England and Wales High Court (Commercial Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Commercial Court) Decisions >> Saudi Arabian Airlines Corporation v Sprite Aviation No. 6 DAC [2024] EWHC 371 (Comm) (13 March 2024) URL: http://www.bailii.org/ew/cases/EWHC/Comm/2024/371.html Cite as: [2024] EWHC 371 (Comm) |
[New search] [Printable PDF version] [Help]
KING'S BENCH DIVISION
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
COMMERCIAL COURT
Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
SITTING AS A JUDGE OF THE HIGH COURT
____________________
SAUDI ARABIAN AIRLINES CORPORATION |
Claimant |
|
- and - |
||
SPRITE AVIATION NO. 6 DAC |
Defendant |
____________________
Edward Cumming KC and Catherine Hartston (instructed by Pillsbury Winthrop Shaw Pittman LLP) for the Defendant
Hearing date: 5 December 2023
____________________
Crown Copyright ©
Christopher Hancock KC:
Introduction.
"On the proper interpretation of the CTA [the Common Terms Agreement], as defined in the Particulars of Claim, was Sprite [the Defendant] obliged to make payments in respect of maintenance work under clause 7.2 of the CTA if Saudia [the Claimant] did not ensure that Sprite received an invoice and supporting documentation reasonably satisfactory to Sprite evidencing performance of the maintenance work before the Expiry Date? This includes, for the avoidance of doubt, any issue as to whether time was of the essence for this purpose, as expressly stipulated at clause 15.6 of the CTA, or otherwise."
The background facts.
"7.2 Maintenance Contributions
If, under the Lease for the Aircraft, Lessee must pay Supplemental Rent, then provided no Event of Default has occurred and is continuing, Lessor will pay the following amounts to Lessee by way of contribution to the cost of maintenance of the Aircraft, upon receipt by Lessor, within six months after commencement of such maintenance and before the Expiry Date, of an invoice and supporting documentation reasonably satisfactory to Lessor evidencing performance of the following work by the Maintenance Performer:…
(c) Engine Refurbishment: With respect to any Engine, the performance, in accordance with the Lease, of Engine Refurbishment in respect of that Engine the lesser of (i) the amount of that invoice and (ii) an amount equal to the aggregate amount of the Engine Supplemental Rent paid under the Lease in respect of that Engine at the date such work starts less the aggregate amount previously paid in respect of that Engine by Lessor under this sub-clause;
[like clauses following dealt with the APU and landing gear]
…Lessor agrees to make the contributions provided for under this Clause 7.2 on the basis that Lessee accepts full responsibility for, and is obliged to undertake, all maintenance, replacement and repair work (including the obligations under Clauses 8.10, 8.11 and Schedule 6)."…
…15.6
"The time stipulated in the Lease for all payments payable by Lessee and the prompt, punctual performance of Lessee's other obligations under the Lease are of the essence of the Lease."
Relevant principles of contractual interpretation.
"29. The parties referred specifically to what Lord Neuberger had said at paragraphs 15 and 19 of Arnold in relation to the interpretation of a lease as follows:-
"15. When interpreting a written contract, the court is concerned to identify the intention of the parties by reference to "what a reasonable person having all the background knowledge which would have been available to the parties would have understood them to be using the language in the contract to mean", to quote Lord Hoffmann [at paragraph 14 in Chartbrook Ltd v. Persimmon Homes Ltd [2009] 1 AC 1101]. And it does so by focussing on the meaning of the relevant words … in their documentary, factual and commercial context. That meaning has to be assessed in the light of (i) the natural and ordinary meaning of the clause, (ii) any other relevant provisions of the lease, (iii) the overall purpose of the clause and the lease, (iv) the facts and circumstances known or assumed by the parties at the time that the document was executed, and (v) commercial common sense, but (vi) disregarding subjective evidence of any party's intentions.
