BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Stellite Construction Ltd v Vascroft Contractors Ltd [2016] EWHC 792 (TCC) (14 April 2016) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2016/792.html Cite as: [2016] EWHC 792 (TCC), 165 Con LR 108, [2016] BLR 402 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Stellite Construction Limited |
Claimant |
|
- and - |
||
Vascroft Contractors Limited |
Defendant |
____________________
Mr Paul Darling Q.C. and Ms Jennie Wild (instructed by Clarkslegal LLP) for the Defendant
Hearing date: 22nd March 2016
____________________
Crown Copyright ©
The Hon. Mrs Justice Carr DBE :
Introduction
a) That the Decision is unenforceable because the Adjudicator breached the rules of natural justice ("Issue 1");
b) That the Decision that a reasonable time for completion was 5th March 2016 is unenforceable because it was outside the Adjudicator's jurisdiction and /or the Adjudicator breached the natural rules of justice ("Issue 2").
a) For Stellite : witness statements of Mr Nikesh Haria of Stellite's solicitors dated 19th February, 3rd and 14th March 2016;
b) For Vascroft : witness statements of Mr David Rintoul of Vascroft's solicitors dated 1st and 7th March 2016.
Save where otherwise expressly stated, all references to clauses below are references to clauses in the Contract.
The Contract
"Shell and core comprising a piled basement, construction of a nine bedroom house using a structural steel frame, flat roof, timber sliding sash windows, high-quality wall, floor and ceiling finishes, mechanical and electrical services, swimming pool and associated external works and landscaping…"
a) The Completion Date for the Contract Works was 20 October 2014; and
b) The rate of liquidated damages was £23,000 per week.
".1 If in the Architects/Contract Administrator's opinion, on receiving a notice and particulars under clause 2.27:
.1 any of the events which are stated to be a cause of delay is a Relevant Event;
and
.2completion of the Works or of any Section is likely to be delayed thereby beyond the relevant Completion Date,
then, save where these Conditions expressly provide otherwise, the Architect/Contract Administrator shall give an extension of time by Works or Section as he then estimates to be fair and reasonable."
"The following are the Relevant Events referred to in clauses 2.27 and 2.28: …
.1 Variations and any other matters or instructions under which these Conditions are to be treated as, or as requiring, a Variation;
…
.6 any impediment, prevention or default, whether by act or omission, by the Employer, the Architect/Contract Administrator, the Quantity Surveyor or any of the Employer's Persons, except to the extent caused or contributed to by any default, whether by act or omission, of the Contractor or any of the Contractor's Persons; ..."
".1 Provided:
.1 the Architect/Contract Administrator has issued a Non-Completion Certificate for the Works or a Section; and
.2 the Employer has notified the Contractor before the date of the Final Certificate that he may require payment of or may withhold or deduct, liquidated damages,
the Employer may, not later than five days before the final date for payment of the amounts payable under clause 4.15, give notice to the Contractor in the terms set out in clause 2.32.2..."
"Further to our meeting of 27 July 2015, we write to confirm that it is the intention of our Client, Stellite Construction Limited, to enter into a formal Building Agreement with your company, Vascroft Contractors Limited, based upon the JCT Building Contract Without Quantities 2011 and bespoke amendments, to carry out the above works.
Please accept this letter as the instruction to commence with the works, pending agreement and execution of the Building Contract. Any works completed under this instruction be governed by the terms and conditions of the Building Contract mentioned above ...
In the event that Stellite Construction Limited decides not to proceed with the contract works, for any reason, prior to the formal execution of the Building Agreements, then it is agreed that your company shall be reimbursed costs incurred up to the time of cessation of the works to a limit of £2,000,000 (two million pounds) plus VAT (where applicable) to be agreed between your company and Adair Associates Limited ...
This letter shall expire and cease to be in effect, 90 days from the date of this letter, unless extended by mutual consent. On expiry, if the Building Agreement has not been executed or an extension to letter issued, you will be under no obligation to continue with the work set out herein, and will be entitled to the reimbursement of any costs incurred as outlined above.
Please sign and return this Letter of Intent as acknowledgement of your agreement to commence with the works on the basis outlined above."
