BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Cooper & Anor v Thameside Construction Company Ltd [2016] EWHC 1248 (TCC) (27 May 2016) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2016/1248.html Cite as: [2016] EWHC 1248 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
(1) Mr Marcus Cooper (2) Mrs Katie Amelia Cooper |
Claimants |
|
- and - |
||
Thameside Construction Company Ltd (in administration) |
Defendant |
____________________
Neil Moody QC and Andrew Miller QC (instructed by Kennedys Law LLP) for the Defendant
Hearing dates: 10th, 11th, 12th, 16th and 19th May 2016
____________________
Crown Copyright ©
Mrs Justice Carr:
A. Introduction
a) For Mr and Mrs Cooper: Mr and Mrs Cooper; Peter Beer of Ottima (Specialist Joinery and Furniture) Limited ("Ottima") ("Mr Beer"); Jonathan Evans of Metropolitan Development Consultancy Limited ("MDC") ("Mr Evans"). A written statement from Mr Bachelard of Dr JH Burgoyne and Partners LLP ("Burgoynes"), was agreed;
b) For Thameside: Frank Cosgrove of Darenth ("Mr Cosgrove"); Paul Johnson, a self-employed plumber contracted to Darenth ("Mr Johnson"); Paul McBryde, a carpenter who worked on the property for Thameside ("Mr McBryde"); Glenn Gradwell, contracts manager and a former director of Thameside ("Mr Gradwell"); Michael Lynch, construction site manger for Thameside at the property ("Mr Lynch").
a) For Mr and Mrs Cooper: Dr Simon Jones of Burgoynes. Dr Jones is a chartered mechanical engineer specialising in the investigation of incidents of mechanical failures;
b) For Thameside:
i) Mrs Daphne Wasserman of Cadogan International Limited ("Cadogans"). Mrs Wasserman is a chartered engineer;
ii) Mr Gerry Brannigan also of Cadogans. Mr Brannigan is a building services consulting engineer.
a) Section B: The JCT contract and duties owed by Thameside;
b) Section C: The Polyplumb connector and the cause of the flood;
c) Section D: A general chronological overview of events;
d) Section E: The documentary evidence relating specifically to bathroom 6;
e) Section F: The burden of proof and the fact-finding exercise;
f) Section G: The witnesses;
g) Section H: The access hatch and panel;
h) Section I: Did Mr Johnson (or another Darenth plumber) install the Polyplumb connector?
i) Section J: Possible alternative explanations for the installation of the Polyplumb connector;
j) Section K: Possible adverse inferences;
k) Section L: The position of Ludek;
l) Section M: Conclusion.
B. The JCT contract and duties owed by Thameside
"Intentions of the Parties
Contractor's obligations
1.1 The Contractor shall carry out and complete the Works in a proper and workmanlike manner and in accordance with the Contract Documents identified in the Second recital and with the Health and Safety Plan…
3. Control of the Works
…
Sub-contracting
3.2 The Contractor shall not sub-contract any part of the Works other than in accordance with clause 3.3 without the written consent of the Architect/the Contract Administrator whose consent shall not be unreasonably delayed or withheld. The Contractor shall remain wholly responsible for carrying out and completing the Works in all respects in accordance with clause 1.1 notwithstanding the sub-contracting of any part of the Works.
Named Persons as sub-contractors
…
3.3.1 Where it is stated in the Specification/Schedules of Work/Contract Bills that work described therein for pricing by the Contractor is to be executed by a named person who is to be employed by the Contractor as a sub-contractor the Contractor shall not later than 21 days after entering into this Contract enter into a sub-contract with the named person using Section III of the Form of Tender and Agreement NAM/T referred to in the First recital…
3.3.7 Whether or not a person who has been named as a sub-contractor under any of clauses 3.3.1 to 3.3.5 is responsible to the Employer for exercising reasonable care and skill in:
- the design of the sub-contract works insofar as the sub-contract works have been or will be designed by the named person;
- the selection of the kinds of materials and goods for the sub-contract works insofar as such materials and goods have been or will be selected by the named person; or
- the satisfaction of any performance specification or requirement relating to the sub-contract works,
the Contractor shall not be responsible to the Employer under this Contract for anything to which the above terms relate, nor through the Contractor, shall the person so named or any other sub-contractor be so responsible; provided that this shall not be construed so as to affect the obligations of the Contractor or any sub-contractor in regard to the supply of goods and materials and workmanship.
