BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Twintec Ltd v GSE Building and Civil Engineering Ltd [2003] EWHC 605 (TCC) (24 March 2003) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2003/605.html |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
BIRMINGHAM DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION COURT
BIRMINGHAM CIVIL JUSTICE CENTRE 33 BULL STREET BIRMINGHAM B4 6DS Date of judgment: 24 March 2003 |
||
B e f o r e :
____________________
TWINTEC LIMITED | Claimant | |
and | ||
GSE BUILDING AND CIVIL ENGINEERING LIMITED | Defendant |
____________________
Mr Paul Darling QC of Counsel (instructed by Knowles Lawyers Limited) for the Defendant
Dates of hearing: 27 and 28 January and 16 February 2003
Date of draft judgment: 18 March 2003
____________________
BEFORE:
HER HONOUR JUDGE FRANCES KIRKHAM
DATE OF HTML VERSION OF DRAFT JUDGMENT: 18 MARCH 2003
HTML VERSION OF JUDGMENT
Crown Copyright ©
Introduction
(1) Twintec's quotation Q0518B of 31 July 2001
(2) GSE's letter of 13 August 2001
(3) Twintec's letter of 15 October 2001
(1) that they did not accept unequivocally Twintec's quotation Q0518B
(2) that GSE's letter of 13 August 2001 was expressly said to be a letter of intent and
(3) that their clear and unambiguous intention as at 13 August 2001 was that a legally binding agreement had not been concluded between the parties.
(4) Twintec's letter of 15 October 2001 amounted to no more than an offer or counter offer which GSE never accepted.
Background
(1) the sub base preparation
(2) external car park slab
(3) external sales area and hard standing, and
(4) materials testing.
5) "Commercial - 2½% MCD for prompt order? Guaranteed maximum price as per Q0518B 31/07/01… including details (local thickening)". The words "Guaranteed maximum price as per Q0518B 31/7/01" are underscored.
"Please find enclosed the following documents to enable the registration of TU0192GB
copy quotation Q0518B
cost sheet for car parking
cost sheet for hard standing
The project is suspended on piles…
Our contract for this element is with [GSE]. The internal slab will be with Wates Construction and will be a separate contract and order number.
Please confirm you have registered the B & Q external area for July…"
"Re: New B&Q, Belvedere
With reference to the above contract, we confirm our intent to place a sub contract order with yourselves as follows:
Lump sum, fixed price, all risk quotation totalling £637,897.46 nett to supply labour, plant and material to concrete all the external hard standing areas to the engineers specification.
On my return from holiday, we need to arrange a meeting with Wates Construction to agree a sequence of works."
"19. Rates: As per quotation Q0518B and remeasurable at the end of work".
"[Mr Parker] will send order at latest by Wednesday 19 December:
[Mr Parker] held off placing order until confirmation received by GSE legal team that GSE not in breach of contract;
DE [presumably Mr Eddy] threatened an injunction to stop job!
AD on phone several times in similar vein".
Conclusion