BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just Β£1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales Lands Tribunal |
||
You are here: BAILII >> Databases >> England and Wales Lands Tribunal >> Barrington v Sloane Properties Ltd [2007] EWLands LRX_31_2006 (12 April 2007) URL: http://www.bailii.org/ew/cases/EWLands/2007/LRX_31_2006.html Cite as: [2007] EWLands LRX_31_2006 |
[New search] [Printable PDF version] [Help]
LRX/31/2006
LANDS TRIBUNAL ACT 1949
LANDLORD AND TENANT - service charges -lease permitted recovery from tenant of "actual cost" of building works in relevant years - interrelationship of dates for payment of interim certificates under building contract to relevant years - whether erroneously calculated demands for service charges were validly made - powers of Tribunal to correct errors - appeal allowed.
IN THE MATTER OF AN APPEAL AGAINST A DECISION OF THE LEASEHOLD VALUATION TRIBUNAL FOR THE LONDON RENT ASSESSMENT PANEL
BETWEEN ELAINE BARRINGTON Appellant
and SLOANE PROPERTIES LIMITED Respondent
Re: Ground Floor Flat
10 Kensington Park Gardens
London
Wll 3HD
Before: His Honour Judge Gilbart QC
Sitting at: Procession House On 26th February 2007
Charles Scott, instructed by Windsor and Co, Solicitors of Tottenham for the Appellant Michael Pryor, instructed by Payne Hicks Beach, Solicitors of Lincolns Inn, for the Respondent
The following cases are referred to in this decision:
Henry Boot Construction Ltd v Alstom Combined Cycles Ltd [2005] EWCA Civ 1814
Marenco v Jacramel Ltd[1964] EG Digest 349
Jones v Sherwood Computer Services PLC [1992] 1WLR 277 (CA)
Nikko Hotels Ltd v MEPC [1991] 1 EGLR 1
National Grid Company Plc v M25 Group Ltd [1998] EWCA Civ 1968 [1999] 08 EG 169
The following additional cases were cited in the skeleton arguments
Benedictus v Jaralam [ 1989] 1 EGLR 251
Re Davstone's Estates Ltd's Lease [1969] 2 Ch 378
Troop v Gibson [ 1986] 1 EGLR 1
The following works were cited in the skeleton arguments
Snell's Equity(31st Ed 2005) p 259-260
Woodfall's Law of Landlord andTenant 2007 Volume 1 paragraph 7.180
DECISION
(as perfected after submissions from Counsel)
(i) | 31st October 2000 | £13,406.76 |
(ii) | 31st October 2001 | £ 1,117.64 |
(iii) | 31st October 2002 | £31,133.89 |
"The Tribunal grants leave to appeal on the issue of certification as this issue is complex and may have significant implications in this and other cases. Apart from the issue of construction of the lease the main issue is whether the Tribunal can allow the amounts claimed for building works even if the year in which they were certified is different from the year in which they were claimed."
Permission to appeal on other grounds was refused by both the LVT on 1st February 2006 and by the Lands Tribunal (HH Judge Rich QC) on 27th March 2006.
a. the final certified sum under the Phase 1 contract is now given as the net figure before VAT (£532.03 instead of £625.14). The correct figure had in fact been used by me in the calculations thereafter. I reject all other recalculations suggested by either party;
b. a typographical error appeared in the calculation of the Phase II works for the year ending 1st November 2002. I have amended that error, which makes a difference of £4,400 in the charge for that year, but which still remains less than the Respondent had claimed.
I have also corrected some minor infelicities in my typing, punctuation, syntax and computer formatting. Subsequent paragraphs have also been renumbered because of the insertion of this paragraph.
The facts
"an annual sum of money equal to an eight-thirty-three of the actual cost to the Landlord of providing ( ) insurance repairs painting decoration lighting furnishing and carpeting and also the landlord's general administration expenses including (but without prejudice to the generality of the foregoing) the fees of the landlord's managing agents for the general management of the Building and the fees of architects surveyors accountants solicitors and other professional persons for services rendered for the benefit of the building as a whole or of the tenant and other tenants as a class .such sum to be certified by the accountant for the time being of the landlord (whose certificate in writing shall be conclusive) in respect of each year (calculated from the First of November) or the sum of One hundred and sixty pounds in any year when this shall be greater than the sum so certified ( ) on the quarterly day for payment next ensuing after the date of such certificate."
It was agreed that an " eight-thirty-three" (or in fraction terms 8/33) amounts to 24.24%.
(i) The supervising architect would value the work done from time to time and issue an interim certificate, which was due for payment by the landlord to the contractor after 14 days of issue of the contractor's invoice
(ii) The certificate would represent the value of work done, less the amount(s) already paid, and less 5% or 2.5% retention depending on the certificate
(iii) As the work proceeded there would be omissions from the works specified in the original contract documents, or items of work added to them. Those omissions and additions would be valued also, and taken account of in the certification procedure.
(iv) At the conclusion of the work, a final certificate would be issued and the retention monies released to the contractor.
