BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> RWE Npower Plc v Alstom Power Ltd & Ors [2010] EWHC 3061 (TCC) (30 November 2010) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2010/3061.html Cite as: [2010] EWHC 3061 (TCC), 133 Con LR 155 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
RWE NPOWER PLC |
Claimant |
|
- and - |
||
(1) ALSTOM POWER LIMITED (2) ALSTOM NORWAY AS (3)ALSOM POWER SWEDEN AB (4) AMEC GROUP LIMITED |
Defendants |
____________________
Andrew White QC and Simon Hughes (instructed by Ms J Davin of AMEC Legal Department) for the Defendants
Hearing dates:8-9 November 2010
____________________
Crown Copyright ©
Mr Justice Akenhead:
The Site and the Works
The Contract
"Nothing contained in the Specification shall override or modify the application or interpretation of that which is contained in the Agreement or the Conditions of Contract"
Apart from this, the Contract documents were to be read together and to be considered as mutually explanatory of each other; this was subject to the priority to be given to the documents in the order set out in the first sentence of this paragraph.
(a) Clause 1.1
"1.1.27 "Contractor's Permits" means those consents, licences, permissions, assessments, orders and approvals or variations thereof required from an authority whether statutory, public, local, European or otherwise which are required for the performance of the Works as set out in Contract Schedule 5 and any non planning related or temporary consents, licences, permissions, assessments, orders and approvals required in relation to the construction of the Works and the Contractor's construction methodology but not including any Purchaser's Permits.
1.1.81 "Permits" means the Contractor's Permits and the Purchaser's Permits.
1.1.85 "Presumed Physical Ground Conditions" means the presumed physical ground conditions as set out at Contract Schedule 15.
1.1.92 "Purchaser's Permits" means all consents, licences, permissions, assessments, orders and approvals or variations thereof required from an authority whether statutory, public, local, European or otherwise including (without limitation) those as may be required by the Environment Agency to be obtained by the Purchaser or as set out in Contract Schedule 5 and any other planning related consents, licences, permissions, assessments, orders and approvals required in relation to the permanent development of the Project but not including any Contractor's Permits.
1.1.111 "Specification" means the Purchaser's Specification and the Contractor's Specification and any modifications thereto made hereunder.
1.1.127 "Works" means all Plant to be provided and all Plant, work and things to be commissioned, designed, manufactured, supplied, executed, constructed, installed, completed, carried out, undertaken, tested or done by the Contractor to fully realise and put into commercial operation the Modified Units, all in accordance with or as reasonably inferred by the Contract and any reference to the "Works" includes a reference to a Section or part thereof."
(b) Clause 9.9.2
"Subject to Sub-Clause 13.3.4 the Purchaser does not warrant the accuracy or sufficiency for any purpose of the Purchaser's Information or any part thereof. The Contractor shall be responsible for verifying the correctness and sufficiency for any purpose of the Purchaser's Information and for any errors, omissions or discrepancies in the Purchaser's Information and accepts entire responsibility for any design contained in the Purchaser's Information."
The "Purchaser's Information" is defined in Clause 9.9.1 as the "Purchaser's Drawings, the Purchaser's Specification and any other information provided by the Purchaser or the Purchaser's Representative whether before or after the Contract Date".
(c) Clause 13.1
"The Contractor acknowledges that the gross generation output of each Unit will increase if and to the extent that the Purchaser renews and/or modifies the steam turbines at Aberthaw Power Station… Notwithstanding any such renewal and/or modification the Contractor warrants to and undertakes with the Purchaser that the Works will be carried out and that it will otherwise perform its obligations under the Contract:
(a) with all the skill, care and diligence as should be exercised by a suitably qualified, experienced, competent contractor, fully skilled and experienced in the carrying out of work similar in nature, complexity and extent to the Works; and
(b) in accordance with the Purchaser's Specification: and
(g) so that the Works and each Section shall when complete meet the relevant Guaranteed Performance Criteria; and…
(j) otherwise in all respects in accordance with the Contract.
