BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £5, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Durham County Council v Jeremy Kendall (t/a HLB Architects) [2011] EWHC 780 (TCC) (31 March 2011) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2011/780.html Cite as: [2011] CILL 3017, [2011] BLR 425, [2011] EWHC 780 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
DURHAM COUNTY COUNCIL |
Claimant |
|
- and - |
||
JEREMY KENDALL (Trading as HLB Architects) |
Defendant |
____________________
Duncan McCall QC (instructed by Beachcrofts LLP) for the Defendant
Hearing date: 11 March 2011
____________________
Crown Copyright ©
Mr Justice Akenhead:
The History and Factual Background
"Sufficient site investigations to determine ground conditions and location and adequacy of existing services will need to be carried out by the appointed Consultant once the outline details of the scheme are confirmed…"
Paragraph 3.1 stated:
"The appointed Lead Consultant will be required to bring together ideas, observations, perceptions and ultimately establish a common understanding of the building which will provide all the requirements and facilities for all the partners involved in the project…"
"Part 1-Pre Feasibility Concept Development Ideas (already completed)
Part 2-Confirm Part 1 and Feasibility Study with Cost Plan and Detailed Presentation
Part 3-Detailed Design, Bills of quantities and all Works prior to Tendering
Part 4-Construction Works, Contract Administration and all Work up to and including final account"
Paragraph 6 sets out what was involved in Part 2, which unsurprisingly dealt "with the feasibility of the scheme to establish the most appropriate form of construction, design and layout, infrastructure…external and internal appearance, landscaping and security". A detailed cost plan was needed together with a preliminary timetable. A detailed presentation with drawings, brochures, technical information and the cost plan was to be provided.
"I understand that Parts 3 and 4 will only proceed once the council has agreed funding for the project".
At Paragraph 7 he stated:
"I/We agree to our tender remaining open for acceptance for a period of two months from the date set for submission of tenders."
"I am pleased to advise you that the Council wish to appoint you as the Lead Consultant for the above project.
As the scheme is subject to funding from Sport England we do not have in place the full approval to proceed with carrying out the work contained within our 'Brief'. However, in order for the project to progress the Council are prepared to fund Part 2 of the scheme only. The work involved includes confirming Part 1 and to undertake a Feasibility study with a Costing Plan and Detailed Presentation to the Client, the cost of this work is as per your tender sum of £14,940.00.
Once I am in receipt of any further information regarding approvals from Sport England to proceed beyond Part 2 of the scheme I will advise you accordingly, meanwhile I would be obliged if you will contact me to arrange a meeting so we can progress the scheme..."
"4.0 RTB to organise site investigation.
IT thought this was part of consultants and.
RTB said the consultants usually arranged but costs usually paid by client-as planning/building regulations.
RTB will check and confirm with IT.
9.0 Programme
9.1 Arrange survey of site existing/building perimeter within 10 days.
9.2 Arrange site investigation within next two weeks…
9.4 Develop Feasibility/Design Proposals/Services beginning Sept '03-3-4 weeks
9.5 Develop agreed layout, services and cost plan for presentation 2/3 weeks end of Sept/Oct '03."
"As discussed and agreed at the meeting between myself and Richard Bulmer the cost of the site investigation should be included in the fee bid for the Feasibility Study as stated in the Lead Consultant's Brief item 2.3, a copy of which is enclosed."
I will refer to this as the "site investigation issue".
"I confirm the Council's request for you to commence work on Part 3 of your tender for the above project. This involves the Detailed design, Bills of Quantities and all works prior to tendering.
You should now be in a position to provide a detailed cost plan together with a preliminary timetable from design to construction and completion and a planned expenditure profile in accordance with the requirements of Part 2 of your tender.
Please contact me if you require any further information or have any queries with regard to the above."
Again, there is no issue that HLB proceeded to do what this letter called for.
