BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> National Trust Thames and Chilterns Region v Mates (t/a Ccw Mates Stone Restoration) & Ors [2003] EWHC 1209 (TCC) (04 June 2003) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2003/1209.html Cite as: [2003] EWHC 1209 (TCC) |
[New search] [Printable RTF version] [Help]
QUEENS BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
B e f o r e :
____________________
THE NATIONAL TRUST THAMES AND CHILTERNS REGION |
Claimant |
|
AND |
||
(1)CHARLES MATES (t/a CCW MATES STONE RESTORATION) |
||
(2) AJAP CONTRACTING LIMITED |
||
(3) GRACE CONSTRUCTION PRODUCTS LIMITED |
Defendants |
____________________
For the defendant: Jane Davies (Hazell & Co solicitors)
Dates of hearing: 6,7,8,12 May 2003
____________________
Crown Copyright ©
The judgment of His Honour Judge Bowsher Q.C. is as follows:
THE ACTION
THE WORKS
PRELIMINARY ISSUES
(a) "What were the terms of Mr Mates' retainer?
(b) Did Mr Mates retain the Second Defendant as his subcontractor?
(c) Assuming, solely for the purpose of the hearing of preliminary issues, that there are defects of workmanship and materials, is the First Defendant liable to the Claimant in respect of:
(i) Any defective workmanship of and/or materials supplied by Ajap;
and/or
(ii) Any defective materials supplied by Grace?"
THE CLAIMANTS' CASE
"The Claimant have permission to amend its Particulars of Claim in the form appended hereto and initialled by the Judge.
"The claimant be debarred from producing evidence at trial which goes outside the pleading."
At the trial, in response to an application by Miss Davies, I struck out of two witness statements some short passages on the basis of that agreed order.
THE CASE OF THE DEFENDANT
(a) "The key question in this case is: did Mr. Mates agree to carry out these specialist works? The answer is that he did not so agree, and there is not one scrap of evidence that he did so. One is not liable for the performance of independent contractors, save in contract in circumstances where the works of those independent contractors form part of the contract works. Then, and only then, might any terms in Mr. Mates' agreement with the Trust (whether express or implied, either by statute or common law) as to workmanship and materials be applicable to the bituthene applied to the East Curved Link roof. Since those bituthene works were not part of Mr. Mates' works, no such terms apply and the claim must fail.
(b) However, if, contrary to the weight of the evidence, it is found that Mr. Mates did indeed agree to carry out the specialist bituthene works, the relationship between the Trust and Mr. Mates, and the Trust's conduct (through its architect) when selecting Grace's materials and Ajap as contractor, were such that (a) the terms of IFC 84 were not incorporated into the agreement between Mr. Mates and (b) the usual terms as to workmanship and material were negatived."
RELATIONSHIP OF MR. MATES WITH CLAIMANTS
"Charlie has devoted many years of his life to Cliveden and has expressed a commitment to continue working into the 21st century (as long as he is able). He is a small contractor set up specifically to work for the Trust, and his whole livelihood is dependent on Cliveden. He is a craftsman of rare skill and dependability who is practically irreplaceable . . ."
PROGRESS OF THE WORKS
WAS MR. MATES RESPONSIBLE FOR THE WORKS?
"It had been intended to carry out the roof works in the spring of 1995 but this was inconvenient for the hotel. It was determined therefore to carry out the works in October and as part of the build-up to that I recall attending a pre-contract meeting in July 1995 with Mr. Mates, Caroline Wilson and myself. I either did not take any notes of that meeting or they are now lost but I note that Mr. Mates records in his diary my attendance on site on 7th July 1995. This accords with my recollection of a pre-contract meeting at about that date.
It was usual for Julian Harrap Associates and Sawyer Fisher to hold a pre-contract meeting with the main contractor for any works, on this occasion Mr. Mates. The purpose of the meeting was to discuss the scope of the works, and Mr. Mates was given the opportunity to comment on the amount of responsibility he was willing and able to take on. In the case of the roof works I recall that he confirmed that he was happy to act on the 'usual' terms; that is, main contractor under IFC 84 terms (see later). I recall a contract; that is, the Clock Tower reconstruction, where Mr. Mates was initially very keen to take on the role of main contractor, but the Trust and its professional advisers did not consider that he had the necessary experience/expertise. It was very useful to have him on site to assist Ellmers, the contractor ultimately appointed, and accordingly they paid him a daily rate to carry out 'site agent' type duties".
"I have a recollection of a meeting in July, 1995 to discuss the roof works. Again my notes of that meeting have been destroyed or are missing and I am unable to refresh my memory as to the terms of that discussion."
"I am adamant that all the parties including Mr. Mates intended that his works, over a number of years and including the roof works would be carried out by him as main contractor. [He then referred to a document]. I am in no doubt that Mr. Mates was aware that he was carrying out these and other works as Main Contractor under IFC 84."
43. Although the pleading does not allege that Miss Wilson was at that alleged meeting, in her evidence she said that she was. What she said about it in her written evidence was:
"I recall that I attended a pre-contract meeting with Charlie Mates in July 1995 and whilst I cannot recall the date, it seems most likely that this is the meeting referred to in Charlie Mates' diary for the 7th July 1995. That meeting was attended by Julian Harrap, who was rarely on site save for important matters such as pre-contract meeting. I also recall Stephen Scammell attended that meeting. I do not recall the terms of the discussions at that meeting, but it would have been arranged with a view to agreeing the general nature of the works, details of who the various parties to the contract were and what works they would carry out. It was used as a forum for informing Mr. Mates of the scope of the works. Whilst I do not recall a discussion on the form of contract I am in no doubt that firstly, all the parties assumed that the works would be carried out under the usual terms, and I am further in no doubt that the usual terms were that Mr. Mates would be the main contractor and that the terms of his appointment would be subject to the IFC 84 form of contract."
CONCLUSION
(a) Mr. Mates was not retained as main contractor for the roof works of the East Curved Link;
(b) Mr. Mates did not retain Ajap as his sub-contractor.
(c) Mr. Mates is not responsible for any defective workmanship of or materials supplied by Ajap and is not responsible for any defective materials supplied by Grace.
Action against first defendant dismissed.
Claimant to pay costs of the first defendant including costs reserved on an interlocutory hearing to be the subject of detailed assessment on the standard basis.
Permission to appeal refused.