 slots of 13-metre length. In fact, 146 slots of 13 metres gave an overall length of 1,898 metres. It was thus always contemplated that the slots would be longer than 13 metres. The fact that on this calculation each slot would have an additional length of 0.69 of a metre did not impinge on the allegation that the breach was failing to provide a slot of 13 metres plus 0.15 of a metre since that figure of 0.15 of a metre was merely the agreed figure for the purposes of calculating the liquidated damages.
(5)Paragraph 104 of the specification, to which the judge gave far too little weight, expressly referred to road trailers as having a length of 13 metres. This was a clear confirmation that 13 metres was intended to be the length of the trailer fitting into the slot and not the length of the slot itself. Paragraph 202, which specified that decks were to be designed for trailers with a maximum weight of 45 tons, showed that the figure of 30 tons for a trailer in paragraph 104 of the specification was a merely notional weight; likewise, the length of the trailer was a notional length, but it was that notional length of trailer that had to be accommodated in the slot.
(B)Breach of the provisions for contractual carrying capacity
(C)True construction of the liquidated damages clause
"So long as the sum payable in the event of non-compliance with a contract is not extravagant, having regard to the range of losses that it could be reasonably anticipated it [the relevant clause] would have to cover at the time the contract was made, it can still be a genuine pre-estimate of the loss that would be suffered and so a perfectly valid liquidated damage provision."
"A sum may, therefore, be regarded as penal if it might have become due on a trifling breach, even though the breach which actually occurred was quite a serious one, and one for which the sum could be regarded as a genuine pre-estimate. In this way, the rule can invalidate perfectly fair bargains. The courts will do their best to avoid such results by construing the contract so as to make the sum payable only on major breaches, for which it is a valid pre-estimate."
(D)Loss of right to rely on liquidated damages clause
Conclusion