Clause 13.2.1
"The Contractor shall obtain:
(a) the Contractor's Permits"
(d) Clause 13.3
"13.3.1 The Contractor warrants that prior to entering into the Contract, he has fully satisfied himself as to all local, regional, national and Site conditions including the nature, location and condition of Aberthaw Power Station and the Site which could affect the Works, including:
(a) the form, condition, nature and location of the Site and its surroundings and the services, artificial obstructions or hazards in or on the Site (including but not limited to ground, hydrographical, hydrological, climatic, geological, geotechnical, chemical and physical and subsoil conditions including all services, pipelines, cables and the like)…
(c) the coastal location and any associated coastal and marine conditions;
(d) the adequacy (including the load capacity) of access roads and all means of transportation and access to and from the Site;
(e) the equipment, facilities and resources (including accommodation) needed for the carrying out of the Works;
(f) the extent and nature of the work and materials necessary for the performance of its obligations under the Contract; and
(g) generally, or in any other local conditions including climatic and weather conditions and/or other conditions of or affecting the Site and all other risks, conditions and circumstances that affect or may affect the Contractor's ability to carry out the Works or the performance of its obligations under the Contract or both.
13.3.2 No failure on the part of the Contractor to discover or foresee any such condition, risk, or circumstance whether the same ought reasonably to have been discovered or foreseen or not shall entitle the Contractor to an addition to the Contract Price or to an extension of the Time for Completion.
13.3.3 The Purchaser gives no warranty and makes no representation as to the condition of the Site or of Aberthaw Power Station or of any services in or under the Site or Aberthaw Power Station or as to the accuracy or sufficiency of any survey data or other data contained in any document provided to the Contractor and any such representation previously made by or on behalf of the Purchaser is hereby withdrawn.
13.3.4 Notwithstanding Sub-Clauses 9.9.2, 13.1.1 and 13.3.3:
(a) if any of the following necessitates an alteration in, an amendment to, and omission of, an addition to or otherwise a variation of any part of the Works, then the Purchaser shall be deemed to have issued a notice pursuant to Sub-Clause 30.2.1 in relation thereto and the provisions of Clause 30 shall apply:
(i) any error in the Presumed Physical Ground Conditions…"
(e) Clause 13.4
"On agreeing the Contract Price the Contractor shall be deemed to have satisfied itself and taken account of:
(a) all the conditions and circumstances affecting the Contract Price including compliance with any relevant Law;
(b) carrying out the Works as described in the Contract;
(c) the general circumstances at the Site and Aberthaw Power Station…"
(a) Schedule 5
This listed seven specific consents or approvals required to be or already procured by RWE, including under the Electricity Act for the construction and operation of the FGD plant, a Deemed Planning Permission for Construction of the FGD plant dated 16 June 2004, "together with any other planning related consents, licenses, permissions, assessments, orders and approvals required in relation to the permanent development of the Project.". The Contractor's Permits were to comprise:
"1. Consent to discharge from site (if required) under Water Resources Act 1991
2. Special orders for abnormal load movements
3. Waste Management Licence during construction
4. Consent under Town and Country Planning Act for erection of signage
together with any non-planning related or temporary consents, licenses, permissions, assessments, orders and approvals require[d] in relation to the construction of the Works and the Contractor's construction methodology but not including the Purchaser's permits."
(b) Schedule 15
"The Presumed Ground Conditions are those described by items 1 to 6 of the Agreed Conclusion to Tender Questionnaire Item AA 010b, which is included in Part 4 of the Purchaser's Specification"
The Issues and Part 8
"Issue 1: Discharge
10.1 Subject to compliance with the remaining provisions of the Contract, was AA [the Contractor] entitled under the Contract and/or was RWE obliged physically to permit AA, by reference to paragraph 8.4.1 of the Environmental Statement at page 1312 Purchaser's Specification or otherwise to discharge water from the Sea Water Treatment Plant excavations via the existing outfall structure(s) identified in the Environment Agency Variation Notice, Table 3.1, page 2272 Purchaser's Specification?
10.2 If AA was so entitled and/or RWE so obliged under the Contract
(a) was such entitlement and/or obligation subject to any limit on suspended solids in the discharge water, and if so what? In particular was there
(i) by reference to Table 3.3 page 2273 Purchaser's Specification, a concentration limit of 50 mg/l?
(ii) by reference additionally to the table following page 770 Purchaser's Specification, a higher limit of 73 mg/l, 117 mg/l or otherwise (and if so what)?
