BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Laker Vent Engineering Ltd ("Laker") v Jacobs E&C Ltd ("Jacobs") [2014] EWHC 1058 (TCC) (08 April 2014) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2014/1058.html Cite as: [2014] EWHC 1058 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Royal Courts of Justice Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Laker Vent Engineering Limited ("Laker") |
Claimant |
|
- and - |
||
Jacobs E&C Limited ("Jacobs") |
Defendant |
|
And Between |
||
Jacobs E&C Limited |
Claimant |
|
-and- |
||
Laker Vent Engineering Limited |
Defendant |
____________________
Steven Walker QC (Instructed by Fenwick Elliott LLP) on behalf of Jacobs.
Hearing date: 14 March 2014
____________________
Crown Copyright ©
Mr Justice Ramsey :
Introduction
Adjudication enforcement proceedings
Affirmation of the decisions
"26. In my judgment the underlying decisions on election or approbation and reprobation, as applied in the context of adjudication, show that a party cannot both assert that an adjudicator's decision is valid and at the same time seek to challenge the validity of the decision. The party must elect to take one course or the other. By taking a benefit under an adjudicator's decision, the party will generally be taken to have elected a particular course and will be precluded from challenging the adjudicator's decision. In Macob the benefit was the claim to have the proceedings stayed to arbitration in relation to the decision. In Shimizu the benefit was the right to have the decision corrected under the slip rule.
…
29. PTB also relied on the fact that ROK had paid the Adjudicator's fees and had thereby elected to treat the Adjudicator's decision as valid. I do not consider that, in the absence of evidence to show that the payment was a mistake, the court can come to that conclusion as a matter of inference or otherwise, as Mr Lee sought to submit. Rather, the natural inference from the payment of the adjudicator's fees is that ROK intended to make payment in respect of a valid decision requiring such payment. Did that payment amount to an election? Mr Lee submits that it is difficult to characterise ROK's payment as amounting to ROK taking a benefit. There is strength in that point but, in my judgment, the taking of a benefit, whilst sufficient for there to be an election, is not necessary. What has to be determined is whether there has been an election. Objectively, a party who decides to pay a sum awarded against it in an adjudicator's decision does so in reliance on that decision being valid. I consider that, in the absence of any circumstances indicating to the contrary, by making that payment ROK elected to treat the adjudicator's decision on fees and expenses as being a valid decision, at least to that extent."
I confirm receipt of the three Decisions. Having reviewed the same, we believe there may be a small slip at paragraph 8.8 of Award Number 1 re the extension of time.
…
We have attached a note which shows what we believe to be the effect of this on your collection set out at paragraph 8.8.
We would be grateful if you could consider this and, if you agree, amend the decision accordingly.
As before, we fully reserve our client's position in relation to your jurisdiction and for the avoidance of doubt, this email is written without prejudice to that general reservation of our client's position in relation to your jurisdiction."
"… We consider that an appropriate adjudicator in this matter would be a legal adjudicator, i.e. a barrister with construction experience, rather than a surveyor. The issues in dispute are not technical ones…
We would also bring to your attention the fact that we have not had a letter of claim from your client, and therefore issuing a Notice of Adjudication is premature.
We also reserve our position in respect of the jurisdiction of the adjudicator, bearing in mind that the Contract is now at an end, and will probably be the subject of either legal proceedings or arbitration, we are quite happy for either to take place, but put you on notice that we reserve our position on challenging the adjudicator's jurisdiction…"
"It must follow that there may be numerous types of jurisdictional challenge and there can also be different types of reservation. One can reserve generally or specifically. I will leave open the issue as to whether a general reservation as to jurisdiction without any hint or suggestion as to what the grounds are can be effective; it may be so indefinite as to be a meaningless and ineffective reservation but it may be that in a particular context a general reservation may suffice. In this case however, Counsel both accepted. properly and correctly in my judgment that, if a specific reservation was made on one ground and it was established that the ground in question was an invalid jurisdictional objection, the party in question must be taken to have acceded to the jurisdiction only subject to the specific failed ground; in those circumstances, the parties will be taken to have submitted to the jurisdiction even if there are other good grounds which existed but were not mentioned."
