England and Wales High Court (Administrative Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Administrative Court) Decisions >> Friends of the Earth Ltd & Anor, R (on the application of) v North Yorkshire County Council & Anor [2016] EWHC 3303 (Admin) (20 December 2016) URL: http://www.bailii.org/ew/cases/EWHC/Admin/2016/3303.html Cite as: [2017] Env LR 22, [2016] EWHC 3303 (Admin) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
PLANNING COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
THE QUEEN on the application of (1) FRIENDS OF THE EARTH LIMITED (2) FRACK FREE RYEDALE (BY DAVID DAVIS AND JACKIE CRAY) |
Claimants |
|
- and - |
||
NORTH YORKSHIRE COUNTY COUNCIL |
Defendant |
|
THIRD ENERGY UK GAS LIMITED |
Interested Party |
____________________
Sasha White QC and Gwion Lewis (instructed by Legal & Democratic Services) for the Defendant
Nathalie Lieven QC (instructed by Eversheds LLP) for the Interested Party
Hearing dates: 22 November and 23 November 2016
____________________
Crown Copyright ©
Mrs Justice Lang:
GROUNDS FOR JUDICIAL REVIEW
i) The Council unlawfully failed to take into account (as part of its consideration of the environmental impacts of the proposed development) an assessment of the material indirect/secondary/cumulative climate change impacts arising from the burning of the gas at Knapton in the production phase of the development.
ii) The Council misdirected itself in law that it could not require Third Energy to provide a financial bond in relation to any long term environmental pollution impacts arising from the fracking.
i) The Council was entitled not to consider the effects of emissions generated by burning the produced gas outside the Site for which planning permission was sought. Such emissions could not be calculated. In any event, any such emissions could not exceed the levels permitted at Knapton by the Environment Agency permits.ii) The Council was entitled to decide not to require Third Energy to provide a financial bond, and to conclude that the financing of restoration and aftercare would instead be dealt with adequately by conditions 35 to 38 of the planning permission.
GROUND 1: ENVIRONMENTAL IMPACT ASSESSMENT
Legal framework
"the environmental statement, including any further information and any other information, any representations made by any body required by these Regulations to be invited to make representations, and any representations duly made by any other person about the environmental effects of the development."
"(a) that includes such information referred to in Part 1 of Schedule 4 as is reasonably required to assess the environmental effects of the development and which the applicant can, having regard in particular to current knowledge and methods of assessment, reasonably be required to compile, but
(b) that includes at least the information referred to in Part 2 of Schedule 4."
Thus, the information required under Part 1 is such as is "reasonably required" whereas the information required under Part 2 is a mandatory minimum requirement.
"Information for inclusion in environmental statements
Part 1
1. Description of the development, including in particular:
(a) a description of the physical characteristics of the whole development and the land-use requirements during the construction and operational phases;
(b) a description of the main characteristics of the production processes, for instance, nature and quantity of the materials used;
(c) an estimate, by time and quantity, of expected residues and emissions (water, air and soil pollution, noise, vibration, light, heat, radiation, etc.) resulting from the operation of the proposed development.
2. An outline of the main alternatives studied by the applicant or appellant and an indication of the main reasons for the choice made, taking into account the environmental effects.
3. A description of the aspects of the environment likely to be significantly affected by the development, including, in particular, population, fauna, flora, soil, water, air, climatic factors, material assets, including the architectural and archaeological heritage, landscape and the inter-relationship between the above factors.
4. A description of the likely significant effects of the development on the environment which should cover the direct effects and any indirect, secondary, cumulative, short, medium and long-term, permanent and temporary, positive and negative effects of the development, resulting from:
(a) the existence of the development;
(b) the use of natural resources;
(c) the emission of pollutants, the creation of nuisances and the elimination of waste,
and the description by the applicant of the forecasting methods used to assess the effects on the environment.
5. A description of the measures envisaged to prevent, reduce and where possible offset any significant adverse effects on the environment.
6. A non-technical summary of the information provided under paragraphs 1 to 5 of this Part.
7. An indication of any difficulties (technical deficiencies or lack of know-how) encountered by the applicant in compiling the required information.
Part 2
1. A description of the development comprising information on the site, design and size of the development.
2. A description of the measures envisaged in order to avoid, reduce and, if possible, remedy significant adverse effects.