(b) Was RWE obliged (by reference to the definitions of Purchaser's Permits and Contractor's Permits in sub-clauses 1.1.92 and 1.1.27 of the Conditions and to Contract Schedule 5, or otherwise) to secure any (and if so what) license or permit permitting the discharge by AA of water from the excavations from any (and if so what) discharge point? In particular-Was RWE obliged to obtain permission from the Environmental Agency for AA to discharge water from the SWTP excavations into the Seal Pit?
(c) If so, did any such obligation arise only upon AA making of RWE request, accompanied (by reference to sub-clauses 1.1.4.12, 2.1.2.12.1 of the Conditions or otherwise) by all technical and other information necessarily and/or reasonably required to enable RWE to make such an application?
Issue 2: Control by Sump Pumping
10.3 Do the "Presumed Physical Ground Conditions" (sub-clause 1.1.85 of the Conditions and Contract Schedule 15) include that inflow of water into the excavations would be "little more than seepage" as set out at paragraph 7 of AA 010a Tenderer's Response on page 83 2444, Purchaser's Specification, Volume 2?
10.4 if so-
(a) if the inflow of water into the excavations were to be significantly more than seepage, would that operate as an "error in the Presumed Physical Conditions" for the purposes of sub-clause 13.3.4 (a) (i) of the Conditions?
(b) does "water" for this purpose mean ground water only or does it also include
(i) seawater entering excavations by flooding or operation of tides, and/or
(ii) surface water entering excavations, and/or
(iii) water from any other source."
Issue 2
"The Contract is based upon the following assumptions…
5. Water Table: For open excavations, inflowing groundwater will not affect the stability of the excavation and can be controlled using sump pumping provided by the Contractor…
The tenderer confirms that no other assumptions regarding the existing ground conditions at the Site have been necessary in arriving at the design of the Works…"
"QUESTION TITLE: GROUND CONDITIONS: "CURRENT UNDERSTANDING"
PURCHASER'S QUESTION: In Part O, Tender Schedule 4, the tenderer states: "Should ground conditions prove to be different from our current understanding we reserve the right to revise our price."
Setting aside the issue of potentially "contaminated ground", the tenderer is requested to define comprehensively what constitutes his "current understanding" of "ground conditions" as they affect the design and construction of various parts of the works-inter alia, the sea water treatment plant…
AA10 TENDERER'S Response:
We confirm that our proposal is based on the ground conditions and site services indicated within the ITT [Invitation to Tender].
An interpretive geotechnical report has not been prepared at this stage, however, based on our knowledge and experience of the ground descriptions used in the site survey we have developed a design which we consider will be suitable.
Should the ground conditions proved to be different, or the descriptions inaccurate, we reserve the right to revise our price."
"The tenderer's response to Questionnaire Item No. AA 010 advises that he has based his design upon certain conditions derived from the information supplied in the Enquiry Document. In the tender, Part O, Tender Schedule 4, the tenderer indicates that prior to commencement of design work he will obtain additional information regarding ground conditions, validate the accuracy of reports across the entire FGD area and prepare an interpretive geotechnical report. In order to allow the effects of such work on the tenderer's design to be assessed, the tenderer is requested to describe in detail the following design parameters used in it, and in each case state whether they are based on data in the Enquiry Document or other assumptions…7. water table…9. All other design parameters influenced by ground conditions."
"The Site Investigation included within the Tender Enquiry Documentation is unclear and, in some instances, contradictory. Assumptions have therefore been made based on the exhibited investigation but supplemented by engineering judgement and previous experience…
7) Water Table
Water strike records within the enquiry document boreholes are contradictory-most boreholes have no indication of water at all. The ones that do vary from a depth of 0.9m to 7.5m below EGL. Even so, inflows appear to be little more than seepage.
For open excavations, it has been assumed that any water will be little more than seepage, will not affect the stability of the excavation and can be controlled using sump pumping. Photographs taken during previous contracts at Aberthaw seem to indicate dry excavations."
10.3 The relevant Presumed Physical Ground Condition is, for open excavations, inflowing ground water such as will not affect the stability of the excavation or such as can be controlled using sump pumping provided by the Contractor. Inflowing ground water in whatever quantities or of whatever type which affects the stability of the excavation or which can not be controlled using sump pumping is not within the Presumed Physical Ground Condition.
