BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> BDW Trading Ltd v Lantoom Ltd [2020] EWHC 2744 (TCC) (16 October 2020) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2020/2744.html Cite as: [2020] Costs LR 1597, [2020] EWHC 2744 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS
OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
Fetter Lane, London, EC4Y 1NL |
||
B e f o r e :
____________________
BDW TRADING LIMITED |
Claimant |
|
- and - |
||
LANTOOM LIMITED |
Defendant |
____________________
Ms Jennifer Jones (instructed by Stephens Scown LLP) for the Defendant
Hearing date: 02 October 2020
____________________
Crown Copyright ©
Mr Justice Kerr :
"a) The number of documents requiring review for the purposes of disclosure was over 3 times more than we had envisaged. Within the assumptions within the Claimant's Cost Budget, we stated that the amount of documents collected would be less than 50,000 and that the individual review of documents would be no more than 15,000 after key words were applied. It became clear throughout the course of the proceedings that over 250,000 documents were collected which were reduced to 200,000 after applying initial key words. Thus, we collected 4-5 times more documents than our stated assumption in the Claimant's Cost Budget. Fortunately, we managed to reduce the number of documents for individual review down to approximately 70,000 by grouping family members and using de-duplication however this was still over 4 times more than we stated as assumed within the Claimant's Cost Budget.
b) We had anticipated that much of the additional volume of documents related to photographs, repetitive correspondence and quantum information which would be reduced during the final disclosure review or would otherwise require minimal time during the witness evidence preparation phase. Our client did not therefore expect an increase to the costs of the witness statement phase at the time of seeking a variation to its Cost Budget for the disclosure phase. However, it subsequently proved necessary to consider a substantial amount of the increased volume of documentation with the witnesses.
c) At the time of preparing the Claimant's Cost Budget, within the assumptions we stated that there would be 3 witnesses of fact. However, after reviewing the voluminous amount of documents disclosed by both parties and in the context of the statements of case, it was necessary for our client to prepare 6 witness statements in the first round of witness statements. This was double the number of witnesses and witness statements than our stated assumption in the Claimant's Cost Budget. It was not until we started proofing and drafting statements that it was identified that other witnesses would be required to adequately address the various factual issues.
d) In addition to our client providing 6 witness statements in the first round of witness statements, our client also filed 6 witness statements by way of supplemental statements. Whilst 4 out of the 6 statements were from the same individuals involved in the first round of statements, the remaining 2 were completely new witnesses (from KCC and Yennadon) and as such, additional time was spent providing them with the relevant information, proofing and drafting. These additional witnesses were necessary to respond fully to points raised within your client's witness statements regarding KCC's performance and alleged issues with Yennadon's stone at other sites. Thus, our client incurred the cost of engaging with – and preparing the statements for – nearly three times the number of witnesses in our stated assumption in the Claimant's Cost Budget, i.e. eight witnesses instead of three.
Moreover, the supplemental statements were also substantial statements (totalling 34 pages) rather than the minimal supplemental statements that had been assumed in our client's Cost Budget. This was due to the number of issues referred to by your client's witnesses which were not anticipated.
e) Finally, the Covid-19 crisis has meant that the production of both rounds of witness statements took longer than originally budgeted as face to face meetings were avoided, save for one witness, and statements were necessarily taken by telephone and email / virtually (as indicated at the start of each witness statement).
We note this increase results in the estimated costs of the witness statement phase being £136,970. Given the various additional issues that our client's statements were required to address to properly cover the matters raised by your client in its Defence and/or its supplemental statements, such as the alleged defects in the properties, discovery of defects with the Lantoom stone, remedial works and losses and the fact that the quantum of our client's claim is also now circa £5.3m, the increase to our client's Cost Budget is reasonable and proportionate in all the circumstances."