"This letter is to confirm the Borough Council's intention to proceed with the project to construct a new regional gymnastics centre at Spennymoor Leisure Centre. Although the Borough Council's Cabinet do not meet until the 2 September 2004 at which time they will formally agree to the scope of the project in line with our recent discussions, this letter confirms the Council's intention to agree the purchase of the steel contents of the project…
As Director of Leisure Services I am authorised to send this letter of intent."
The Adjudication
"Accordingly, all the contract terms are not evidenced in writing and there is no agreement in writing for the purposes of the Act. In the circumstances, there is no valid reference to adjudication and you do not have jurisdiction to determine this adjudication…
For the avoidance of doubt our client does not agree to be bound by any findings which you may make in regard to the matters raised in this letter and reserves the right to raise any or all of these points or related points in connection with any enforcement proceedings which may ultimately arise."
I will refer to this as "the first reservation". The "second reservation" followed in an e-mail to the Adjudicator on the following day reiterating its specific jurisdictional arguments and concluding:
"The Responding Party reserves the right to raise any jurisdictional and/or other issues, in due course, whether previously raised or not and whether within the forum of adjudication or other proceedings and the Responding Party's correspondence and/or submissions in this adjudication are made entirely without prejudice to this right."
"For the reasons given it is clear that, in each of the grounds we have raised there is no jurisdiction to you to determine this dispute. For the reasons given we invite you to resign…
For the avoidance of any doubt our client does not agree to be bound by any findings which you may make in regard to the matters raised in this response and reserves the right to raise any or all of these points or related points in connection with any enforcement proceedings which may ultimately arise."
I will refer to this as the "third reservation".
"The Responding Party identifies three challenges to the Adjudicator's jurisdiction in correspondence as follows:
1.1 I There is no crystallised dispute between the parties;
1.2 The named Responding Party is not a legal personality capable of (a) being a party to an adjudication or (b) entering into a contract. It is a trading name only;
1.3 There is no agreement in writing (and in this respect submission 1.2 (b) is repeated).
2. These challenges remain and are not waived by this Response.
3. The named Responding party is not a legal personality. It is not capable of being a party to this adjudication or-and in any event-the alleged underlying agreement.
4. The Architect on this project was Jeremy Kendall, as the Referring Party well knew. He is not a party to this adjudication.
5. References to the Responding Party within this document are, therefore, wholly artificial and assume that HLB Architects is a legal personality. This assumption is incorrect. The submissions set out below are entirely without prejudice to this overarching point.
6. For the avoidance of doubt, Beachcroft LLP is instructed on behalf of Jeremy Kendall t/a HLB Architects…
8. Accordingly the Responding Party does not agree to be bound by any findings that the Adjudicator may make in regard to the matters raised in this adjudication and reserves the right to raise any or all of these points and the jurisdiction points previously raised and/or related points in connection with any enforcement proceedings which may ultimately arise."
"For the avoidance of any doubt our client does not agree to be bound by any findings which you may make in regard to the matters raised in this e-mail and fully reserves all its rights in connection with the various jurisdictional objections previously made with regard to any enforcement proceedings which may ultimately arise."
These Proceedings
(A) It is said that not all of the terms of the contract were made or evidenced in writing;
(B) It is said that even if all terms of the contract were in writing there were on analysis three separate disputes under three separate contracts relating respectively to Parts 2, 3 and 4.
(C) The Defendant as named in this action is not the same as the party named as the responding party in the adjudication and, because there is no decision against the Defendant in these court proceedings, Durham can not enforce against him.
The Law
"(2) There is an agreement in writing—
(a) if the agreement is made in writing (whether or not it is signed by the parties),
(b) if the agreement is made by exchange of communications in writing, or
(c) if the agreement is evidenced in writing.
(3)Where parties agree otherwise than in writing by reference to terms which are in writing, they make an agreement in writing.
(4) An agreement is evidenced in writing if an agreement made otherwise than in writing is recorded by one of the parties, or by a third party, with the authority of the parties to the agreement."
This latter point is of some materiality here in that, in my judgement, if one of the parties to the agreement produces an agreed minute of a meeting, that is capable of being a written record if and to the extent that the minute records agreement in writing on a material term.