10.4 Since I have not answered Question 10.3 with a simple "yes" or "no", Issue 10.4 does not or does not necessarily follow but nonetheless I answer as follows:
(a) if there was an inflow of ground water which was significantly more than or even equivalent to seepage, that could operate as an "error in the Presumed Physical Ground Conditions" for the purposes of Clause 13.3.4 (a) (i) of the Conditions of Contract. However, the inflow would either have to affect the stability of the excavation or be such as could not be controlled using sump pumping. I specifically decline to speculate as to what scope and extent of any such sump pumping is envisaged by Paragraph 5 of the Agreed Conclusion.
(b) It is only "ground water" which is referred to in the Presumed Physical Ground Condition set out in Paragraph 5 of the Agreed Conclusion. It does not include seawater or other surface water directly entering the excavations. Again, I decline to decide the point at which water from any given source becomes "ground water".
Issue 1
(a) Clause 1.1.4.2
"The Contractor's responsibilities shall include but not be limited to the following.
- The overall and complete responsibility for project management, design, coordination and general management and security of the Works. This shall include the management of all interfaces between the respective stages of the Works, and all other work intended to be carried out including manufacture, procurement and delivery to the Site by or on behalf of the Purchaser.
- Subject to and in strict accordance with the provisions of the Conditions of Contract and the Purchaser's Specification the design, manufacture, supply deliver, construct, erect, test and commission the Works [sic], and provide defect rectification for the Defect Liability Period.
- The provision of all necessary plant, labour and materials, construction plant, temporary works, equipment, auxiliaries and accessories, special tools, and performing all operations and work required for design, fabrication, furnishing, delivering, transporting, installing, finishing, painting, testing and putting into commercial operation of the Plant…
- The construction of all foundations, structures and buildings, together with the erection and installation of all equipment, auxiliaries and accessories, putting the plant into operational service, making all adjustments required to ensure entirely satisfactory operation under all specified conditions. This element of work includes:
- the carrying out of studies, including air quality and water sampling, Site and soil investigations, necessary to establish the design of the Works and all other studies including noise studies and surveys and modelling required to complete all parts of the Works…
- the obtaining and maintenance of all necessary permissions and approval from local and other authorities with the exception of those major consents and licences which will be obtained by the Purchaser.
- All work not expressly called for in the Purchaser's Specification, but necessary for the complete and proper installation and operation of the equipment and accessories, which shall be performed and furnished by the Contractor at no additional cost to the Purchaser."
(b) Clause 1.1.4.4.4
"The scope of supply associated with the aforementioned plant, equipment and systems will include all necessary items as follow…
- Above- and below-ground civil works including but not limited to:
- excavations and disposal of arisings…
- temporary works…
- On-Site disposal of the waste arising from demolition work, in so far as such waste can be used in the construction of the Works, landscaping or other purposes at the direction of Purchaser
- Off-Site disposal of waste arising from demolition work, in so far as such waste cannot be so used."
(c) Clause 1.1.4.12
"The application for consent to construct under Section 36 of the Electricity Act 1989 was approved on 16 June 2004, together with Deemed Planning Consent Conditions…
The Plant shall be designed and constructed in such a manner as to comply with the Consent Conditions and Deemed Planning Consent Conditions during both construction and subsequent operation.
The tenderer shall make himself fully aware of the consent conditions and other relevant information details in Part 3.01 especially in relation to the anticipated layout of the plant…, noise control during construction, dust control, general drainage arrangements, approved routes are construction traffic and landscaping agreements…
The Contractor shall provide the necessary technical information and full support for the Purchaser, including presentations to local, statutory and other authorities, community groups and the Local Liaison Committee as necessary, in order that the Purchaser can meet these obligations and responsibilities, and satisfy the relevant authorities.
The Contractor shall be responsible for providing information required by the Purchaser for the various consents, the Integrated Pollution Prevention and Control (IPPC) Permit and related purposes in sufficient time to enable submissions to be prepared and approvals obtained by the Purchaser to meet the Contractor's own programme.
