BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> ALE Heavylift v MSD (Darlington) Ltd [2006] EWHC 2080 (TCC) (31 July 2006) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2006/2080.html Cite as: [2006] EWHC 2080 (TCC) |
[New search] [Printable RTF version] [Help]
HIGH COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
ALE HEAVYLIFT |
Claimant |
|
- and - |
||
MSD (Darlington) Ltd |
Defendant |
____________________
Audio & Verbatim Transcription Services
10 Herondale, Haslemere
Surrey GU27 1RQ
Telephone : 01428 643408
MR. B. QUINEY (instructed by Merritt & Co) for the Defendant
Hearing dates: 31st July 2006
____________________
Crown Copyright ©
HIS HONOUR JUDGE TOULMIN CMGC:
The Facts
35 Dispute Resolution
"35(b) The Scheme for Construction Contracts contained in the Scheme for Construction Contracts (England and Wales) Regulations 1998 (The Scheme) or any amendment or re-enactment thereof for the time being in force shall apply to the contract. The person (if any) specified in the contract to act as Adjudicator may be named in the offer. The specified nominating body to select Adjudicators shall be the Construction Plant Hire Association acting by its President or Chief Executive for the time being. In paragraph 21 of the scheme" this paragraph "shall be deleted and 'paragraph 20' substituted.
"35(c) The owner and the hirer shall comply forthwith with any decision of the Adjudicator and shall submit to summary judgment and enforcement…in respect of such decisions in each case without any defence, set-off, counterclaim, abatement or deduction…"
"We are pleased to inform you that we confirm our order for the hire of your Gottwald AK912 crane in line with your quotation ALE-HL-254/rev1 and as agreed in our meeting dated 15th August 2005 with yourself, Mr. I Cottam, Mr. M. Johnson and the undersigned.
"Please note the error in your quotation under the heading of Option 2. The rail possession starts from midnight Saturday 10th September to 0500 hours Monday 12th September 2005."
"As quote 'ref ALE-HL-254/rev1 and our letter 16.08.05."
"(1) A party to a construction contract may not withhold payment after the final date for payment of a sum due under the contract unless he has given an effective notice of intention to withhold payment…
(2) To be effective such a notice must specify
(a) the amount proposed to be withheld and the ground for withholding payment or
(b) if there is more than one ground, each ground and the amount attributable to it, and must be given not later than the proscribed period before the final date for payment.
(3) The parties are free to agree what the prescribed period is to be. In the absence of such agreement, the period shall be that provided by the Scheme for Construction Contracts."
"(10) Any notice of intention to withhold payment mentioned in section 111 of the Act shall be given not later than the prescribed period, which is to say not later than seven days before the final date for payment determined in accordance with the Construction Contract or where no such provision is made in the contract in accordance with paragraph 8 above."
"The contract was made on or about the 16th August 2005 and was in the form of the following documents."
"In conclusion ALE. seeks that the Adjudicator makes the following decision (which will be binding between the parties) to have the effect set out in section 108(3) and/or paragraph 23 of the Scheme.
17.1 That MSD do pay forthwith to ALE the sum of £94,000 as per ALE's invoice i.e 495, dated 30th September 2005…"
"MSD denies that the sum of £94,000 is payable under the invoice dated 30th September 2005 as a result of the adjudication. First because as set out above MSD believes that adjudication under the Scheme or Act should not apply to the contract. Second, the sum is not due and in the alternative (which is strenuously denied) if any sums were due then there is a valid counterclaim in excess of the amount in the invoice."
"Accordingly on that basis I find that the purported notice in the form of the letter from Merritt & Company of the 17th November 2005 is ineffective as a withholding notice. Notwithstanding that, I have considered the letter of the 17th November 2005 and I do not consider that it meets the requirements of section 111."
"ALE. carried out the work albeit over periods different from those envisaged in options 1 and 2. From the submissions and evidence provided by the parties I find that ALE. are entitled to the sum claimed of £80,000, plus VAT. As I have said, for the reasons given, I have not considered MSD's counterclaim."
The Law
"108(3) The contract shall provide that the decision of the Adjudicator is binding until the dispute is finally determined by legal proceedings…or by agreement."
"Had answered directly the questions put to him."
"If he answered the right question in the wrong way his decision will be binding. If he answered the wrong question it would be a nullity."
"85. The objective which underlines the Act and the statutory scheme requires the courts to respect and enforce the Adjudicator's decision unless it is plain that the question which he has decided was not the question referred to him or the manner in which he has gone about his task is obviously unfair. It should only be in rare circumstances that the courts will interfere with the decision of an Adjudicator. The courts should give no encouragement to the approach adopted by DML in the present case…which may indeed be aptly described as 'simply scrabbling around to find some argument to resist payment'."
"Section 107(1). The provisions of this Part only apply where the construction contract is in writing and any other agreement between the parties as to any matter is effective for the purpose of this Part only if in writing…
(2) There is an agreement in writing
(a) if the agreement is made in writing (whether or not it is signed by the parties)
(b) if the agreement is made by exchange of communications in writing
(c) if the agreement is evidenced in writing…."
"An exchange of written submissions in adjudication proceedings or in arbitral or legal proceedings in which the existence of an agreement otherwise in writing is alleged by one party against another and not denied by the other party in its response constitutes as between those parties an agreement in writing to the effect alleged."
"There was no intention by Parliament to provide that submissions made by a party to an un-authorised adjudication should give to the supposed Adjudicator a jurisdiction which he did not have when appointed."
"Subsection (5) is a specific provision. Where there has been an exchange of written submissions in the adjudication proceedings in which the existence of an agreement, otherwise than in writing, is alleged by one party and not denied by the other, then that exchange constitutes 'an agreement in writing' to the effect alleged."
"19. On the point of construction of section 107 what has to be evidenced in writing is literally the agreement which means all of it. A record of the agreement also suggests a complete agreement, not a partial one. The only exception to the generality of that construction is the instance falling within subsection 5, where the material or relevant parts alleged and not denied in the written submissions in the adjudication proceedings are sufficient."
"The common law rules of natural justice and procedural fairness are two-fold. First, the person affected has the right to prior notice and effective opportunity to make representations before a decision is made. Secondly, the person affected has the right to an un-biased tribunal."
"(c) The court has stayed the proceedings or judgment."
"Where a judgment is given or order made for the payment of money and the court is satisfied
(a) that there are special circumstances which render it inexpedient to enforce the judgment or order or
(b) that the applicant is unable from any cause to pay the money
then…the court may by order stay the execution of the judgment, or order…either absolutely or for such period and subject to such conditions as the court thinks fit."
"In my view, on an application for a stay, where a party has entered into a contract with a company whose financial status is or may be uncertain and finds itself liable to pay money to that company under an Adjudicator's decision, the question may properly be posed: is this not an inevitable consequence of the commercial activities of the applicant that it finds itself in the position it is in? It has, as it were, contracted for the result. That is not normally a ground for avoiding the consequences of a debt created by the contractual mechanism (which is how in the absence of express terms adjudication operates – see section 114 of the Act). It is very easy (and prudent and relatively inexpensive) to carry out a search or to obtain credit references against a company whose financial status and standing is unknown. Not to do so inevitably places a person at a significant disadvantage.
"It has only itself to blame if the company selected by it proves not to have been substantial (as opposed to a material deterioration since the date of the contract)."
Conclusions