BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Harlow & Milner Ltd v Teasdale [2006] EWHC 54 (TCC) (16 January 2006) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2006/54.html Cite as: [2006] EWHC 54 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
B e f o r e :
B E T W E E N :
____________________
HARLOW & MILNER LTD. | Claimant | |
- and - | ||
LINDA TEASDALE | Defendant |
____________________
THE DEFENDANT did not appear and was not represented.
____________________
Official Shorthand Writers and Tape Transcribers
Quality House, Quality Court, Chancery Lane, London WC2A 1HP
Tel: 020 7831 5627 Fax: 020 7831 7737
Crown Copyright ©
JUDGE COULSON QC:
"The issue of liability for costs [would be] reserved to a Judge at the Technology and Construction Court".
(a) That the Claimant's work is defective and there is therefore a counterclaim in her favour;
(b) That the adjudication proceedings were in some way unfair, partly because the proceedings were so quick;
(c) That there is a risk that the Claimant will be unable to repay any sums that may eventually be found to be due to the Defendant.
(a) Defective work
This was a matter that could have been, and up to a point was, raised in the adjudication proceedings. In any event the Defendant is not entitled to set up such matters by way of a defence of set off to a claim based on an existing adjudicator's decision: see, amongst many other cases on this topic, VHE Construction v RBSTB Trust Company [2000] BLR 107.
(b) Unfair
The Defendant's complaint appears to focus on the speed with which the adjudication was conducted. That simply misses the point altogether. Adjudication is supposed to be quick; that is its main feature. The only question for the court, when points of fairness are raised by the unsuccessful party in an enforcement application, is to consider whether or not the adjudicator failed to allow the Defendant to raise or answer points made by the Claimant, or in some other way ignored the submissions made by the Defendant. On the material that I have, there is nothing to suggest that the adjudicator conducted this adjudication in anything other than an entirely fair and appropriate way. The Defendant was allowed to make all the points that she wished to make during the adjudication, and there was no question of any breach of the rules of natural justice.
(c) Risk that the claimant would be unable to repay
The risk that the Claimant might be unable to repay any sums awarded is not of course a defence to an application for summary judgment in any event. At best it might be a reason to stay any judgment that I give. The principles governing a stay in these circumstances are summarised in Wimbledon Construction v Vago [2005] BLR 374. There is no evidence here on which I could find that the Claimant might be unable to repay any of the sums ordered by the adjudicator, or that there are any other factual matters which should lead me to exercise my discretion in favour of a stay.