The Adjudication
a) Stellite served its Notice of Intention to Refer a dispute to adjudication ("the Notice of Intention to Refer") on Friday, 13th November 2015;
b) Stellite served its Referral notice ("the Referral Notice") on Friday, 20th November 2015;
c) Vascroft served its Response ("the Response") on Tuesday, 1st December 2015;
d) Stellite served its Reply ("the Reply") on Wednesday, 16th December 2015;
e) Vascroft served a Rejoinder ("the Rejoinder") on Thursday, 24th December 2015;
f) Stellite served a Surrejoinder ("the Surrejoinder") on Wednesday, 13th January 2016;
g) The Adjudicator issued the Decision on Sunday, 17th January 2016.
The Notice of Intention to Refer a Dispute to Adjudication
"Under the Contract the date for completion of the Works was 20 October 2014. Pursuant to cl.2.32.2 of the Contract Particulars liquidated damages are set at the rate of £23,000 per week. On 20 October 2014 a Non-Completion Certificate was served in accordance with cl.2.32.1.1. On 4 November 2015 Stellite notified Vascroft in accordance with cl.2.32.1.2 of the Contract, that it may require payment of or with-hold or deduct, liquidated damages. Also on the 4 November 2015 Stellite issued a pay less notice in accordance with cl.4.1.3.1.1 of the Contract indicating liquidated damages due to Stellite of £1,064,158.38. By letter dated 10 November 2015 but sent on 11 November 2015, Stellite requested full payment of the liquidated damages. Vascroft failed to make payment. Accordingly, there is a dispute between the Parties."
"… find that Vascroft must pay Stellite £1,064,158.38 or such other amount that the Adjudicator deems appropriate."
The Referral Notice
"The dispute concerns the failure by Vascroft to make any payment in respect of liquidated damages."
The Response
"91.1 Stellite has no entitlement to the LAD's [sic] claimed because it has not met the condition precedent to entitlement required by clause 2.32.1.1 [the issue of a valid Non-Completion Certificate];and/or
91.2 Stellite has no entitlement to the LAD's [sic] claimed because it has agreed with VCL to move the Completion Date to 18 September 2016, or such other date as the Adjudicator deems the parties to have agreed; and/or
91.3 Stellite has no entitlement to the LAD's [sic] claimed because it has waived the Completion Date in the Contract and/or taken partial or entire possession of the Site; and/or
91.4 Stellite has no entitlement to claim LAD's [sic] because the Contract mechanism has fallen down and time is at large; and/or
91.5 The LAD's [sic] represent an unenforceable penalty; and/or
91.6 VCL is entitled to an extension of the Completion Date beyond the present date, or whatever extension the Adjudicator deems fair and reasonable in accordance with the Contract, in respect of the delays listed in paragraphs 79 and 85 of this Response, and on the basis of the evidence advanced by this Response; and/or
91.7 Stellite has no entitlement to the LAD's [sic] claimed far any other reason and to any other extent as the Adjudicator may decide."
"4.3. Notwithstanding that Stellite has failed to issue a valid Non-Completion Certificate, and so is not entitled to apply LAD's [sic] in any event, and that the parties have reached an agreement to move the Completion Date, Stellite's efforts to convince the adjudicator that this dispute is a simple matter of applying LAD's [sic]to a time overrun represent a significant and disappointing attempt to avoid the fact that its own acts of prevention and/or significant instructions, Variations and other Relevant Events have delayed VCL in completing the Works…
4.5. Despite VCL's entitlement to significant extensions of time, Stellite has refused to administer the Contract correctly (or at all), which, together with Stellite's failure properly to separate Phases I and 2, and to procure the Phase 2 works in a timely manner, and so caused the Contract machinery to fall down. The original date for completion has fallen away and Stellite has not yet progressed the design and specification for the project to a point where a completion date can be fixed."
"4.9.3 In the second alternative, the date for completion of the works has passed and time is at large as a result of extensive acts of prevention and/or refusal to administer the delay mechanisms in the contract on the part of Stellite, which has led to the contractual mechanisms falling down and, together with the conduct outlined in the attached witness statements and report, represents a waiver by estoppel of any right Stellite may have had to rely on the Completion Date."