19. The third point I should mention is that commercial common sense is not to be invoked retrospectively. The mere fact that a contractual arrangement, if interpreted according to its natural language, has worked out badly, or even disastrously, for one of the parties is not a reason for departing from the natural language. Commercial common sense is only relevant to the extent of how matters would or could have been perceived by the parties, or by reasonable people in the position of the parties, as at the date that the contract was made. …
20. Fourthly, while commercial common sense is a very important factor to take into account when interpreting a contract, a court should be very slow to reject the natural meaning of a provision as correct simply because it appears to be a very imprudent term for one of the parties to have agreed, even ignoring the benefit of wisdom of hindsight. The purpose of interpretation is to identify what the parties have agreed, not what the court thinks that they should have agreed. … Accordingly, when interpreting a contract a judge should avoid re-writing it in an attempt to assist an unwise party or to penalise an astute party.
30. Both parties also referred to the iterative process that should be engaged when interpreting documentation relating to collateral loan obligations and the like. That process involves checking each of the rival meanings against other provisions of the document and investigating its commercial consequences (see Re Sigma Finance Corp [2010] 1 All ER 571 ("Sigma") per Lord Mance at paragraph 12 and Lord Collins at paragraph 37, and Rainy Sky per Lord Clarke at paragraph 28). " "
The parties' respective cases.
Sprite's contentions.
(1) If the Lessee, Saudia, did not provide any invoice or supporting documentation to the Lessor, Sprite, so that it received the same (i) within six months of the commencement of any of the work in respect of which it seeks a contribution, or, in any event, (ii) before the Expiry Date (in August 2019), Saudia would not be entitled to the payment of the contribution.
(2) This was not only apparent from the words that the parties chose to use in their bargain, but because of the obvious need for contractual and commercial certainty in the complex and sophisticated world of aircraft leasing and finance.
(3) It made perfect commercial sense for the parties to have stipulated time limits prior to which the Lessee, Saudia, was obliged to seek a contribution from the Lessor if it was to seek one. Otherwise, there would be the prospect of (i) unedifying and unduly complex disputes (of the kind that will arise in these proceedings, if Sprite fails on the preliminary issue) regarding the scope and cost of maintenance work, potentially many years after work had taken place, and potentially after any commercial relationship between the parties had ended and the aircraft had been delivered to, and operated by, other third parties, such that it would be hard for such disputes to be effectively adjudicated, and (ii) Sprite having ongoing uncertainty, after the Expiry Date of the Lease, as to its financial obligations in respect of the Aircraft, where that uncertainty would stand to cause real challenges for Sprite in considering what approach to take to the future leasing-out of the Aircraft.
(4) In this latter regard, the requirement for Saudia to have ensured that Sprite received any invoices or other documentation before the Expiry Date can be seen as imposing, essentially, a practical 'long-stop date' by when this had to happen. The 'double-barrelled' time limit, with reference to six months of the commencement of any work and such a 'long-stop date', underscores the importance of the 'long-stop date': see Lewison, 'The Interpretation of Contracts', (7th ed., 2020) at paragraph 15.51, and Petrocapital Resources plc v Morrison & Foerster (UK) LLP [2014] 1 WLR 2365 (in which it was held that the better view was that time was of the essence in respect of a stipulation that convertible notes be redeemed "in any event within 12 months").
(5) To adapt the words of Longmore LJ, when giving judgment in the Court of Appeal in FG Wilson (Engineering) Limited v. John Holt & Co (Liverpool) Limited [2013] EWCA Civ 1232 at paragraph 36, it would be a most surprising result if the time stipulations in clause 7.2 were to be given no effect. Indeed, the average businessperson who was told that time stipulations of this kind could be entirely disregarded, would hardly be able to contain his/her disbelief.
(6) Paragraph 15.6 supported this submission. This is, on its proper interpretation, an express stipulation that, insofar as Saudia is required to do anything under the Lease, including, under clause 7.2, to provide appropriate documentation, including invoices, evidencing performance of maintenance work to Sprite before the Expiry Date (if Sprite is to contribute to the cost of that maintenance work), the time stipulated is of the essence. Sprite was not obliged to make payments in respect of maintenance work if Saudia did not ensure that Sprite received appropriate documentation evidencing performance of the work before the Expiry Date.
