BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Hochtief (UK) Construction Ltd & Anor v Atkins Ltd [2019] EWHC 2109 (TCC) (31 July 2019) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2019/2109.html Cite as: [2019] EWHC 2109 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
(1) HOCHTIEF (UK) CONSTRUCTION LIMITED (2) VOLKERFITZPATRICK LIMITED |
Claimants |
|
- and - |
||
ATKINS LIMITED |
Defendant |
____________________
Luke Wygas (instructed by CMS Cameron McKenna Nabarro Olswang LLP) for the Defendant
Reading day: 29th October 2018
Hearing dates: 30th, 31st October 2018, 1st, 5th, 15th November 2018
21st, 22nd, 23rd, 24th January 2019
____________________
Crown Copyright ©
Mrs Justice O'Farrell:
i) the Cottington Road Bridge ("the Bridge"), a two-span bridge carrying the A256 dual carriageway road over the Canterbury to Ramsgate railway line and Cottington Road; and
ii) the Cliffsend Underpass ("the Underpass"), a 120-metre-long tunnel under the railway line to accommodate the A299 dual carriageway.
Evidence
i) Mark Pritchard, the JV's design manager for the contractor designed elements of the project;
ii) Santiago Daniele, the JV site agent for the construction of the Underpass;
iii) David Ongley of Crawford & Co Adjusters (UK) Ltd, the loss adjuster for claims made in respect of the remedial works;
iv) Christopher Fry, technical director of Atkins and lead engineer for the Bridge;
v) Tomasz Kucki of Atkins, design team engineer in respect of the Bridge and the Underpass;
vi) Wai Hung Wales Cheung of Atkins, project manager for the Bridge.
i) Robert Jessep of Robert Jessep & Partners Ltd, engineering expert for the JV;
ii) Tony Bracegirdle of Geotechnical Consulting Group, engineering expert for Atkins.
The Subcontract
"21.1 The Consultant provides the Services in accordance with the Scope.
21.2 The Consultant's obligation is to use the skill and care normally used by professionals providing services similar to the services."
"(9) To Provide the Services means to do the work necessary to complete the services in accordance with this contract and all incidental work, services and actions which this contract requires.
(11) The Scope is information which either
- specifies and describes the services or
- states any constraints on how the Consultant Provides the Services
and is either
- in the documents which the Contract Data states it is in or
- in an instruction given in accordance with this contract."
i) Sections 2.1 and 2.2 of Atkins' proposal dated 24 September 2009 (excluding the programme referred to therein) ("the Atkins Proposal Document");
ii) Paragraphs 1 to 3 of section 3.5 of Atkins Proposal Document;
iii) the document entitled "East Kent Phase 2 Design Interfaces for the Cliffsend Underpass";
iv) the document entitled "Amendments and Clarifications to the Scope of Works as set out in Section 2 of Atkins' proposal dated 24 September 2009, agreed between Atkins and VFH" dated 30 October 2009 ("the Clarifications Document").
"Civil and structural design is required for two structures, based on the outline designs which have been produced by Jacobs for the Project Client, Kent County Council ('KCC'), and expressed in the Client ITT.
During the tender stage, Atkins has developed, in conjunction with Hochtief (UK), a 'non-conforming' scheme for the Cliffsend Underpass and a 'conforming' scheme for the Cottington Road bridge.
…
It is understood that the following services are required of Atkins:
Cliffsend Underpass - Outline and detailed design of the underpass structure …
Cottington Road Bridge - Preliminary and detailed design of structure …"
"The works are to be designed in accordance with the requirements of the Main Contract, including, but not limited to:
- Volume 2A Specification; and
- Volume 2B "Structures to be designed by the Contractor"
- Volume 2D Drawings…
The Subcontractor (Atkins) shall provide all of the civil and structural design deliverables that the Contractor (VFH) is required to provide to Kent County Council under the Main Contract for the structures included within the scope of this agreement, including:-
- intermediate and intimate earthworks which have structural impact on / interaction with the main structural elements...
All designs shall be prepared in accordance with the requirements of the Main Contract.
The scope includes provision of multiple design submissions (including AIP's, Form Cs, Design and Check Certificates) as required to obtain TAA approvals and Network Rail acceptance in accordance with the requirements of the programme ...
The Subcontractor (Atkins) shall prepare general arrangement drawings for review by the Contractor (VFH) prior to provision of formal design submissions, attend meetings to discuss those drawings and take cognisance of the comments arising in those meetings in development of the design.