"43. The genesis of the "time at large" principle is Holme v Guppy (1838) 3 M&W 387 and its finding that "the plaintiffs were therefore left at large and consequently are not to forfeit anything for the delay". There is a large body of case law which has subsequently applied this principle, not least Trollope & Coils Ltd v North West Metropolitan Regional HospitaI Board [1973] 1 WLR 601, where the House of Lords affirmed previous authority that an act of prevention puts time at large. Lord Denning in the Court of Appeal said that:
"it is well settled that in building contracts — and in other contracts too — when there is a stipulation for work to be done in a limited time, if one party by his conduct — it may be quite legitimate conduct, such as ordering extra work — renders it impossible or impracticable for the other party to do his work within the stipulated time, then the one whose conduct caused the trouble can no longer insist upon strict adherence to the time stated. He cannot claim any penalties or liquidated damages for non-completion in that time."
44. The need to undertake Phase 2 works in order to progress the Phase 1 Works, led to the Agreement (to move the Completion Date to 18 September 2015) set out in VCL's first alternative defence (above). Should the adjudicator take the view that the relevant terms of the Agreement have been superceded or withdrawn for any reason, it must follow that the events described in the witness statements and expert report appended hereto have resulted in there being no current Completion Date applicable to the "Works" (whatever element of the overall project they may encompass).
45. The events that led to and followed the Agreement (whlch are set out in more detail in the appended witness statements of Chandni Vora (tab 3), Mitesh Vekaria (tab 2), and Shashi Vekaria (tab 1)) have meant that Stellite has been responsible for a vast number of Relevant Events pursuant to clauses 2.29.1, 2.29.2 and 2.29.6. In brief, and with particular reference to paragraphs 10 to 16 of the witness statement of Mitesh Vekaria (tab 2), the project went from a single-stage tender to a two-phase project, which exercise was undertaken by the Contract Administrator without input from VCL. As a result, the parties relied on the expertise of the Contract Administrator to split the works between phases 1 and 2, but:
45.1. The Phase 1 drawings included Phase 2 details;
45.2. Relevant omissions were not made from the specification, but were omitted from the Contract Sum Analysis; and
45.3. There was no demarcation between the two phases in the National Building Specification.
46. When it became clear that the phase 1 contract had failed, Stellite attempted to rectify its Contract Administrator's mistakes by commencing negotiations with VCL for the phase 2 works in early 2015 (the appended witness statements refer). Whilst Stellite was trying to decide what to do about its procurement of Phase 2 (and which works would be included therein), it issued the letters of intent referred to in the first alternative defence set out above, to allow the works to move forward at least on a piecemeal basis. No new letters of intent have been issued, no phase 2 contractor has been appointed, and VCL has concluded those elements of the phase 2 works instructed pursuant to the existing letters of intent. In the circumstances, Stellite is still not in a position to fix a Completion Date for the Works (phases 1 and/or 2).
47. The foregoing may explain why the contractual extension of time mechanism has not been operated properly by Stellite. In fact, and probably as a result of the need to combine phases 1 and 2 of the project, Stellite has refused to apply the Contract mechanism at all. As such, the Contract Administrator has failed to operate clause 2.28 of the Contract by failing to give any fair and reasonable extensions of time pursuant to clause 2.28.1 or 2.28.5, or to notify VCL of its decision pursuant to clause 28.2 or 2.28.5.
48. The appended report of Mr Stephen Smith (in File 2), confirms that, on analysis, the contract mechanisms have fallen down because:
"There are certain Principal delay issues, for which the Employer is responsible, that have prevented and currently continue to prevent Vascroft from completing the Works."
In overview, these issues relate to elements of the Works which were dependent upon the execution of work that the Employer had intended to carry out in a future phase following on after the Shell and Core Works.
In short, in order that Vascroft could complete certain parts of the Shell and Core Works, it was necessary for the Employer/the CA to have, for example:
• In the first instance, included such works in the shell and core contract that were necessary for its completion.
• Failing the above, designed the Shell and Core works in such a way that did not rely upon works intended for a future phase.
• Instructed Vascroft on a timely basis to carry out such additional works as may be necessary for if to be able to complete the Shell and Core works; and/or
• Employed, on a timely basis, others to carry out the necessary works that would allow and enable Vascroft to complete the Shell and Core Works by the due date or such date as may be ascertained.
