BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Shimizu Europe Ltd. v LBJ Fabrications Ltd. [2003] EWHC 1229 (TCC) (29 May 2003) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2003/1229.html Cite as: [2003] BLR 381, [2003] EWHC 1229 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
BIRMINGHAM DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION COURT
BIRMINGHAM CIVIL JUSTICE CENTRE 33 BULL STREET BIRMINGHAM B4 6DS Date of hearing: 23 April 2003 Date of draft judgment: 12 May 2003 |
||
B e f o r e :
____________________
SHIMIZU EUROPE LIMITED |
Claimant |
|
and |
||
LBJ FABRICATIONS LIMITED |
Defendant |
____________________
Mr Peter Collie of Counsel (instructed by Wright Hassall) for the Defendant
____________________
DATE OF HTML VERSION OF JUDGMENT: 29 MAY 2003
BEFORE HER HONOUR JUDGE FRANCES KIRKHAM
HTML VERSION OF JUDGMENT
Crown Copyright ©
"If the Contract is not concluded between us, we shall pay you for any work done pursuant to this instruction up to a maximum of £84,074.25 plus VAT subject however, to this sum being reduced by the amount of any claim or set off which we might have against you from your breach of contract. You will not be entitled to any further payment by way of quantum meruit or otherwise."
No DOM/1 form of contract was signed. There are issues concerning the formation of the contract. It is common ground that the LOI provided for adjudication under the TeCSA rules.
1. Shimizu is not prevented from withholding payment of all or part of the sum of £47,718.39 (plus VAT as appropriate) if that sum be due in accordance with Shimizu's contractual and statutory right to serve notice of intention to withhold payment following receipt of LBJs VAT invoice.
2. No dispute had crystallised in relation to Shimizu's future right to serve notice of intention to withhold payment in respect of a payment not due at the date of the Notice of Adjudication, and no such dispute was or could be referred to the adjudicator.
3. The adjudicator's decision is invalid, void, unenforceable or in excess of jurisdiction insofar as it does purport to prevent Shimizu withholding payment of all or part of sum of £47,718.39 (plus VAT as appropriate).
4. Further or alternatively, by reason of the matters set out above the adjudicator has failed to act impartially and/or in accordance with the rules of natural justice. His decision is therefore unenforceable.
5. In the further alternative, the decision is invalid, void or unenforceable insofar as the decision purports to decide or determine the basis of the contractual relationship either on grounds of no crystallised dispute and/or excess of jurisdiction (absence of referral) or for breach of the rules of natural justice.
6. In the further alternative, the adjudicator has purported to reach a decision under a sub-contract that the parties do not purport to exist and under which he was not appointed. He has not reached his decision under the LOI. His decision is therefore a nullity and/or unenforceable.
"11. The scope of the Adjudication shall be the matters identified in the notice requiring adjudication, together with
(i) any further matters which all the parties agree should be within the scope of the Adjudication, and
(ii) any further matters which the Adjudicator determines must be included in order that the Adjudication may be effective and/or meaningful.
12. The Adjudicator may rule on his own substantive jurisdiction, and as to the scope of the Adjudication.
14. Decisions of the adjudicator shall be binding until the dispute is finally determined by legal proceedings, by arbitration (if the Contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement.
28. Every decision of the adjudicator shall be implemented without delay. The Parties shall be entitled to such reliefs and remedies as are set out in the decision, and shall be entitled to summary enforcement thereof, regardless or whether such decision is or is to be the subject of any challenge or review. No party shall be entitled to raise any right to set off, counterclaim or abatement in connection with any enforcement proceedings."
33. No party shall, save in the case of bad faith on the part of the Adjudicator, make any application to the Courts whatsoever in relation to the conduct of the Adjudication or the decision of the Adjudicator until such time as the Adjudicator has made his decision, or refused to make a decision, and until the Party making the application has complied with any such decision."
.
The proper construction of the adjudicator's decision
"21.1 The first and interim payments and the Final Payment shall… be made to [LBJ] in accordance with the provisions of clause 21.
…
21.2.3 The final date for payment for the first and interim payments shall be not later than 28 days after the date when they become due.
21.3.1 Subject to any agreement between the Sub Contractor and the Contractor as to stage payments and subject to any decision of the Adjudicator under clause 38A or of an arbitrator or the Courts under clauses 38B or 38C as the case may be, the amount of the first and each interim payment to the Sub Contractor shall be the Contractor's gross valuation as referred to in clause 21.4………
21.2.4 Notwithstanding any other provision of this Sub-Contract, the following conditions precedent must all be satisfied in relation to each interim payment and to the Final Payment before that payment becomes due under this Sub-Contract :
[LBJ] shall have delivered to [Shimizu] a VAT invoice or authenticated VAT receipt in respect of the relevant interim payment or the Final Payment (as the case may be)…
21.3.2 Not later than 5 days after the date on which any interim payment becomes due [Shimizu] shall give a written notice to [LBJ] which shall specify:
.1 the amount of the interim payment which is proposed to be made in respect of the sub contract works and the basis on which such amount was calculated; and
.2 by way of deduction from such amount, the amount of any payment proposed to be made from [LBJ] to {Shimizu] and the basis on which such amount was calculated
.3 Not later than 5 days before the final date for payment of any interim payment, [Shimizu] may give a written notice to [LBJ] which shall specify any amount proposed to be withheld and/or deducted and the amount of the withholding and/or deduction attributable to each ground. If no notice is given, [Shimizu] shall pay the amount stated in his notice under clause 21.3.2 by the final date for payment of it.
…
21.3.3 Not later than 5 days before the final date for payment of any interim payment, [Shimizu] may give a written notice to [LBJ] which shall specify any amount proposed to be withheld and/or deducted from the amount notified under clause 21.3.2, the ground or grounds for such withholding and/or deduction and the amount of the withholding and/or deduction attributable to each ground. If no notice is given, [Shimizu] shall pay the amount stated in his notice under clause 21.3.2 by the final date for payment of it."
Did the adjudicator act in breach of natural justice and/or outwith his jurisdiction in making findings in relation to the sub contract?
"6.2.2 This wording is typical of a letter of intent, which seeks to cap liability and provide a degree of protection in the event a contract is not concluded. A Sub-Contract was however concluded between the parties and in consequence variations to the Sub-Contract Sum of £84,074.25, excluding 2½ discount and VAT, fall to be valued in accordance with the Sub-Contract mechanism rather than the limit imposed by the letter of intent.
6.2.3: …LBJ's entitlement to payment is not capped by reference to the LOI but ascertained by reference to the Sub-Contract Sum of £84,074.25 excluding 2.5% discount and VAT, together with the Sub-Contract mechanism."
TeCSA rules
Conclusion
(1) On a true construction of the adjudicator's decision, the adjudicator did not decide that Shimizu had no future right of set off. The decision did not have the effect of removing any of Shimizu's remaining rights under the sub contract and the Act or of preventing Shimizu from exercising any future rights which Shimizu may have. Accordingly, Shimizu was entitled to serve a withholding notice in relation to the sum which the adjudicator decided would become due on delivery of the VAT invoice.
(2) The adjudicator's decision is invalid insofar as it purports to decide the basis of the contractual relationship between the parties. The parties had agreed that their agreement was based on the LOI and the adjudicator did not have jurisdiction to decide the matters he dealt with at paragraphs 6.2.2 and 6.2.3 of his decision.