BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Mirant Asia-Pacific Construction (Hong Kong) Ltd & Anor v OVE Arup & Partners International Ltd & Anor [2003] EWHC 1304 (TCC) (11 June 2003) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2003/1304.html Cite as: [2003] EWHC 1304 (TCC), 90 Con LR 40 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
IN THE TECHNOLOGY & CONSTRUCTION COURT
B e f o r e :
____________________
(1) MIRANT ASIA-PACIFIC CONSTRUCTION (HONG KONG) LTD | First Claimant | |
(2) SUAL CONSTRUCTION CORPORATION | Second Claimant | |
- and - | ||
(1) OVE ARUP AND PARTNERS INTERNATIONAL LTD | First Defendant | |
(2) OVE ARUP AND PARTNERS (HONG KONG) | Second Defendant |
Counsel for defendant: Mr Andrew Bartlett QC Instructed by: Beale & Co Solicitors
____________________
Crown Copyright ©
"12.1 failing to provide a design for the G2 and G5 foundations that was suitable for the ground conditions
12.2 failing to appreciate that the ground conditions in which those foundations were to be situated did not satisfy the design assumption that had been made...
and
12.3 causing or permitting the G2 and G5 foundations to be constructed in ground conditions which were inadequate and which did not satisfy the said design assumption that had been made."
5. THE ISSUES
1. "Did the terms of that contract include FIDIC terms with a five-year duration of liability (clause 17) and a cap of £4m (clause 18.1)?" I note that neither Issue 1 nor Issue 2 asks specifically when that contract was made. This is an essential question, which I include within question 1.
2. "Who were the parties to the contract under which OAPIL and/or OAPHK were responsible for the design of the Unit 1 boiler foundations?"
3. "Insofar as there was a contract under which OAPIL and/or OAPHK had some obligation in relation to the inspection of foundation excavations approving ground conditions and/or inspecting formations for the Unit 1 boiler foundations, who were the parties to such contract?"
4. "What were the nature and terms of the contractual obligations in relation to inspection of foundation excavations, approving ground conditions and/or inspecting and approving formations for the Unit 1 boiler foundations?" At the end of the hearing the parties asked me to amend the question, see paragraph 312 below.
5. "If the FIDIC terms applied, was the claimants' letter dated 2 May 2001 a formal claim within the meaning of clause 17?"
At the outset it is useful to consider how the defendants now put Issue 2. At the beginning of the hearing, the defendants claimed that the contract was partly oral and partly in writing and was made on one of a number of dates. They contended that the Letter of Intent signed on 29 May 1995 did not have any legal effect. They said that if, contrary to their submission, it had legal effect, further terms were added to it on the dates when they say that the contract in fact was made.
I have to bear in mind that most of the events took place seven to eight years ago. Much has happened to the witnesses in the meantime. This undoubtedly affected the quality of their evidence. There were also occasions when I felt that the witnesses were tailoring their evidence to the particular case that was being put forward. The claimant's former managing director, Mr Elliott, was called to give evidence by the defendants to the evident annoyance of the claimants.
There are three issues of law which are relevant to the questions which I am asked to consider:
a) the formation of the contract;
b) as a topic subsidiary to (a), the identity of the contracting parties; and
c) the law of estoppel.
The relevant basic law is well known and can be set out in the following propositions:
"In the case of a contract which is based partly upon oral exchanges and conduct, a party may have a clear understanding of what was agreed without necessarily being able to remember the precise conversation or action which gave rise to that belief. As the Court of Appeal pointed out, the Tribunal did not make any specific findings about what was said at the interviews or on any other occasion. But the terms of the engagement must have been discussed and these conversations must have played a part in forming the views of the parties about what their respective obligations were.
The evidence of a party as to what terms he understood to have been agreed is some evidence tending to show that those terms in an objective sense, were agreed. Of course the tribunal may reject such evidence and conclude that the parties misunderstood the effect of what was being said and done. But when both parties are agreed about what they understood their mutual obligations (or lack of them) to be, it is a strong thing to exclude their evidence from consideration. Evidence of subsequent conduct which would be inadmissible to construe a purely written contract may be relevant on similar grounds, namely that it shows what the parties thought they had agreed."