(7) In response to Saudia's argument that clause 7.2 imposed no obligation, Sprite contended that Saudia's case seems to be that (i) clause 15.6 only refers to time being of the essence for "obligations" of Saudia under the CTA, (ii) Saudia characterises the requirement for it to provide the necessary invoices and supporting documents to Sprite before the Expiry Date, if Sprite were to be obliged to contribute to the relevant maintenance costs, as a "right", and not as an "obligation", and (iii) accordingly, time is not of the essence in respect of the requirement for Saudia to provide the necessary invoices and supporting documents. However, on any natural reading of clause 15.6, the word "obligation" encompassed the requirement for Saudia to provide Sprite with the necessary invoices and supporting documents in order to become entitled to a payment from Sprite. Any other reading would be deeply artificial – both with an eye to the terms of the clause and with an eye to the sorts of distinctions to which commercial counterparties might be likely to agree – and would subvert a common-sensical and commercial interpretation of the clause.
(8) In any event, even if the court were to take another view, Saudia's pre-emptive reliance on clause 15.6 overlooks that Sprite does not need to rely on clause 15.6 to succeed on the Preliminary Issue, given the express terms of clause 7.2, and its wider context, as addressed above. Consequently, even if Saudia is right as to how clause 15.6 should be interpreted, it is, at the absolute most, neutral for Sprite's position on the Preliminary Issue. Even if the need for Saudia to provide the necessary invoices and supporting documents to Sprite before the Expiry Date, if Sprite were to be obliged to contribute to the relevant maintenance costs, were not to be characterised as an obligation of Saudia, then it would – at the very least – be a condition precedent to any obligation on the part of Sprite to contribute to the maintenance costs. It is well-established that strict compliance with a condition precedent is generally required: see Lewison at ¶16.105 to ¶16.108.
(9) Sprite also emphasised the undesirability of a full trial of the claim, which is what would result from Saudia's construction. Such a trial would involve, inter alia, (a) disclosure in respect of (i) issues relating to the adequacy of the invoices and documents that Saudia belatedly provided to Sprite more than two years after the Expiry Date, and (ii) the work that was allegedly carried out by or for Saudia, (b) witness evidence on each of those matters, and (c) expert evidence in respect of the complex world of aircraft maintenance and the reasonableness of sums allegedly incurred by Saudia or the extent to which the work carried out tallied to the categories of work in respect of which Sprite could ever be entitled to make a contribution to Saudia's costs under clause 7.2 of the CTA.
Saudia's contentions.
(1) First, Sprite says that Saudia failed to provide documentation which was "reasonably satisfactory" to it. Here, it was agreed that there is a factual dispute which the parties accept should go to a full trial so that the court can evaluate the quality of the paperwork.
(2) Second, Sprite says that various Events of Default had occurred and were continuing at the relevant time so as to bar Saudia's claim under clause 7.2. However, Saudia had never disputed its liability to pay the outstanding rent, or to pay the US$200,000 agreed between the parties upon redelivery of the Aircraft. Furthermore, Saudia has now paid all outstanding rent sought under Sprite's counterclaim, which was paid promptly following the Order of Foxton J dated 16 June 2023.
(3) Third, Sprite says that the effect of a Transfer Certificate made by the parties on 17 January 2019 extinguished its obligation to reimburse Saudia under clause 7.2 in respect of any work before that date, i.e. before Sprite became the lessor under the Lease. Again, Saudia said, this was not before me at this hearing.
(1) Whether clause 15.6 of the CTA makes time of the essence for the provision of the relevant documents under clause 7.2.
(2) Whether time is otherwise of the essence for the provision of the relevant documents under clause 7.2.
