BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Brookfield Construction (UK) Ltd v Mott Macdonald Ltd [2010] EWHC 659 (TCC) (31 March 2010) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2010/659.html Cite as: [2010] EWHC 659 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
BROOKFIELD CONSTRUCTION (UK) LIMITED (formerly MULTIPLEX CONSTRUCTIONS (UK)LIMITED) |
Claimant |
|
- and - |
||
MOTT MACDONALD LIMITED |
Defendant |
____________________
Mr Andrew White QC, Ms Chantal-Aimee Doerries QC, and Mr Nicholas Collings (instructed by Fishburns) for the Defendant
Hearing dates: 13th January, 19th February, 30th March 2010
____________________
Crown Copyright ©
Mr Justice Coulson:
1. INTRODUCTION
3.1. MPX claim that they relied on Mott's inadequate design information when they submitted their original tender, so that as a result, MPX's tender price was to low. This is referred to as the Notional Tender Claim. It is said to be worth in excess of £13 million.3.2. MPX say that Mott's design failures made them vulnerable to substantial claims from Cleveland Bridge (UK) Ltd, who were the steel work sub-contractors. In consequence, MPX say that they acted reasonably in entering into SV 399 and the Settlement Agreement in order to compromise CBUK's claims and to mitigate the delay and disruption caused to the steel works up to 2nd August 2004. This claim is, therefore, in the nature of a claim pursuant to Biggin v Permanite [1951] 2 KB 314, and is said to be worth almost £28 million.
3.3. MPX have a parallel claim for their own prolonged and increased costs as a result of a difficulties up to 2nd August 2004, which claim is valued at in excess of £4 million.
3.4. MPX 's biggest single claim is for the delay and disruption to the steel works from 3rd August 2004 onwards, and includes a claim for the loss of the benefit of CBUK's fixed tender price. This claim is quantified at just under £100 million.
3.5. MPX also make further Biggin v Permanite type claims against Mott in respect of the settlements that they reached with other follow-on sub-contractors including the Structure/Enclosure trades; the Fit Out trades; and the M and E trades. These claims are said to amount to £41 million.
3.6. Further MPX have additional claims for delay and disruption including increased preliminary costs, liquidated damages imposed by WMSL, the loss of a bonus for early completion, the loss of opportunity to earn revenue on other projects, and their legal costs. These various heads of loss together are said to amount to more than £60 million.
3.7. Finally, there is a claim in respect of invalid and/or over-valued variations in the sum of £2.7 million.
2. THE LITIGATION
9.1. The deficiencies in MPX's pleaded case;9.2. The best way to try this enormous claim.
3. THE SCOPE OF THE PROPOSED SUB-TRIAL IN 2011
a) First, the majority of the claims, and certainly the big-money claims in this case, are concerned with delay, in one form or another. In damages claims of this sort, in order to recover, a claimant generally needs to demonstrate critical delay caused by the breaches complained of. Critical delay is usually assessed at the end of the project, when all relevant factors can be taken into account. It was therefore difficult to see how any meaningful decisions as to critical delay could be made at a sub-trial which had a cut-off date part-way through the project, namely 2nd August 2004.
b) Secondly, if the scope of the issues for the sub-trial was limited to the claims outlined at paragraphs 3.1-3.3 above, then I would be dealing with claims that were, at the very most, worth only 20% or so of the overall claim. How would a decision on a relatively small percentage of the overall claim lead to a settlement of the whole case?
"(1) All issues of breach (save for the variations claims)
(2) The Notional Tender Claim (Section 7 of the Amended Particular of Claim)
(3) The following CBUK Settlement Claims:
(i) the claim for £799,139 in respect of SV 399;
(ii) the claim for £5,250,000 paid to CBUK under the CBUK Settlement Agreement;
(iii) the claim for £6,073,279 in respect of the additional premium within the £12 million lump sum agreed with CBUK;
(iv) the claim for the premium paid for the fabrication of steel for the PPT and bowl by Hollandia (excluding the quantum of such claim);
(v) the claim for £1,280,700 in respect of the premium paid for the steel which was to be fabricated by CBUK's subcontractor in China, Shanghai Grand Tower, but which was returned to the UK for fabrication;
(vi) the claim for £68,911 in respect of the audit of the moving roof carried out by Hollandia;
(vii) the claim for £1,230,527 in respect of the premium paid for the pre-cast terracing installation by PCE;
(viii) the claims for £6,001,955 and £167,549 in respect of payments made on a cost reimbursable basis for steel site erection works up to 2 August 2004;
(ix) the claim for £500,000 in respect of the premium paid to CBUK for the use of its temporary works.
(4) All issues of causation (including delay and disruption) up to 2 August 2004. It is recorded that the parties have agreed that:
(i) the Court should investigate the causes of delay up to 2 August 2004;
(ii) the Court should determine which events caused critical delay to the Project judged at 2 August 2004;
(iii) if the Court concludes that as at 2 August 2004 critical delay had occurred for which Mott is responsible, the question of whether that delay caused critical delay to the completion of the Project may depend on facts which occurred after 2 August 2004 which are not the subject
of the Sub-Trial.
(iv) The Court will not investigate or determine the credit that is to be applied to any claim."
a) The witnesses of fact will give their evidence during the Easter term in 2011, starting in January and finishing at the end of March. The parties will have to agree a detailed timetable to ensure that that is done. There can be no question of any extension of that part of the timetable.b) The expert evidence will commence after the Easter vacation, in April. The expert evidence must be completed by the end of term in late May, and will again need to be the subject of an agreed timetable. The parties are optimistic that this will not prove a difficulty.
c) The final submissions will be provided in writing some time in the second week of June and there will be oral submissions in the last week of June. That will then allow me to break the back of the subsequent Judgment during July 2011.
4. COSTS
"(a) Each party's estimate of costs provided to the Court in advance of the CMC on 11 December 2009 is to be regarded as their respective maximum likely recovery on costs at the end of the Sub-Trial, subject to (b) below.
(b) If either party's estimate has good reason to have incurred higher costs it is open to that party to identify and explain to the Court why those costs are in excess of the estimate."
5. THE WAY FORWARD