BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just Ā£1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> CIB Properties Ltd. v Birse Construction [2004] EWHC 2365 (TCC) (19 October 2004) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2004/2365.html Cite as: [2004] EWHC 2365 (TCC), [2005] BLR 173, [2005] 1 WLR 2252, [2005] WLR 2252 |
[New search] [Printable RTF version] [Buy ICLR report: [2005] 1 WLR 2252] [Help]
QUEEN'S BENCH DIVISION
TECHNICAL & CONSTRUCTION COURT
B e f o r e :
____________________
CIB PROPERTIES LIMITED |
Claimant |
|
- and - |
||
BIRSE CONSTRUCTION |
Defendant |
____________________
Counsel for the Defendant: MR PAUL DARLING QC & MISS SARAH HANNAFORD instructed by Messrs Hammonds)
Hearing date : 19 October 2004
____________________
Crown Copyright ©
A. There was no dispute in being at the date of the notice of adjudication so that the Adjudicator had no jurisdiction to hear and determine the matters before him. Birse says that any possible dispute had not crystallised because there were ongoing discussions to resolve CIB's claim and CIB had agreed to a further meeting due to take place after CIB served the notice of adjudication.
B. Birse claims that the adjudication could not be and was not conducted fairly and impartially because
(a) it was irredeemably prejudiced by CIB's tactics and conduct before the notice of adjudication was served which meant that Birse was put at a disadvantage before the adjudication started which could not be cured. The limited and piecemeal extensions of time given to Birse in the course of the adjudication could not eliminate the prejudice which had already taken place.
(b) The pressure, which not only Birse but also the Adjudicator was under, led the Adjudicator to act unfairly and to the prejudice of Birse in relation to (i) the time for Birse's response; (ii) the timetable and timescales generally; (iii) the expert evidence and; (iv) the documentation generally.
(c) It led the Adjudicator, because of pressure, into making a slip in his award which transformed what should have been an award in Birse's favour into the present award in favour of CIB.
C. The size and complexity of the dispute meant that it could not be resolved fairly by adjudication. Birse cites in support comments made by Judges in other adjudication cases.
D. The Adjudicator made a slip which the court has power either to correct itself or, in the circumstances of this case, the court has power to invite the Adjudicator to correct. Birse contends that the Adjudicator decided in section 9 of his decision that Birse had no liability for defects in the cladding but in section 14 of his decision he awarded CIB the costs of remedial works in relation to defects in the cladding for which, in section 9, he had said that Birse was not liable. Birse contends that the Adjudicator's letter in response to their own constituted exceptionally an invitation to the court to make a finding on this issue which the court should accept.
The Law
"108(1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section. For this purpose 'dispute' includes any difference.
(2) The contract shall
(a) enable a party to give notice at any time of his intention to refer a dispute to adjudication;
(b) provide a timetable with the object of securing the appointment of the Adjudicator and referral of the dispute to him within 7 days of such notice;
(c) require the Adjudicator to reach a decision within 28 days of referral or such longer period as is agreed by the parties after the dispute has been referred;
(d) allow the Adjudicator to extend the period of 28 days by up to 14 days with the consent of the party by whom the dispute was referred;
(e) impose a duty on the Adjudicator to act impartially and;
(f) enable the Adjudicator to take the initiative in ascertaining the facts and the law."
"the Adjudicator shall act impartially in carrying out his duties and shall do so in accordance with any relevant terms of the contract and shall reach his decision in accordance with the applicable law in relation to the contract."
"Adjudication is a highly satisfactory process. It comes under the rubric of 'pay now argue later' which is a sensible way of dealing expeditiously and relatively inexpensively with disputes which might hold up completion of important contracts."
"The timetable for adjudication is very tight (see section 108 of the Act). Many would say unreasonably tight and likely to result in injustice. Parliament must be taken to be aware of this."
"Parliament has not abolished arbitration and litigation of construction disputes. It has merely introduced an intervening stage in the dispute resolution process."
(a) There must be a dispute arising under a construction contract which is capable of being referred to adjudication.
(b) Notice must be given to the other party to refer that dispute to adjudication.
(c) A timetable must be provided under which, if there is no designated Adjudicator, the Adjudicator must be appointed within 7 days.
(d) The Adjudicator must reach a decision on the dispute which has been referred to him.
(e) The Adjudicator must (subject to (f) below) reach his decision within 28 days of the referral or such longer period as is agreed by the parties after the dispute has been referred.
(f) The Adjudicator is permitted to extend the 28 day time limit to up to 42 days with the agreement only of the referring party.
(g) The Adjudicator has an overriding duty to act fairly and impartially. This requires the Adjudicator to direct the procedure so that each party has a proper and equal opportunity to present its case.
"For there to be a dispute for the purpose of exercising the statutory right of adjudication it must be clear that a point has emerged, given the process of discussion or negotiation has ended and there is something that needs to be decided."