The provision of this clause 3.3.7 shall apply notwithstanding that the Sub-Contract Sum stated in article 2 of Section III of the Tender and Agreement NAM/T referred to in clause 3.3.1 or 3.3.2 included for the supply of any design, selection or satisfaction as referred to herein, and that such Sub-Contract Sum is included for within the Contract Sum or the Contract Sum as finally adjusted.
…
3.3.9 Save as otherwise expressed in the Conditions the Contractor shall remain wholly responsible for carrying out and completing the Works in all respects in accordance with clause 1.1 notwithstanding the naming of a sub-contractor for the execution of work described in the Specification/Schedules of Work/Contract Bills.
…
Work not forming part of the Contract
3.11 Where the Contract Documents provide for work not forming part of this Contract to be carried out by the Employer or by persons employed or engaged by the Employer, the Contractor shall permit the execution of such work on the site of the Works concurrent with his execution of the Contract Works. Where the Contract Documents do not so provide the Employer may nevertheless with the consent of the Contractor (which consent shall not be unreasonably delayed or withheld) arrange for the execution of such work.
Every person so employed or engaged shall for the purposes of clauses 6.1 [injury and damage] and 6.3 [insurance of the Works] be deemed to be a person for whom the Employer is responsible and not a sub-contractor.
6. Injury, damage and insurance
Injury to persons and property and indemnity to Employer
…
6.1.2 The Contractor shall be liable for, and shall indemnify the Employer against, any expense, liability, loss, claim or proceedings in respect of any loss, injury or damage whatsoever to any property real or personal in so far as such loss, injury or damage arises out of or in the course of or by reason of the carrying out of the Works and to the extent that the same is due to any negligence, breach of statutory duty, omission or default of the Contractor, his servants or agents or of any person employed or engaged upon or in connection with the Works or any part thereof, his servants or agents or of any person who may properly be on the site upon or in connection with the Works or any part thereof, his servants or agents…"
a) That the materials used in the Works would be reasonably fit for the purpose for which they were required in the works (section 4 (5) of the Supply of Goods and Services Act 1982 ("the Act"));
b) That the materials used would be of satisfactory quality (section 4(2) of the Act); and
c) That the works would be carried out with reasonable care and skill (section 13 of the Act).
C. The Polyplumb connector and the cause of the flood
D A general chronological overview of events
a) the installation of the pipework necessary to deliver hot and cold water to the taps for the basin in bathroom 6 was included under the JCT contract;
b) Thameside sub-contracted its mechanical and electrical and plumbing obligations under the JCT contract to Darenth;
c) Darenth was not a "nominated" sub-contractor.
a) Specialist joinery and furniture works were made the subject of a separate direct contract between Mr and Mrs Cooper and Ottima. Mr Beer was Ottima's owner and managing director. Ottima supplied the vanity unit above the basin in bathroom 6;
b) Specialist stoneworks were taken out of the JCT contract and made the subject of a separate contract between Signature Stone Limited ("Signature") and the Coopers either direct or via Ottima. Mr Jose Nona Balola ("Mr Balola") was a director of Signature from June 2005 to December 2011. It appears that Signature entered into creditors' voluntary liquidation in June 2012 and was dissolved in December 2013. Signature supplied the basin, and the stone for the wall below and around the basin in bathroom 6.
"Practical completion, as such, took place in January 2009. There is no certificate."
E. The documentary evidence relating specifically to bathroom 6
"...As there has been little progress on site over the past few months I am therefore detailing services information that is still outstanding and which must be confirmed before any real progress can be achieved:
1. O[t]tima are now fitting finished furniture in Bathrooms but to-date there is no sanitary/brassware schedule. Although all of our services are in position in partitions, final fix of the ply cladding cannot occur until the carcassing of the brassware is complete. In most cases this means the rear of the diverters/taps must be in position and wastes positioned exactly to accept the sanitary ware…."
"Bathrooms 5 & 6, Vanity's [sic] made fitted, removed and brought back to workshop. Now being redesigned. Waiting for sanitary ware and plumbing before stone can be fitted. Vanity being repriced along with solid stone basin. Existing ones to be save[d] to see what can be reused..."
