BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> DPM Property Services Ltd v Emerson Crane Hire Ltd [2017] EWHC 3092 (TCC) (06 December 2017) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2017/3092.html Cite as: [2017] EWHC 3092 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
DPM Property Services Limited |
appellant/Claimant |
|
- and - |
||
Emerson Crane Hire Limited |
respondent/Defendant |
____________________
Mr Michele De Gregorio (instructed by Diamond Solicitors) for the Defendant/respondent
Hearing date: 6 December 2017
____________________
Crown Copyright ©
The Hon. Mr Justice Coulson :
1. INTRODUCTION
2. THE PROCEDURAL HISTORY
"In relation to the defects claims pleaded in paragraphs 30-34 of the Defence and Counterclaim dated 6 October 2015, the Defendant is debarred from adducing evidence at trial (whether relating to an alleged breach of duty, cost of remedial work or otherwise) of any issue that is not particularised in the Scott Schedule of Defects completed by the parties and signed by the Claimant on 4 March 2016."
"My final point is, if your Honour suggests that this report is going in, I am going to have to ask for some sort of declaration or ruling as to what precisely is the defendant's claim we are meeting, because it is not in their Scott Schedule. Their figures have to presumably come from somewhere in a Joint Statement that is so nebulously drafted that there is almost no agreement between the experts, so in effect we are saying their pleaded claim is somewhere in their own report, and their application in my submission comes down to this. The defendant comes to Your Honour and says "our pleaded case is so woeful that you have to allow us to find it somewhere in our evidence.""
"What I am ruling is…well, yes, I will. I mean they can have (inaudible) – alright – and they can – it probably doesn't matter that this – the figures are reworked into a schedule, that would be neater if they were, but I'm saying at the same time because of the way in which they conducted themselves they can never be awarded more than £165,000. You go into this trial knowing that the maximum that can be awarded against you is the figure pleaded in paragraph 33 [the £161,000 odd]."
"(2) The defendant has permission to rely on the expert report of Ashley Woods dated 29 September 2017. Sections 4, 5 and 6 of the report are relied upon in substitution for the corresponding sections (sections 6, 7 and 9.3-9.5 respectively) of Mr Woods' report dated 25 August 2016.
(3) The defendant is permitted to advance trial claims for the losses set out on page 43 on Mr Woods' report of 29 September 2017, totalling £332,671.34; but shall not be entitled to recover judgment in respect of those losses, in excess of the cap of £160,175 plus VAT pleaded in paragraph 33.2 of the Amended Defence and Counterclaim."
"1.1 The learned judge wrongly concluded that the losses and claims included within the report of Mr Ashley Woods, dated 29 September 2017, had been particularised by the defendant in the Scott Schedule of defects completed by the parties and signed by the claimant on 4 March 2016 ("the Scott Schedule"). Those losses and claims had not been particularised, adequately or at all.
1.2 Alternatively, the learned judge failed to give effect to his earlier order of 16 January 2017 by which the defendant had been debarred from adducing evidence at trial (whether relating to any alleged breach of duty, cost of remedial work or otherwise) of any issue that was not particularised in the Scott Schedule."
In his helpful skeleton argument, Mr Oram said that it was convenient to take these two elements in reverse order. I respectfully agree.
"By allowing the Defendant to advance at trail claims for losses totalling £332,671.34, and requiring the Claimant to meet those claims despite the fact that the pleaded value of the counterclaim was limited to £160,175 plus VAT, the decision of the learned judge was wrong and/or constituted a serious procedural irregularity that was unjust within the meaning of CPR r.52.21(3)(a) and (b) it was wrong or unjust, in particular:
2.1 Because it failed to give proper effect to the debarring order made on 16 January 2017;
2.2 Because the action had been set down for trial on the basis that the claimant was meeting a claim for a lower sum, not £332,671.34, and there is insufficient trial time allocated to that larger claim to be fairly determined; and/or
2.3 Because of the late stage at which the ruling was made, namely at the pre-trial review."
3. THE RELEVANT PRINCIPLES
"Case management decisions are discretionary decisions. They often involve an attempt to find the least worst solution where parties have diametrically opposed interests. The discretion involved is entrusted to the first instance judge. An appellate court does not exercise the discretion for itself. It can interfere with the exercise of the discretion by a first instance judge where he has misdirected himself in law, has failed to take relevant factors into account, has taken into account irrelevant factors or has come to a decision that is plainly wrong in the sense of being outside the generous ambit where reasonable decision makers may disagree. So the question is not whether we would have made the same decisions as the judge. The question is whether the judge's decision was wrong in the sense that I have explained."
4. DELAY
5. GROUND 1.2: THE DEBARRING ORDER
"Well, I really can't remember quite what was going through my head when I made the finding, but I am sure it wasn't to make an order which prohibited the defendant from running any pleaded Scott Schedule item simply because it hadn't been quantified."
Of course, the fact that the relevant wording was that of the appellant, and not that of the judge, may explain this disjunct.
6. GROUND 1.1: LOSSES HAD BEEN PARTICULARISED ALREADY
7. GROUND 2: THE SO-CALLED CAP
8. CONCLUSIONS
Note 1 There are some additional general items for consequential losses but those are not relevant to this appeal because they are not dealt with in Mr Woods’ new report. [Back]