BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Estor Ltd v Multifit (UK) Ltd [2009] EWHC 2108 (TCC) (12 August 2009) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2009/2108.html Cite as: 126 Con LR 40, [2009] EWHC 2108 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
ESTOR LIMITED |
Claimant |
|
- and - |
||
MULTIFIT (UK) LIMITED |
Defendant |
____________________
Paul Stafford (instructed by Blakemores) for the Defendant
Hearing dates: 7 August 2009
____________________
Crown Copyright ©
Mr Justice Akenhead :
Introduction
The factual background
"Can you please [review] this and send me [an] order confirmation by return e-mail. I have also attached our company account form and my first quote to hub design.
I have also given Alan a cheque for £7850 plus vat (Total £9223.75p inc) for his payment for the manufacturing.
We still owe him £7050 plus Vat just to make sure that he can complete on time (originally not in our contract)
Summary of Works:
Main contract Value £82,635 plus Vat
Extras:
1. Plying floor areas £2660.00
2. Main shop £1200.00
3. Fire alarm £7000.00
4. Safety Beacon on back fire doors £500.00
5. Armour colour to visual wall areas only £5200.00
6. Plumbing costs to form changes and fit extra back wash and additional chemical pump £1265.00
7. Extra shot fitting costs due to changes in existing fire lobby £1450.00
8. Extra cost to move location of the fire alarm panel £250.00
9. Total costs of the bling ceiling feature £14,900.00 (excluding payment made by hub design
10. Specialist fittings required to the bling feature supplied by multifit £96.00
Total cost £117,156+ VAT
Balance paid so far from Hub design to Multifit UK Ltd £46,545.00 + Vat
Total remaining £70,611.00 plus VAT
Items Not allowed for:
- payment of Air conditioning.
- cost of the resin flooring.
- Cost of armour colour if applied on all wall areas.
- Any final connection charges for any services supplying unit 2025
- Supplying Chelsea Artisan specialist glass."
"I/We consent to My/Our Bankers providing a Credit Reference on me/us on an ongoing basis
I/We hereby apply for credit facilities to be granted to me/us and confirmed that we will comply with your Trading Terms and agreed to be bound by your standard terms and conditions of sale"
It was accepted by Multifit's Counsel that the second of these two entries was immaterial as both parties knew that Mr Warner did not want credit facilities.
"…that's fine can you carry the work out from the [revised] quote. thank you. if have any problems just call me"
There was no hint or indication in that email as to which company was accepting Multifit's quote.
The Adjudication
(i) Was the contract between Multifit and Estor, Ginger Group Ltd and Westfield? If so, was it in writing for the purposes of the Housing Grants and Regeneration Act 1996 ("HGCRA")?
(ii) Was Multifit responsible for the resin flooring?
(iii) Were there defects in the resin flooring and elsewhere for which Multifit was liable?
(iv) Costs.
The first issue was obviously a jurisdictional issue. It is accepted that Estor reserved its position about the adjudicator's jurisdiction.
(i) There was a contract between Multifit and Estor; in this context, he provided some detailed reasoning. He was impressed by the fact that the credit check was agreed to be done on Estor and he believed that no explanation had been offered as to why someone should "obtain a credit check on another and then contract with a different party that it knew had a poor credit rating". He formed the view that the contract was evidenced by the emails of 20 and 23 October 2009, Multifit's quotation of 23 September 2008, the credit reference form signed by Mr Warner and Multifit's Terms and Conditions referred to in that form.
(ii) There was no novation of the contract, by which Multifit was substituted for Hub.
(iii) As for the resin floor, he found on a balance of probabilities that CT Flooring was a sub-contractor of Multifit, that the contract between Multifit and Estor originally did not include the work but somehow thereafter Multifit became responsible for it and that Multifit was responsible to Estor for it.
(iv) None of the defects were proved on a balance of probability.
(v) £37,624 inclusive of VAT was due to Multifit.
(vi) So far as costs were concerned, he decided that Estor should pay £6,240 for Multifit's costs. In respect of his fees and expenses, he had an invoiced sum of £22,907.25, which he ordered Multifit to pay; of that sum, he ordered Estor to pay £17,760 exclusive of VAT. He had presented a bill after the abortive adjudication on 15 May 2009 in the sum of £4,347inclusive of VAT for time spent. He wrote to the parties saying that there was an "overlap" between his work on the abortive adjudication and the later one and in effect said, that where there was an overlap he proposed to take it into account. In effect, what he was saying was that, where there was work which he had done on the abortive adjudication which did not have to be duplicated second time round, he would take it into account but, where the time on the abortive adjudication was wasted, Multifit would have to bear it.
These proceedings
(i) There was no construction contract between Estor and Multifit.
(ii) There was no construction contract in writing as required under Section 107 of the HGCRA.
(iii) The adjudicator decided that there was a different contract from that identified by Multifit in the Notice of Adjudication or Referral Notice.
(iv) The adjudicator decided that Multifit's terms and conditions were applicable and there were unwritten terms in respect of the resin floor.
(v) The adjudicator had no jurisdiction to decide that Estor should pay the lion's share of the costs or at least any part of his fee for the abortive adjudication.
This was opposed and challenged by Multifit which argues that there is simply no realistic defence to its application for summary judgement.
The law
Discussion
(i) There is no disagreement between the parties that the adjudicator had jurisdiction to decide which party should pay his fees and in what proportions.
(ii) Arithmetically, he has ordered Multifit to pay the whole of his bill of £22,907.25. Presumably and predictably he knew that Estor would not pay initially; of this, he ordered Estor to pay to Multifit £17,760, which excluded VAT. Thus, Multifit had to pay a net £5,147.25 of his bill itself. The total bill was broken down as to £19,215 plus £2882.25 VAT. Therefore, in fact he required Multifit to be responsible for £1455 net of VAT of his bill although in his decision he says that Multifit should bear only £1365 plus VAT. Thus, he appears in one sense to have put down to Estor's account £2,325 of his account for the abortive adjudication (£3,780-£1,455), which at his rate of £210 per hour equates to about 11 hours.
(iii) It seems clear that what the adjudicator did was to assess what part of his bill was abortive and charge Multifit with that. He decided that some time spent on the abortive adjudication should be capable of being the subject of his order against Estor because that time would otherwise have had to have been spent again and in the ordinary course of events that was fair. Put another way, he was saying that 11 hours' worth of his time on the abortive adjudication was hours worked which he did not have to do a second time round but which he would have had to do for the purposes of the second adjudication.
(iv) This is not an issue of jurisdiction at all. The adjudicator had a discretion under the jurisdiction which he had (subject to the issue of who the contract was with). He exercised it and allowed within the ambit of fairness a reasonable amount to be borne by the losing party. The losing party loses no more than it would have done if the abortive adjudication had not taken place. There can be no challenge about the amount of hours worked so far as this enforcement is concerned; that can be taken up with the adjudicator.
(v) Even if I was wrong, the adjudicator's decision would still be enforceable save in respect of the identifiable part of his decision upon which on that premise he did not have jurisdiction, namely £2,325; he would simply have included a clearly identifiable element on which he did not have jurisdiction. It is no different from a decision in which two sums are awarded to a claimant and on one of them the adjudicator had no jurisdiction. The Court will usually enforce the part of the decision in respect of which he had jurisdiction. I do not in this regard consider that my observations in Cantillon v Urvasco [2008] EWHC 282 (TCC) (Paragraph 63) were wrong or need distinguishing: here, if the adjudicator had no jurisdiction over the fees for the abortive adjudication, it could be said that the dispute about that fee was a separate dispute, the decision upon which was severable and separable from the rest of the decision.
Decision