The Contractor shall be responsible for obtaining all other consents, licences and certificates during the construction period including, but not limited to, the following:
- Temporary consents, licences and agreements specifically required during the construction work, such as those associated with: heavy loads transport; drainage from the Site…"
(d) Clause 1.1.6.1
"The principal terminal points to the Works are defined below and detailed in Table 1.1.8. It shall be the responsibility of the Contractor to ascertain the suitability of these terminal points with regard both to the performance requirements of the plant and equipment supplied under the Contract, and the continued integrity of the existing plant. The definitions of terminal points in the following are provided to indicate to the tenderer the proposed physical location of interfaces between the Works and the existing power station"
Table 1.1.8 identified in effect the connection points between new work and plant to be supplied by the Contractor and the existing plant at the Power Station. Thus, it indicated where in the Seal Pit the Contractor was to break into in order to provide the Seawater inlet and discharge, running to a from the SWTP. There was no indication that these "terminal points" were to be or could be used for temporary works. However, various process water drains, sewerage, foul drainage and surface drainage points (connecting to existing systems) were identified.
(e) Clause 1.1.11.1
"The Plant shall be designed with due consideration to the maintenance of environmental quality and the impact that the Plant will have on the environment."
(f) Clause 1.3.2.3 provided that the Contractor was to arrange for the "design, supply, installation and testing of a separate dedicated water supply system for the Site…". Clause 1.3.2.4 provided for the drainage of surface water and for foul drainage.
(g) Clause 2.1.2.1.1
"Civil work shall include design, supply, erection and construction of all civil, structural, building services, landscape and architectural works reasonably implied and necessary the proper completion of the Works. Such definition shall include:
- Underground facilities including surface water and process drainage…"
(f) Clause 2.1.2.6.1
"Groundworks shall be executed in accordance with BS 6031:1981…
The Contractor shall properly dispose of water from the Site from whatever source during the construction phase. All contaminants whose presence would render water unsuitable for discharge into drains or watercourses external to the Site shall be effectively removed prior to discharge and, where appropriate, such extracted contaminants shall be transported to a licensed disposal site."
(g) Clause 2.1.2.12.1
"The Contractor shall design and construct all necessary drainage systems within the Site including surface water run-off…foul drainage and ground water…
Drainage systems shall efficiently collect, transport and process effluent prior to discharging it at a suitable disposal point(s) which will be proposed to the Purchaser (taking account of Part 1.1, Table 1.1.8). There shall be no discharge of surface water that prevents it being collected for use in the operation of the power plant, including during the construction of the Works.
The Contractor shall provide all necessary conditioning, treatment, sampling and protection facilities to ensure that all effluent leaving the Site conforms to the requirements of the relevant IPC Authorisation or to other national regulatory authority requirements, as appropriate. The disposal of contaminants removed from effluent or by-products of treatment or conditioning processes shall be fully considered in the Design. The Contractor shall obtain all necessary licenses/consents/authorisations for the discharges from drainage systems during the construction phase and shall fully support the Purchaser in obtaining licenses/consents/ authorisations for the operational phase."
(g) Clause 2.1.2.12.9
"The Contractor shall provide sufficient lavatories and ablution facilities across the Site to meet the requirements of all personnel engaged on the Works.
The Contractor shall install, operate and maintain all necessary drainage and sewerage systems during the construction of the Works, including those for Contractors' areas..."
"(23) Except for the Permitted Preliminary Works, the commencement of the Development shall not take place until there has been submitted to, approved in writing by, and deposited with the Council [Vale of Glamorgan], in consultation with the Environment Agency, a scheme showing the method and working on drainage facilities on the Site. Such facilities shall be put in place in accordance with the approved scheme.
(24) The scheme referred to in Condition (23) shall include:
(i) measures to ensure that no leachate or any contaminated surface water from the Site shall be allowed at any time to enter directly or indirectly into any watercourse or underground strata or onto adjoining land…
(25) Any surface water contaminated by hydrocarbons which are used during the construction of the Development shall be passed through oil/grit interceptor(s) prior to being discharged any public sewer or watercourse or to any other surface water disposal system approved by the Environment Agency."
"The seawater discharge temperature is expected to increase by about 1°C above current operation. This temperature rise produces negligible changes relative to current operation. No environmental standards are compromised. The discharge pH is expected to change from a background value of 8, to a value of 6.6 under difficult conditions and 6 under worst case conditions. Due to rapid dilution and the natural characteristics of seawater, the low pH of the discharge is only evident very close to the outfalls. At this location, the discharge complies with all relevant standards for the protection of marine life. Increased nitrate concentrations are similarly evident very close to the outfall but comply with standards and are extremely unlikely to result in adverse water quality."