The Subcontractor (Atkins) shall develop a single design solution for each structure following the initial value engineering period.
The Subcontractor (Atkins) shall endorse Construction Certificates / Certificates of Construction Compliance for the designs included in the Scope."
"Any highway design and associated drainage facilities including, in particular, revisions of the highway design to comply with the requirements of VHF's tender design for Cliffsend Underpass."
The Bridge - chronology
"Design of earthworks to the approach embankment of the new position of the over bridge. This is still the responsibility of Jacobs. It was pointed out that there is to be an increase in the height of the embankment to the south-east corner to allow for a noise bund."
"Differential settlement to be allowed for in the design of the structure.
A maximum 10mm differential settlement along the centreline of the structure will be allowed for in the design. A maximum 20mm differential settlement between the structure and approach embankment will be allowed for in the design."
- "Install abutment drainage.
- Backfill immediately behind the end abutments with polystyrene blocks.
- Construct reinforced earth embankment to NE wing wall.
- Seal the polystyrene with two layers of High Density Polythene.
- Place Class 6N capping material.
- Construct slab foundations for Vehicle Restraint Systems.
- Transport material excavated from Cliffsend site via Sevenscore roundabout for formation of the bridge approach.
- Compact material to form bridge approach."
"The structural backfill has been changed from a granular material to polystyrene blocks. This solution considerably reduces weight of the backfill material therefore embankment settlement immediately behind the abutment should be minimised."
Against that statement, the following comment was added by Jacobs:
"Our calculations have shown that settlement at existing ground level behind the abutment could be of the order of 68mm. Please confirm what settlement is expected behind the abutment at carriageway level."
Atkins' further response was:
"The construction work will be scheduled so that most of the settlement of the fill behind the abutment will occur during construction stage. Long term settlement will have a minimum impact of the highway surfacing and asphaltic plug joint, as both will be installed after most of settlement will [have] occurred."
"Please consider extending the polythene sheets along the drainage of the abutment wall due to possible accidental contact with the petroleum solvents at the lower level."
"Noted. Full containment of the polystyrene is being considered, subject to agreement with the TAA and discussions with polystyrene suppliers."
"I have attached the sketch up file and some pictures of the polystyrene outline for the South Abutment.
Also I would like to confirm that the whole polystyrene block would need to be encased in HDPE, seam welded membrane to prevent damage to polystyrene in case of an oil spillage."
"The HDPE should be 1.0mm thick, hydrocarbon resistant membrane. All joints must be welded.
Please use GX Geomembrane by Visqueen Building Products or similar."
"The proposal is not acceptable as the interface of the HDPE sheet on the 1:1 slope could create a slip plane between the polystyrene blocks and the soil surface. This would induce increased earth pressure on the abutment wall which is not acceptable."
"1. Cut earthworks batter to approx 1:1 (see TQ 87).
2. Install Filcor lightweight material and hollow blockwork / drainage pipework to rear of abutments and wingwalls. Voids between cut earthworks batter and Filcor material will be filled with self compacting material e.g. single-sized pea shingle as described in TQ 87.
3. Install 1.5 mm HDPE liner with welded joints above top layer (approx 900 mm below FRL or FGL on batters). Install 150 dia perforated drainage pipe along perimeter of proposed HDPE layout leading into 150 dia carrier and connect positively into highway drainage…
The benefits will be:
- Spillages will be captured and positively drained into highway drainage.
- Significant reduction in the amount of welding required to HDPE liner.
- Minimise the risk of damage to the HDPE liner during installation of Filcor material and whilst backfilling.
- Shorter programme duration.
Please confirm that the above proposal will be acceptable."
The accompanying marked up drawings showed the HDPE membrane laid under the 6N capping on the top layer of EPC blocks, extending approximately 5 metres beyond the edge of the EPC blocks. The drawings showed 150mm diameter perforated pipe drains around the perimeter of the membrane, with notes stating that they should be connected positively into the highway drainage.
"All the bridge drainage will be discharged to a new highway drainage system, fitted with pollution interceptors (Jacobs design). This is the case for the current design and could be left as it is for the proposed alternative.
