BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Pearson Pension Funds v Gurney Consultants [2005] EWHC 2804 (TCC) (01 December 2005) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2005/2804.html Cite as: [2005] EWHC 2804 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Fetter Lane, London, EC4A 1HD |
||
B e f o r e :
____________________
PEARSON PENSION FUNDS |
Claimant |
|
- and - |
||
GURNEY CONSULTANTS |
Defendant |
____________________
MR. PAUL SUTHERLAND (instructed by Messrs. Reynolds Porter Chamberlain) for the Defendant
____________________
Crown Copyright ©
HIS HONOUR JUDGE PETER COULSON QC:
(a) the court will not grant amendments if they cause irredeemable prejudice as a result of their lateness (see Woods v. Chaleff [1999] EWCA (Civ) 1522);
(b) the court will not grant late amendments if it means that the trial date will be lost (again, see Woods v. Chaleff and Cobbold v. London Borough of Greenwich [1999] EWCA (Civ) 2074).
These amendments include all the amendments to the Part 20 particulars of claim (excluding paragraphs 55, 58(mm) and 79A) and paragraphs 1-11 of the further information on causation. Having heard the parties, it is clear that:
(a) these amendments do not affect the trial date;
(b) further particulars of the allegations are required and will be served by Gurney on either 2nd or 6th December;
(c) it is appropriate and convenient for both Pearson and for the Part 20 defendants to deal with these new points by making consequential amendments and serving supplementary factual and expert evidence if so advised. That material will have to be served on Gurney no later than 4.30 p.m. on 13th December 2005.
Category 2
(a) The reduction in the size of the column.
"Further, any failure of the column and/or inadequacy in its ability to withstand vertical loads was attributable to the foregoing reduction in the size of the column without any reference to Gurney. Without that reduction the column would have been about 33 per cent larger in cross-section and would have had spare load capacity of about 50 per cent and the collapse would not have occurred."
(b) The Mechanism of Collapse
Category 3 deals with amendments as to quantum. As I have said, it is of no interest to the Part 20 defendants. It is, however, of great interest to Pearson. On their behalf Mr. McMullan originally said that Category 3 appeared to comprise the entirety of Gurney's counter-schedule of loss and damage. However, in essence it became apparent that Pearson's objections boiled down to three points proposed to be added to the counter-schedule:
(a) Point 1: Gurney's case that, but for the collapse, the works would have been finished in August and December 1999, as opposed to Pearson's case that the works would have been completed by February, March and May 1999;
(b) Point 2: Gurney's case that, following the collapse, numbers 8 and 10 should have been completed by 16th October 2000 not 15th or, in the alternative, 22nd January 2001, the dates asserted by Pearson;
(c) Point 3: Gurney's case that, following the collapse, the remedial works should have been commenced in May 1999 not the end of August 1999.
I deal with each of those points below.
Point 1: Notional Completion
(a) Pearson always had to prove the notional completion dates which they relied on. This point was always, therefore, in issue. Furthermore, as a result, at least some of the points raised by Gurney in their Point 1 amendment would have beeen permissible by way of cross-examination in any event;
(b) I am not persuaded that Point 1, on its own, first advertised by Gurney on 11th November, will have the consequences asserted by Mr. McMullan. I accept, of course, that it is going to involve additional work that Pearson are going to have to carry out, but on the material that I have I am confident that Pearson can be ready to deal with Point 1 properly by the time of the trial in the latter part of January. It is perhaps right to point out that an adjudicator could deal with and decide this point in less than the period available to Pearson to prepare the additional evidence that they will need in order to supplement the statement of Mr. Jeanes.
(a) that the parts of Mr. Tipling's report that support the three notional dates relied on by Gurney together with all the supporting material be provided to Pearson by 4.00 p.m. tomorrow, 2nd December;
(b) that permission to Gurney to rely on expert programming evidence is limited to those parts of Mr. Tipling's report that have been provided to Pearson by 4.00 p.m. on 2nd December 2005;
(c) that Pearson have permission to produce and rely on their own expert programming evidence and further factual evidence in response, confined solely to this issue, such report and further evidence to be provided to the other parties and the court by Thursday, 12th January 2006.
Point 2: Actual delay in completion on number 8 and number 10
Point 3: Actual Delay in Commencement
Conclusion on Category 3