"It must also be recognised that there may be some disputes, particularly arising at the end of a project, which are too complex to permit a fair adjudication process within the time limits of the scheme."
"In the absence of any specific agreement to the contrary, a term can and should be implied into the contract referring the dispute to adjudication that the Adjudicator may, on his own initiative, or on the application of a party correct an error arising from an accidental error or omission. The purpose of the adjudication is to enable broad justice to be done between the parties. Parties acting in good faith would be bound to agree at the start of the adjudication that the Adjudicator could correct an obvious mistake of the sort which he made in this case."
"It is a distinction between having second thoughts and intentions and correcting an award to give effect to first thoughts or intentions which creates the problem. Neither an arbitrator or a judge can make any claim to infallibility. If he assesses the evidence wrongly or misappreciates the law the resulting award or judgment will be erroneous but it cannot be corrected under section 17 (of the Arbitration Act 1950) or under the old Order 20 Rule 11. It cannot normally be corrected under section 22 (where the arbitrator has made a mistake). The remedy is to appeal if the right of appeal exists. The skilled arbitrator or judge may be tempted to describe this as an accidental slip but this is a natural form of self-exculpation."
"This enables the arbitrator to make an award on a claim which he has inadvertently overlooked such as an award of interest or to correct errors of accounting or arithmetic such as attributing a credit item to the wrong party but the section does not give the arbitrator licence to give effect to second thoughts on a matter on which he has made a conscious judgment."
"He was doing precisely what he was asked to do and was answering the right question albeit in the wrong way."
The appeal was dismissed (see [2001] BLR 522) The Court of Appeal held that (subject to a separate point relating to bankruptcy law) Dyson J had stated correctly the relevant law and its application to that case.
"In my view, putting the matter at its lowest, it is at least arguable that it is right."
The facts
"Owner or contractor may at any time give written notice of its intention to refer any dispute arising under the contract for construction to adjudication. The adjudication provisions of the Scheme for Construction Contracts shall apply."
"19(i)(c) such period exceeding 28 days after the referral notice as the parties to the dispute may, after the giving of that notice, agree."
In other words, the contract was in conformity with the Act that any extension of time beyond the 28 days required the agreement of both parties (subject to the exception of up to 42 days at the request of the Adjudicator).
"We note your statement that final costs are likely to exceed £11 million. No doubt we will be given the opportunity to comment on your arguments and valuation in due course. Notwithstanding the issue of termination, our own final account which is in preparation for the works will be in the region of £11.25 million including VAT but excluding legal costs and finance charges. We will, however, forward to you our version of the final account upon its completion so as to facilitate dialogue on the amounts payable either way. It is regrettable, and notwithstanding arguments as to fault, that the project came to an unseemly end. However, we in return give notice that we will continue to pursue our own entitlements under the contract."
"He has full authority to deal with this matter and it is his remit to bring it to resolution. Therefore, please address all future correspondence and communication to him at our Northampton office. This will ensure prompt attention is given to any matters raised."
"We believe it would be sensible to proceed to the provisional appointment of a mediator for a mediation to take place during March next year."
"As previously advised, our client has not and does not irrevocably agree to mediation."
"For the avoidance of doubt, the above is without prejudice to our client's right to issue any demand for payment pursuant to the terms of the contract for construction dated 8th August 2000 and to pursue any remedies contractual or otherwise."
"Should contractor not respond to these demands for payment within the time limits indicated, owners will conclude that its entitlement of payment is disputed. In that case, owner reserves the right to take all available steps to enforce its legal rights as set out in this letter without further notice to contractor."
"The demand states that unless payment is received within 30 days we will deem it to be disputed and hence adjudication will then follow."
"We are gearing up for a second adjudication."
"In the absence of the aforesaid payment, CIB reserves the right to take all available steps to enforce its legal right as set out in the demand without further notice."
73. CIB's letter does indicate agreement, without prejudice, to a meeting. It ends by looking forward to Birse's early payment on the demand.
74. There follows considerable correspondence between the parties. CIB's letters, including those ostensibly from Mr Dupont, read like solicitors' letters attempting to put CIB in a good light. The various references to CIB adopting an open and candid approach (see eg the letter of 10th September 2003) sound hollow in the context of the existing plan without any direct warning to proceed to adjudication, as was clear from the internal correspondence.
"There is a real risk that Citibank may refer the entirety of the claim or discrete parts of it to adjudication in the immediate future."
"At the time of receiving the demand Birse's greatest concern was that Citibank would refer the demand to adjudication. Birse adopted a tactic of questioning the claimant to clarify issues while avoiding crystallising the dispute."
"Given the ongoing meetings between our clients in relation to this matter we are surprised at the course of action that you have adopted. You will recall that at the conclusion of the meeting on 5th November 2003 your client specifically agreed to reconvene a further meeting for the first week of December, a date to be agreed."