3. The data required to identify and assess the main effects which the development is likely to have on the environment.
4. An outline of the main alternatives studied by the applicant or appellant and an indication of the main reasons for his choice, taking into account the environmental effects.
5. A non-technical summary of the information provided under paragraphs 1 to 4 of this Part."
"56. In dealing with the submissions that I have summarised, I deal first with the issue of the legality of the decision to grant planning permission. In considering that issue, the starting point must be Regulation 3, which provides that the relevant planning authority shall not grant planning permission for an EIA development unless they have first taken the environmental information into consideration. By virtue of Regulation 2(1), environmental information includes the environmental statement which itself has to include the information referred to in Part II of Schedule 4 to the Regulations. I agree with Sullivan J. that it is for the relevant planning authority to judge the adequacy of the environmental information, subject of course to review by the courts on the normal Wednesbury principles, but information that is capable of meeting the requirements of Part II of Schedule 4 to the Regulations must be provided and considered by the planning authority before planning permission is granted.
57. Paragraphs 1 to 3 of Part II of Schedule 4 are not, it seems to me, in a logically correct sequence. Firstly, the environmental statement must contain a description of the development (paragraph 1). Secondly, it must contain the data required to identify and assess the main effects which the development is likely to have on the environment (paragraph 3). Thirdly, it must contain a description of the measures envisaged to avoid, reduce and, if possible, remedy significant adverse effects (paragraph 2). The requirement to provide the paragraph 2 information relating to the measures to be taken does not arise if, in the planning authority's view, there are no "significant adverse effects". Similarly, the requirement to provide the paragraph 3 information relating to the data does not arise if, in the planning authority's view, it is not required to identify and assess the "main effects" of the development.
58. Applying those principles to the facts of this case, if the nature conservation aspects relating to the bats, badgers and liverwort did not involve "significant adverse effects", there would be no requirement for the environmental statement to contain the measures envisaged to deal with them and no duty on the respondent to consider those measures before granting planning permission. Similarly, if those nature conservation aspects did not amount to "main effects" there would be no requirement for the environmental statement to contain the data to assess them and no duty on the respondent to consider that data before granting planning permission. It is therefore necessary to consider whether the respondent could rationally conclude that those nature conservation aspects did not amount to "significant adverse effects" or "main effects"."
"32. Where there is a document purporting to be an environmental statement, the starting point must be that it is for the local planning authority to decide whether the information contained in the document is sufficient to meet the definition of an environmental statement…..
33. The local planning authority's decision is, of course, subject to review on normal Wednesbury principles: see R v Cornwall CC, ex p. Hardy [2001] JPL 786, per Harrison J. at para [65], applying R v Rochdale MBC, Ex p. Milne [2001] Env. LR 416 at para [106].
34. Information capable of meeting the requirements of Sch. 4 to the Regulations must be provided: see Hardy (ibid) and R v Rochdale MBC Ex p. Tew [1999] 3 PLR 74 at 95G.
…..
38. The Regulations envisage that the applicant for planning permission will produce the environmental statement. It follows that the document will contain the applicant's own assessment of the environmental impact of his proposal and the necessary mitigation measures. The Regulations recognise that the applicant's assessment of these issues may well be inaccurate, inadequate or incomplete. Hence the requirements in Regulation 13 to submit copies of the environmental statement to the Secretary of State and to any body which the local planning authority is required to consult. Members of the public will be informed by site notice and by local advertisement of the existence of the environmental statement and able to obtain or inspect a copy: see Regulation 17 of the Regulations and Article 8 of the Town and Country Planning (General Development Procedure) Order 1995.
39. This process of publicity and public consultation gives those persons who consider that the environmental statement is inaccurate or inadequate or incomplete an opportunity to point out its deficiencies. Under Regulation 3(2) the local planning authority must, before granting planning permission, consider not merely the environmental statement, but "the environmental information", which is defined by Regulation 2 as "the environmental statement, including any further information, any representations made by any body required by these Regulations to be invited to make representations, and any representations duly made by any other person about the environmental effects of the development".