I have got serious doubts about getting an approval from KCC for the proposed detail. In the AIP stage we have shown the HDPE layer over the top of the polystyrene only, wrapping about 1.0m down the polystyrene blocks. KCC picked up on this in one of their AIP comments and requested full wrapping of the blocks. I remember that it has been an issue for TGP as well.
From my point of view we should be saying "no" to the TQ. There are some technical issues associated with this proposal, e.g. we need to look at potential spillage from vehicles travelling at low level (Cottington Road and new slip road). But, more importantly, we have already got a problem with TAA approvals affecting our profit margin (I needed to bite into our risk pot) and this solution would only make things worse.
I am inclined to refuse the proposed solution, unless Tony [Heron] can demonstrate to us how much it is worth to him and give us an incentive to fight the battle with Kent."
"There will be settlement of both the underlying formation strata and the embankment filled material. An overall settlement of 237mm is predicted. In terms of the underlying strata, about 100mm of settlement is predicted to occur within the top 2 m. The top 2 to 4.5 metres of the formation strata are considered to be compressive. It was stated that initial estimated settlement of up to 230mm is predicted to occur over the first four weeks after the embankment infill with the remaining residual settlement of up to 10% occurring later…
Alternative measures to reduce differential settlement were discussed: …
(a) confirm what degree of settlement is likely;
(b) identify what degree of remedial expenditure is appropriate to mitigate that settlement;
(c) confirm the question of the degree to which this is a problem …
Mark Pritchard is to ask Atkins if they are satisfied with the likely level of settlement that will take place under the polystyrene lightweight fill …
The JV proposal to use polystyrene lightweight fill entails the incorporation of an HDPE liner to isolate the polystyrene from potential hydrocarbon contamination from traffic accident fuel spills and from everyday use.
Mark Pritchard advised that the current under stepped arrangement for the polystyrene blocks would be impracticable to construct. The welded liner should only be necessary to resist the downward penetration of hydrocarbons. Sketched proposals for a welded liner over the top only of the polystyrene lightweight fill, with suitable perimeter overlaps, edge seals to the abutment structure upstand walls, etc and perimeter drains were tabled for review by Jacobs. Would Jacobs accept this design development - Jacobs to comment …"
"Settlement
Whilst settlement in general may only be in the order of 50mm, this could not be guaranteed and comes down to a question of confidence the possibility of 100mm of settlement would require preventative action.
Mark Pritchard was to verify that Atkins was satisfied with the likely level of settlement that will take place under the polystyrene lightweight fill but Mark replied that this was not an issue in terms of VFH/Atkins design responsibility because VFH/Atkins had no design responsibility for the embankment design and therefore Atkins did not need to consider this issue.
…
Light weight fill / membrane / backfill interface
Mark Pritchard advised that the liner options to resist the downward and sideway penetration of hydrocarbons were still being developed in terms of sealing around the sides, etc. Jacobs (Ian Payne) accepted the use of a high level HDPE liner extending over the top of the lightweight fill in principle, subject to agreeing the edge seals."
"In accordance with BA 42/96, clause 3.8 the backfill material to integral bridge abutment should be free draining selected granular fill with properties and grading complying with classes 6N and 6P
…
In order to reduce the lateral pressure typically exerted on the back of integral bridge abutments by granular backfill material we propose to use polystyrene blocks as the backfill material…"
In accordance with BD 30/87, clause 4.1 the following classes of material… are acceptable for backfilling retaining walls and abutments:
(a) Class 6N – selected well graded granular material
(b) Class 6P – selected uniformly graded granular material (note: this includes chalk)
…
In order to reduce the lateral pressure typically exerted on the back of integral bridge abutments by granular backfill material we propose to use polystyrene blocks as the backfill material
…
The polystyrene blocks will be covered in a hydrocarbon resistant high-density polyethylene membrane to prevent its deterioration in case of an oil spillage on the East Kent access route.
Polystyrene blocks will also be protected by 150mm layer of mass concrete."
"The detail of the HDPE layer is subject to discussion with KCC and TGP; both of them have requested full wrapping of the blocks."
"We're virtually there just a few minor changes:
- Abutments – all liner will be 1.5mm smooth not textured on the flat section, need mortar fillet where the liner meets the structure as it cannot be bent through 90 deg.
- Wing Walls – 1.5mm smooth attached to concrete and 1.5mm textured underneath.
- Mortar fillet against concrete face to avoid 90 deg. bend
- No concrete protection to the liner on the wing walls – not necessary
- Fill / below the liner to be Structural Fill
I've marked up 1 abutment and 1 wing wall drg. Alterations needed on all similar drgs."