"Bathroom 6 mark 2 Smaller unit to be drawn and costed. The unit will also need steel support arms for the sink to be made."
"Further to our telephone conversation yesterday I have now fully investigated the sanitary ware schedule ordered from Wash with the Bathroom drawings issued on 26th January 2007 for the three second floor shower rooms …
En suite Bathroom 6
…Basin
Gessi Retangolo deck mounted monoblock mixer tap chrome 20001
The Ottima drawing details a chrome wall mounted tap discharging into the bespoke basin. Should the tap be chrome 20085? There is no waste specified and we assume this will be supplied with the bespoke basin…."
(Chrome 20085 taps were wall mounted. Chrome 20001 were deck mounted). The same comment was made for bathroom 5.
"1. Set out and size of wall slot required to shower rooms 5 & 6 to receive cabinet and basins. Thameside… to remove ply fitted by Ottima and prepare opening accordingly…"
"Showerrooms 5 & 6 units & stone 10 days start Tuesday 010507 finish mon 140507"
"Ottima have programmed to be onsite on Tuesday 24th April at which time they will be getting on with all ensuite bathrooms…
Ottima are supposed to be co-ordinating with Signature... and Darren [of Sheldon]."
"1.52 Ottima and Signature Stone to start bathroom 5 and 6 this week. Outstanding."
"… Extend cables to heated mirror pad now that Ottima basin is installed."
"… To second fix bedrooms and ensuites 4, 5 & 6 electrically, with white plates to the power. Light fittings as approved. Protect the stone in 5 & 6, have the sloped soffits plastered and fit the sanitaryware, taps and shower fittings."
"Bedroom 6 Ensuite
… 1.35 Supply and fix stone below basin. Ottima"
(with an identical entry for bathroom 5).
"Bedroom 6 ensuite
1.01 Supply stone access panel and fix on ply access board fixed on magnets and pull catches below basin and mastic in place. Outstanding Signature Stone/Ottima"
with an identical entry for bathroom 5.
"Can you please organise for the following bits to be completed as soon as possible on the second and first floor so that Ottima and Jose can get the top floor finished and continue with the first:
The ply access panels under the basins in en suites to bedrooms 5 and 6 need fixing properly so Jose can fix the stone to it…"
"…This has been going on from before Christmas… The holes Signature… have drilled are not only too large but slightly egg shaped. Signature… have tried to recess the outer rim of the waste to be flush with the stone which has not been sufficiently accurate as they have tried to carry out the work on site instead of drilling the stone on a jig."
"... Supply stone access panel and fix with a mastic joint – Signature Stone/Ottima"
"2nd Floor Bathrooms – all stonework completed except for architraves Awaiting basin waste detail. JB [Signature] agreed to remake the basins. Shower screen and mirror trim details required. Vanity units to be returned to site by 14th July 2008."
"Access for Maintenance. [Mr Beer] and [Mr Balola] requested details of the bath access panels and [MDC/Sheldon Studios] to sort out. [Mrs Cooper] advised that all areas had to be readily accessible and she did not want to be breaking out stone etc so that ordinary maintenance could be carried out. [MDC/Sheldon Studios] to take this on board and this will require alterations to areas elsewhere where the practical side of things has been totally forsaken for design. URGENT – 7 DAYS"
"… 1.38 JB [Signature] to either source new waste for approval by DG that fits the holes already in the basins or he is to change the basin bases and recut the holes to suit the waste on site."
"2nd Floor Bathrooms – all stonework completed except for architraves. Awaiting basin waste detail. JB [Signature] agreed to remake the basins and will be delivered this week. Shower screen and mirror trim details required. Vanity units not yet returned to site. Will mostly be dealt with within LT [Ludek] contract period. Shower trays to be broken out and replaced with Dallmer styled outlets with removable tops so that proper access can be afforded…"
"32. The ensuites to bedrooms 4, 5 and 6 can now be completed and should be as soon as possible. Mastic contractor to be appointed by Darren – Ludek to advise when the rooms will be ready for him. OUTSTANDING Ludek/Signature.../Ottima/DG [Sheldon]"
F. The burden of proof and the fact-finding exercise
"In approaching this question it is important that two matters should be borne constantly in mind. The first matter is that the burden of proving, on a balance of probabilities, that the ship was lost by perils of the sea, is and remains throughout on the shipowners. Although it is open to underwriters to suggest and seek to prove some other cause of loss, against which the ship was not insured, there is no obligation on them to do so. Moreover, if they chose to do so, there is no obligation on them to prove, even on a balance of probabilities, the truth of their alternative case."