40. In the light of the environmental information the local planning authority may conclude that the environmental statement has failed to identify a particular environmental impact, or has wrongly dismissed it as unlikely, or not significant. Or the local planning authority may be persuaded that the mitigation measures proposed by the applicant are inadequate or insufficiently detailed. That does not mean that the document described as an environmental statement falls outwith the definition of an environmental statement within the Regulations so as to deprive the authority of jurisdiction to grant planning permission. The local planning authority may conclude that planning permission should be refused on the merits because the environmental statement has inadequately addressed the environmental implications of the proposed development, but that is a different matter altogether. Once the requirements of Schedule 4 are read in the context of the Regulations as a whole, it is plain that a local planning authority is not deprived of jurisdiction to grant planning permission merely because it concludes that an environmental statement is deficient in a number of respects.
41. Ground 1 in these proceedings is an example of the unduly legalistic approach to the requirements of Schedule 4 to the Regulations that has been adopted on behalf of claimants in a number of applications for judicial review seeking to prevent the implementation of development proposals. The Regulations should be interpreted as a whole and in a common-sense way. The requirement that "an EIA application" (as defined in the Regulations) must be accompanied by an environmental statement is not intended to obstruct such development. As Lord Hoffmann said in R v North Yorkshire County council ex parte Brown [2000] 1 AC 397, at page 404, the purpose is 'to ensure that planning decisions which may affect the environment are made on the basis of full information'. In an imperfect world it is an unrealistic counsel of perfection to expect that an applicant's environmental statement will always contain the "full information" about the environmental impact of a project. The Regulations are not based upon such an unrealistic expectation. They recognise that an environmental statement may well be deficient, and make provision through the publicity and consultation processes for any deficiencies to be identified so that the resulting 'environmental information' provides the local planning authority with as full a picture as possible. There will be cases where the document purporting to be an environmental statement is so deficient that it could not reasonably be described as an environmental statement as defined by the Regulations (Tew was an example of such a case), but they are likely to be few and far between.
42. It would be of no advantage to anyone concerned with the development process – applicants, objectors or local authorities – if environmental statements were drafted on a purely 'defensive basis', mentioning every possible scrap of environmental information just in case someone might consider it significant at a later stage. Such documents would be a hindrance, not an aid to sound decision-making by the local planning authority, since they would obscure the principal issues with a welter of detail."
Conclusions
The Scoping Opinion
i) Pre-Stimulation Workoverii) Hydraulic Fracture Stimulation
iii) Production Test
iv) Production
v) Site Restoration.
"The scoping of the project has been carried out on the basis of the information submitted by …. Third Energy UK Gas Ltd in their Scoping Request.
…..
The Applicant has proposed a range of assessment requirements to be included in the Supporting Statement to the Application and the Environmental Statement. It is considered that the Scoping set out in that letter broadly covers all the main environmental and cumulative impacts of the proposed development….. There are particular aspects which the County Council consider should be addressed in more detail. These are highlighted in the section below and take account of the responses of consultee organisations."
"Air Quality
This impact has been proposed to be 'scoped' into the prospective Environmental Statement citing reference to the need to assess "emissions from generators, emissions from vehicles transporting equipment, materials, personnel and waste to and from the site and also potential for fugitive emissions from the well". However, regard should also be had to the responses to consultation relating to matters of air quality including dust, odour and any other fugitive emissions arising from any aspect of the proposed development as well as the specific queries which have been raised; including concerns relating to radon and/or methane gas leakage, other noxious emissions, and use of chemicals in the 'fracking' process. Particular regard should be had to the comments within the Environment Agency's consultation response dated 24th February 2015, that of Ryedale District Council and Public Health England (both received on 26th February 2015), that of the Director of Public Health at the County Council (received on 23rd February 2015) and the consultation response of Natural England dated 16th February 2015."
"Climate change (including greenhouse gas emissions)
This impact has been proposed to be 'scoped' into the prospective Environmental Statement citing reference to the need to assess the potential for impact from each phase of the proposed development. In particular, regard should be had to the responses to consultation relating to matters of how the proposed development is compatible with the climate change agenda and the nation's carbon reduction targets. Particular regard should be had to the comments on climate change adaption made by Natural England in its response dated 16th February 2015."