This does not require a separate exposition of the law. Where the contract is exclusively in writing, the court will construe the document. Where the agreement is partly oral and partly in writing, the court will look at the evidence, including the surrounding circumstances and reach an objective conclusion.
In Johnson v Gore Wood [2002] 2 AC 1, 33 Lord Bingham cited with approval the statement of principle set out by Lord Denning MR in Amalgamated Investment & Property Co Ltd v Texas Commerce International Bank Ltd [1982] QB 84 at 122.
"When the parties to a transaction proceed on the basis of an underlying assumption — either of fact or of law — whether due to misrepresentation or mistake makes no difference — on which they have conducted the dealings between them — neither of them will be allowed to go back on that assumption when it would be unfair or unjust to allow him to do so. If one of them does seem to go back on it, the courts will give the other such remedy as the equity of the case demands."
This approach was endorsed by Lord Cooke and Lord Hutton.
"Such an estoppel is not, as I understand it, based on a common underlying assumption so much as on a representation by the representor that he does not intend to rely upon his strict legal rights against the representee which is so acted upon by the representee that it is inequitable for the representor thereafter to enforce those rights against him."
THE FACTS
It is convenient to start with a more detailed consideration of the parties to the dispute.
THE PAST HISTORY
The present project started with Mr Elliott, as the managing director of CEPAS at Sual, approaching Ove Arup to see whether they would be interested in becoming involved as consulting engineers in the Sual power project.
"We request all payments in pounds sterling as this is to be the currency in which the majority of our costs will be incurred. If the Project Office were to be located other than in the UK we would agree to reviewing the currency of payment in line with our exposure."
"We request the Form of Agreement under which the engineering services to Slipform are provided, reflects the technical and commercial proposals of this tender. We are willing to provide a draft agreement for discussion at Slipform's request."
'Revision A 31 March 1994 — Draft for Review. Revision B — Tender dated 6 April 1995 and
Revision C — Tender dated 11 April 1995.'
"The team will be drawn together from within Arups on a best-man-for-the-job basis. The team will be assembled in Hong Kong for a six month front end concept phase followed by the establishment of a project office in London."
"Details of work scope, payment mechanism and contractual arrangements will be defined in greater detail in a new agreement currently being developed. A draft proposal for part of this agreement has been produced in a format similar to the appendices of a FIDIC type contract and is attached for discussion purposes."
"Following our recent meeting, we would like to confirm the agreement reached on the following principles relating to our appointment as civil engineering designers on the Sual project."
"(3) The fee for concept, preliminary and detailed design of the defined scope of the works is to be £3.75 million."
"A separate proposal will be made regarding the option of adopting a gainshare approach to fee payment and will be the subject of a later agreement. There will be no effect on our agreement relating to total fee payable if gainshare is not eventually included in the agreement."
"As agreed, details of work scope, payment mechanism and contractual arrangements will be defined in greater detail in a draft contract being prepared by us."
"If you agree with the contents of this letter, we request that you sign a copy and return it to us as confirmation of our agreement and of your intention to appoint us as your design contractor. On that basis we will commence work".
"ix) A draft contract prepared by Arup was submitted to CEPA on 11 August. The intention is to reach an agreement with CEPA before full commitment is made to detail design.
x) Invoices for the months of June, July and August totalling $437,819 have been submitted to CEPA on 11 August, 11 August, and 5 September respectively. The invoices for June and July should have been paid by 25 August in accordance with the proposals in the draft contract,"
"21. The agreement is effective from the date of receipt by the Consultant of the Client's Letter of Acceptance of the Consultants Proposal or of the latest signature necessary to complete the Formal Agreement, if any, whichever is the later."
"Neither the client nor the consultant shall be considered liable for any loss or damage resulting from any occurrence unless a claim is formally made on him before the expiry of the relevant period stated in Part II or such earlier date as may be prescribed by law."
"The Duration of liability is five (5) years."
"18.1 the maximum amount of compensation payable by either party to the other in respect of liability under clause 16 is limited to the amount stated in Part II ..."
Under Part II it is proposed as "four (4) million pounds sterling".
"22. services shall be commenced and completed at the times or within the period stated in Part II, subject to extensions in accordance with the Agreement."
Under Part II "Commencement shall be 3 June 1995. Completion shall be 2 June 1997."