In the event, the Employer took none of these courses of action and instead, engaged Vascroft, under a Letter/Letters of Intent to carry out work intended for a future phase, effectively a separate contract, at such a late stage, that as a consequence prevented and continues to prevent Vascroft from completing the Shell and Core works"
"…It is clear that the "delays" faced on the project stem from the initial failure of Stellite to separate the original single-stage project into two phases. There was no "clean" separation of the two phases, which has meant that phase 1 works have never been capable of completion, through no fault of VCL. Such failure on the part of Stellite clearly represents an act of prevention, which acts to extinguish any entitlement to LAD's [sic] either by virtue of the Completion Date being "at large", or by virtue of VCL's contractual entitlement to extensions of time, the extent of which the Adjudicator is asked to decide..."
"2.1.4 Vascroft is wrong to allege that time is at large as a result of Stellite's alleged refusal to administer the Contract correctly or at all. First, because Stellite is not responsible for administering the Contract. Secondly, because there has been no application for an extension of time pursuant to c1ause 2.28.1 and, accordingly, there is no obligation for the CA (or, as Vascroft alleges, Stellite) to consider whether any extension of time should be given. Thirdly, even if an application had been made and Stellite had failed to respond properly at all, it is contrary to authority to state that this would result in the contract machinery breaking down. Finally, Vascroft's assertion that Stellite failed to separate Phase 1 and Phase 2 works is untenable; the Contract identifies what works Vascroft was required to be carried out and Vascroft agreed to carry out those works by the completion date and Vascroft has recently maintained that it is committed to do so. Its failure to do so cannot be a reason to put time at large."
"...There are mechanisms within the Contract in respect of instructing variations which can add, omit or amend the works which mean that the Contract was entirely workable even if, as commonly happened, variations were required. Such variations would give rise to an entitlement to an extension of time if they meant that the works would be delayed beyond the completion date…"
"8.4 In Multiplex Constructions (UK) Limited v Honeywell Control Systems Limited (No.2) (2007) EWHC 447 (TCC), Jackson J explained the prevention principal as follows:
"The essence of the prevention principle is that the promise cannot insist upon tie performance of an obligation which he has prevented the promisor from performing.
In the field of construction law, one consequence of the prevention principle is that the employer cannot hold the contractor to a specified completion date, if the employer has by act or omission prevented the contractor from completing by that date. Instead, time becomes at large and the obligation to complete by the specified date is replaced by an implied obligation to complete within a reasonable time. The same principle applies as between main contractor and sub-contractor.
It is in order to avoid the operation of the prevention principle that many construction contracts and sub-contracts include provisions for extension of time. Thus, it can be seen that extension of time clauses exist for the protection of both parties to a construction contract or sub-contract." (paragraphs 47-49)
8.5 Jackson J. then went on to review the authorities on the prevention principle, including those identified by Vascroft in paragraph 43 of the Response and from his review, identified the following three propositions:
(i) Actions by the employer which are perfectly legitimate under a construction contract may still be characterised as prevention, if those actions cause delay beyond the contractual completion date.
(ii) Acts of prevention by an employer do not set time at large, if the contract provides for extension of time in respect of those events.
(iii) In so far as the extension of time clause is ambiguous, it should be construed in favour of the contractor." (paragraph 56)
8.6 It is the second proposition which is of importance in this case; the Contract contains a standard form mechanism for providing an extension to the completion date should there be an act of prevention by Stellite which delays the works beyond the completion date. Accordingly, this should be the Adjudicator's starting point when considering whether time has been set at large as alleged by Vascroft. For the reasons set out below, the Adjudicator is invited to find that time is not at large in relation to the Phase 1 Works."
"8.3. As regards paragraph 8.5 of the Reply (The Prevention Principle): The paragraphs from Multiplex relied on by Stellite confirm that either: (1) time is at large; or (2) VCL is entitled to an extension of time, and: "insofar as the extension of time clause is ambiguous, it should be construed in favour of the contractor."
The Decision
"As there was, in my view, no binding agreement in respect of the Phase 2 works, it seems to me that what then has to be addressed is what affect (sic) the carrying out of over £500,000 worth of Phase 2 work had in respect of the Phase 1 [Shell and Core Contract] work? The parties have, from slightly different angles to me, addressed this issue in their submissions under the headings: Vascroft "Time at Large" and Stellite "Time is Not at Large."
"Stellite refer to the "three propositions" set out by Jackson J in Multiplex at paragraph 56 of the Judgment and rely in particular to that enunciated at paragraph 56(ii), which provides :"
(ii) Acts of prevention by an employer do not set time at large, if the contract provides for extension of time in respect of those events."