"General comments resulting from the consultation exercise also include recommendations that every aspect of the proposed development must be assessed with regard to its potential environmental impacts including, for example, the use of the existing underground pipeline as mentioned in the Scoping Request documentation that those impacts should have regard to each stage of the proposed development from commencement of construction through to cessation of operations, site restoration and on-going management and monitoring in the short-, medium- and long-term. Furthermore, an outline of the main alternatives as well as an indication of the main reasons for the choice of site, taking into account the environmental effects, should be provided ….."
"Greenhouse Gases
We note from Section 5.5.5 that an assessment of the impacts of greenhouse gas emissions will be produced. We understand that gas from the KM8 well will be captured and sent via the existing pipeline to Knapton Generating Station and as such no flaring of gas at the site is proposed. In Table 17 the applicant has described the risk of fugitive emissions as 'negligible'."
The Environmental Statement
"EXECUTIVE SUMMARY
- The proposed development is being undertaken within an existing wellsite where multiple drilling operations, natural gas production and the injection of produced liquids have been undertaken over the last 20 years
- The proposed development does not contemplate flaring of natural gas. Natural gas will be exported off site via an existing underground pipeline to Knapton Generating Station where it will be used to generate electricity.
- The impact from greenhouse gases has been assessed for all five (5) phases of the proposed development, although the potential impact will be greatest during the first two phases, pre-stimulation workover and hydraulic fracture stimulation/well test.
- A baseline for greenhouse gases has been established using both contextual data and baseline air quality monitoring. The total greenhouse gas emissions emitted in 2013 from the energy supply sector was 189.7 MtCO2 equivalent (189,700,000 tonnes).
- Embedded mitigation is incorporated into the development proposals through the design and construction of the KM8 borehole in accordance with the applicable regulation, a vigorous equipment maintenance and monitoring programme by the Applicant, the short term temporary eight (8) week duration of the pre-stimulation workover and hydraulic fracture stimulation/well test phases and the monitoring of natural gases, with associated process controls.
- Additional mitigation is provided by way of competent supervision, best industry practice and monitoring.
- The expected release rate of greenhouse gases during the proposed development will be circa 1,680 tCO2 equivalent with the maximum upper estimate of 2,602 tCO2 equivalent. The maximum upper estimate equates to a percentage contribution of 0.0014% to the total UK greenhouse gas emission from the energy supply sector in 2013.
- The residual effects from greenhouse gases with mitigation in place are considered by the Assessment Team to range from Neutral/Slight to Slight with the potential for a Negligible change in the baseline conditions."
"12.26 An assessment is needed, based on the whole project. This application has merely added up the greenhouse gases during the development and production stages ….neglecting the CO2 emissions of gas produced from the project is misleading.
12.27 The assessment needs to include the real dangers of the whole scheme and not just the carbon footprint of the development and extraction process. The project involves release of fossil hydrocarbons. The current submission is therefore underestimating the quantities of greenhouse gases by orders of magnitude.
12.28 There is no attempt at a risk assessment to consider the impact of those greenhouse gases. The clear intention is that the fuel will be burnt and the waste CO2 will be emitted to the atmosphere in a decade when it is clear that National and International policy is to cut such emissions…"
"1.9 Impacts from the Knapton generating station should be assessed through EIA in addition because a "functional connection" exists between the generating station and the fracking site. Leading case law makes clear that "proposals should not be considered in isolation if in reality it is properly to be regarded as an integral part of an inevitably more substantial development" (Swale BC ex p. RSPB [1991] 1 PLR 6. The courts have also made clear that sites which are "functionally interdependent" must be assessed as a single project. (R (Burridge) v Breckland DC [2013] EWCA Civ 228).
1.10 In this case, the functional connection …. arises out of the supply of fresh water from Knapton in order to frack and the return flow of gas to the station to burn so as to generate electricity. The applicant should therefore assess the emissions, including the greenhouse gas emissions from the Knapton station so far as these are occasioned by or connected to the application as well as other environmental impacts in accordance with the [EIA Directive]."
"31. It is well established that planning officers' reports to committee must be read not in an unduly critical way, but fairly and as a whole. Councillors on planning committees can be expected to be reasonably familiar with local circumstances and with relevant policies at national and local level, and to understand what statute requires of them when determining an application for planning permission. If criticism is directed at an officer's report as a means of attacking an authority's grant of planning permission, the question for the court will always be whether the officer has failed to guide the members sufficiently, or has actually misled them, on a matter essential to their decision. Where the officer's advice is founded on planning judgment it will be unassailable unless demonstrably bad as a matter of law. There is ample authority to this effect (see, for example, the judgments of Pill L.J. and Judge L.J., as he then was, in Oxton Farms, Samuel Smith's Old Brewery (Tadcaster) v Selby District Council, 18 April 1997 , 1997 WL 1106106)."