"a) The basic agreement is modelled on a standard form which emanates from FIDIC which is fair to both the client and the consultant in terms of rights and obligations.
b) However particular matters are addressed by the Appendices and Annexes and I draw your particular attention to the following:
1) clause 17: Duration of liability 5 years — is this enough?
2) clause 18: limit of compensation £4 million — is this enough?
3) clause 31: payment of invoices within 14 days with overdue payments at base rate plus 3 per cent.
4) clause 32: currency of agreement in Pounds Sterling but currency of payment to be in US dollars therefore there is a currency risk."
"Contract issued but no response yet RH (Higson) has spoken to F+V.
JR (Roberts) to arrange to meet with SWGE (Elliott)"
The annotation is "meeting possible during JR visit to HK 11-17 October."
"For the purpose of completing the documentation of the contract between CEPA and Arup we have identified milestone dates for the Late Finish Programme as shown on the attached sheets. We propose that these should be inserted in the contract documents."
"Once a working programme is agreed, we will issue a corresponding detailed design programme and manpower mobilisation schedule, so that payments based on neutral funding matching the actual pace of the project can be agreed. Until then we propose to continue invoicing you on the basis of the payments schedule in our submission.. . ."
"John Roberts would also like to meet with Stewart (Elliott) next week to discuss performance, programme and resources, to progress the Arup/CEPAS contract and to resolve some payment matters."
"While it is fairly early in the design process we wish to start using the system to ensure that there is discipline and management of change and variations. We also believe that it is in the best interest of CEPAS that we advise you of any GECA variations that we are aware extend or change the scope of your works."
This procedure for change order requests proceeded throughout the design work.
"The amount requested reflects the Letter of Intent between CEPAS and Arup dated 23 May and the draft contract issued to you on 11 August 1995."
"1. The ground investigation work described in this document shall be governed by the Client/Consultant Model Services Agreement (the main agreement) entered into by CEPA Slipform Systems Limited (CEPAS) and Ove Arup and Partners International Limited (OAPIL) for the design of the civil engineering works of the Sual power station except as modified below."
"We have received no comments on the original draft; we would like to discuss the contract with you as a matter of priority as detail design of most of the critical path elements is well advanced."
"Progress was reviewed against the Arup level 1 contract programme and a revision of this programme indicating the current status and the proposal for future progress was tabled and discussed (note for future SWGE not happy with micro.dot programme). A marked up programme summarising the discussions and indicating the current status is attached to these minutes. This indicates that overall at the end of December the design is delayed in the order of three weeks."
"Please note that Mr Elliott has approved these invoices 'on account' pending finalisation of the terms of contract."
"As agreed at our meeting on the 10 December 1995 in Jakarta, the amount requested reflects the letter of intent between CEPA and Arup dated 23 May and the draft contract issued to you on 11 August 1995."
"Following our discussions in Jakarta, I have revised the payment schedule as we agreed".
"Would you please review and agree the payment schedule as currently presented so that we may insert it into the contract documents between CEPAS and Arup."
"I propose the payments be adjusted in the manner described in my letter of l5 November 1995 which we went through in Jakarta."
"CEPA Slipform Power System Limited has issued a letter to Ove Arup and Partners International Limited expressing its intention to enter an agreement for the design for certain engineering works in connection with the Sual power station."
"Form of agreement FIDIC
Client/Consultant Model Services Agreement
Part 1 standard conditions modified for SUAL project by
Part 2 Conditions of Particular Application 2nd Edition 1991."
"Until the agreement comes into force Arup is providing the services on the basis of a letter of intent signed by the client dated 23 May 1995."
"The ground investigation work described in this document shall be governed by the Client/Consultant Model Services Agreement (the Main Agreement) entered into by CEPA Slipform Power System Limited (CEPAS) and Ove Arup and Partners International Limited (OAPIL) for the design of the civil engineering works of the Sual Power Station except as modified below."
"Task 3
We propose to provide one full-time geotechnical engineer to supervise the bore hole, trial pit and probe hole investigation. We believe that one person can supervise two drilling rigs simultaneously. However, if more than two rigs are in use at any one time an additional engineer may be required. . .
We propose that Andrew (Talbot) be appointed as site engineer for a minimum of six months. As well as supervising the ground investigation work he would be able to fulfil the requirements of a site foundation engineer in such matters as approving ground conditions for foundations, confirming levels, dealing with specification and placement of backfill and checking slope stability for temporary works."
