BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just Β£1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Hackwood Ltd v Areen Design Services Ltd [2005] EWHC 2322 (TCC) (31 October 2005) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2005/2322.html Cite as: [2005] EWHC 2322 (TCC), (2006) 22 Const LJ 68 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
IN AN ARBITRATION CLAIM
Royal Courts of Justice Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Hackwood Ltd |
Claimant |
|
- and - |
||
Areen Design Services Ltd |
Defendant |
____________________
Mr. Andrew Goddard QC (instructed by Lane & Partners) for the Defendant
Hearing dates: 21st October 2005
____________________
Crown Copyright ©
Mr. Justice Field :
Introduction
39B Arbitration
A reference in clause 39B to a Rule or Rules is a reference to the JCT 1998 edition of the Construction Industry Model Arbitration Rules (CIMAR) current at the Base Date.
39B.1.1 Where pursuant to article 6A either Party requires a dispute or difference to be referred to arbitration then that Party shall serve on the other Party a notice of arbitration to such effect in accordance with Rule 2.1 which states:
"Arbitral proceedings are begun in respect of a dispute when one party serves on the other a written notice of arbitration identifying the dispute and requiring him to agree to the appointment of an arbitrator";
and an arbitrator shall be an individual agreed by the Parties or appointed by the person named in the Appendix in accordance with Rule 2.3 which states:
"if the parties fail to agree on the name of an arbitrator within 14 days (or any agreed extension) after;
(i) the notice of arbitration is served, or
(ii) a previously appointed arbitrator ceases to hold office for any reason, either party may apply for the appointment of an arbitrator to the person so empowered."
39B.2 Subject to the provisions of article 6A and clause 30.8, the Arbitrator shall, without prejudice to the generality of his powers, have power to rectify this Contract so that it accurately reflects the true agreement made by the Parties, to direct such measurements and/or valuations as may in his opinion be desirable in order to determine the rights of or the Parties and to ascertain and award any sum which ought to have been the subject of or included in any payment and to open up, review and revise any account, opinion, decision requirement or notice issued, given or made and to determine all matters in dispute which shall be submitted to him in the same manner as if no such account, opinion, decision, requirement or notice had been issued, given or made.
The facts
Areen Design Services Limited
(Address)
Attention Mr. Peter Heath
Dear Sir
HACKWOOD HOUSE BASINGSTOKE
We refer to our various discussions and meetings and to your letter dated 16 March 2001 confirming your offer to complete the design, construction and fitting out of the works on the above project in the sum of £13,200,000.00 (Thirteen Million Two Hundred Thousand Pounds) excluding VAT.
We confirm our instruction for you to formally commence on site on 5 June 2001 with a construction programme on site of 65 weeks completing on 2 September 2002. We also confirm that the basis of the contract will be the Standard Form of Building Contract with Contractor's Design 1998 Edition incorporating Amendments 1:999, 2:2000, 3:2001.
Would you please take this letter as our formal instruction to proceed with the design, construction and fitting out of the works as set out in the Contractor's Proposal document, pending the issue of the formal contract documentation which is currently being prepared for completion by yourselves and our company.
In the event that a formal contract is concluded then all work instructed and carried out under this letter and any sums paid by us shall be taken into account.
If for whatever reason we at any time give notice to cease work (in which event you shall as soon as practicable cease all work) we shall reimburse all reasonable and proper costs incurred by you in accordance with the terms of this letter.
Please sign below and return this letter to us.
Yours faithfully
For and on behalf of
HACKWOOD LIMITED
Did the 4th June letter incorporate the terms of The JCT Contract?
"Pending execution of a formal contract based upon an amended standard form of Building Contract with Contractor's Design 1998 Edition . and any further amendments as specified and any other amendments as may be agreed between ourselves, we hereby issue this letter of intent of instruction in relation to your firm price tender for the execution of the above works ."
Until the execution of a contract in the form referred to above .. the terms of payment and all other terms and conditions, including the arbitration agreement in Article 5 (sic), shall be as contained in the form of contract referred to above."
The amendments are, as I have already indicated, those set out in the schedule. It would be theoretically possible to carry out work even of this substantial nature and magnitude on an unamended JCT form, but it would not be possible to do so on an unamended JCT form which did not have some, at least, of Appendix 1 to that contract completed, because that Appendix requires decisions as to matters essential to an effective contract for any work, and certainly this work. Unless the options are selected and the Appendix is completed the form is incomplete and unusable and lacks the certainty required for the contract and envisaged by it. I cannot believe that the defendant would have allowed work to have started on such an uncertain basis, or that the claimant would have accepted such uncertainty. Accordingly. I read the words "amended standard form" as including the defendant's proposals set out in the schedule as it relates to the Appendix.
Are the arbitral proceedings properly constituted?
Are Hackwood debarred from participating in the arbitration?
A person alleged to be a party to arbitral proceedings but who takes no part in the proceedings may question
(a) whether there is a valid arbitration agreement,
(b) whether the tribunal is properly constituted, or
(c) what matters have been submitted to arbitration in accordance with the arbitration agreement,
by proceedings in the court for a declaration or injunction or other appropriate relief.
Conclusion