This is clearly a reference to what can be expected following completion of the FGD process works. There are relatively brief descriptions (for instance at Paragraph 2.4) of the construction stage. There is mention (at Paragraphs 5.2 and 5.3) of the potential for the use of waste materials arising from the construction for landscaping on the Site or if appropriate for it to be taken off the site. Paragraph 5.2.1 states:
"The construction of the FGD plant…will inevitably result in the generation of spoil and other waste materials. Where possible, the spoil will be used in landscaping purposes on the power station site. Should this not prove applicable, surplus material will be transported off-site and utilisation elsewhere or, as a last resort, the disposal at a site licensed for its receipt. Similarly, other waste streams produced during construction will be dealt with in line with current waste management practice and only sent for disposal where other options, such as reuse, recycling and recovery, prove impossible."
A large chapter deals with transport to and from the Site. Chapter 6 identifies that the site is, immediately, served by the B4265. Paragraph 6.8 identifies that the estimated construction traffic is no more than six vehicles in and six vehicles out at the morning and evening peaks respectively.
"8.3 Design Mitigation
8.3.1 Construction Phase
It is not anticipated that there will be any environmental impact or effect on the marine environment associated with the construction of the Seawater FGD Process, hence no mitigation is proposed…
8.4 Predicted Impacts and Effects
8.4.1 Construction Phase
The Seawater FGD Process will use the existing outfall structures to discharge waste water to the marine environment. Hence there will be no construction impacts."
There were comparable provisions under the heading in Paragraph 8.5 of "Evaluation of Effects" that the Seawater FGD Process would use the existing outfall structures to discharge waste water to the marine environment and that there would be no impacts during the construction and commissioning phases.
"The construction phase will not result in any releases or disturbance to the marine environment. There will therefore be no impact during the construction phase."
It is clear that large bulk of this Chapter is concerned with the potential impact on marine life during the phase when the Power Station and the FGD Process are up and running.
"3.1 A release from the Authorised Process into controlled waters from a release point specified in Table 3.1 shall arise only from the source specified in that Table and shall be released only into the receiving waters specified in that Table.
TABLE 3.1
Outlet Number | Location | Effluent | Receiving waters |
2 | Twin concrete discharge structures [grid references given] | Releases from B station: Water treatment plant, condenser cooling water, boiler blow-down combined with water from dirty drains within B Station power plant building discharge via underground oil interceptor pit and, surface water run-off. | The Severn Estuary |
3 | 0.9 metre (36'') diameter pipe at [grid reference] | Surface water drainage from fuel oil storage via the tilting plate oil separator and coal plant areas and associated road drainage | The Severn Estuary |
3.3 The determinands measured in releases from the Authorised Process into controlled waters shall not exceed the relevant limits or criteria specified in Tables 3.2 and 3.3.
TABLE 3.2
Discharge reference | Location of Outlet | Nature of Discharge | Daily Volume (m) |
1B | Twin concrete outlets at [Grid reference] | Condenser cooling water | - |
2B | Twin concrete outlets at [Grid reference] | Water treatment plant effluent | 540 |
3B | Twin concrete outlets at [Grid reference] | Storm water and surface drainage | Dependent on weather |
4B | Twin concrete outlets at [Grid reference] | Boiler blow down water | 1705 |
5B | Twin concrete outlets at [Grid reference] | Boiler gas side washings dust and acidic deposits | 455 |
6B | Twin concrete outlets at [Grid reference] | Dirty water from drains within B power plant building | - |
TABLE 3.3
Determinands | Outlet No 2 | Outlet No 3 |
Suspended solids determined as the differential concentration between incoming and outgoing water (mg/l) (a) | 50 | - |
Suspended solids ((mg/l) (a)… | - | 200 |
(a) One sample shall be taken and analysed each week. Suspended solids are to be measured following drying at 105°C…"
"Authorised Process" was defined in Part 9 as meaning "the process subject to this authorisation", which clearly meant the power station process.