"The second matter is that it is always open to a court, even after the kind of prolonged inquiry with a mass of expert evidence which took place in this case, to conclude, at the end of the day, that the proximate cause of the ship's loss, even on a balance of probabilities, remains in doubt, with the consequence that the shipowners have failed to discharge the burden of proof which lay upon them."
a) A judge is not bound always to make a finding one way or the other. This is a point "of great importance". The unsatisfactory state of the evidence may make this the only just course for him to take;
b) The dictum can only apply when all relevant facts are known, so that all possible explanations, except a single extremely improbable one, can properly be eliminated;
c) The legal concept of proof of a case on a balance of probabilities must be applied with common sense. If a judge concludes on a whole series of cogent grounds that the occurrence of an event is extremely improbable, a finding by him that it is nevertheless is more likely to have occurred than not, does not accord with common sense.
"64. It is not an uncommon feature of litigation that several possible causes are suggested for the mishap which the court is investigating. If the court is able, for good reason, to dismiss causes A, B and C, it may be able to reach the conclusion that D was the effective cause. But the mere elimination of A, B and C is not of itself sufficient. The court must also stand back and, looking at all the evidence, consider whether on the balance of probabilities D is proved to be the case. See Nulty v Milton Keynes Borough Council [2013] EWCA Civ 15 at [34] per Toulson LJ and Graves v Brouwer [2015] EWCA Civ 595 at [24] to [30]".
"34. A case based on circumstantial evidence depends for its cogency on the combination of relevant circumstances and the likelihood or unlikelihood of coincidence. A party advancing it argues that the circumstances can only or most probably be accounted for by the explanation which it suggests. Consideration of such a case necessarily involves looking at the whole picture, including what gaps there are in the evidence, whether the individual factors relied upon are in themselves properly established, what factors may point away from the suggested explanation and what other explanation might fit the circumstances. As Lord Mance observed in Datec Electronics Holdings Limited v UPS Limited [2007] UKHL 23, [2007] 1 WLR 1325, at 48 and 50, there is an inherent risk that a systematic consideration of the possibilities could become a process of elimination "leading to no more than a conclusion regarding the least unlikely cause of loss", which was the fault identified in The Popi M. So, at the end of any such systematic analysis, the court has to stand back and ask itself the ultimate question whether it is satisfied that the suggested explanation is more likely than not to be true. The elimination of other possibilities as more implausible may well lead to that conclusion, but that will be a conclusion of fact: there is no rule of law that it must do so. I do not read any of the statements in any of the other authorities to which we were referred as intending to suggest otherwise."
a) The court is entitled to engage in a systematic analysis of competing theories and eliminate one in favour of the other;
b) That, in itself, may lead to the conclusion that the preferred theory is more likely than not to be true; but
c) The court must always then stand back and ask itself the ultimate question as to whether or not the preferred explanation is more likely than not to be true.
a) Mr Balola of Signature;
b) Mr Tucny of Ludek.
G. The witnesses
a) He readily accepted his original errors and explained that he identified them once he was shown the relevant documentation. I found his explanations for his errors to be genuine and that the making of the errors was not such as to undermine fundamentally his reliability for all purposes. The events in question took place a long time ago. He does not appear to have been shown much, if any, of the relevant contemporaneous documentation to assist him with dates and detail at the time of his first statement, or to have understood the importance or relevance of certain issues. Thus I accept his evidence that he did not understand the importance of sequencing at the time of his original statement;
b) It was he who, shortly before trial, found – by chance – his 2006 diary and his passport showing his movements in 2007. He quite rightly volunteered them up;
c) He made fair concessions without hesitation, for example as to the effect of the facing wall on access to the pipework; on the difficulties of using a spanner in the space available; that the facing wall with its tiling prevented any access to the pipework under the basin. He confirmed that he had never seen the facing wall demolished and had never seen any operatives of Ludek carrying out any plumbing work on site. He made fair concessions in relation to paragraph 11 of his first witness statement, conceding that Darenth had used Polyplumb fittings on some of the waste and soil pipes, which formed part of the plumbing on the project, although he was able to maintain that only HEP20 fittings were used by Darenth on pressurised delivery pipework.
