BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Westshield Civil Engineering Ltd & Anor v Buckingham Group Contracting Ltd [2013] EWHC 1825 (TCC) (28 June 2013) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2013/1825.html Cite as: [2013] EWHC 1825 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
(1) WESTSHIELD CIVIL ENGINEERING LIMITED (2) WESTSHIELD LIMITED |
Claimants |
|
- and - |
||
BUCKINGHAM GROUP CONTRACTING LIMITED |
Defendant |
____________________
Serena Cheng (instructed by Trowers & Hamlin LLP) for the Defendant
Hearing date: 13 June 2013
____________________
Crown Copyright ©
Mr Justice Akenhead:
Introduction
The Factual Background
"9(1) The period within which payment shall become due after the period end ('the payment due date'), the final date for payment and the relevant period under the provisions of this Sub-Contract shall be as detailed in Part IV of the Appendix, or as otherwise provided by this Agreement.
9(2) Payment may be withheld or prejudiced [sic] if any of the Sub-Contractor's obligations be unfulfilled or outstanding, subject to a Notice to Pay Less be issued by the Contractor to the Sub-Contractor no later than one day ('the prescribed period') prior to the final date for payment.
9(3) Within 60 days, unless stated elsewhere, of completion of the Sub-Contract Works, the Sub-contractor shall provide a detailed Final Statement of the value of works executed, which shall include all matters or things arising out of or in connection with the Sub-Contract or the execution of the Sub-Contract Works. The period within which payment of any sum due arising from submission of the Final Statement and the final date for payment under the provisions of this Sub-Contract shall be as detailed in Part IV of the Appendix, or as otherwise provided by this Agreement."
Part IV in relation to the final payment stated that: "Payment shall become due within 60 days of the end of the relevant period and the Final Date for payment shall be 30 days later."
"The decision of the Adjudicator shall be binding on the parties and they shall comply with it until the dispute is finally determined either by agreement, by legal proceedings or by arbitration. Should either party be dissatisfied with the decision of the adjudicator that party may within 28 days of the Adjudicator's decision refer the dispute to either legal proceedings or arbitration in accordance with clause 15 of this Sub-Contract. If no such proceedings are commenced within the said 28 days then the Adjudicator's Decision shall be final and binding on the parties."
It is common ground that the parties contractually opted for litigation and not arbitration.
The Adjudication
"Faced with this position Buckingham may well wish to withdraw from this adjudication and re-commence with [WL] or alternatively, and the most sensible solution, would be to substitute and read [WL] for the Responding Party in lieu of [Civil Engineering]".
The Response went on to assert that the true overall value of the Sub-Contract Works was £641,048.17.
"1…It is clear from the Minutes of Pre-Order Meeting that the Parties were always aware that WCEL were trading as [WL], the Tender was from [WL] and incorporated into the Contract, correspondence was from/to [WL] and payments made to [WL] who received them on behalf of WCEL…
24a There was some disagreement about the correct identity of the Responding Party and the Referring Party was very firm in that the Contract had been placed with [Civil Engineering] and any references to [WL] are erroneous. I must agree with the Referring Party as the Contract Agreement is clear and unambiguous…
"MY DECISION
25. I Declare that the sum due to the Responding Party under the Contract is £505,474.66 (plus Applicable VAT).
26. I Decide that as the sum due being greater than £363,766.81 (plus applicable VAT) it is not for the Responding Party to make payment and as no overpayment has been made there is no interest payable by the Responding Party to the Referring Party.
27. I Decide that each party pays half the fees and expenses of the Adjudicator and accordingly I attach invoices each Party in equal sums of £16,632…
PAYMENT DUE
82. In relation to the contractual payment terms I find that money are due to WCEL but do not have jurisdiction, in this Adjudication, to order payment. I do FIND an amount due from [Buckingham] to WCEL £505,474.66 plus VAT [£513,172.24 - £7,697.58 being 1.5% retention] from which previous payment should be deducted.
INTEREST ON LATE PAYMENT
83. There is no overpayment to WCEL, on the contrary there is an underpayment and interest is due on such sum in accordance with the Sub-Contract or Statute.,,
WHEN IS PAYMENT TO BE MADE
89. I FIND that payment is to be made by [Buckingham] to WCEL but as correctly stated in the Reply to the Response that direction is beyond my jurisdiction in this Adjudication - I can and have the jurisdiction to declare the sums due between the parties but the Notice of Adjudication does not give me the jurisdiction to make any award of sums to [Civil Engineering]. Neither was my jurisdiction enlarged during the currency of this Adjudication."