"63. I consider that the judgment of Jackson J in Multiplex to be particularly germane to this Decision and for that reason have attached an extract (paragraphs 47 to 66) at the end of this Decision. As correctly noted by Stellite the proposition confirmed by the learned Judge at paragraph 56(ii) is highly relevant.
64. On my reading the proposition in the Judgment at paragraph 56(ii) is qualified or limited to "Acts of prevention by an employer do not set time at large, if the contract provides for extension of time in respect of those events. [Emphasis added]
65. Accordingly, it is necessary to confirm what matters are included in the Shell and Core Contract in respect of "those events" which would otherwise be acts of prevention.
66. The Shall and Core Contract, being in the JCT Standard Form of Building Contract (as noted above, refers to "those events" as Relevant Events. The Relevant Events are listed at clause 2.2.9.
67. What I have given consideration to is whether the issue of the Letter of Intent dated 7 August 2015...fairly and properly falls within any of the Relevant Events noted in the Shell and Core Contract.
68. I have concluded, and so decide, that the provisions of Vascroft any extensions of time for the issue of the Letter of Intent and the work undertaken by Vascroft in connection with that letter (and for which it now claims its costs and is, as appears to be the case, being paid separately by Stellite). Accordingly, I determine, and so decide, that time has been set at large in respect of the Shell and Core Contract – that is, that there is no fixed date for the completion the Phase 1 works. It follows, on the authorities, that Vascroft's obligation is (or was, if completion has since been attained) to "complete within a reasonable time"."
"that in respect of paragraphs 91.2, 91.4 and 91.7 of the Response, and for the reasons noted above at paragraphs 57–73, that Stellite has no entitlement to the liquidated damages claimed as the time for completion of Phase 1 work has been set at large and that Vascroft's obligation is to complete the Phase 1 work in a reasonable period, that being by no later than 5 March 2016."
The Law
Jurisdiction
a) Courts (and indeed adjudicators and arbitrators) should not adopt an over legalistic analysis of what the dispute between the parties is;
b) One does need to determine in broad terms what the disputed claim or assertion (being referred to adjudication or arbitration as the case may be) is;
c) One cannot say that the disputed claim or assertion is necessarily defined or limited by the evidence or arguments submitted by either party to each other before the referral to adjudication or arbitration;
d) The ambit of the reference to arbitration or adjudication may un-avoidably be widened by the nature of the defence or defences put forward by the defending party in adjudication or arbitration.
a) Determine from the adjudicator's decision what he actually found (Balfour Beatty Engineering Services (HY) Ltd v Shepherd Construction Ltd [2009] 127 Con LR 110 per Akenhead J at paragraph 50);
b) Analyse what claims and assertions were made by the referring party prior to adjudication "[b]roadly, and in the round" (Balfour Beatty (supra) at paragraphs 51 and 55. Thus, a dispute "somewhat like a snowball rolling downhill gathering snow as it goes, may attract more issues and nuances as time goes on" (see Witney Town Council (supra) per Akenhead J at paragraph 33);
c) Analyse whether the whole of the pre-adjudication claims and assertions were referred to adjudication (Balfour Beatty (supra) at paragraph 56);
d) Consider the pleadings in the adjudication to determine what "the dispute encompassed, or through the response and the reply and the evidence deployed by both parties during the adjudication became" (Balfour Beatty (supra) at paragraphs 59 to 60).
Rules of natural justice
"Is the Adjudicator obliged to inform the parties of the information that he obtains from his own knowledge and experience or from other sources and of the conclusions which he might reach, taking those sources into account? In my judgment it is now clear that, in principle, the answer may be: Yes. Whether the answer is in the affirmative will depend on the circumstances."
"… it is very necessary to bear in mind that the point or issue which is to be brought to the attention of the parties must be one of which is either decisive or of considerable potential importance to the outcome and not peripheral or irrelevant."
"From this and other cases, I conclude as follows in relation to breaches of natural justice in adjudication cases:
(a) It must first be established that the Adjudicator failed to apply the rules of natural justice;
(b) Any breach of the rules must be more than peripheral; they must be material breaches;
(c) Breaches of the rules will be material in cases where the adjudicator has failed to bring to the attention of the parties a point or issue which they ought to be given the opportunity to comment upon if it is one which is either decisive or of considerable potential importance to the outcome of the resolution of the dispute and is not peripheral or irrelevant.