"90. A great many of LBC's grounds involve criticisms of the officers' reports to CBC's committee. Accordingly, it is necessary to refer to the legal principles which govern challenges of this kind. I gratefully adopt the summary given by Mr Justice Hickinbottom in the case of The Queen (Zurich Assurance Ltd trading as Threadneedle Property Investments) –v- North Lincolnshire Council [2012] EWHC 3708 (Admin) at paragraphs 15-16:
"15. Each local planning authority delegates its planning functions to a planning committee, which acts on the basis of information provided by case officers in the form of a report. Such a report usually also includes a recommendation as to how the application should be dealt with. With regard to such reports:
(i) In the absence of contrary evidence, it is a reasonable inference that members of the planning committee follow the reasoning of the report, particularly where a recommendation is adopted.
(ii) When challenged, such reports are not to be subjected to the same exegesis that might be appropriate for the interpretation of a statute: what is required is a fair reading of the report as a whole. Consequently:
"[A]n application for judicial review based on criticisms of the planning officer's report will not normally begin to merit consideration unless the overall effect of the report significantly misleads the committee about material matters which thereafter are left uncorrected at the meeting of the planning committee before the relevant decision is taken" (Oxton Farms, Samuel Smiths Old Brewery (Tadcaster) v Selby District Council (18 April 1997) 1997 WL 1106106, per Judge LJ as he then was).
(iii) In construing reports, it has to be borne in mind that they are addressed to a "knowledgeable readership", including council members "who, by virtue of that membership, may be expected to have a substantial local and background knowledge" (R v Mendip District Council ex parte Fabre (2000) 80 P & CR 500, per Sullivan J as he then was). That background knowledge includes "a working knowledge of the statutory test" for determination of a planning application (Oxton Farms, per Pill LJ).
16. The principles relevant to the proper approach to national and local planning policy are equally uncontroversial:
(i) The interpretation of policy is a matter of law, not of planning judgment (Tesco Stores Ltd v Dundee City Council [2012] UKSC 13).
(ii) National planning policy, and any relevant local plan or strategy, are material considerations; but local authorities need not follow such guidance or plan, if other material considerations outweigh them.
(iii) Whereas what amounts to a material consideration is a matter of law, the weight to be given to such considerations is a question of planning judgment: the part any particular material consideration should play in the decision-making process, if any, is a matter entirely for the planning committee (Tesco Stores Ltd v Secretary of State for the Environment [1995] 1 WLR 759 at page 780 per Lord Hoffman)."
91. I would also draw together some further citations:
"[The purpose of an officer's report] is not to decide the issue, but to inform the members of the relevant considerations relating to the application. It is not addressed to the world at large but to council members, who, by virtue of that membership, may be expected to have substantial local and background knowledge. There would be no point in a planning officer's report setting out in great detail background material, for example in respect of local topography, development plan policies or matters of planning history if the members were only too familiar with that material. Part of a planning officer's expert function in reporting to the committee must be to make an assessment of how much information needs to be included in his or her report in order to avoid burdening a busy committee with excessive and unnecessary detail." (per Sullivan J in R v Mendip DC ex p Fabre (2000) 80 P&CR 500 at 509).
92. In R (Siraj) v Kirkless MBC [2010] EWCA Civ 1286 Sullivan LJ stated at para. 19:
"It has been repeatedly emphasised that officers' reports such as this should not be construed as though they were enactments. They should be read as a whole and in a common sense manner, bearing in mind the fact that they are addressed to an informed readership, in this case the respondent's planning subcommittee"
93. In R (Maxwell) -v- Wiltshire Council [2011] EWHC 1840 (Admin) at paragraph 43 Sales J (as he then was) stated:
"The Court should focus on the substance of a report of officers given in the present sort of context, to see whether it has sufficiently drawn councillors' attention to the proper approach required by the law and material considerations, rather than to insist upon an elaborate citation of underlying background materials. Otherwise, there will be a danger that officers will draft reports with excessive defensiveness, lengthening them and over-burdening them with quotations of material, which may have a tendency to undermine the willingness and ability of busy council members to read and digest them effectively."