"I cannot remember precisely when, but I do recall that on one particular day, post June 2007, during one of my walks around the site, I noticed that stone below the basin in ensuite 6, had been taken off. I also noted that the wash basin remained in place.
The reason why I noticed the hacked off stone was because I was concerned that there could be damage to other fittings and fixtures in the ensuite and that Thameside would be blamed for any such damage and have to make good the damage.
I specifically remember speaking to someone at Signature Stone informing them that if they were carrying out works and taking off the stone that they should ensure that they protected the wash basin. I was told by the Signature Stone representative that there was no need to worry about damaging the wash basin while removing the stone because the basin was going to be changed. I did not need to take this matter further as such works were not within Thameside's ambit."
H. The access hatch and panel
a) Not a single drawing for bathroom 5 or 6 shows an access hatch or panel below the basin. An access panel was shown in the vanity units. Without an express instruction before 3rd July 2007, of which there is no evidence at all, the hatch and panel would not have been created by then;
b) The first document to mention the need to fix stone below the basin in bathroom 6 is dated 15th July 2007 (some 6 days after Signature was on site on 9th July 2007). Express reference to an access panel below the basin in bathroom 6 is first made on 21st August 2007;
c) This is consistent with the question of access for maintenance generally at the property being something of an afterthought, perhaps triggered here by someone seeing the fully tiled stonework right up to the basin in bathroom 6 in early July 2007. The minutes of a site progress meeting on 1st July 2008 record that design had been prioritised over practicality/access for maintenance;
d) Mr Cosgrove's evidence, which I accept on this issue, is that he was never aware of an access hatch or panel below the basin in bathroom 6;
e) Mr Johnson was very clear that there was no hole below the basin when he carried out the second fix. The wall was stone clad up to the basin – a finished wall. I accept his firm evidence on this issue;
f) In particular, Mr Johnson's unchallenged recollection of the second fix is important in this context. He stated that as part of the second fix he placed a chrome flange over a horizontal (first fix) pipe and placed it up against the tiling. The flange, which can be seen on photographs, allows for any discrepancy in the cutting and fixing of the tiles around the chrome pipe. He would not have been able to do this if there had been an open hatch without an access panel in place. This would be a remarkable embellishment of recollection if it were not true. I accept his evidence on this issue.
I. Did Mr Johnson (or another Darenth plumber) probably install the Polyplumb connector?
a) Did Mr Johnson do the plumbing to the basin in bathroom 6?
b) If so, did he install the Polyplumb connector?
c) If not, did another Darenth plumber do the plumbing in bathroom 6?
d) If so, did that other plumber install the Polyplumb connector?
Did Mr Johnson do the plumbing to the basin in bathroom 6?
a) That the letter shows that both horizontal and vertical pipes had been laid by 13th November 2006;
b) By reference to Mr Johnson's 2006 diary, that Mr Johnson could not have carried out the laying of the horizontal or vertical pipes.
"Nobody else put in the horizontal piping. I put it in."
"It's not something that takes a long time, it's just a pain drilling it all, but to pull the pipe through from one end of a bathroom is…..you know, it's not a difficult job."
If it was Mr Johnson, did he install the Polyplumb connector?
a) He was working on a bare stud wall with no fixtures or fittings in place;
b) All he had to do was connect a length of pipe between the T-joint and join a piece of pipe long enough to reach the tap box connections. He used a single length of pipe for each of the hot and cold water supplies;
c) There was simply no reason for him to make the length of pipe shorter. Connecting two different lengths of pipe would not only result in additional work and materials but would not be good practice;
d) If for some reason he had misjudged the length of pipe needed, he would simply have discarded those lengths of pipe and cut another piece. He would not have pieced together two small pieces of pipe with a joint connection and then repeated the same for the other piece of pipe. Such small pieces of piping are not used and are always thrown in the skip. There was no shortage of pipe material on site as it was drawn from a large 50m coil.