"a) The number of documents requiring review for the purposes of disclosure was over 4 times more than we stated as assumed within the Claimant's Cost Budget (see above) which resulted in the need for our client's experts to review and address substantially voluminous documents for the purposes of preparing their reports.
b) It was not until discussions between our clients' respective experts that our client became aware that your clients' experts had visited many other sites, not just St Martin's, and that your client's experts were relying on those other site visits in expressing their opinions. To be able to adequately respond to points being raised by your client's experts, our client's experts have had to visit various other sites to gather relevant information. Within the Claimant's Cost Budget, we had provided estimates based on the fact that there would be no visits required for the materials / structural experts to other sites, only 1 site visit required to the site for the materials experts and only 2 site visits for our client's structural expert. Given our client's experts are not based in Cornwall, the additional visits required to other sites were fairly substantial and outside of the costs budgeted for in the Claimant's Cost Budget.
c) The parties' liability experts were originally due to file their joint statement in accordance with CPR 35.12(3) on 29 May 2020 however due to the need for additional issues to be discussed and considered the liability experts' joint statement process took a lot longer than expected. Discussions commenced on 13 June 2020 and progressed throughout June, July and August with the joint statement eventually being finalised and filed on 27 August 2020. Within our Claimant's Cost Budget we estimated 7.5 hours for our client's Materials / Geologist Expert together with 25 hours for our client's Structural Expert for the joint statement however the time spent was significantly in excess of this for the reasons explained. The Materials / Geologist Expert has incurred 19.75 hours and the Structural Expert has incurred 118 hours in respect of the Joint Statement.
d) Within the Claimant's Cost Budget we estimated £10,000.00 in respect of stone and mortar tests in addition to the £6,870.00 already incurred. As the issues have been analysed further as a result of the need to respond to matters raised by your client, further testing has become necessary. In particular, further testing has become necessary to address the various specification issues raised in the Defendant's Second Request for Information and in response to requests for further test information from our client's experts. Our client has expended £28,369.45 excluding VAT to date on testing Lantoom stone (i.e. £11,499.45 more than originally budgeted).
e) The variation in relation of our client's quantum expert is as a result of the detailed and voluminous nature of the quantum documents which have required detailed review and auditing to enable our client's quantum expert to make a reasoned assessment of the costs incurred. At the time of our client's Cost Budget, the quantum of our client's claim was anticipated to be circa £2.5m. This has now more than doubled to circa £5.3m. This reflects the additional work required by our client's quantum expert both on the joint statement and in the preparation of his quantum report. Our client budgeted £2,900 regarding the Joint Statement plus £725 for conferencing and £15,000 for the expert report. Our client's expert now anticipates incurring £5,075 for joint statements and £18,624 for his expert report, being an increase of £2,175 and £3,624 for these phases of work respectively.
f) The variation in relation to our client's Counsel is as a result of the need to consider much more documentation as well as to review more drafts and for longer than expected (for a combination of all of the reasons set out above). Our client's Cost Budget assumed 3 review meetings with our client's experts (i.e. 9 in total) but these have been exhausted and further review meetings are and will be taking place. We expect 2-3 times the number of draft reports meetings stated as assumed in the Claimant's Cost Budget.
g) Finally, the Covid-19 crisis has meant that the production of joint statements and expert reports has taken – and is taking – longer than originally budgeted as face to face meetings have been avoided and work has necessarily been done virtually and via email.
We note this increase results in the estimated costs of the expert phase being £221,588.94. Given the numerous technical issues in this case and the fact the quantum of our client's claim is now circa £5.3m, this increase to our client's Cost Budget is reasonable and proportionate in all the circumstances."
"1. The Claimant has already been allowed an increase to the disclosure phase of their budget of £90,000. This is notwithstanding the fact that the Claimant should have known the extent of its own disclosure at the outset.
2. The Claimant seeks an increase to the witness statement phase based on the fact that the number of documents that required review was 3 times higher than expected. On the basis that the costs for the disclosure phase have been increased by £90,000, it is not appropriate for a further increase to be included related to increased volume of disclosure in the witness statement phase.