(1) Saudia would have paid US$9.7m in Supplemental Rent, which Sprite can keep.
(2) Saudia would have spent an additional US$12.7m on improving the Aircraft.
(3) Sprite would take, at the end of the Lease, repossession of the Aircraft in a much-improved condition, at Saudia's expense.
Does clause 15.6 make time of the essence for the provision of documents?
"The time stipulated in the Lease for all payments payable by Lessee and the prompt, punctual performance of Lessee's other obligations under the Lease are of the essence of the Lease."
Was time "otherwise of the essence" for the provision of documents?
(1) Saudia paid Supplemental Rent.
(2) Saudia was responsible for maintenance, replacement and repair work to the Aircraft.[3]
(3) Saudia provided invoices and supporting documentation reasonably satisfactory to Sprite, which evidenced performance of the maintenance work done to the Aircraft.
(4) Sprite became obliged to pay Saudia contributions towards the cost of maintenance.
(5) Sprite's contributions to the cost of maintenance were capped by reference to various factors, including the amount of Supplemental Rent paid by Saudia.
(6) The existence of a continuing Event of Default suspended Sprite's obligation to pay.
"The basic question is whether the failure to comply with a contractual provision within the time limited by the contract constitutes a repudiation of the contract i.e. is time of the essence of that contractual provision. The phrase 'time is of the essence of the contract' is capable of causing confusion since the question in each case is whether time is of the essence of the particular contractual term which has been breached."
"The treatment of time limits in mercantile contracts does not appear…to be justifiable by any presumption of fact or rule of law, but rather to be a practical expedient founded on and dictated by the experience of businessmen."
"Indeed in many non-commercial contracts the requirement of certainty would seem to be just as important as in commercial contracts. One feature of commercial contracts to which attention is often drawn is that the particular contract may be only one of a string of contracts, so that failure in prompt performance of one contract may have repercussions along the string. However, it is not easy to see how this differs in practical effect from a contract for the sale of a house which is frequently one of a chain, and in respect of which a failure in prompt performance may also have effects down the chain. A better starting point in respect of all contracts would be to attempt to examine the potential harm which might flow from delayed performance."
"I do not think that the question of principle…can be solved by classifying the contract of tenancy as being of a commercial character. In some stipulations in commercial contracts as to the time when something must be done by one of the parties or some event must occur, time is of the essence; in others it is not. In commercial contracts for the sale of goods prima facie a stipulated time of delivery is of the essence, but prima facie a stipulated time of payment is not (Sale of Goods Act 1893, section 10 (1)); in a charter-party a stipulated time of payment of hire is of the essence. Moreover a contract of tenancy of business premises would not appear to be more of a commercial character than a contract for sale of those premises. Nevertheless, the latter provides a classic example of a contract in which stipulations as to the time when the various steps to complete the purchase are to be taken are not regarded as of the essence of the contract."
(1) First, on Sprite's interpretation, Saudia would lose a very valuable right to reimbursement for work actually done and paid for, merely because, for example:
(a) Saudia had not yet received the requisite invoices or underlying supporting documentation from the relevant maintenance performer by the Expiry Date.
(b) Saudia had provided invoices and supporting documents just before the Expiry Date but, for whatever reason, the documents were not reasonably satisfactory to Sprite but could easily have been supplemented albeit only after the Expiry Date.
(c) Saudia had provided the relevant documents a single day after the Expiry Date.
(2) Second, on Sprite's preferred interpretation, Sprite would obtain a substantial benefit in the form of valuable improvements to the Aircraft, for which it had provided no consideration, but Sprite would have suffered no prejudice whatsoever as a result of the late provision of the relevant documents.
Discussion and conclusions.
(1) The first is that time was of the essence for the performance of Saudia's obligation to present invoices to Sprite, as a precondition to its entitlement to reimbursement for the works that, at this hearing, I must assume were done.