a) This was a very poor piece of plumbing work indeed on a project which Mr Johnson knew was to be of the highest quality and standard. There was no sensible plumbing reason for the use of connectors, let alone the use of a second hand fitting. In opening, it was described for Mr and Mrs Cooper as "a piece of unbelievably shoddy plumbing". Yet Mr Johnson is and was a highly competent and experienced plumber. Mr Evans was clear that there were no problems with or complaints about Darenth's work on the project. Thameside has continued to use Darenth on other projects. It is very difficult to associate Mr Johnson (or any other Darenth plumber) with such a piece of work. He is also accepted on all side as being an honest man. If he had made such a mistake, my assessment is that he would simply have admitted it;
b) No credible reason has been identified for Mr Johnson (or any other Darenth employee) to cut lengths of pipe that were too short, necessitating the use of connectors. The theory advanced has been that there was uncertainty as to whether or not the taps were to be deck mounted or wall mounted. Mr Beer recalled no discussion at any stage of deck mounted taps. From his point of view, the taps were always to be wall mounted. Mr Johnson, the relevant individual on my findings, at no time thought that the basin in bathroom 6 was to have deck mounted taps. This was clear to him from the drawings, and also from the size and configuration of the bathroom, which was small and very narrow. The designers made a mistake at one stage, but Mr Cosgrove picked that up and obtained clarification that it was indeed a mistake. Even if there was a period when Mr Cosgrove had to query the position on 1st February 2007, there was only a short period of uncertainty. And even if he had a doubt, he never positively believed that deck mounted taps would be used. The incorrect fittings were returned not used, as Mr Evans confirmed;
c) Even if the pipes were cut too short, Mr Johnson appeared genuinely unable to understand why the solution would be to insert straight connectors. He would just have started again to cut longer lengths of pipe, cheaply and readily available. He was working on an open stud wall. I am not persuaded that anything in Darenth's financial history undermines the evidence of both Mr Johnson and Mr Cosgrove that there was never any shortage of piping materials. Mr Cosgrove was clear that was never any shortage. Nothing in his conduct on the project in early 2007 suggested that he (or Darenth) was in turmoil: rather the contrary, his correspondence at that time appears careful, detailed and prompt;
d) The fact that the faulty joint was a Polyplumb connector, not a HEP20 connector, suggests that the work was not that of Darenth. Whilst both Mr Cosgrove and Mr Johnson were incorrect in saying that Darenth did not use Polyplumb products anywhere on site, there is no evidence to suggest that they were wrong in maintaining that none of Darenth's work on the pressurised hot and cold water installation system involved Polyplumb products, let alone second-hand Polyplumb products.
a) they were not being approached by Thameside (or anyone else), to provide any information or answer questions in relation to the incident;
b) Mr Johnson had told Mr Cosgrove, for whom he had been working at the time, that he had not installed the Polyplumb connector;
c) Mr Cosgrove had informed his insurance brokers of the incident and was told not to make any statements in respect of the incident,
J. Possible alternative explanations for the installation of the Polyplumb connector
"Definitely not. The debris and the way the stone was smashed with a hammer…"
a) The fact that he stated unequivocally in his second statement that Ludek was never engaged by Thameside as a sub-contractor. As appears in section L below, in fact, as Mr Gradwell accepted, the position is more nuanced than that. Two points can be made: i) this issue has nothing to do with seeing the demolition of the wall in bathroom 6 and ii) the statement was made the day before his oral evidence in response to the late positive case mounted for Mr and Mrs Cooper that Ludek as finishing contractor was Thameside's subcontractor. Although Mr Gradwell did of course sign and verify the statement, it smacks of being drafted over-enthusiastically by lawyers and in a rush during trial without full consideration of the relevant documents. When Mr Gradwell was taken to those documents, he readily explained the subtler position that there was a sub-contract between Thameside and Ludek in around July 2008, but it was only a mechanism;
b) The fact that he incorrectly suggested that Thameside was denied access to the property from the end of 2007 through 2008. Mr Lynch said that as site manager, he did have access if he needed it. This point again does not strike at the heart of the matter: it is clear that there was handover of rooms as they were completed by Thameside to Ludek or for snagging purposes;
c) The fact that he allegedly downplayed his position within Thameside as director. I do not consider this to be a fair criticism. It was clear from Mr Gradwell that he did not consider himself a main player in Thameside. He was a director, but his role was really that of contracts manager. He held only 5 out of 100 shares in Thameside. Nor am I impressed by the criticism of his failure to mention what he saw in bathroom 6 to Thameside's insurers. I accept that his evidence that he was not involved in the arguments being advanced on behalf of Thameside. Mr Harris was dealing with that side of things. Mr Gradwell's role was just to carry on with Thameside's projects.