3. Whilst the Claimant has produced initial witness statements from 6 witnesses rather than the 3 that were allowed for in the original budget assumptions, the statements are all short. 3 of the statements are less than 10 pages. The statements were as follows:
- Philip Havenhand – 2 pages
- Steven Fowler – 4 pages
- Brian Avery – 8 pages
- Daniel Mountstevens – 19 pages
- Kate Smallwood – 23 pages
- Tim Davies – 21 pages
4. In relation to the supplemental witness statements, these were not substantial. In fact they amounted to a total of only 34 pages. The total number of pages of witness evidence is therefore 111 pages. The Claimant's original budget for this phase was £68,333.
5. It is not understood how or why the Covid situation has caused an increase to the budget for witness statements. If anything, the fact that discussions related to the statements have taken place by telephone or remotely would have reduced costs as there would be no travel time for visiting witnesses.
6. The Claim and the Defence have not changed since the date that the original budget was prepared. Whilst it is noted that the Claimant is now seeking to amend its claim and to increase the value, the Claimant's solicitors say in their covering letter that the proposed amendments will not require any new evidence and will in fact reduce the amount of evidence required as "there will not be any need for witnesses of fact to be cross examined on the said variation orders".
7. The Claimant is seeking an increase of £69,620 for the witness statement phase. This is double their original budget. The Defendant considers this to be wholly disproportionate.
8. There has been no significant change of circumstances that would justify an increase to this phase of the budget. The increase in the amount of disclosure documents has already been generously accounted for in the disclosure phase increase.
9. It is also relevant that the Claimant challenged the Defendant's original budget for the witness statement phase and the Defendants budget for this phase was reduced by £40,000."
"10. The Claimant has already been allowed an increase to the disclosure phase of their budget of £90,000. This is notwithstanding the fact that the Claimant should have known the extent of its own disclosure at the outset.
11. The Defendant has already agreed an increase to the Claimants' original budget for this phase as they consented to the structural engineer's fees element being increased by £8,500. This is reflected in the consent order dated 28 April 2020.
12. The fact that the Defendant's experts had visited other sites is not a significant development. It should have been obvious that the experts would need to carry out a review of other sites that utilise similar products to those being complained of as a comparison.
13. The delay to the dates for the joint statement and the expert … reports did not in itself increase the amount of work required. It just shifted the dates when that … had to be undertaken.
14. The additional testing is something that should have been anticipated in the original budget. The Defendant's case has not changed in relation to this issue.
15. The Claimant should have known the extent of the documentation related to quantum when they prepared their original budget.
16. Insofar as the Claimant seeks to justify the increase to their budget on the fact that the quantum has increased from £2.5m to £5.3m, this is the subject of a pending application to amend the Claimant's case. If that application to amend the claim is allowed then the usual costs order would be that the Defendant is awarded their costs of and associated with any amendment. The Claimant would not be entitled to any increase in costs and therefore any increase to the expert's phase of the budget as a result of the quantum increasing should not be allowed.
17. The Covid situation has not caused any increase in work for the expert's phase. The experts have in fact had face-to-face meetings and the conduct of other discussions by telephone or video will have saved travel cost.
18. The proposed increase of £106,008 is nearly double the original budget for this phase and is wholly disproportionate.
19. There has been no significant change of circumstances that would justify an increase to this phase of the budget. The increase in the amount of disclosure documents has already been generously accounted for in the disclosure phase increase and the increase in the quantum resulting from the proposed amendment is not something that the Claimant should be allowed additional cost for.
20. It is also relevant that the Claimant challenged the Defendant's original budget for the experts report phase and the Defendants budget for this phase was reduced by £50,000."
"any event, circumstance or step which is of such a size and nature as to go beyond the events, circumstances and steps which were taken into account, expressly or impliedly, in the budget previously approved or agreed. A development is taken into account impliedly if it is something that was, or should reasonably have been, anticipated by the applicant for revision with regard to the previously approved or agreed budget or to any earlier budget."