"The detailed design of the Cottington Bridge embankments, the lightweight fill behind the Cottington bridge abutments and the likelihood of differential settlement of the embankments has been regularly reviewed over the last 12 months. There is currently an opportunity to introduce transition slabs over the lightweight fill/embankment structural fill interfaces. Confirmation is required regarding the advisability of the transition slab option. If this option is instructed, we would need your requirements to be able to take it further."
The Bridge - investigations
"The CPT data indicated the following zones of weaker, softer or looser materials generally based on a correlation between cone resistance and sleeve friction and generalised soil descriptions and cone resistance to shear strength correlations:
a. South West (CPT 1): a weaker/soft layer in chalk fill at a depth of between 2.2 m to 2.5 m in a layer generally described as a medium dense sand to silty sand;
b. South Central (CPT 6): a soft layer of about 0.2 m thickness at about 4 m depth in Thanet Sand fill in a layer generally described as a stiff clay;
c. South East (CPT 4): locally loose/soft/weaker chalk fill between about 1.6 m and 1.8 m depth (described as locally loose silty sand to sandy silt) and four layers of soft loose Thanet Sand fill between about 2.5 m depth and 4 m depth (in layers generally described as firm to stiff clayey silt to silty clay);
d. North West (CPT 2): a layer of weaker/very loose chalk fill between about 1.5 m and 2 m depth (generally described as a very loose sandy silt to clayey silt);
e. North Central (CPT 5): locally loose/weaker chalk fill between about 0.9 m to 1.2 m depth (described as loose sandy silt to clayey silt) and a layer of soft to firm Thanet Sand fill between about 2 m and 3 m depth (generally described as a firm clay);
f. North East (CPT 3): a layer of loose/weaker chalk fill was reported between 0.5 m and 1.0 m (described as loose sandy silt clay silt)."
"Settlement of the newly opened road on the approach embankments to Cottington Bridge was first noted towards the end of 2011. Small differential movements could be seen across the 'plug joints' in the asphalt at the back of the bridge abutments, together with opening of the movement joints between the bridge wing walls and abutments; in addition, acoustic fencing on the southeast approach suffered loss of vertical alignment over about four panel lengths. Subsequently, depressions of the kerb lines became noticeable on both sides of the bridge, with a gap developing between the asphalt surfacing and kerb line locally on the southwest approach. Cracks in the verge topsoil have also become evident where the reinforced soil wall abuts the northeastern wing wall of the bridge…
Recent reading of the settlement cells indicate that some foundation movement has occurred between the end of the earthworks settlement period and current date. Interpolation of settlement cell data suggests that since the road was opened more foundation settlement has taken place to the south of the bridge (a maximum of 78mm at SC2, as at 18.3.12) than to the north (a maximum of 29mm at SC4, as at 18.3.12). This foundation settlement has obviously contributed to the overall settlement of the road but is unlikely to be the sole cause of localised depressions, such as the loss of vertical alignment of acoustic fencing to the southeast of the bridge and separation of asphalt surfacing and kerbs to the southwest. It is of interest to note that the settlement cells furthest from the bridge (SC1 and SC6) show virtually no movement since the road was opened…
Where weak zones have been identified in the chalk fill it is suspected that they are the result of post construction inundation by water from rainfall infiltration. Collapse settlement may have been triggered at some point thereafter, which could have led to the more localised settlement expressions that have been observed… Site testing records show that the chalk fill was placed at moisture contents within the range permitted by the project specification and that average air voids were below the prescribed target mean of 8%...
It is evident from the survey data that (except adjacent to the start of the reinforced soil wall) settlement of the road is more pronounced on the south side of the bridge…
On the south side of the bridge in particular, settlement of the east and west road channels, is greater than the central reserve. This is consistent with water penetration of the embankment fill, since the 'soft' verges adjacent to the channels would be more prone to infiltration by rainfall/snow melt water than the 'hardened' central reserve. However, a factor to consider is that road settlement is also taking place (to a lesser degree) above the lightweight polystyrene blocks backing the bridge abutments and over immediately adjoining earthworks fill areas where the inclusion of a concrete protection/transition slab and an impervious membrane below the pavement layers would be expected to prevent water ingress.