94 In Morge v Hants CC [2011] UKSC 2; [2011] PTSR 337 at [36] Baroness Hale of Richmond said:
"…in this country planning decisions are taken by democratically elected councillors, responsible to, and sensitive to the concerns of, their local communities. As Lord Hoffmann put it in R (Alconbury Developments Ltd) v Secretary of State for the Environment, Transport and the Regions [2003] 2 AC 295, para 69: "In a democratic country, decisions about what the general interest requires are made by democratically elected bodies or persons accountable to them." Democratically elected bodies go about their decision-making in a different way from courts. They have professional advisers who investigate and report to them. Those reports obviously have to be clear and full enough to enable them to understand the issues and make up their minds within the limits that the law allows them. But the courts should not impose too demanding a standard upon such reports, for otherwise their whole purpose will be defeated: the councillors either will not read them or will not have a clear enough grasp of the issues to make a decision for themselves. It is their job, and not the court's, to weigh the competing public and private interests involved."
95. In R (Bishops Stortford Federation) v East Herts DC [2014] PTSR 1035 Cranston J held at paragraph 40:
"The courts have cautioned against undue judicial intervention in policy judgments by expert tribunals within their areas of special competence (see AH (Sudan) v Secretary of State for the Home Department (United Nations High Comr for Refugees intervening) [2008] AC 678, para 30, per Baroness Hale of Richmond), and this reticence has been applied to considering the decisions of planning inspectors on issues of planning judgment: see Wychavon District Council v Secretary of State for Committees and Local Government [2009] PTSR 19, para 43, per Carnwath LJ. Arguably, the same applies to experienced planning committees with their training and codes of conduct." "
i) European legislation on environmental protection.ii) National legislation and policy on meeting climate change objectives by cutting greenhouse gases and moving away from fossil fuels (including gas) towards clean renewable energy supplies.
iii) National policy in favour of shale gas.
iv) National planning policy on meeting the challenges of climate change and support for a transition to a low carbon future in the NPPF and the Planning Practice Guidance ("PPG").
"UPON CONSIDERING that the Environmental Statement, including further and other information submitted by the applicant, includes such information as is reasonably required to assess the environmental effect of the development and which the applicant could be reasonably required to compile; and
HAVING TAKEN INTO ACCOUNT the environmental information relating to this application, namely the Environmental Statement, including further and other information submitted by the applicant, and duly made representations about the environmental effects of the development;"
The resolution clearly evidences the Committee's consideration of the ES and its conclusion that the ES was adequate.
GROUND 2: FINANCIAL BOND
"Notwithstanding the merit within seeking a mechanism for ensuring that key obligations are met in the event that the developer is unable (including a circumstance of company failure) and providing reassurance that obligations will be met the County Planning Authority is advised that this [i.e. the ability to require a bond or similar] is engaged in this particular instance but such a mechanism cannot be used in the circumstances as called for by those opposing the proposed development."
"1. What are mineral resources and why is planning permission required?
…
Planning for the supply of minerals has a number of special characteristics that are not present in other development:
…..
- working is a temporary use of land, although it often takes place over a long period of time;
…..
- following working, land should be restored to make it suitable for beneficial after-use.
….
The mineral planning authority is the county council (in two-tier parts of the country), the unitary authority, or the national park authority. Minerals extraction may only take place if the operator has obtained both planning permission and any other permits and approvals. These include permits from bodies such as the Environment Agency, and licenses from Natural England and, in relation to coal resources, the Coal Authority.
…
12. What is the relationship between planning and other regulatory regimes?
The planning and other regulatory regimes are separate but complementary. The planning system controls the development and use of land in the public interest and, as stated in paragraphs 120 and 122 of the National Planning Policy Framework, this includes ensuring that new development is appropriate for its location – taking account of the effects (including cumulative effects) of pollution on health, the natural environment or general amenity, and the potential sensitivity of the area or proposed development to adverse effects from pollution.
In doing so the focus of the planning system should be on whether the development itself is an acceptable use of the land, and the impacts of those uses, rather than any control processes, health and safety issues or emissions themselves where these are subject to approval under regimes. Mineral planning authorities should assume that these non-planning regimes will operate effectively.