"8. Variations
Variations to the scope of the ground investigation services provided by Ove Arup and Partners International Limited shall be dealt with in accordance with item C3 of Appendix C of the Main Agreement."
"My understanding was that there was a development of an agreement and that that agreement became an understanding, an agreement between the two parties. I never had any doubt in my mind as to what Stewart Elliott understood as to what we had proposed to him. He would have been very clear if he had disagreed. I am absolutely convinced of that. We had worked before on a contract that had never been signed and we had settled the whole deal on a contract that had never been signed. So I was familiar with Stewart and signatures ... I never had any doubt he knew he was signing next to FIDIC."
"I consider that there has been no progress in getting the contract agreed and signed and limited success in achieving a full co-ordinated civil/M&E programme (despite continually pushing our own design programmes under CEPAS nose). Also the original payment schedule has now been clearly refuted by the client and the requested revised schedule dismissed. In their place we now have a percentage complete payment release system that appears to be accepted by the client although dates and milestones for gross profit payment are not (I believe) fully defined or agreed."
Contract
"The OAPIL offer letter was signed by Stewart Elliott on behalf of CEPA Slipform. There is no detailed signed contract although a draft FIDIC contract has been presented to the clients; this includes detailed scope. Change procedures and scope of services are detailed in letters and other documents which are cross referenced to the offer letter."
"Accordingly, it is believed that there is a contract in law evidenced by performance and payment. It was noted that the client will normally sign off the concept design at each stage of the development."
"3. A copy of the Letter of Intent signed by CEPAS and Arup together with copies of the relevant programmes taken from Arup's final submission and unsigned agreement. I understand that Rick Higson has issued you with a copy of the Agreement."
"I agree with your sentiments regarding the status of our contract. Although there is a letter signed by CEPA Slipform Power System Limited cross referring to the proposal which formed the basis of the draft contract I think it would be prudent to conclude the formal arrangements even though the matter has largely become a fait accompli."
"The background is that a letter of intent was signed by CEPAS on 29 May 1995 for our work on Sual. The letter of intent refers to our proposal Rev E dated 11 April 1995. We started work at the beginning of June 1995. Contract documents were prepared based on our proposal and issued as Rev B on 15 November 1995. Both parties have generally been working to the spirit of this (unsigned) contract ever since.
May I ask you to review this document which I consider the appropriate basis for our work on Sual."
"I view the FIDIC form proposed as far too favourable to the consultant and also need to restate our objections to some specific terms. The actual consistent practice between Ove Arup and CEPA (and prior to that Hopewell) was the form of contract used in Pagbilao and I want to continue it.
Ove Arup has worked on four or five jobs on the basis of the type of form used. Let me ask you the reasons why you want to change to FIDIC."
"You will have to tell me whether we are going to settle down into the FIDIC trenches if we can't resolve with Southern. I recognise that in principle as well as in law, we probably already have a contract (I actually mentioned this and both lawyers remain silent) (ie Mr Reynolds and Ms Baster) but we are in the early days of the Southern relationship and I am thinking of all that lovely future work we might jeopardise if we irritate the wrong man."
I shall deal with Issues one and two in reverse order. I shall then deal with Issue five before turning to Issues three and four.
Issue 2
(a) The invoices sent by Ove Arup subsequent to December 1995 and paid by the claimants make no reference to Revision B.
(b) The formal contract review form signed by Mr Roberts and Mr Higson on 16 July 1996 after the review meeting made no mention of Revision B.
(c) Ove Arup's contract review meeting on 13 December 1996, attended by Mr Roberts, Commercial Manager, and by Mr Fox as the Assistant Project Manager reporting to Mr Higson, had before it a review pack prepared by Mr Roberts which said "there is no detailed signed contract although a draft FIDIC contract has been presented to the client". This opinion is also the conclusion of the Sual Commercial Review Panel. If in fact there had been a clear oral agreement Mr Roberts, as an experienced contracts manager would have been the first to say so, indeed he would have been the first to have written to the claimants immediately if such an agreement had taken place to confirm in writing what had been agreed orally. This never happened.
Issue 1
Who were the parties to the contract under which OAPIL and/or OAPHK are responsible for design of the Unit 1 boiler foundations?
