BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> West 3 Mechanical Contractors Ltd v Mizen Design Build Ltd [2013] EWHC 4004 (TCC) (13 December 2013) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2013/4004.html Cite as: [2013] EWHC 4004 (TCC) |
[New search] [Printable PDF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
13/12/2013 |
B e f o r e :
____________________
WEST 3 MECHANICAL CONTRACTORS LIMITED | Claimant | |
- and - | ||
MIZEN DESIGN BUILD LIMITED | Defendant |
____________________
Seb Oram (instructed by GSC Solicitors LLP) for the Defendant
Hearing dates: 11th, 12th and 18th November 2013
Judgment
____________________
Crown Copyright ©
Mr Justice Ramsey : Introduction
"the responsibility for the inability of the system installed at Ira Court, 214-38 Norwood Road, Tulse Hill, London SE27, to deliver adequate gas pressures to a substantial number of the flats in that development".
(1) What was West 3's contractual obligation under the Agreement as regards the size of the gas pipework?
(2) Was the original contractual obligation ever effectively varied and, if so, what was the effect of any such variation?
(3) Did the system as originally installed fail to deliver sufficient gas pressure to a substantial number of flats and would the system in the revised drawings have delivered adequate gas pressures to all the flats?
(4) Did the defect which caused the failure to deliver sufficient gas pressure result, wholly or partly, from West 3' s breach of the terms of the Agreement?
Chronology
"Gas meters are to be situated in the basement in locations as tabled at the Pre-Order meeting. Extra over costs requested for track pipe sub-mains from the meter positions up the risers and into the flat distribution network. "
"Please could you confirm with the consultants as to what size pipe is suitable for the gas runs."
"Supply of Labour, Materials to include Sanitaryware, and associated Plant to carry out the Plumbing and Heating (Mechanical) Subcontract to the 103 Residential Properties and associated Communal Distribution Network/Pipework at the above Development. "
"2.2 [Mizen] advised that the first area of work would be the installation of the gas pipes, 1st fix to the A block 1st floor flats; screeding is presently programmed to commence on Tuesday, 21st November 2006 and then proceed at the rate of 2 flats per day. [West 3] are to advise if they can commence on Monday, 20th November.
Post Meeting note:
[West 3] have confirmed that they will be commencing on Monday 20th November and will be able to keep in front of the screeders
2.3 [Mizen] are to chase [Wilkins MacKenzie Associates] for issue of revised drawings."
"The drawing and specifications prepared by Wilkins Mackenzie Associates, against which you tendered and on which basis you completed the project, calls for gas distribution network of varying sizes from 28mm diameter upwards and for a network that delivers the gas to consumer outlets with a pressure drop not exceeding 1 mbar.
I have become aware that the network is single size (28mm diameter) throughout except for a 1.5/2.0m step down (to 15mm diameter) upside of the boilers.
As you can see from the attached report, inter alia, the dynamic pressure loss is measured down to 14/15 mbar from a figure of 21 mbar underside of the gas meters.
I am aware that you adopted in your tender documents, a 25mm diameter distribution system, but from our perspective that had to be without prejudice to the gas pressure criteria written elsewhere in the paperwork- pressure loss ≤ 1.0 mbar throughout.
Please accept this letter as a Formal Notice of Defect and Claim against West 3 Fabrications Limited in the matter and we urgently call for and await your remediation proposals post haste."
"6.3 A technical solution is needed with regards to increasing the size of the flues where the [TracPipe] runs up. By increasing the size of the [TracPipe], there is space
for fewer [TracPipesj. As such, consideration needs to be
given as to whether this flue can be enlarged.
6.4 Mizen have advised that there is a strong possibility that this can be done by drilling through the floor slab."
"An update was requested on whether it was possible to enlarge the flues containing the gas [TracPipe]. [Mr Charlton] has said that he has submitted the drawings to the Structural Engineers and is awaiting official confirmation that this is possible, [Mr Charlton] to chase."
Evidence
8.1 an agreement on scope and price had to be reached prior to execution.
"The pressure drop between the outlets of the meter and the points to be connected shall not exceed 1 mbar at maximum flow conditions."
"At the initial stages of building design and planning the designer/installer shall verify that the installation pipes will be adequate for both immediate and probable future requirements."
What was West 3's contractual obligation under the Agreement as regards the size of the gas pipework?
"Subject to the Special Conditions these General Conditions of Sub-Contract are the applicable terms and conditions of the Sub-Contract Agreement and are the entire agreement between the Contractor and the Sub- Contractor and no variation or amendment or the delivery of the Sub-Contractor's terms and conditions shall have effect unless expressly confirmed in writing by the Contractor. In the event of an inconsistency between the General Conditions and Special Conditions, the Special Conditions shall prevail."
Was the original contractual obligation ever effectively varied and, if so, what was the effect of any such variation?
"The Sub-Contractor shall comply with any instruction issued by the Contractor whether to vary the Sub-Contract Works or otherwise. No variation to the Sub-Contract Works shall be effective unless agreed and set out in writing (both in terms of scope and value) and signed by an authorised representative of the Contractor before execution."
Did the system as originally installed fail to deliver sufficient gas pressure to a substantial number of flats and would the system on the revised drawings have delivered adequate gas pressures to all the flats?
Did the defect which caused the failure to deliver sufficient gas pressure result, wholly or partly, from West 3's breach of the terms of the Agreement?
Summary and Conclusion
(1) West 3's contractual obligation under the Agreement as regards the size of the gas distribution pipework from the meters to the valve in the flats was to install 1 inch TracPipe.
(2) Any question of the suitability of that size of pipe to meet the 1 mbar gas pressure drop requirement or otherwise was a matter for Mizen and its designers and not for West 3 who had no design responsibility.
(3) West 3's obligation was to carry out the Sub-Contract Works in accordance with the drawings issued on 24 August 2006 subject to the amendments made at the pre-order meeting on 20 October 2006 and recorded in the documents incorporated into the Agreement.
(4) West 3's original contractual obligation was never varied.
(5) The revised drawings were not issued to West 3 with Mizen's letter of 22 November or the letter of 13 December 2006 or on site on about 13 December 2006.
(6) There was no variation of the Sub-Contract Works under Clause 8.1 of the general conditions nor by any other method.
(7) The designs contained in the revised drawings were practically possible to implement.
(8) The gas distribution system as originally installed using 1 inch TracPipe would have failed to deliver sufficient gas pressure to a substantial number of flats.
(9) The gas distribution system on the revised drawings would not have delivered adequate gas pressures to all the flats because it would not, on balance, have met the required 1.0 mbar pressure drop requirement in Flat 41 by a small margin.
(10) The defect which caused the failure of the gas distribution supply system to deliver sufficient gas pressure did not result, wholly or in part, from West 3's breach of the terms of the agreement.