(a) There is a very wide ranging obligation on the Contractor in effect to do all that is necessary to design and carry out the Works. For instance, Clause 13.1.1 of the Conditions of Contract imposes a warranty on the Contractor that, amongst other things, the Works will be carried out in accordance with the Purchaser's Specification. Clause 1.1.4.2 of the Purchaser's Specification imposes upon the Contractor responsibility, amongst other things, for the
"provision of all necessary plant, labour and materials, construction plant, temporary works, equipment, auxiliaries and accessories, special tools, and performing all operations and work required to design, fabrication, furnishing, delivering, transporting, installing, finishing, painting, testing and putting into commercial operation of the Plant".
(b) It is, rightly, uncontroversial that the removal of water from an excavation which is to house permanent works (such as the SWTP) and which is necessary to enable those permanent works to be done involves "temporary works"; similarly, work done to prevent water getting into the excavation, such as banks of earth or possibly dewatering, will be "temporary works". This type of work is necessary to enable the permanent work, often concreting, to be done.
(c) The effect and impact of, amongst other terms, Clause 13.3 of the Conditions of Contract is that the Contractor takes the risk for problems associated with ground (physical and sub-soil), water (hydrographical and hydrological) and geotechnical conditions except for the matters set out in Clause 13.3.4 (such as an error in the Presumed Physical Ground Conditions).
(d) Thus, unless there is some wording in the Contract documentation which suggests otherwise, the Contractor has the responsibility for the disposal of water within the excavations. Indeed Clause 2.1.2.6.1 expressly says that the "Contractor shall properly dispose of water from the Site from whatever source during the construction phase." That Clause goes on to require contaminants to be effectively removed prior to discharge into drains or watercourses.
(e) The question then arises as to whether water which the Contractor is required to dispose of, in effect to enable it to carry out the Works, can be "properly" disposed of through the Seal Pit and Outlet Nos. 2 and 3.
(f) Whilst the Contractor was required to design and construct the Works (including the Plant) so as to secure compliance with the Deemed Planning Consent plus Conditions (Clause 1.1.4.12 of the Purchaser's Specification), and whilst effectively this required compliance with or at least observation of the terms of the Environmental Statement, it is clear that this latter document is mainly concerned with the overall Seawater FGD Process and what is expected of it once it has been provided. Although there are references to the construction phase or stage and as to what will be done then, there is nothing, on analysis, in the terms relied upon by the Contractor (all relevant ones being set out earlier in this judgement), which suggests that the Contractor will be entitled during the construction phase to pump untreated or indeed any water present in its excavations into the Seal Pit or through the Outlets into the sea. The references in Paragraphs 5.2.1 and 5.3.1 of the Environmental Statement are not apt to describe such water.
(g) Primary reliance has been placed by the Contractor on Paragraphs 8.3 and 8.4 of the Environmental Statement. Paragraph 8.1 says that the chapter concerns "the impact of the discharge from the Seawater FGD Process at Aberthaw Power Station on the Bristol Channel/Severn Estuary." Clause 8.3.1 simply says that no environmental impact or effect on the marine environment was "anticipated"; this anticipation may be right or it may be wrong but that language does not give to the Contractor a contractual right as such to discharge directly or indirectly into the Bristol Channel. Clause 8.4.1 involves simply a statement that, in effect because the ultimate Seawater FGD Process would use the existing outfall structures to discharge wastewater to the marine environment, there would be no construction impacts. One can not read into this a right on the part of the Contractor to dispose of water generated as a product or consequence of the construction activities through the existing outfall structures. The reference to "wastewater" in Paragraph 8.4.1 is obviously to that generated by the completed Process. Similar considerations apply to the wording in Paragraph 8.5.1.
(h) Finally reliance is placed upon the Variation Notice which, in my judgement, is largely irrelevant to the issues in these Part 8 proceedings. The Variation Notice is clearly talking about releases (amongst others) into the sea ("Controlled Waters") from the Authorised Process, which is, in context, the completed FGD Process. That is clear from the wording of Clause 3.1 and also from the Tables which identify expressly that the "effluent" which can be discharged into Outlets Nos. 2 and 3 is that from specific parts of the Power Station such as liquid or other material from the "water treatment plant" or "condenser cooling". There is nothing in these Tables which allows or permits water from excavations (created to enable new work to be constructed) to be put through either Outlet.