"I did know I did not have a contract with SCC (Sual) I know that the contracts we put forward were to CEPAS. I worked with both parties. I had a working relationship with SCC."
Issue 5
"Neither the client nor the consultant shall be considered liable for any loss or damage resulting from any occurrence unless a claim is formally made on him before the expiry of the relevant period stated in part II or such earlier date as may be prescribed by law."
"Subject to clause 17 any claim for loss or damage arising out of a breach or termination of an agreement shall be agreed between the client and consultant or failing agreement shall be referred to arbitration in accordance with clause 44."
"Dear Sirs,
Sual Power Station
We refer to negotiations which have been progressing with a respect to claims arising from the construction of the Sual Power Station namely:
• Claims arising from the failure of the boiler foundation; and
• Claims arising from the failure of the cooling water outfall channel.
We note receipt of your letter dated 27 April 2001 (without prejudice) in which Ove Arup continue to deny liability. In those circumstances and also given a specific request from John Roberts we have in this letter formally set out our claims relating to both the above matters."
"3. Summary
MAP confirms that it is claiming total damages from Ove Arup in the amount of US$72.5 million and hereby demands payment of that amount."
"1. a claim (which need not be put forward with any formality);
2. an attempt by the parties to agree; and
3. failing agreement, a reference to arbitration, ie a formal claim.
Issue 3
"In so far as theme was a contract under which OAPIL and/or OAPHK had some obligation in respect of foundation excavations approving ground conditions and/or inspecting of formations for the Unit 1 boiler foundations, who were the parties to that contract?"
Issue 4
313. 4(a) On the true construction of Paragraph 5 of the ground investigation proposal dated 8 March 1996 and signed by Mr Elliott (the site work agreement) was Ove Arup
(i) as the claimants contend, under an obligation to provide a site engineer who would fulfil the requirements of a site foundation engineer in such matters as approving ground conditions for foundations? Or
(ii) as the defendants contend, under an obligation to provide for the supervision of the ground investigation work an engineer who was also competent to fulfil the requirements of a site foundation engineer in such matters as approving ground conditions for foundations?
314 (b) Was the site work agreement part of the parties' prior contract for design purposes or was it a separate agreement? Are the parties correct in concluding that it was a separate agreement?
315. (c) Was the site work agreement varied in the manner or partly in the manner alleged in paragraph 43 of the me-amended defence so that Ove Arup was under an obligation to inspect specific formations subject to notice being given to Ove Arup by CEPAS or being procured by CEPAS from NSBC?
316. (d) Was the site work agreement subject (whether by agreement or by estoppel and/or by waiver) to the FIDIC conditions including the conditions of particular application contained in Revision B of the draft contract dated 15 November 1995?
"Task 1 — a combined geophysical and hydro-graphic off-shore investigation (now completed).
Task 2 — an initial trial pit and probe investigation of critical areas such as the pump house and chimney (now completed).
Task 3 - a bore hole, probe and trial pit ground investigation of the whole site including shore facilities. A limited amount of laboratory testing will be undertaken on samples recovered from the site investigation in relation to tasks 2 and 3 of the scope. The results will be summarised in an interpretive report containing recommended design values. It is assumed that these reports will provide both CEPAS and GECA with all necessary information to complete the geotechnical design of the SUAL power station."
"GECA has requested that CEPA undertake a geotechnical ground investigation in the area of each turbine block. The scope of the request has not yet been defined. We await CEPAS instructions."
5. Task 3 - We propose to provide one full-time geotechnical engineer to supervise the borehole, trial pit and probe hole investigation. We believe that one person can supervise two drilling rigs simultaneously. However, if more than two rigs are in use at one time an additional engineer may be required.
The engineer proposed is Andrew Talbot; his curriculum vitae is attached.
We propose that Andrew be appointed as site engineer for a minimum of six months. He would be able to fulfil the requirements of a site foundation engineer in such matters as approving ground conditions for foundations, confirming levels, dealing with specification and placement of back fill and checking slope stability for temporary works. We have assumed that the geotechnical engineer will work 55-60 hours per week."
"8. Variations - Variations to the scope of the ground investigation services provided by Ove Arup and Partners International Limited shall be dealt with in accordance with Item C3 of Appendix C of the Main Agreement."