BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> LPI (Hotels) Ltd v Technical & General Guarantee Company SA [2010] EWHC 2049 (TCC) (02 August 2010) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2010/2049.html Cite as: [2010] CILL 2926, 132 Con LR 90, [2010] EWHC 2049 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
LPI (HOTELS) LIMITED |
Claimant |
|
- and - |
||
TECHNICAL & GENERAL GUARANTEE COMPANY SA |
Defendant |
____________________
Alexander Nissen QC (instructed by Bayham Solitors LLP) for the Defendant
Hearing dates: 29 July 2010
____________________
Crown Copyright ©
Mr Justice Akenhead:
The Law and the Practice
"(1) The Court has discretion as to-
(a) whether costs are payable by one party or another;
(b) the amount of those costs; and
(c) when they are to be paid…
(4) In deciding what order (if any) to make about costs, the court must have regard to all the circumstances, including-
(a) the conduct of all the parties…
(6) The orders which the court may make under this rule include an order that the party must pay-
(a) a proportion of another party's costs…
(c) costs from or until a certain date only..
(e) costs relating to particular steps taken in the proceedings…
(f) costs relating only to a distinct part of the proceedings at…"
"Expert evidence shall be restricted to that which is reasonably required to resolve the proceedings."
CPR Part 35.4 prevents parties from calling experts or putting in evidence expert reports without the Court's permission. In the TCC, the issue of expert evidence will almost invariably be raised at the first Case Management Conference and then reviewed as necessary for instance at the Pre-Trial Review. In practice, the parties, their solicitors and Counsel will often agree that experts in a certain discipline may be called and such agreements will be reflected in the Court's order. Although the Court necessarily retains a discretion in this regard to refuse permission to call experts, it will be common for the Courts to endorse a consent order in this regard, particularly where experienced solicitors and Counsel are involved and relatively large sums are in issue. However, the fact that the Court has endorsed without query or specific investigation can not be taken as an endorsement that it was reasonable or necessary to have such expert evidence.
"31. In other words what is required is a two-stage approach. There has to be a global approach and an item by item approach. The global approach will indicate whether the total sum claimed is or appears to be disproportionate having particular regard to the considerations which Part 44.5(3) states are relevant. If the costs as a whole are not disproportionate according to that test then all that is normally required is that each item should have been reasonably incurred and the cost for that item should be reasonable. If on the other hand the costs as a whole appear disproportionate then the court will want to be satisfied that the work in relation to each item was necessary and, if necessary, that the cost of the item is reasonable. If, because of lack of planning or due to other causes, the global costs are disproportionately high, then the requirement that the costs should be proportionate means that no more should be payable than would have been payable if the litigation had been conducted in a proportionate manner. This is turn means that reasonable costs will only be recovered for the items which were necessary if the litigation had been conducted in a proportionate manner.
37. Although we emphasise the need, when costs are disproportionate, to determine what was necessary, we also emphasise that a sensible standard of necessity has to be adopted. This is a standard which takes fully into account the need to make allowances for the different judgments which those responsible for litigation can sensibly come to as to what is required. The danger of setting too high a standard with the benefit of hindsight has to be avoided. While the threshold required to meet necessity is higher than that of reasonableness, it is still a standard that a competent practitioner should be able to achieve without undue difficulty. When a practitioner incurs expenses which are reasonable but not necessary, he may be able to recover his fees and disbursements from his client, but extra expense which results from conducting litigation in a disproportionate manner cannot be recovered from the other party.
38. In deciding what is necessary the conduct of the other party is highly relevant. The other party by co-operation can reduce costs, by being uncooperative he can increase costs. If he is uncooperative that may render necessary costs which would otherwise be unnecessary and that he should pay the costs for the expense which he has made necessary is perfectly acceptable. Access to justice would be impeded if lawyers felt they could not afford to do what is necessary to conduct the litigation. Giving appropriate weight to the requirements of proportionality and reasonableness will not make the conduct of litigation uneconomic if on the assessment there is allowed a reasonable sum for the work carried out which was necessary."
This case
"At [the meeting of the 21 July 2008] it became clear that, even on a best case scenario, the Contractor was in considerable difficulties, was technically insolvent and not in a position to trade. The Claimant's representative David Drew formed the view that the Contractor had not hitherto fully appreciated its financial position. However, the Claimant now has reason to believe that Mr Drew was mistaken in this regard and in fact the Contractor had for some time been aware of the extent of its financial difficulties. It was apparent to all at that meeting that the works would not be completed by the Contractor as it was not able to perform its obligations under the Building Contract despite the assistance provided by the Claimant. As the minutes of that meeting (Attached…) record, the Contractor indicated that it had no option but to cease all works on site and the Claimant confirmed that, if it did so, security would be brought to the site to secure the site and minimise the Contractor's losses."
(1) The first sentence… is denied:
(b) It is specifically denied that the Contractor was insolvent and/or technically insolvent, as set out above;
(c) It is specifically denied that the Contractor was not in a position to trade…
(4) The fourth sentence of Paragraph 12 is denied:
(a) It is denied that the Contractor was not able to perform its obligations under the Building Contract as alleged and/or at all."
In Paragraph 32, the Defendant denied an allegation that the winding up order was made "as anticipated" and it went on to plead that:
"The Claimant's improper and tactical issue of the Negative Valuation (which, for the avoidance of doubt, is denied) led the Contractor to believe that its prospects of defeating the petition were fatally affected…"
This Negative Valuation was produced on behalf of LPI on 21 July 2008 and purported to show a substantial six-figure sum due from the Contractor to LPI.
Paragraph 36(4) pleaded:
"It is reiterated that the cessation of trading and/or decision not to defend a winding up petition was brought about by the Claimant's unconscionable conduct and/or breaches of the implied terms of the Building Contract, as more fully particularised above. In the premises, if, which is denied, a cessation of trading amounts to and/or evidences a breach and/or repudiatory breach of contract, the Defendant avers that the Claimant is prevented from claiming relief as a result of such breach as to do so would enable the [Claimant] to rely upon and or benefit from its own breach of contract."
Discussion
Decision