"43. However, the matter does not end there because I have formed a clear view that there was in effect and in practice no valid or effective jurisdictional reservation made by Paradigm on the grounds that no dispute had crystallised in relation to the financial consequences of the unlawful termination as asserted by Allied. One needs to analyse what was said and what was not said by Paradigm and its advisers:
(a) Their solicitor's letter of 10 July 2009 does not reserve a jurisdictional objection in relation to quantum matters or indeed on the grounds of non-crystallisation of any dispute. The fact that Paradigm had "not had a letter of claim from" Allied is not a jurisdictional point at all; it is more a complaint or criticism that there has been no formal claim beforehand. There is of course no requirement under the adjudication clause or in the HGCRA for there to be such a formal claim beforehand. It follows that their complaint that the issue of a Notice of Adjudication was premature was also unfounded. The language of the letter suggests that the solicitors were aware of the need to reserve their position in relation to jurisdictional matters because they go on to reserve "their position in respect of jurisdiction of the adjudicator" on a specific ground, albeit one that was totally unjustified and is no longer pursued. The fact that they did not raise the language of reservation in relation to the "letter of claim" point supports the view that there was no intention to make a jurisdictional reservation with regard to that point.
…
44. It follows from the above that there was no objection to the jurisdiction of the adjudicator in relation to that part of the dispute or claims referred to adjudication on the grounds that all or some of those claims have not effectively been disputed. Thus, subject only to the bad jurisdictional objections which they did register, Paradigm not only did not make any effective reservation to the jurisdiction of the adjudicator but also acceded to the jurisdiction of the adjudicator to resolve all the claims which were the subject matter of the Referral. In those circumstances, the adjudicator's jurisdiction to resolve and issue a decision in respect of, all those claims is un-challengeable."
"I respectfully adopt that approach which seems to me to be equally applicable in the case of adjudication. The question in this case is therefore whether the words of general reservation were sufficiently clear to prevent Ringway's subsequent participation in the adjudication from amounting to a waiver or an ad hoc submission. In my judgment the words used both in the letters of 3 and 10 July 2009 and in the Response were sufficient to prevent a waiver of any jurisdictional argument, including one based on the alleged agreement of compromise/withdrawal and, as a result, there was no ad hoc submission."
"The task of the adjudicator is not to act as arbitrator or judge. The time constraints within which he is expected to operate are proof of that. The task of the adjudicator is to find an interim solution which meets the needs of the case."
Whether a construction contract
"It seems to me that this is the central issue between the parties. If the site is defined as the small areas on which the generators stood in Oldham and Watford, surrounded by a security fence, then the primary activity of the sites must be power generation, because the only activity of those sites is power generation. That must be so even though the activity (as shown by the planning applications) was intended to be merely temporary. If the site is defined as the whole areas occupied by MCP at Oldham and Watford, then it cannot conceivably be said that the primary activity of those sites is power generation. Taking those sites as a whole, power generation can only be regarded as ancillary to the primary activity of printing colour magazines whether or not excess power might be sold to others."
33. That definition, made in a contract to which neither Zedal nor ABB were party, might be thought to support the case presented by ABB. However, I do not accept that what some other parties defined as the site is the same as what was envisaged by Parliament for different purposes particularly when in the same contract they refer to the site in more general terms.
34. When Parliament refers in section 105(2) to "a site where the primary activity is…" the reference must be to a place broader than a generator surrounded by a security fence. To make any sense of the Act, one has to look to the nature of the whole site and ask what is the primary purpose of the whole site? Is the primary purpose power generation, or, in this case, printing?"
"Mr Blackburn submitted that section 105(2) should be read as a whole. I agree. It must also be read in the context of sections 104 and 105(1). In my judgment section 105(2) when compared with section 105(1) therefore shows that it was the intention of Parliament that exemption should be given by applying an additional and different test: was the object of the 'construction operation' to further the activities described in section 105(2)(c)... since in those industries or commercial activities it was not thought necessary that at any level there need be a right to adjudicate or to payment as provided by the Act.
The object of this subsection is therefore that all the construction operations necessary to achieve the aims or purposes of the owner or of the principal contractors, as described in it, would be exempt. If these approaches are correct then an interpretation should be given to section 105(2)(c) which would further and not thwart them"
"(1) Tullis Russell is the owner of a commercial and industrial site at Rothesfield, Markinch, Fife and carries on from that site the business of paper manufacturing;
(2) RWE proposes to erect on Tenant's Site the Plant and thereafter to operate the Plant; and
(3) Tullis Russell and RWE have agreed to enter into a lease to permit the construction, commissioning, operation, maintenance, repair and ultimately decommissioning of the Plant."