"(a) For there to be a construction contract in writing for the purposes of Section 107 and Part II of the HGCRA, all the terms of the contract must be in writing and recorded in one of the ways set out in Section 107.
(b) Whilst adjudicators (and indeed judges) should be robust in determining whether trivial matters said to have been agreed only orally between the parties can prevent what would otherwise be a written contract for the purpose of Section 107 being a written contract, the exercise of determining what is trivial must be an objective one in relation to the particular contract and parties concerned. What may be "trivial" in one contract may not be in another. Thus, for example, an oral agreement on a million pound project as to which of two mildly differing shades of light blue paint might be used may be trivial on one development but not on another.
(c) It is always necessary to determine whether a so-called agreement made orally was in reality expected or intended to be binding as between the parties. Thus, the parties having discussed and agreed something orally might later have reduced their agreement into writing in such a way as to supersede the earlier oral agreement. A later oral agreement may not be binding; for instance, it may lack consideration or otherwise may not be intended to be binding."
"31. On the issue of reservation relating to jurisdiction, the position was at least generally summarised in the judgment in Allied P & L Ltd v Paradigm Housing Group [2009] EWHC 2890 (TCC) at Paragraph 32:
"It has long been established in the relatively short period of time in which the Housing Grants Construction and Regeneration Act 1996 ("HGCRA") has been in force that it is necessary for a party challenging the jurisdiction of the adjudicator to reserve its position in relation to its challenge; for instance, although not cited in argument, this issue was raised and commented upon by Mr Justice Dyson as he then was in The Project Consultancy Group v The Trustees of the Gray Trust [1999] BLR 377 at Paragraphs 14 and 15. Having reserved its position appropriately and clearly, that party can safely continue to participate in the adjudication and then, if the decision goes against it, to challenge its enforceability on jurisdictional grounds in the Court. If it does not reserve its position effectively, generally it cannot avoid enforcement on jurisdictional grounds. I say generally because there might be unusual circumstances in which a jurisdictional challenge can be mounted when there has been no reservation; for instance, if the party making the challenge did not know or could not reasonably have ascertained the grounds of challenge before the decision was issued. It is however difficult to envisage circumstances in which a jurisdictional challenge on the grounds that there is no dispute should not and can not be the subject of a reservation of rights."
32. In Aedifice Partnership Ltd v Ashwin Shah [2010] EWHC 2106, the Court reviewed a number of the relevant authorities:
"15. So far as jurisdictional objections that have been or could be taken during the adjudication, one will need to ascertain whether the parties have expressly agreed to give the adjudicator jurisdiction to resolve those objections or, even if they have not as such done so, whether the objecting party has effectively reserved or waived its position on jurisdiction. For instance in Pilon Ltd v Breyer Group Ltd [2010] EWHC 837 (TCC), Mr Justice Coulson said:
"12. The law on this topic is clear. Jurisdictional issues often arise during the course of an adjudication, and it is usually sensible for the parties to ask the adjudicator to investigate the issue and state his conclusion. But, unless the parties have also agreed to be bound by the result of the adjudicator's investigation into his own jurisdiction, his ruling on that issue will not be determinative, and the challenger can defeat any subsequent enforcement proceedings by showing a respectable case that the adjudicator had reached an erroneous conclusion as to jurisdiction: see, in particular, paragraph 10 of the judgment of May LJ in Pegram Shopfitters Limited v Tally Weijl (Uk) Limited [2003] EWCA Civ 1750.
13.Accordingly, there needs to be either an express agreement between the parties that the adjudicator's decision on jurisdiction is to be binding or, at the very least, an implied agreement to the same effect, which may arise where the objecting party fails to reserve its position, or there has been a unilateral waiver of any jurisdictional objection. In both JW Hughes Building Contractors Limited v GB Metal Work Limited [2003] EWHC 2421 (TCC) and Nordot Engineering Limited v Siemens Plc [2001] CILL 1778, the court found an ad hoc agreement between the parties that they would be bound by the adjudicator's decision as to jurisdiction, but such cases are rare. Generally speaking, as Dyson LJ put it in Amec Projects Limited v Whitefriars City Estates Limited [2004] EWCA Civ 1418, "the 'decision' of an adjudicator as to his jurisdiction is of no legal effect and cannot affect the rights of the parties….""
