England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Drive (Edgware) Ltd v S & T (UK) Ltd [2019] EWHC 3139 (TCC) (09 January 2019) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2019/3139.html Cite as: [2019] EWHC 3139 (TCC) |
[New search] [Printable PDF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY & CONSTRUCTION COURT (QBD)
Fetter Lane London, EC4A 1NL |
||
B e f o r e :
____________________
DRIVE (EDGWARE) LTD | Claimant | |
- and - | ||
S & T (UK) LTD | Defendant |
MR P. CLARKE (instructed by Messrs Fletcher Day) appeared on behalf of the Claimant.
MR J. RAYNES (instructed by Steptoe & Johnson UK LLP) appeared on behalf of the Defendant.
____________________
Crown Copyright ©
MR JUSTICE WAKSMAN:
"The subcontractor shall comply with all reasonable directions issued by the contractor within the timescale detailed on the directions. If the subcontractor fails to comply with the directions within the timescale stipulated thereon, the contractor may implement whatever action is necessary to ensure compliance with the direction. If no timescale is stipulated thereon, the timescale shall be within a reasonable period from the date of issue by the contractor. The subcontractor shall use best endeavours to ensure such period does not delay the contractor's on site progress. Any costs incurred by the contractor ensuring compliance with or execution of the work required by the directions, including but not necessarily limited to the employment of additional resources, may be set off against monies due or that may become due to the subcontractor."
I will refer to the meaning and effect of those provisions a little later in this judgment.
"Dear all, with immediate effect please issue site instructions signed by the commercial manager and project manager on every live project to replace the current nominated address for subcontracts, applications for payment. The instruction is to read as follows:"
"Please issue all future applications for payment to the email address below and cc in the relevant QS for the project. Any applications issued to any other email address/persons will not be recognised. Scheduled application dates within the order are still applicable, [email protected]. If you have any queries please do not hesitate to contact Ashlyn McGee ..."
The email of Ashlyn McGee is then given.