BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> ISG Retail Ltd v Castletech Construction Ltd [2015] EWHC 1443 (TCC) (22 May 2015) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2015/1443.html Cite as: [2015] EWHC 1443 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, 7 Rolls Buildings London EC4A 1NL |
||
B e f o r e :
____________________
ISG Retail Ltd |
Claimant |
|
- and - |
||
Castletech Construction Ltd |
Defendant |
____________________
(instructed by Knights Solicitors LLP) for the Claimant
Peter Oliver Esq
(instructed by Contract & Construction Consultants Ltd) for the Defendant
Hearing dates: 14th May 2015
____________________
Crown Copyright ©
Mr. Justice Edwards-Stuart:
Introduction
The facts
"ISG has suffered loss as a consequence of CC's breaches, in the sum of £35,000 plus VAT. This sum must be repaid to ISG forthwith, plus interest plus costs."
"As a matter of law, if a defendant has been paid in advance but fails fully to perform its obligations as it promised to do, it follows that the claimant can recover its advance payment by virtue of total failure of consideration. That is exactly what has occurred in this matter."
Then, at paragraph 17:
"In the event, ISG has incurred a loss and is entitled to recover in restitution the sum of £35,000 plus VAT by reason of a total failure of consideration."
This paragraph, together with paragraph 16 immediately before it, included for the first time a reference to restitution.
"32.1 That CC acted in breach of contract as set out above.
32.2 That as a result ISG suffered the loss summarised above.
32.3 That CC owes sums to ISG as a consequence.
32.4 That ISG is entitled to payment by CC in the sum of £35,000 plus VAT, or such other greater or lesser sum as the Adjudicator may decide is due.
32.5 That ISG is entitled to interest on such sums."
"ISG are not entitled to the remedy that they have claimed (restitution) in adjudication at all because that is an equitable remedy not within an adjudicator's jurisdiction/power."
Then, at paragraph 4.4:
"There is no pleaded or factual basis on which the adjudicator can find any breach of contract/partial failure of consideration other than a 100% failure to perform (which is clearly not the case on the evidence)."
The point was repeated at paragraph 15 where CC denied being in breach of contract or that there was a total failure of consideration.
"This confirms that ISG's restitutionary claim is not made under the sub-contract - because restitutionary claims are not made under contracts, they are made in equity, restitution being an equitable remedy - and as such the adjudicator has no jurisdiction/power to decide it."
The grounds on which CC resists the application for summary judgment
i) The adjudicator made a decision that was outside the scope of the dispute referred to him; orii) The dispute was not a dispute arising under the contract.
The authorities
"On discharge of a contract of this kind a buyer who has paid the whole or part of the price in advance is entitled, in the absence of any agreement to the contrary, to recover what he has paid by reason of a total failure of consideration. He therefore has a right to recover in restitution any payments he has made in respect of the price, a right which is quite distinct from any right he may have (if he is the injured party) to recover damages for the loss of his bargain. In the present case the parties made specific provision for the repayment of instalments and Gearbulk could not, of course, recover both under the contract and in restitution; to do so would result in double recovery. In fact, however, Gearbulk is not seeking to recover the advance payments since it has already done so. There is no inherent inconsistency, however, in recovering instalments of the price under Article 10 and recovering damages for loss of bargain at common law."
The application of the law to the facts of this case
Conclusion