16. In Thomas-Fredric's (Construction) Ltd v Keith Wilson [2003] EWCA Civ 1494, Simon Brown LJ (as he then was) said:
"33. The position can I think be summarised in the following two propositions. (1) If a defendant to a Part 24(2) application has submitted to the adjudicator's jurisdiction in the full sense of having agreed not only that the adjudicator should rule on the issue of jurisdiction but also that he would then be bound by that ruling, then he is liable to enforcement in the short term, even if the adjudicator was plainly wrong on the issue. (2) Even if the defendant has not submitted to the adjudicator's jurisdiction in that sense, then he is still liable to a Part 24(2) summary judgment upon the award if the adjudicator's ruling on the jurisdictional issue was plainly right."
17. There is obviously no great difficulty about an express agreement made by both parties with their eyes open that the adjudicator should have jurisdiction to produce a binding decision that he has jurisdiction to resolve the particular dispute referred to adjudication. It is with the implied agreement or waiver or abandonment of a jurisdictional objection that parties and indeed adjudicators get into murkier waters. There is no doubt that, when one party raises a jurisdictional objection, good or bad, adjudicators, like arbitrators, are entitled to enquire into their own jurisdiction. In practice in adjudication, that will usually involve considering the Referral, witness statements and other documents available to the adjudicator at the time that he is making that enquiry. Even if no objection is made, an adjudicator who believed that he had no jurisdiction could raise the issue with the parties and, unless persuaded otherwise or the parties agreed to give him jurisdiction, he could stand down.
18. There have been a number of observations in various cases about what is needed for a party making a jurisdictional objection during the course of the adjudication effectively to do so. In Project Consultancy Group v Trustees of the Gray Trust (1999) 65 Con LR 146, Mr Justice Dyson had to deal with an allegation that there had been an ad hoc agreement to refer a jurisdictional issue to the adjudicator. He said dealing with the particular facts:
"In my view, the defendants' solicitor's letter of 9 March 1999 stated in the clearest terms that the defendants protested the adjudicator's jurisdiction, and that they would not recognise and comply with any decision to award money to the claimant. The letter also made it clear that, if the adjudication proceeded, they reserved their rights to participate, but without prejudice to their contention that there was no jurisdiction. I do not consider that there can be any reasonable doubt as to the meaning of that letter. The only real question is whether, by participating in the adjudication process, the defendants waived the jurisdiction point, and agreed to submit to abide by the decision of the adjudicator on that issue. The only material relied on by Ms Rawley [Counsel] is the content of the defendants' response…But, in their response, the defendants continued to assert that the adjudicator had no jurisdiction…It is a matter of fact whether a parties submit to the jurisdiction of the third person…"
19. In Euro Construction Scaffolding Ltd v SLLB Construction Ltd [2008] EWHC 3160 (TCC), the judge said:
"So far as jurisdiction challenge to an adjudicator is concerned, it is necessary for the party objecting to the adjudicator's jurisdiction to make a clear and full reservation".
The report of that case goes on to review whether an adequate reservation was made and considers, amongst other things, whether the adjudicator proceeded on the basis that there had been a reservation about jurisdiction. In that case, there had been an effective reservation but in the event the jurisdictional challenge was not a good one.
20. In CJP Builders Ltd v William Verry Ltd [2008] EWHC 2025 (TCC), the following was said at Paragraph 72:
"Various cases such as Thomas Frederic's (Construction) Limited v Keith Wilson [2004] BLR 23 and The Project Consultancy Group v The Trustees of the Grey Trust [1999] BLR 377 make it clear that if there is to be an objection to jurisdiction of the arbitrator generally there should be a clear reservation of the objecting party's stance on jurisdiction. Such a reservation will usually be done effectively by clear words but it could also be done by unequivocal conduct."