A correlation between fill softening and road settlement is suspected…"
"These excavations revealed the fill over the verges and at the ends of the membranes was saturated, and where this was chalk fill, this was very soft, including under the end of the membrane in the verge 20m away from the abutment on the south east of the bridge. Photographs of these excavations show the presence of water above the membrane."
The Bridge - issues
i) whether Atkins was responsible for the final design of the abutments and wingwalls, including the EPC blocks and HDPE membrane details, and any required sub-soil drainage;
ii) the nature and extent of any undue differential settlement on the Bridge approaches;
iii) the cause(s) of the differential settlement on the Bridge approaches:
a) whether Atkins' design for the approach embankments made adequate provision for sub-surface drainage;
b) whether the JV's works were in accordance with Atkins' design and to a reasonable standard;
c) whether the differential settlement was caused and/or contributed to by design and/or workmanship issues;
iv) whether Atkins were in breach of the Subcontract and/or negligent;
v) whether the remedial works carried out by the JV were reasonable and necessary as a result of any inadequacies in Atkins' design.
Design responsibility
"Q. As I understand it in relation to the highway the division of responsibility was between you and Jacobs over the bridge?
A. Yes, there was an interface.
…
Q. Would you also agree that you could not design your elements of the work without having regard to the other elements of the work which were being designed by the employer's designer, Jacobs?
A. Yes, we need the input for alignment of the highway and for the drainage.
Q. Specifically you were responsible for providing the design of the bridge structure itself and a section of structural fill on either side of the bridge?
A. Yes.
…
Q. There was an interface, was there not, between the approach embankments that were your responsibilities and the approach embankments which were Jacobs' responsibility?
A. Yes.
…
Q. Your responsibility extended to the approach embankments on either side because the structural fill behind the abutments was your responsibility wasn't it?
A. Yes.
…
Q. Do you agree that when you are carrying out your design, in general terms, as a competent designer, you would consider the impact of your design on other elements of the works?
A. Yes, to the extent of the knowledge of what they have designed.
Q. Yes, you can't design your element entirely in isolation, can you, you have to think about what the effect of any changes to your design, for example will have, and how your design will fit with the other design?
A. Yes.
Q. If you see a problem you either change your design or you, at the very least, raise that with the other designer?
A. Yes."
The Bridge - nature and extent of the settlement
"Q. There were a number of issues with the bridge that were not centred around the edge of the membrane?
A. Yes.
Q. And it was all those issues taken together which were causing the speed restrictions?
A. Yes, although I think it would have been the main areas that would have been the main concern to the KCC supervision team, that would have drawn our attention to it."
i) It provides evidence of increased total settlement and consequent differential settlement broadly coinciding with the ends of the membrane to the south-east, north-east, north central reservation and south-west of the bridge.
ii) A similar pattern applies to some extent on the south central reservation, although there is increased apparent settlement extending over the length of the infill section of this part of the embankment.
iii) To the north-west of the bridge the apparent differential settlement occurred between the abutment and the end of the membrane.
iv) There is also evidence of increased settlement and differential settlement about 50 metres from the abutment on the south-west line which is unrelated to the issues in this case.
i) The settlement for each point on the bridge is relatively consistent over the period of monitoring, indicating that the embankment fill settled together, although some parts settled more than others.
ii) The settlement in the north-east is explained by the presence of a chalk fill, reinforced soil structure extending from the edge of the embankment towards the centre line of the embankment. Over this section the chalk fill extends to the full depth of the embankment and therefore the settlement is greater.
iii) The data shows that the settlement is largest at approximately 15 metres from the abutment wall on the south side of the bridge. Although there is some doubt as to the final extent of the membrane it was probably about 25 metres from the abutment. Therefore, the largest settlement was indicated underneath the membrane and not at the ends of the membrane.
The Bridge - cause of the differential settlement
The Bridge - discussion and findings on cause of settlement
"Sub-surface drainage is normally necessary in order to remove any water which may permeate through the pavement layers of the roads in both cut and fill situations. This can be achieved on embankments by the provision of fin or narrow filter drains …
Sub-surface drainage is effected by installation of longitudinal sub-surface drains at low edges of road pavements. These serve to drain the pavement layers and pavement foundations they also prevent ingress of water from verge areas adjacent to the pavement.
It is also essential that water is not retained within the sub base and for that matter the capping layer. Water reaching the formation and sub-formation must be drained to longitudinal sub-surface drains by adequate shaping of the formation and sub- formation such that no undrainable low spots occur."