(1) "Landlord's Site" means the Rothes Mill Site under exception of Tenant's Site;
(2) "Plant" means the power plant to be constructed and commissioned by or on behalf of the Tenant on the Tenant's Site pursuant to Clause 4.1…
(3) "Premises" means the Tenant's Site and the Plant and any alteration, improvement or addition to them;
(4) "Rothes Mill Site" means the subjects at Rothes Mill, Cadham Road, Glenrothes, registered in the Land Register of Scotland under Title Number FFE17575;
(5) "Tenant's Site" means ALL and WHOLE those areas of ground extending to 11.776 acres (4.765 hectares) or thereby in total, comprising (a) that area shown outlined in orange on the Plan and (b) the Gas Pipe Land, all forming part of the Rothes Mill Site;
"The Tenant or its contractors shall, at the Tenant's sole cost, design carry out and complete the construction and commissioning of the Plant in a good and workmanlike manner with all due diligence and in compliance with all Applicable Law;"
"Subject to the Landlord's option to purchase the Standby Boiler Plant in terms of the ESC and also notwithstanding the termination of this Lease pursuant to Clauses 3.3, 3.5 or 7.1 or by effluxion of time, ownership of the Plant in and on the Tenant's Site and any alteration, improvement or addition to the Plant shall remain with the Tenant and shall, in questions between the Landlord and the Tenant, remain a Tenant's trade fixture."
"Upon termination of this Lease, howsoever determined, the Tenant shall, unless otherwise agreed with the Landlord in writing:
(a) Demolish, dismantle and remove from the Tenant's Site all buildings and other erections, equipment, machinery structures, installations (including foundations) or erections thereon (including the Plant to ground level); and
(b) clear the Tenant's Site and leave the Tenant's Site clean and tidy, in a condition commensurate with compliance by the Tenant with its obligations contained in Part 3 of the Schedule."
"18. It appears that the site had been previously used for waste disposal but that such use had ceased to enable the new waste incinerator and electricity generation plant to be built. This gives rise to the question whether it could be said that the site was one where the primary activity was either waste disposal or power generation when, because the plant was being built, neither of those activities could take place. This problem arises out of the use in section 105(2)(c) of the word "is". His Honour Judge Humphrey LLoyd QC considered this point in ABB Power Construction Ltd v Norwest Holst Engineering (2000) 77 Con LR 20. In argument counsel for the claimant pointed out that it would make little sense if work done to improve an existing complex would be exempt whilst work for a new project would not, and the Learned Judge endorsed that argument, stating that such a result would be an absurdity. I respectfully agree with that conclusion. In my judgment "is" in this provision means "is, or will be".
…
20. The wording in the section under consideration is "the primary activity" (my emphasis). What is "the primary activity" at a particular site is a question of fact. Whilst I accept that the primary purpose of a site will always be a relevant consideration in deciding what is its primary activity, it is possible to imagine situations which could give rise to an argument that an activity embarked upon for only secondary reasons is in fact (eg because of its scale or output, etc) the primary activity."
"The CHP scheme will replace the existing power plant at Tullis Russell, which is nearing the end of its planned operational use, with a new cleaner form of energy generation which will reduce the company's carbon emissions and safeguard jobs at the mill.
The additional capability will allow more energy to be exported to the local grid helping to meet Scotland's ambitious renewable electricity targets."
"A £200 million state-of-the-art biomass plant is on its way to being realised after RWE npower renewables officially took over the site of the new power station at Tullis Russell in Markinch today (17 November 2010).
Construction is now underway for combined heat and power (CHP) plant, which will be owned and operated by RWE npower renewables and provide 40 permanent jobs in the operation of the plant and fuel-processing facility. It will provide Tullis Russell with steam, which it needs for paper drying, as well as electricity and helps to safeguard 540 jobs at Markinch while reducing the papermill's fossil fuel CO2 emissions by around 250,000 tonnes each year."
New auxiliary steam supply plant will be required to provide a top-up, start-up and back-up steam supply to the existing Tullis Russell CHP plant during the 'interim period' and through the operating life of the new biomass CHP.