21. I can draw these various strands together:
(a) An express agreement to give an adjudicator jurisdiction to decide in a binding way whether he has jurisdiction will fall into the normal category of any agreement; it simply has to be shown that there was an express agreement.
(b) For there to be an implied agreement giving the adjudicator such jurisdiction, one needs to look at everything material that was done and said to determine whether one can say with conviction that the parties must be taken to have agreed that the adjudicator had such jurisdiction. It will have to be clear that some objection is being taken in relation to the adjudicator's jurisdiction because otherwise one could not imply that the adjudicator was being asked to decide a non-existent jurisdictional issue which neither party had mentioned.
(c) One principal way of determining that there was no such implied agreement is if at any material stage shortly before or, mainly, during the adjudication a clear reservation was made by the party objecting to the jurisdiction of the adjudicator.
(d) A clear reservation can, and usually will, be made by words expressed by or on behalf of the objecting party. Words such as "I fully reserve my position about your jurisdiction" or "I am only participating in the adjudication under protest" will usually suffice to make an effective reservation; these forms of words whilst desirable are not absolutely essential. One can however look at every relevant thing said and done during the course of the adjudication to see whether by words and conduct what was clearly intended was a reservation as to the jurisdiction of the adjudicator. It will be a matter of interpretation of what was said and done to determine whether an effective reservation was made. A legitimate question to ask is: was it or should it have been clear to all concerned that a reservation on jurisdiction was being made?
(e) A waiver can be said to arise where a party, who knows or should have known of grounds for a jurisdictional objection, participates in the adjudication without any reservation of any sort; its conduct will be such as to demonstrate that its non-objection on jurisdictional grounds and its active participation was intended to be and was relied upon by the other party (and indeed the adjudicator) in proceeding with the adjudication. It would be difficult to say that there was a waiver if the grounds for objection on a jurisdictional basis were not known of or capable of being discovered by that party."
33. There is little to add to these observations. If a party does not effectively reserve its position on a given jurisdiction issue, of which it had actual or constructive knowledge, it can not raise it as an effective objection to a claim for the enforcement of the relevant adjudication decision. It becomes a somewhat different point if there arises an issue as to whether the parties have or are to be taken to have agreed that the adjudicator is to have jurisdiction to decide his or her own jurisdiction. One then needs to determine whether there was by words or conduct or both an agreement, express or implied, to that effect. Even if there was agreement, however, the Adjudicator must adjudicate upon it; he or she must go further than simply enquiring into his or her jurisdiction and reaching a provisional view. If he or she does not adjudicate upon jurisdiction which the parties have by agreement conferred on him or her, then there will be no binding decision on that issue and the Court may then have to resolve the issue."
"35. Akenhead J [in Allied P& L v Paradigm] did not in that paragraph deal with the position where there was a general reservation with specific reservations and left open the position on the effect of general reservations.
36. Generally a party who wishes to do so can object to the jurisdiction of an adjudicator and may seek to do so either in general terms or by making a reservation on a specific matter.
37. The underlying issue is whether, taking account of the particular reservation, a party by participating in the adjudication has waived its right to object on grounds of jurisdiction. If the party does not raise any objection and participates in the adjudication then, even if there is a defect in the jurisdiction of the adjudicator, that party will create an ad-hoc jurisdiction for the adjudicator and lose the right to object to any decision on jurisdictional grounds. If a party raises only specific jurisdictional objections and those jurisdictional objections are found by the court to be unfounded then that party is precluded from raising other grounds which were available to it, if it then participates in the adjudication. That participation amounts to a waiver of the jurisdictional objection and confers ad-hoc jurisdiction. Obviously this assumes that, at the relevant time when the party participated in the Adjudication, the jurisdictional objection was available. Some jurisdictional objections, for instance as to the scope of the dispute, may only become apparent during the adjudication process or at the time of the decision.