"Chalk fills are generally protected against inundation. Collapses have occurred where fills have been constructed over ground subjected to flooding. Prolonged saturation can cause degradation of intact blocks by softening and fines production. Drainage along margins or through chalk fills needs to be well constructed and regularly checked."
"Poorly compacted, or excessively dry, fill is always likely to be vulnerable to collapse compression …
A wide variety of types of unsaturated fill formed in different circumstances can be vulnerable to collapse compression, for example … chalk fill …
Inundation can be due to either submergence by a rising groundwater level water infiltrating downwards from the ground surface…
The objective is to prevent the occurrence of collapse settlement in the fill and several possible approaches could be considered:
- place and compact and engineered fill so that it has no collapse potential,
- eliminate collapse potential of an existing non-engineered fill by increasing the fill density by some form of ground treatment before building takes place,
- eliminate collapse potential of an existing non-engineered fill by inundating the fill before building takes place, and
- prevent inundation of the fill occurring during the life of the structure. …
Where construction is to take place on a fill with collapse potential, a solution might be to prevent inundation occurring during the life of the structure. However, while in theory it may be possible to prevent water penetrating the surface crust of the fill by care in design and construction, in practice it will be difficult to ensure that some water does not penetrate into the backfill during the life of a structure …
In most situations and approach relying primarily on prevention of inundation does not provide a satisfactory solution to the hazard posed by a fill with collapse potential."
"Q. So do you agree then that if that guidance had been followed, Atkins design should not have provided for water to be draining off over the edge of the embankments?
A. No, I do not accept that at all because the Atkins design was something completely outside this document … As long as you have got a system which provides for a dry foundation for the highway and by foundation, I mean typically the top metre or half a metre, as long as that's not saturated, it's fine and you can discharge water off the sides, providing it's done in a way that doesn't prevent stability issues with the sides of the embankment …
Q. Your evidence is that the design didn't comply with these requirements specifically but provided that the effect of the design was such that it didn't cause any problems then you can't complain about it.
A. That's absolutely right yes…
Q. Because we are not talking about following the guidance. We are talking about moving away from the guidance, allowing the water to flow off the end of the membrane into the chalk fill beyond and allowing it to fall off the sides of the embankment in a way that wouldn't normally be permitted.
A. Wouldn't normally be done yes…"
"I think the sections shown on our drawings, which followed on from the discussions that took place on TQ 88, were quite clear that the only buildable practical way in which we saw this being undertaken was to have a 1:40 fall which was perpendicular to the back face of the abutments, and there would have to be some modifications when you reached the wing walls, depending upon whether they had a sloped top or not.
…
… We recognised that there was an issue about any water that actually permeated through the road surface. We were confident that the majority of the water would be taken by the kerb drainage system which ran on the North approach. But anything that permeated would have to sit on the membrane and find its way out, and the best way of finding its way out would be for it to be taken down the membrane which was draped over the side slopes.
…
… We had chosen to employ a 6N capping to the HDPE membrane onto the carriageway, with the recognition that this was a drainage medium
…
the 6N material was provided as a drainage medium, not just on capping underneath the carriageway but also, as demonstrated on our drawings, on the side slopes above the membranes…"
"Q. So we have a fall away from the abutments at 1:40?
A. Yes…
Q. …what this section is telling you is above the membrane we put 6N capping all the way down over the top of the membrane?
A. Yes.
Q. And that continues down over the membrane, doesn't it?
A. That is the requirement, on top of the membrane, yes…
Q. That is the same with the wing walls as well, isn't it, the membranes fall away from the wing walls, so you don't end up with water going –
A. Yes, it is the same principle but of course it is not the carriageway then, it is the side fill…"
"A. … all of these drawings, for all of the wing walls as well as the abutment systems, show 6N above the HDPE membrane.
Q. I agree with you but the difficulty is that they don't provide the detail of what happens at the end of the blocks, do they?
A. Not these drawings, no.
…
Q. … Your design does allow for the membrane, which you designed to extend into that general embankment fill, doesn't it?
A. Over the top of it, yes…
Q. And at the end of the membrane it would meet that general embankment fill, wouldn't it?
A. Yes."
The Bridge – breach/negligence
Remedial works
"Let me say it was necessary to put drains in because I feel real concern, and I would have felt real concern at the time, of the possibility of uncontrolled rising water level above the membrane due to water being trapped in there."