(2) The second is that timely presentation of invoices was a condition precedent to Saudia's right to reimbursement, with the result that any delay in the presentation of such invoices led to the loss, once and for all, of any right to reimbursement.
Time of the essence.
"Time "of the essence of the contract"
A number of difficulties surround the law relating to time stipulations in contracts. The first is that the phrase which is commonly employed, namely "time is of the essence of the contract", is potentially misleading in that the question in each case is whether time is of the essence of the particular term which has been broken, not whether time is of the essence of the contract as a whole. The agreement by the parties that "time is of the essence" in relation to a particular term of the contract is another way of identifying the term as a condition of the contract so that any failure to comply with it will in principle entitle the other party to terminate further performance of the contract.
Common law and equity
The second point of difficulty is that, historically, common law and equity adopted a divergent approach to time stipulations in contracts. At common law a strict approach was taken so that, as was once stated by Sir John Romilly MR:
"… at law time is always of the essence of the contract. When any time is fixed for the completion of it, the contract must be completed on the day specified, or an action will lie for breach of it."
However, even at common law there were exceptional cases where time was held not to be of the essence of the contract. But the thrust of the approach of the courts at common law was clear: stipulations as to time were generally of the essence of the contract, so that a party was entitled to terminate further performance of the contract if the other party's performance was not completed on the date stipulated by the contract. A different set of rules, however, evolved in equity where time was not of the essence of the contract, except in the three cases considered below:
"The court of equity was accustomed to relieve against a failure to keep the date assigned … if it could do justice between the parties";
"… relief is given against mere lapse of time where lapse of time is not essential to the substance of the contract."
Law of Property Act 1925 s.41
Section 41 of the Law of Property Act 1925 provides that:
"Stipulations in a contract, as to time or otherwise, which according to the rules of equity are not deemed to be or to have become of the essence of the contract, are also construed and have effect at law in accordance with the same rules."
Thus the rules at law are now the same as those in equity: the effect of s.41 is that:
"… contractual stipulations as to time … shall not be construed as essential, except where equity would before 1875 have so construed them—i.e. only when the strict observance of the stipulated time for performance was a matter of express agreement or of necessary implication";"
or, in other words, s.41:
"… does not negative the existence of a breach of contract where one has occurred, but in certain circumstances it bars any assertion that the breach has amounted to a repudiation of the contract",
which entitles the innocent party to terminate the contract. Following the enactment of s.41, it is only in the three cases set out in the next two paragraphs that time is of the essence of a contract.
Time made expressly or implicitly "of the essence"
Time is of the essence:
(1)Where the parties have expressly stipulated in their contract that the time fixed for performance must be exactly complied with, or that time is to be "of the essence".
(2)Where the circumstances of the contract or the nature of the subject matter indicate that the fixed date must be exactly complied with, e.g. the purchase of a leasehold house required for immediate occupation; the sale of business land or premises, such as a public-house as a going concern; the sale of a reversionary interest; the exercise of an option for the purchase or repurchase of property, or for determining a lease under a "break" clause or an option to acquire a leasehold interest in futuro (since in these cases, "the parties on the exercise of the option, are brought into a new legal relationship"); "mercantile contracts", such as a contract for the sale of goods where a time is fixed for delivery, or for the sale of shares liable to fluctuate in value (where the contract stipulated a time for payment). However, the mere fact that the contract can be labelled "mercantile" or "commercial" does not determine the issue. Nor does the fact that the contract confers on a party the right to terminate or withdraw from the contract on the breach of a term of the contract, such as the failure to pay hire "punctually" under a charterparty, have the consequence that the term relating to the payment of hire has the status of a condition. Whether a time limit is of the essence of a contractual provision is a question of interpretation of the provision in the context of the contract as a whole. The question is whether the time specified in the particular clause was (expressly or by necessary implication) intended by the parties to be essential, e.g. because they needed to know precisely what were their respective obligations. Thus, where the buyers were required to give 15 days' notice of readiness of the vessel so that the sellers could then nominate the port for loading, the House of Lords held time to be of the essence: performance by the buyers was a condition precedent to the sellers' ability to perform their obligation. (However, under the Sale of Goods Act 1979 s.10, unless a different intention appears from the terms of the contract, stipulations as to time of payment are not deemed to be of the essence of the contract of sale.) Similarly, a court is unlikely to be willing to infer that the parties have agreed that time is to be of the essence in the case of a contract of employment, a commercial agency contract or an analogous contract. In the latter contexts parties wishing to make time of the essence should make express provision to that effect in their contract….