Conduct of the Adjudication
"Despite CIB having provided Birse with further information and further evidence to support its demand and despite CIB having provided Birse with time to consider supporting information, Birse has failed to accept that it is liable to CIB for the demanded sums (or indeed any sums) and Birse has failed to make any payment in respect of CIB's demand. In the circumstances a dispute has now arisen which may be characterised as a dispute over the entitlement of CIB in respect of the heads of claim set out in CIB's letter dated 28th July 2003."
(1) no dispute had arisen;
(2) Birse had been blatantly ambushed by Citibank with the referral;
(3) the matter was extremely complex;
(4) as a result of points (1) to (3) the process was inherently unfair:
"The sums of money involved, together with the amounts of documentation, render this matter inappropriate for resolution by way of adjudication. It is not possible to deal with this matter in the time that is available."
"We also stress that the last three points cannot be cured simply providing an extra two weeks (or any further period) in the event that Knowles agree to such an extension."
"may request any party to the contract to supply him with such documents as he may reasonably require."
"whose principal task will be [to] assist me in handling and collating the many valuations and accounts that need to be considered."
At one stage Birse made a complaint of procedural unfairness in relation to a hearing with the Assessor where each party put forward an audit trail to prove certain documents. In cross-examination Birse's expert, Mr Crowter, accepted that the matter had been dealt with properly.
"As a consequence of your decisions regarding discovery, no doubt due to the inherent nature of the process in which the parties are engaged, it has been denied the opportunity to properly investigate and/or assess the claims made against it to significantly test the assertions made and be in a position properly to defend that case."
1) A quantum experts' meeting on 30th January 2004;
2) Hearings on 2nd and 4th February 2004 for witnesses of fact;
3) A 'sweep up' hearing for legal submissions on 16th February 2004;
4) The decision be delivered on 23rd February 2004.
The letter concluded by inviting the Adjudicator to draw the conclusion that CIB had failed to prove its case.
"We are concerned that, when you later considered the amounts which should be deducted from the cladding claims at paragraphs 14.20 and 14.21 of your decision you have made an accidental slip by not fully taking into account this finding when undertaking your valuation."
"The matter which has been raised by Hammonds, namely the way in which the decision at paragraphs 9.609.15 of the decision have been applied in section 14, is an issue with which I am familiar. I am aware that it could have been argued on both sides that the figure to be deducted from the E3 account by reason of the decision at paragraph 9.15 could have been materially different from those which I, in fact, accepted. In the circumstances of the adjudication, particularly the pressure of time, I consider the appropriate decision was to accept Mr Crowter's figure for categories Z2, Z3 and Z4 in full. I fully accept that had time been available Birse would have contended for much greater deductions and CIB for lesser deductions. Given the exchange between the parties I do not consider that it would be useful for me to express any view on whether my approach contains any error. If the parties or the court decide that there is any error I should be happy to review the decision and to receive further submissions from the parties "
The Decision
"The scheme does not envisage that there should be a provisional resolution of a dispute by an Adjudicator at all costs. That would be far greater an injustice than that which the HGCR Act was enacted to remedy."
"I consider that I have been able to do substantial justice between the parties and to arrive at an overall figure which reflects the merits of the case as I find them."
Birse's Contentions
1) The alleged secret preparation for adjudication.
2) The alleged failure to refer to the possibility of an adjudication in correspondence with Birse.
3) After they decided to go to adjudication CIB allegedly gave the false impression that they were prepared to enter into meaningful discussions.
4) Refusal to answer and/or dilatory conduct in answering Birse's questions.
5) The dilatory conduct in copying the 52 files.
6) The statement that they would consider further Birse's points made at the meeting on 5th November 2003.
7) The statement on 5th November 2003 that CIB would be providing further information in relation to its corporate structure.
"I was able merely to make inferences as to the magnitude of the cost relative to the work that was left and draw inferences about the time it took but I was not able to quantify or understand why these things happened or understand the processes that had gone on after Birse left the site. Birse did not have that information other than the 52 files which were merely an audit trail to the money. There was no explanation as to how the money had been spent."
1) The fact that over £12 million plus VAT and interest was claimed.
2) Forty-nine files were filed with the referral notice containing 24 experts' reports on defects, 18 lever arch files of reports on quantum, and 16 witness statements.
3) A further 52 files relating to CIB's E3 claim.
4) A further 55 files served by the parties in the course of the adjudication.
5) There were very significant issues to be considered in the course of the adjudication.
CIB's Contentions
1) That in his letter dated 19th March 2004 the Adjudicator indicated that the figures in his adjudication represented his considered view;
2) The decision is explicable by the fact that the Adjudicator was unable to accept in full either of the experts' figures and came to his own conclusion which was properly reflected in his award;
3) That in saying that he is prepared to review his decision if the parties agreed that he had made an error or that he would review it if the decision of the court was that he was required to do so, he was not making any concession or admission that he had, in fact, made an error.
Conclusions