The Underpass - design
"Unusual features of design
The underpass structure will be constructed beneath, and adjacent (in plan) to, the operational railway using a mixture of tunnelling and jacking techniques. The form of construction will require, during construction, gaps between deck downstands and the supporting piled abutments concrete sections, to cater for the deck jack process as well as construction tolerances.
It will be impossible to seal these voids from the outside of the structure after completion of the jacking operation, and it therefore proposed to fill them with high-strength, non-shrink, cementitious grout, using grout tubes previously cast in the deck. The grout will form a non-permeable barrier to prevent seepage water ingress. Additionally, hydrophilic sealant points and water bar details will be provided to provide additional defence against water ingress.
The deck will be installed in 6 sections to allow for installation of inter-jacking stations between precast deck units. There will be no physical connection between deck units neither in temporary nor in permanent situation.
The gaps between units will be filled with high-strength, non-shrink, cementitious grout after completion of the jacking operation. The grout will form a nonpermeable barrier to prevent seepage water ingress. Additionally, hydrophilic sealant points and tok strips will be provided to provide additional defence against water ingress.
To allow the jacking process over cut will be created around the jacked deck and filled with lubricant. After completion of the jacking operation the lubricant will be substituted with cementitious grout."
"The main (temporary works stage) purpose of the west headwall is to provide anchorage for the ADS system … In the permanent solution the gap between the underside of the headwall beam and the top of the last deck unit will be grouted, a small upstand added on the west side and the exposed face clad with masonry."
"Timber shutters will be made to suit the gap between the box and the rails. These shutters will be reused where possible. The shutters will be sealed with silicone to prevent grout loss. At either end of the box 2 no. letterboxes will be created to ensure the grout that is poured in from the one end flows through and fills all the voids.
The grout will be mixed in a grout pan to the manufacturers recommended mix ratio.
The grout will then be discharged into vessels to be transported to the letterbox. This process will be repeated until the grout appears in the end letterbox.
For box 1 and box 6 the outer exposed edges will be shotcreted to seal the vertical gap.
Once the gap between the box and the rails has been successfully grouted the vertical gap between the box and the face and the soffit can then be grouted."
The Underpass – water leakage
"I think that the best solution will be to dig out the West headwall and waterproof the potential paths of water ingress…
I think that most likely the water gets in there between the deck and headwall, through the gap for the ADS. Has this gap been grouted? If yes, what is the likelihood that this has been done robustly?"
The Underpass issue
i) a deficiency in Atkins' design, namely, Atkins' failure to specify additional waterproofing measures, such as a membrane or waterstop, or other water collection system; or
ii) the JV's poor workmanship, namely, failure to remove the ADS sheets from the 100mm gap and/or failure to install the grout properly so as to fill the gap.
The Underpass – expert evidence
The Underpass - Discussion and findings
"Q. But cutting the sheets at the back of the anchor beam was possible, and then you would end up with an ADS sheet of let's call it 4.7 metres, because you would have a bit at either end?
A. Yes, yes.
Q. You could pull those out by hand, couldn't you?
A. If it was completely clear, yes, just about. Yes…
Q. So what we can surmise from that is they were cuttable; the process of building the underpass meant that they were available to be cut?
A. Yes.
Q. And they were removeable?
A. Under the headwall they could have been but bearing in mind that the back of that headwall was underground …
Q. The back of that headwall was not underground at the end of the jacking process was it?
A. Not at the end of the jacking process, no."
"Q. When you cut the ADS sheets at the front of the anchor beam you could have also cut the ADS sheets at the back of the anchor beam?
A. That's correct.
Q. The cutting of ADS sheets would have taken minutes?
A. In my experience it's more than minutes …
Q. Would it have taken an hour? …
A. Based on my experience I would say probably half an hour per pair of sheets, yes, and then obviously on top of that .. that is the cutting but then they have to be safely removed, so you know that would be a manual handling operation as well, but yes we are talking about hours."
"Q. What you could do is you could seal up the front of the 100mm joint …
A. Yes.
Q. with injection ports and have injection ports in that caulking and seal up the back?
A. You would and could and that would obviously all create extra work in this instance, but you could, yes…
Q. Then if you injected the grout through the front, let's say, you would know when it reached the back because it would start to exit the ports at the back?
A. Yes."
Conclusions