38. Where a party raises a general reservation to the jurisdiction of an adjudicator but does not specify any particular ground for such an objection that raises potential difficulties for both the adjudicator and the other party. The adjudicator cannot investigate any specific objection and, if appropriate, decide not to proceed. The other party cannot decide whether any specific objection has merit. If so it might decide whether to take steps to remedy the situation by, for instance, starting a new adjudication. Equally, if a general reservation as to jurisdiction were to be sufficient to cover all matters that had arisen or might arise then there would, in principle, be no need for any specific objection, except to give the other party and the adjudicator a chance to consider it.
39. Those practical difficulties suggest that the use of general reservations is undesirable but that does not answer the question whether a general jurisdictional reservation does permit a party to participate in an adjudication without thereby waiving its right to objection on jurisdictional grounds. The decision in Bothma provides strong support for the effectiveness of a general reservation. In addition in the context of arbitration, prior to the provisions of s.73 of the Arbitration Act 1996, a general reservation was held to the sufficient to preserve objection to jurisdiction by a party who participated in an arbitration. In Compania Maritima Zorroza SA v Sesostris SA, The Marques de Bolarque [1984] 1 Lloyd's Rep 652, the respondent to an arbitration had written at the time of the nomination of an arbitrator by the claimant to say that, "without prejudice to such rights as owners may have", they were nominating an arbitrator. Those general words were held by Hobhouse J at 660 to be a sufficient reservation of the right to object to the jurisdiction of the arbitrator and so did not confer a jurisdiction on the arbitrators which they did not otherwise have.
40. That decision was applied by Potter J in Allied Vision Ltd v VPS Film Entertainment Gmbh [1991] 1 Lloyd's Rep 392 where he said:
"Mr. Justice Hobhouse made clear that what matters is a clear qualification at the time of the appointment of the arbitrator and, implicitly, that if that is done then subsequent participation in the arbitration under the umbrella of the original reservation will not, without more, amount to a waiver or ad hoc submission."
41. I respectfully adopt that approach which seems to me to be equally applicable in the case of adjudication. The question in this case is therefore, whether the words of general reservation were sufficiently clear to prevent Ringway's subsequent participation in the adjudication from amounting to a waiver or an ad-hoc submission. In my judgment the words used both in the letters of 3 and 10 July 2009 and in the Response were sufficient to prevent a waiver of any jurisdictional argument, including one based on the alleged agreement of compromise/withdrawal and, as a result, there was no ad-hoc submission."
Discussion
(a) There can be no doubt that HLB's tender was an offer capable of acceptance. Paragraph 2 actually states that HLB "hereby offer and agree to carry out the service, in accordance with the design brief and letter of invitation…"
(b) It equally clear that the offer was expressed to remain open for acceptance for two months. It is common ground that this had expired by the time that Durham sent its e-mail of 8 August 2003. Therefore, the offer had lapsed and, again it is properly common ground that, this e-mail itself was a counter offer capable of acceptance.
(c) The whole tenor of the meeting of 12 August 2003 as minuted is that HLB was being asked to proceed and was agreeing to proceed. A programme was agreed and it is not controversial that HLB proceeded with the works.
(d) I have no doubt that what was said and minuted and, if necessary, HLB's conduct in proceeding with the work thereafter amounted to acceptance of the counter-offer.
"…reserves the right to raise any or all of these points and the jurisdiction points previously raised and/or related points" (emphasis added)
In context, this type of reservation goes to the points raised and not to any general jurisdictional complaint. The one reservation which is general is the second one where the language is clearly general:
"[HLB] reserves the right to raise any jurisdictional and/or other issues, in due course, whether previously raised or not" (emphasis added)
It is overwhelmingly clear that ultimately, and in particular in the Response, HLB pinned its jurisdictional objection colours only to the mast of specific jurisdictional objections rather than a general objection. Put in more legal language, HLB was clearly abandoning any general jurisdictional objection. Any reasonable party and the Adjudicator would have understood by the conclusion of the adjudication that the only jurisdictional objections being maintained were the specific ones. It would therefore follow that, since none of the objections now raised in these proceedings (other than the identity of HLB) were specifically raised before the adjudicator, HLB or more properly Mr Kendall, has waived any rights to raise such objections.
Decision