….
Restoration and aftercare of minerals sites
36. Who is responsible for restoration and aftercare of minerals sites?
Responsibility for the restoration and aftercare of mineral sites, including financial responsibility, lies with the minerals operator and, in the case of default, with the landowner.
37. When should site restoration and aftercare be considered?
The most appropriate form of site restoration to facilitate different potential after uses should be addressed in both local minerals plans, which should include policies to ensure worked land is reclaimed at the earliest opportunity and that high quality restoration and aftercare of mineral sites takes place, and on a site-by-site basis following discussions between the minerals operator and the mineral planning authority
38. What are the key stages that must be considered when considering restoration and aftercare conditions?
Restoration and aftercare of mineral sites involves a number of key stages, which mineral planning authorities should take into account as appropriate when preparing restoration and aftercare conditions:
- stripping of soils and soil-making materials and either their storage or their direct replacement (i.e. 'restoration') on another part of the site;
- storage and replacement of overburden;
- achieving the landscape and landform objectives for the site, including filling operations if required, following mineral extraction;
- restoration, including soil placement, relief of compaction and provision of surface features;
- aftercare.
39. When should proposals for land restoration and aftercare be submitted to the mineral planning authority?
The minerals operator should submit the proposals as part of the planning application (section 72 and Schedule 5 of the Town and Country Planning Act 1990 advise on the conditions which may be imposed on the grant of planning permission for development consisting of the winning and working of minerals).
…
41. How should the mineral planning authority ensure that applicants will deliver sound restoration and aftercare proposals?
Mineral planning authorities should secure the restoration and aftercare of a site through imposition of suitable planning conditions and, where necessary, through planning obligations.
42. How must mineral planning authorities frame planning conditions for restoration and aftercare?
Conditions must be drafted in such a way that, even if the interest of the applicant applying for permission is subsequently disposed of, the requirements for restoration and aftercare can still be fulfilled, whether by a new operator or in the case of default, by the land-owner.
…
44. How detailed should restoration and aftercare planning conditions be for long-term extraction?
For mineral extraction sites where expected extraction is likely to last for many years, early agreement on the details of at least the later stages of aftercare may not be appropriate. In such cases, it would still be appropriate:
- for the applicant to provide a general outline of the final landform and intended after-use;
- for the mineral planning authority to agree at the outset outlines of requirements covering the main stages of reclamation of a site (e.g. filling, restoration and aftercare), together with detailed schemes for stripping and storage of soil materials
The level of detail provided by the applicant to the mineral planning authority must be sufficient to clearly demonstrate that the overall objectives of the scheme are practically achievable.
Planning conditions for proposals with a longer term duration should:
- normally require the submission of a detailed scheme or schemes for restoration and aftercare, for agreement, by some specific stage towards the end of the life of the permission;
- where progressive reclamation is to be carried out, require submission of schemes for agreement from time to time as appropriate.
…
47. How should mineral planning authorities deal with any concerns about funding of site restoration or aftercare?
Mineral planning authorities should address any concerns about the funding of site restoration principally through appropriately worded planning conditions.
48. When is a financial guarantee justified?
A financial guarantee to cover restoration and aftercare costs will normally only be justified in exceptional cases. Such cases, include:
- very long-term new projects where progressive reclamation is not practicable, such as an extremely large limestone quarry;
- where a novel approach or technique is to be used, but the minerals planning authority considers it is justifiable to give permission for the development;
- where there is reliable evidence of the likelihood of either financial or technical failure, but these concerns are not such as to justify refusal of permission.
However, where an operator is contributing to an established mutual funding scheme, such as the Mineral Products Association Restoration Guarantee Fund or the British Aggregates Association Restoration Guarantee Fund, it should not be necessary for a minerals planning authority to seek a guarantee against possible financial failure, even in such exceptional circumstances.
49. How and when should minerals planning authorities seek a financial guarantee?
Mineral planning authorities should seek to meet any justifiable and reasonable concerns about financial liabilities relating to the restoration of the site through agreeing a planning obligation or voluntary agreement at the time a planning permission is given.
Aftercare conditions
50. What is the purpose of aftercare conditions?
Aftercare conditions are required to ensure that, following site restoration, the land is brought up to the required standard which enables it to be used for the intended after use.