"…As a result of Mr Hale's conduct, we now have a Decision that values sums in favour of WCEL, but even on WCEL's own case, the sums are in fact valued in favour of WL…
The position is as follows:
…If WCEL commences further proceedings to obtain an order for payment of the sums due we have the option of contesting the new adjudicator's decision on the basis that their own evidence states that they are not a party;
If WCEL seeks to enforce the Adjudicator's Decision in the Courts, there is nothing to enforce in the Decision (because there is no order for payment), such a threat is a hollow one…
There seems to be uncertainty as to whether WCEL is trading. If not, they will have great difficulty taking any further action at all…
Next steps and recommended strategy
As you will appreciate, strategically WL/WCEL have got very few options and [Buckingham] is now in an excellent position, as we planned at the outset of this matter…
For WL/WCEL to have any success on contested proceedings, they will not get much change out of £30,000-£35,000 in legal costs. They need to appreciate this…"
The Manchester Proceedings
"The Claimant and the First and/or Second Defendant entered into a contract for inter alia alia, civil engineering works. The claim is for recovery of overpayment(s) made by the Claimant to the First and/or alternatively Second Defendant, together with interest thereon.
The Claimant claims:
(1) damages for breach of contract from the First Defendant and/or alternatively Second Defendant;
(2) payment of a debt and/or debts under the contract;
(3) declaratory relief;
(4) equitable relief;
(5) interest thereon…and/or…and/or costs
(6) such further or other relief as the Court thinks fit."
These Proceedings
(a) Given the impact of Clause 14(6) of the Sub-Contract, have "proceedings" been "commenced" by Buckingham such as to prevent the adjudicator's decision becoming final and binding? WL and Civil Engineering argue that they have not been commenced because they have not been served or, alternatively, that the Details of Claim are insufficient to be considered as a reference to the Court of the same dispute as was resolved by the adjudicator.
(b) Has there been approbation/reprobation by Buckingham with regard to its shifting stance as to who the party was with whom it sub-contracted?
(c) Even if the decision is to be considered as binding until final resolution of the dispute, should there be a stay of execution by reason of the fact that Civil Engineering is dormant and has no assets to speak of?
There were some other issues such as whether or not the sum identified as due was payable in the light of two "Pay Less" notices served after the publication of the adjudicator's decision but these were not pursued.
Discussion
"…Should either party be dissatisfied with the decision of the adjudicator that party may within 28 days of the Adjudicator's decision refer the dispute to either legal proceedings or arbitration in accordance with clause 15 of this Sub-Contract. If no such proceedings are commenced within the said 28 days then the Adjudicator's Decision shall be final and binding on the parties."
In this case, litigation was the chosen final dispute resolution forum and therefore the issue revolves around when court proceedings can be considered to be commenced. More narrowly, the argument is between whether or not simply the issue of court proceedings amounts to commencement and whether there must be service before they can be considered to have been commenced.
"(1) Proceedings are started when the court issues a claim form at the request of the claimant.
(2) A claim form is issued on the date entered on the form by the court."
There is no absolute requirement that Particulars of Claim must be embodied within the Claim form. Part 7.4(1) gives the Claimant the option of either incorporating them within the Claim form or serving them with the Claim form.
(a) The word "commenced" is a relatively simple English word.
(b) The law applicable to this Sub-Contract is that of England and Wales and the parties must either have known or be taken to have known that it is the issue of proceedings within this jurisdiction which heralds the commencement of the proceedings.
(c) Adjudication generally and under this Sub-Contract is a process primarily designed to provide a decision which is temporarily binding after a relatively summary procedure but which can be reversed in the tribunal selected by the parties for final dispute resolution. To take away the right of a party to take the dispute to that final tribunal requires clear wording. Although the parties here do provide for that right to be taken away, it is subject to a step being taken, commencement of proceedings within a time limit, which will have the effect of preventing the decision from becoming finally binding. In my view, one would need absolutely clear and express wording to the effect that the "commencement" of proceedings meant "service".
(d) It is argued that it is somehow unfair or non-commercial that the losing party to an adjudication can in some way "conceal" the fact that it has effectively prevented the decision becoming final and binding by issuing appropriate proceedings but not serving them for up to 4 months. It is neither unfair nor non-commercial. The winning party can go immediately to court to have the decision enforced and the TCC generally will bring the enforcement proceedings to a hearing within 3-4 weeks of the issue of the proceedings; that party therefore can secure the commercial benefit of a decision in its favour. The winning party must at least contractually be aware that in this country the other party may have issued but not yet served proceedings effectively challenging the adjudicator's decision and that therefore the decision may not have become finally binding. If the proceedings are not served on it within four months plus 28 days, it may turn out that the decision had become finally binding. In any event, a defendant can seek to secure the service of the Claim well before the 4 months are up.
"(a) contain a concise statement of the nature of the claim;
(b) specify the remedy which the claimant seeks;
(c) where the claimant is making a claim from money, contain a statement of value in accordance with rule 16.3…"
Decision