The existing Tullis Russell CHP plant comprises: two gas fired package boilers, three operational HP coal fired boilers, a natural gas fired HP boiler and three steam turbine generators. The balance of the power requirement for Tullis Russell can be imported from the national grid via an 11kV connection.
The existing package boilers are located in an area that will be required for the construction of the new CHP plant. These boilers will therefore have to be removed or relocated (to be carried out by others) in order to make way for the new plant. This will leave a period of time, the 'interim period' where the boiler capacity will need to be replaced by the new package boilers to be delivered under this Contract."
Inconsistency between Award No 3 and Award No 1
"8.3 ISSUE
"Whether [Laker] is entitled to an Extension of Time and if so how much?"
ADJUDICATOR'S DECISION: YES, as claimed.
8.3.1 DISCUSSION/ADJUDICATOR'S OBSERVATIONS
It is common ground that the original contract completion period was/is just over 6-months from 30 March 2012 to 12 October2012. But
Practical Completion is about 1-year later."
"8.3.2.2 "Is [Laker] therefore entitled to an extension of time?"
ADJUDICATOR'S DECISION: YES, precisely as claimed.
DISCUSSION:
Plainly the work was being done on instructions (i.e. [Jacobs] to [Laker]). That's the factual cause of taking all of the time it took being 18-months or so."
"(c) That [Laker] is entitled to an EOT of 52 weeks for completion of the subcontract works or such other period as the Adjudicator shall think appropriate.
ADJUDICATOR'S DECISION: Granted to Practical Completion."
"A taking-over certificate was applied for by [Laker] on 20 August 2013. On 06 September [Jacobs] responded but did not issue a taking-over certificate. [Jacobs] maintains that certain documentation has to be supplied by [Laker] before issue of taking-over certificate. In the event [Jacobs] has issued the taking-over certificate on 20 November 2013, backdated to 12 October 2013 with outstanding Works including want of Quality Certification Dossier(s)."
"9.2 ISSUE
"Whether [Jacobs] was correct in not issuing a "Taking-Over Certificate" within 28-days of [Laker] application of 30 August 2013"
ADJUDICATOR'S DECISION: NO. It ought to have issued the Taking-Over Certificate."
The Taking-Over Certificate ought to have been issued stating the date of 30 August 2013 when the Works were complete and ready for taking-over."
The Scheme
"The Sub-Contract shall in all respects be governed by and interpreted in accordance with the Laws of the Country stated in the Special Conditions of Sub-Contract."
"The Sub-Contract shall in all respects be governed by and interpreted in accordance with the Laws of England and shall be subject to the jurisdiction of the English courts."
"Mr. Reed submits that it makes no difference because the nominating authority who purported to nominate the adjudicator, the President of the RICS, would have been the nominating authority under the Scheme (the parties not having made any other agreement about the appointment of an adjudicator). In these circumstances Mr. Reed submits that Twintec is seeking to promote form over substance and that its position is entirely artificial. Whilst, at a practical level, I have some sympathy with this submission, I cannot accept it because the validity of the procedure by which the adjudicator was nominated goes to the heart of his jurisdiction."
The Part 8 Claim
"If any dispute arises between the Contractor and the Sub-Contractor in connection with this Sub-Contract, it shall, subject to the provisions of this Clause, be referred to the arbitration and final decision of a person agreed between the parties, or failing such agreement, the dispute or difference shall be referred for settlement in the same manner as a dispute or difference arising under the Main Contract. In accordance with the Main Contract the dispute or difference shall be referred to and settled in accordance with the provisions of the Main Contract."
"(1) The parties are free to agree on the procedure for appointing the arbitrator or arbitrators, including the procedure for appointing any chairman or umpire.
(2) If or to the extent that there is no such agreement, the following provisions apply.
(3) If the tribunal is to consist of a sole arbitrator, the parties shall jointly appoint the arbitrator not later than 28 days after service of a request in writing by either party to do so."
"(1) The parties are free to agree what is to happen in the event of a failure of the procedure for the appointment of the arbitral tribunal.
…
(2) If or to the extent that there is no such agreement any party to the arbitration agreement may (upon notice to the other parties) apply to the court to exercise its powers under this section."
"On an application under this section the court shall grant a stay unless satisfied that the arbitration agreement is null and void, inoperative, or incapable of being performed."
Summary and Conclusion