51. What is the appropriate form of aftercare conditions?
Mineral planning authorities may impose aftercare conditions in one of two ways:
- at the time of granting planning permission, specifying detailed steps to be taken; or
- through a planning condition which requires an aftercare scheme to be submitted by the applicant or other appropriate person for approval.
52. What are the limitations imposed on aftercare conditions?
There are several limitations imposed on aftercare conditions, as follows:
- they may only be imposed on permissions in conjunction with a restoration condition;
- they may only be imposed in relation to land which is to be used for agriculture, forestry or amenity (including biodiversity) following minerals working;
- they can require only planting, cultivating, fertilising, watering, draining or otherwise treating the land;
- they can only start following compliance with a restoration condition and the mineral planning authority cannot require any steps to be taken after the end of a five year aftercare period without the agreement of the minerals operator (Schedule 5 of the Town and Country Planning Act 1990 sets out the conditions relating to mineral working).
53. How do aftercare conditions apply where progressive restoration takes place?
Where sites are subject to progressive restoration, the aftercare period for each part of the site will begin once the restoration condition for the relevant part of the site has been met."
"Financial commitment – Restoration Scheme – details to be submitted
35. No development authorised by this planning permission shall take place within the site until such time as a detailed scheme for the restoration and aftercare of the KM8 well site has been submitted to and approved by the County Planning Authority. The approved restoration and aftercare measures shall provide any necessary financial commitment required by the applicant to secure the approved scheme and these arrangements shall be retained for the duration of the development programme and for a minimum of six (6) months from the cessation of any authorised works at the KM8 well site.
Reason:
This is a pre-commencement condition and one which is considered warranted given the particular circumstance of this case and also that the securing of a financial commitment is considered necessary in this instance by virtue of the need to have the security that funds would be in place should a circumstance arise that the restoration and/or after-care of the site should fall to the 'public purse'.
36. The restoration scheme and aftercare measures approved under condition number 35 above shall be carried out in accordance with the general approach to restoration and aftercare set out in Environmental Statement Appendix 10, together with a timescale for the work, and proposals for phasing of restoration if likely to be needed. The site access shall be removed and the land restored to a condition suitable for agricultural cultivation in accordance with approved details unless prior approval is obtained for retention of access for agricultural purposes. Restoration shall be implemented within six (6) months of the cessation of gas production. Upon completion of the restoration scheme, an application shall be submitted to the County Planning Authority to restore the route of public right of way 25.53/4/1 to its original route, having been diverted in 2013 to allow the construction of the Kirby Misperton 1 wellsite extension.
Reason:
In accordance with Annex 3 ('Model planning conditions for surface area') of Part 9 within Section 27 of the National Planning Practice Guidance and in order to ensure that the restoration of the site is undertaken in accordance with the approved details and in a timely manner to avoid undue delay in the restoration of the site.
After-care Scheme – details to be submitted
37. Within six (6) months of the certification in writing by the County Planning Authority of the completion of restoration, as defined in this permission, a scheme and programme for the aftercare of the site shall be submitted to the County Planning Authority for approval in writing. The scheme and programme shall contain details of the following:
a. maintenance and management of the restored site to promote its agricultural, forestry or amenity use.
b. weed control where necessary.
c. measures to relieve compaction or improve drainage.
d. an annual inspection to be undertaken in conjunction with representatives of the County Planning Authority to assess the aftercare works that are required in the following year.
Reason:
In accordance with Annex 3 ('Model planning conditions for surface area') of Part 9 within Section 27 of the National Planning Practice Guidance and in order to ensure that aftercare of the site is undertaken in accordance with the approved details and to ensure the land is returned to a satisfactory after-use.
Management of the restored land for a period of five (5) years
38. The Site shall be restored in accordance with the approved restoration scheme and the Site thereafter managed in accordance with the approved 5 year aftercare programme, unless otherwise agreed in writing with the County Planning Authority. The aftercare period shall commence from the date that the County Planning Authority confirms that the restoration works have been carried out and fully implemented in accordance with approved details.
Reason:
In order to ensure the right of control of the development by the County Planning Authority in the interest of the satisfactory restoration and beneficial after-use of the site."
CONCLUSIONS