(d) Whether the issue is decisive or of considerable potential importance or is peripheral or irrelevant obviously involves a question of degree which must be assessed by any judge in a case such as this.
(e) It is only if the adjudicator goes off on a frolic of his own, that is wishing to decide a case upon a factual or legal basis which has not been argued or put forward by either side, without giving the parties an opportunity to comment or, where relevant put in further evidence, that the type of breach of the rules of natural justice with which the case of Balfour Beatty Construction Company Ltd -v- The Camden Borough of Lambeth was concerned comes into play. It follows that, if either party has argued a particular point and the other party does not come back on the point, there is no breach of the rules of natural justice in relation thereto."
"The basis of the Adjudicator's decision was that because the actual appointment of HTA did not include provision for novation at the time of execution of the Building Contract, the Novation Agreement executed by HTA did not represent accurately the appointment as envisaged pre-Contract (ie an appointment including an agreement to novate on the execution of the Building Contract) and was thus void. I find that that was not a contention that was raised by either party and it follows in my judgment that Hillcrest is right in contending that the Adjudicator determined the issue of whether the Novation Agreement dated 26 October 2012 was void on a basis which had not been put forward by either party and which Hillcrest had had no opportunity to address. On that basis there was a material failure to comply with the rules of natural justice and for that reason in my judgment the declarations under paragraphs 23 and 24 of the Decision are unenforceable."
"There is no rule that a judge, arbitrator or adjudicator must decide a case only by accepting the submissions of one party or the other. An adjudicator can reach a decision on a point of importance on the material before him on a basis for which neither party has contended, provided that the parties are aware of the relevant material and that the issues to which it gave rise had been fairly canvassed before the adjudicator. It is not unknown for a party to avoid raising an argument on one aspect of its case if that would involve making an assertion or concession that could be very damaging to another aspect of its case."
The rival positions in summary
Stellite : Issue 1
a) First, the question of whether or not the issue of the Letter of Intent and work undertaken in connection with it caused any delay itself was not in issue. The only case that Stellite had to meet was whether or not delay was caused to the Works by the specific events identified by Vascroft in the Response and the Rejoinder and as supported by Vascroft's programming expert. There was no suggestion there that the issue of the Letter of Intent caused any critical delay to the Works;
b) The question of whether or not Clause 2.29 allowed an extension of time as a result was also not in issue. It was insufficient for Vascroft to submit that there were acts of prevention. At no stage did Vascroft suggest that the issue of the Letter of Intent and/or works carried out thereunder were acts of prevention. Stellite contends that Vascroft only argued that time for completion was at large because the contract mechanism had fallen down meaning that it could not be operated, and sought a declaration to this effect. Vascroft made no submissions about the scope of Clause 2.29 of the Contract and in particular did not submit that delay caused by the issue of the Letter of intent and work carried out pursuant to it fell outside the scope of Clause 2.29. Indeed, it was Vascroft's positive case (in paragraph 45 of the Response as set out above) that the Letter of Intent and the events that followed were Relevant Events within the meaning of Clause 2.29. In these circumstances, Stellite did not address the question of whether delay caused by the Letter of Intent and work carried out pursuant to it fell outside the scope of Clause 2.29.
a) The precise "act of prevention" by Stellite that he considered to have caused delay to the completion date;
b) The precise delay caused to the completion act by that act of prevention, by reference to Vascroft's case or the Adjudicator's analysis, if any;
c) If the act of prevention in his contemplation was one of the delaying events relied on by Vascroft, the basis on which the Adjudicator considered that the Relevant Event or Events identified by Vascroft did not apply;
d) The basis on which the Adjudicator considered that Relevant Event 2.29.6, which concerns "any act of impediment, prevention or default" by Stellite, did not apply to the act of prevention in his contemplation.
Stellite : Issue 2
Vascroft : Issue 1
Vascroft : Issue 2
Analysis
Issue 1 : Time at large
Issue 2 : Reasonable time for completion
Conclusion
a) I find that there was no breach of the rules of natural justice in the Adjudicator holding that time was at large for the reasons that he gave;
b) I find that the Adjudicator acted outside his jurisdiction in holding that a reasonable time for completion was 5th March 2016.