a) The lack of documentary record of any instruction to demolish the wall. But if it was a necessary part of creating the hatch, this absence is not so telling. And the documentation before me appears incomplete;
b) The lack of any evidence of a claim for payment for such work. As already indicated, it is not clear precisely what was charged for and when, but in any event the absence of a claim for repair works at least is consistent with damage being caused through someone's fault (and so not claimed for). And again I am not convinced that all the documentation is available;
c) The fact that no other witness than Mr Gradwell saw the wall down. This is not surprising. The bathroom was a small room at the top of the property;
d) The lack of any evidence of a flood taking place. All the witnesses have been clear that they were never aware of a flood as such. But i) the system may not have been energised ii) even if it was, the entire system could have been isolated by use of the pump set, or the second floor system could have been isolated by use of the individual clearly labelled isolation valves in the plant room described by Mr Cosgrove. This could have been done before the works were carried out, or immediately upon the damage being caused. The damage would have occurred in the presence of at least one tradesman who could also have taken steps to clear up and minimise any flooding;
e) The fact that two pipes were compromised. This merely suggests that both pipes may have been cut to move them or damaged;
f) The fact that Signature was not a plumber. This does not rule out the possibility of Signature installing the Polyplumb connector: the job was relatively simple. The fact that it was done so incompetently suggests in any event that it was not carried out by a professional plumber. Additionally, it appears that Signature and Ludek worked closely together. If there was some sort of incident, Ludek may have helped Signature out;
g) The fact that there is no evidence of anyone seeing the wall down in bathroom 5. This is correct. The focus of the trial and evidence has been very much on bathroom 6. But the wall in bathroom 5 may have been taken down after Mr Gradwell saw the wall down in bathroom 6.
K. Possible adverse inferences
"(1) In certain circumstances a court may be entitled to draw adverse inferences from the absence or silence of a witness who might be expected to have material evidence to give on an issue in an action;
(2) If a Court is willing to draw such inferences, they may go to strengthen the evidence adduced on that issue by the other party or to weaken the evidence, if any, adduced by the party who might reasonably have been expected to call the witness;
(3) There must, however, have been some evidence, however weak, adduced by the former on the matter in question before the court is entitled to draw the desired inference: in other words, there must be a case to answer on that issue;
(4) If the reason for the witness' absence or silence satisfies the court, then no such adverse inference may be drawn. If, on the other hand, there is some credible explanation given, even if it is not wholly satisfactory, the potentially detrimental effect of his/her absence or silence may be reduced or nullified".
L. The position of Ludek
"2. Contract Procedure. [MDC] explained that it had been agreed that all sub-contractors would now be under the control of Thameside…and that everyone must report to [Thameside] about their programme on site, the information outstanding and any construction difficulties which they faced…
5. Ludek Build. Ludeck Tucny was introduced to the meeting as the finishing contractor for the works…..[Mr Tucny] had..to produce a price for acceptance by [Mr Cooper]. He will send this through to [Sheldon Studios] to check the content and to [MDC] for passing on to [Mr Cooper]. The intention is that [Thameside] will hand over areas of the site to [Mr Tucny] who will then see that area through to completion."
"Accordingly please can you formalise Ludek's appointment and agree the programme going forward in order to get Ludek on site without delay."
"Our company is not established for monthly payments and this was the reason why I agreed with Darren [of Sheldon Andrews] that only fortnight payments will allow me to step in to the Redington and work there…"
"…if Marcus wants to take it out of the responsibility of Thameside and the contract that is fine. I will do whatever instructed. The downside is that neither Thameside nor ourselves have any control over the situation but if you can deal with it then that is fine (if Marcus agrees).
M. Conclusion
a) It has always been common ground that the works under the JCT contract included the installation of the pipework beneath the basin in bathroom 6;
b) It has always been common ground that Darenth was Thameside's plumbing sub-contractor under the JCT contract and the only contracted plumber on site;
c) Thameside admitted that Darenth installed the Polyplumb connecter.