(a) Assuming that I am right on Issue 10.1, there was no express entitlement on the part of the Contractor or express obligation on the part of RWE to discharge or permit the discharge of water with or without suspended solids in it into the Seal Pit or otherwise into Outlet Nos. 2 or 3. Therefore the question of whether RWE was entitled to impose a concentration limit of 50 mg/l or 73 mg/l or 117 mg/l is immaterial.
(b) Different considerations might apply if, via another legal route (say an ad hoc agreement, an estoppel by convention or an implied term as to reasonable co-operation), the Contractor was able to establish that it could reasonably expect RWE to assist in the disposal of water which had arisen as a result of an error in the Presumed Physical Ground Conditions, a Variation or a breach of contract on the part of RWE. I consider that it is inappropriate to speculate in those circumstances as to whether it was reasonable or unreasonable or otherwise a breach of contract on the part of RWE for RWE to impose restrictions on the water which was in fact permitted to be discharged into the Seal Pit or through Outlet No. 2.
(c) It also becomes hypothetical and speculative to determine whose obligation in practice it was or would have been to secure any "Permits" to enable such water to be discharged. In fact, I was told during the hearing, although RWE told me that it obtained approval of some sort on an ad hoc basis,, that neither the Contractor nor RWE obtained any new permits to enable the water from the excavations to be discharged into the Seal Pit or through Outlet No. 2. I would not want to speculate in a Part 8 judgement as to whether a permit would have been required from some agency or authority in any event or if the restrictions said to have been imposed by RWE on the water which it did permit the Contractor to discharge had not been imposed. Similar considerations apply to whether the Contractor had to make some request to RWE to encourage or secure that RWE sought or obtained any permit which it was required to obtain.
(d) There was substantial argument as to whether the Contractor was or may have been in breach of criminal provisions of the Water Resources Act 1991 in discharging silt laden water into the Seal Pit and onwards into the sea through Outlet No. 2. Section 85 of that Act provides as follows:
"(1) A person contravenes this section if he causes or knowingly permits any poisonous noxious or polluting matter or any solid waste matter to enter any controlled waters.
(3) A person contravenes this section if he causes or knowingly permit any trade effluent or sewage effluent to be discharged-(a) into any controlled waters…"
I am most reluctant to rule in the absence of expert evidence whether water laden with silt or otherwise with silt suspended in it would in the circumstances of what happened in this case be "poisonous noxious or polluting matter" or "trade effluent". One is of course conscious that the water from many rivers and streams which flow into the sea may naturally carry soil and silt. I am by no means convinced, although I make no ultimate finding, that, as RWE asserts, "any liquid, including even settled or filtered construction water, discharged via the Seal Pit, is trade effluent for the purpose of the Act." If that was the case, then in theory both RWE who permitted, and the Contractor who caused, the discharge of such water could be guilty of an offence.
Decision
(a) to Issue 10.1, which I reformulate as:
"Subject to compliance with the remaining provisions of the Contract, was AA [the Contractor] entitled under the Contract and/or was RWE obliged physically to permit AA, by reference to paragraph 8.4.1 of the Environmental Statement at page 1312 Purchaser's Specification or other express terms of the Contract to discharge water from the Sea Water Treatment Plant excavations via the existing outfall structure(s) identified in the Environment Agency Variation Notice, Table 3.1, page 2272 Purchaser's Specification?"
"No".
(b) to Issue 10.3:
The relevant Presumed Physical Ground Condition is, for open excavations, inflowing ground water such as will not affect the stability of the excavation or such as can be controlled using sump pumping provided by the Contractor. Inflowing ground water in whatever quantities or of whatever type which affects the stability of the excavation or which can not be controlled using sump pumping is not within the Presumed Physical Ground Condition.
(c) to Issue 10.4:
(a) if there was an inflow of ground water which was significantly more than or equivalent to seepage, that could operate as an "error in the Presumed Physical Conditions" for the purposes of Clause 13.3.4 (a) (i) of the Conditions of Contract. However, the inflow would either have to affect the stability of the excavation or be such as could not be controlled using sump pumping.
(b) It is only "ground water" which is referred to in the Presumed Physical Ground Condition set out in Paragraph 5 of the Agreed Conclusion. It does not include seawater, or other surface water, directly entering the excavations.