…Where time is not of the essence
Where none of the three exceptions mentioned in the preceding paragraphs applies, the effect of s.41 of the Law of Property Act 1925 (above) is that the breach of a stipulation as to time is not of itself a repudiatory breach which entitles the innocent party to terminate further performance of the contract. Thus, in a contract for the sale and purchase of land, if the purchaser fails to complete on the date fixed for completion, the effect of s.41 is that the purchaser does not commit a repudiatory breach of contract (entitling the vendor to terminate the contract) provided the purchaser either completes, or is ready to complete, within a reasonable time thereafter: it is not essential for the purchaser to prove that he was ready and willing to complete on the date fixed for completion. Even where time is not (or has not subsequently been made) of the essence in a contract for the sale and purchase of land, a failure to complete the contract on or before the date stipulated for completion is still a breach leading to liability to pay damages for any loss caused by the delay in completion. A further example comes from leases. The presumption is that time is not of the essence in the timetable specified in a rent review clause in a lease, under which various steps must be taken to determine the rent payable during the period following the review date; strict adherence to the timetable will be necessary only if that is expressly stated, or if it is a "necessary implication" from the surrounding circumstances (e.g. in the inter-relation between the rent review clause and other clauses). The fact that the time specified in a rent review clause is held not to be of the essence does not itself mean that there is an implied term that the right to a review must be exercised within a reasonable time. In the case where time is not, and never has been, of the essence of the contract, a party may nevertheless be entitled to terminate further performance of the contract where the effect of the delay in performance is to frustrate the purpose of the contract."
Condition precedent?
(1) In my judgment it is clear that unless and until such invoices were provided, there could be no entitlement to claim reimbursement. In that sense, the provision of invoices was a condition precedent to the right to claim reimbursement.
(2) However, it does not follow that if an invoice was provided late, that would lead to a loss of the right to claim reimbursement forever. In that regard:
(a) On the one hand, it may be said, as Sprite contends, that if the clause is not construed as a condition precedent, then it loses all of its content.
(b) On the other hand, as Saudia says, to hold that it should lose all rights to reimbursement, in a case where millions of dollars have been paid over, and invoices may have been provided only a few days late, is a disproportionate and unlikely result.
(3) Overall, my current, albeit provisional view, is that the parties would have had to spell this result out much more clearly than they have in this contract to lead to a result which I would regard as commercially unlikely. In this regard, I view the analogy with the rent review situation as discussed in the United Scientific case, as the closest analogy with which I have been presented.
Note 1 Airframe, Engines (LLPs and refurbishment), Auxiliary Power Unit (“APU”) and Landing Gear. [Back] Note 2 As explained in Lewison on the Interpretation of Contracts at ¶16.105-108, whilst the general rule is that in the case of unilateral contracts, such as options, all conditions must be strictly performed, otherwise no binding contract comes into existence at all, there are exceptions: “In the first place, part of a bilateral (or synallagmatic) contract which is drafted using the language of options will not necessarily be treated as an option, with the strict consequences which flow from that. Whether it does amount to an option depends on the proper interpretation of the contract as a whole” (citingUnited Scientific). [Back] Note 3 The final paragraph of clause 7.2 expressly links Sprite’s payment of maintenance contributions to Saudia’s obligations to undertake maintenance, replacement and repair work. [Back] Note 4 To use the phraseology of Lord Diplock at p.930F ofUnited Scientific. [Back]