BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales Lands Tribunal |
||
You are here: BAILII >> Databases >> England and Wales Lands Tribunal >> Spears Brothers (a firm) v Rushmoor Borough Council [2006] EWLands RA_39_2004 (02 February 2006) URL: http://www.bailii.org/ew/cases/EWLands/2006/RA_39_2004.html Cite as: [2006] EWLands RA_39_2004, [2006] RA 86 |
[New search] [Printable RTF version] [Help]
Spears Brothers (a firm) v Rushmoor Borough Council [2006] EWLands RA_39_2004 (02 February 2006)
RA/39/2004
LANDS TRIBUNAL ACT 1949
RATING – alteration of rating list – completion notice – workshop – temporary electricity supply from neighbouring workshop in same ownership – whether property completed – held property a self-contained unit and not completed due to absence of permanent electricity supply, wiring for lighting and fire alarm system – Local Government Finance Act 1988, Schedule 4A.
IN THE MATTER OF AN APPEAL AGAINST A DECISION OF THE
HAMPSHIRE NORTH VALUATION TRIBUNAL
BETWEEN SPEARS BROTHERS (a firm) Appellant
and
RUSHMOOR BOROUGH COUNCIL Billing Authority
Re: Workshop
25 South Street
Farnborough
Hampshire GU14 6LN
Before: N J Rose FRICS
Sitting at Procession House, 110 New Bridge Street, London EC4V 6JL
on 9 January 2006
The following cases are referred to in this decision:
Ravenseft Properties Ltd v Newham LBC [1976] 1 ALL ER 580
Post Office v Nottingham City Council [1976] 1 WLR 624
Mr Robert A Spears, with permission of the Tribunal, for the Appellant.
Mr Roger Gear, Local Taxation Manager, Rushmoor Borough Council, with permission of the Tribunal for the Billing Authority.
DECISION
1 (1) If it comes to the notice of a billing authority that the work remaining to be done on a new building in its area is such that the building can reasonably be expected to be completed within 3 months, the authority shall serve a notice under this paragraph on the owner of the building as soon as is reasonably practicable unless the valuation officer otherwise directs in writing.
(2) If it comes to the notice of a billing authority that a new building in its area has been completed, the authority may serve a notice under this paragraph on the owner of the building unless the valuation officer otherwise directs in writing …
(6) In this Schedule 'completion notice' means a notice under this paragraph.
2 (1) A completion notice shall specify the building to which it relates and state the date which the authority proposes as the completion day in relation to the building.
(2) Where at the time a completion notice is served it appears to the authority that the building to which the notice relates is not completed, the authority shall propose as the completion day such day, not later than 3 months from and including the day on which the notice is served, as the authority considers is a day by which the building can reasonably be expected to be completed.
(3) Where at the time a completion notice is served it appears to the authority that the building to which the notice relates is completed, the authority shall propose as the completion day the day on which the notice is served…
4. (1) A person on whom a completion notice is served may appeal to a valuation tribunal against the notice on the ground that the building to which the notice relates has not been or, as the case may be, cannot reasonably be expected to be completed by the day stated in the notice.
(2) Where a person appeals against a completion notice and the appeal is not withdrawn or dismissed, the completion day shall be such day as the tribunal shall determine…
9. (1) This paragraph applies in the case of a building to which work remains to be done which is customarily done to a building of the type in question after the building has been substantially completed.
(2) It shall be assumed for the purposes of this Schedule that the building has been or can reasonably be expected to be completed at the end of such period beginning with the date of its completion apart from the work as is reasonably required for carrying out the work."
"(i) A property will be roofed, glazed, plastered; exterior doors installed, floors and ceilings in place, although any of this work may not be fully completed.
(ii) In the normal pattern of construction electrical wiring and plumbing work will be installed prior to plastering but final fittings not necessarily completed.
(iii) Normally by the time a property has been plastered the electricity, mains water, gas supplies and drainage will be available but not necessarily connected."
"such that the building can reasonably be expected to be completed within 3 months."
However, a broadly similar formula used in Schedule 1 of the General Rate Act 1967 was twice considered by the Court of Appeal in judgments which I consider to be of assistance when interpreting the 1988 Act.
"Where a rating authority are of opinion –
(a) that the erection of a building within their area has been completed; or
(b) that the work remaining to be done on a building within their area is such that the erection of the building can reasonably be expected to be completed within three months,
and that the building is, or when completed will be, comprised in a relevant hereditament, the authority may serve on the owner of the building a notice (hereafter in this paragraph referred to as 'a completion notice') stating that the erection of the building is to be treated for the purposes of this Schedule as completed on the date of service of the notice or on such later date as may be specified by the notice."
The expression "relevant hereditament" is defined in paragraph 15 as meaning
"any hereditament consisting of, or part of, a house, shop, office, factory, mill or other building whatsoever, together with any garden, yard, court or other land ordinarily used or intended for use for the purposes of the building or part."
"The word 'completed' in para 8(1) seems to me to mean completed in the sense of being ready for occupation".
"In my judgment, the effect of these provisions, as interpreted by this court in Ravenseft's case, is that the question is whether the building, as a building, is so far completed as to be capable of occupation or ready for occupation for the purposes for which it was intended – as a house, shop, office, factory or, in this case, a telephone exchange."
Dated 2 February 2006
N J Rose FRICS