* Certificate 8: when paid, this was paid with an extra sum of £ 3159.83 to reflect a works value increased to £144.857.11 after retention at 2.5%
Final Account (before VAT) | £ 59,711.00 |
Less paid for by neighbour | £ (800.00) |
Less works not relevant to recovery | £ (12,242.00) |
(Total deduction) | £ (13,042.00) |
Balance | £ 46,669.00 |
Amount completed by 1st Nov 2000 (90%) | £ 42,002.10 |
Barrington %age (24.24) | £ 10,181.31 |
Vat @17.5% | £ 1,781.72 |
Fees @10% incl VAT | £ 1,196.30 |
24.24% of disbursements (£368.74) | £ 105.02 |
24.24% of planning supervisor fees (£ 500) | £ 142.41 |
TOTAL | £ 13,406.76 |
Final Account (before VAT) | £148,571.39 |
Less improvements/additions | (£ 46,155.38) |
Balance | £102,416.01 |
Barrington %age (24.24) | £ 24,825.64 |
Vat @17.5% | £ 4,344.49 |
Fees @10% incl VAT | £ 3,427.48 |
24.24% of disbursements | £ 347.96 |
24.24% of planning supervisor fees | £ 185.13 |
TOTAL | £ 33,130.70 |
"10 KENSINGTON PARK GARDENS W 11
COST APPORTIONMENT BETWEEN LESSEES
Year ending 31.10.02
Final Account Contract no 2 | £ 148,571.39 |
"Proportion of final account on which | |
E Barrington percentage to be based | |
(refer to cost apportionment dated 31.10.02)" | £ 102,416.01 |
"Amount to be certified at 31.10.02 (cert 08)" | £ 141,697.28 |
At 68.93% | £ 97,671.93 |
At 24.24% | £ 23,675.67 |
VAT @17.5% | £ 4,143.24 |
Total | £ 27,818.91 |
Fees @10% plus VAT on £ 23,675.67 | £ 2,781.89 |
24.24% of Finch Assocs disbursements | £ 347.96 |
24.24% of Planning Supervisors Fees | £ 185.13 |
Total due from E Barrington for year ending 31.10.02 | £ 31,133.89 |
a. The accounts certified by the accountant calculate the architect's fees (other than the disbursements) by reference to the sum calculated for the value of the contract. It follows that any alteration in the calculation of the contract value attributed to any given year will also alter the level of architects' fees in the calculation.
b. At 31st Oct 2000, £47,911 of work had been carried out on Phase 1, and had been certified under the building contract. Of that figure, £24,390.30 plus VAT (totalling £28,658.61) had been due to be paid by the landlord in the year ending 1st November 2000. It had been so paid. Another £21,125.15 plus VAT (totalling £24,822.05) had been certified before 1st November 2000, but was not due for payment, nor paid, until after 1st November 2000. Of the final certified sum (£58,116.50) the amount paid before 1st November 2000 represented just under 42 %. The amount of work done by that date and certified for payment (£45,515.45) amounted to just over 78 % of the eventual certified final sum of £58,116.50. Even the amount of work done without deducting for retention only amounted to £47,911, or 82% of the final contract sum (and 80% of the figure of £59,711 relied on in the accountant's certificates). Thus the amount claimed in respect of the contract works for the year ending 1st November 2000, which is based on an assumption that no less than 90% of £59,711 had been paid (£53,739.90) exceeds the amounts certified for payment by the architect to a very substantial degree, and exceeds the amounts which were payable within that year, whether one takes the retention into account or not, or whether one treats the work certified on 27th October 2000 as reckonable or not for that year's account.
c. Any excess in the year ending 31st October 2000 of the kind described above will go hand in hand with an equivalent understatement of the amount of costs certified under the building contract or paid for the year ending 31st October 2001.
d. As to the year ending 31st October 2002, by 23rd August 2002 work on Phase 2 to a value of £130.520.29 had been carried out, which after retention of 5% and deduction of earlier payments resulted in a certificate that £3,116.30 was payable. The time for payment of the difference (£3,116.30 or £3661.65 incl VAT) had elapsed before 31st October 2002. By 31st October 2002, work had been carried out under the Phase 2 contract to a value of £145,330.55, of which £ 141,697.28 was payable after retention of 2.5%. The relevant certificate was issued after 1st November 2002.
e. In the account relating to Phase 2 presented in September 2003, while the overall contract figure used was the gross value of £148,571.39, the liability was calculated based on the value of the amount certified at 31st October 2002. The amounts which were used to calculate the tenant's contribution were based on a figure of £141,697.28 (£166,494.30 incl VAT) and thus exceed the amounts either certified for payment or paid during the relevant year, but do not exceed the value of the work done once retention is allowed for. As appears below, there is an issue on how the amounts valued on 31st October 2002 are to be treated.
f. The internal alterations and assumptions (the exclusion of items from the amount to be apportioned and the use of the percentage thus derived to the value of the Phase 2 works at stage 8, and thus before completion) are also affected by any changes in figures.
Cases for the Parties
Year ending | Contract works (incl VAT) | Fees etc (incl VAT) | Total (incl VAT) |
31stOct 2000 | £ 28,685.61 | £2,563.69 | £ 31,222.30 |
31st Oct 2001 | Phase 1: | Phase 1: | Phase 1: |
£ 625.14 | £5377.31 | £ 6002.45 | |
Phase 2: | Phase 2: | Phase 2: | |
£ 39,003.15 | £ 6,241.75 | £ 45,244.90 | |
31st Oct 2002 | £142,031.62 | £ 0 | £142,031.62 |
31st Oct 2003 | £ 28,175.49 | £ 10,140.02 | £ 38,315.69 |
31st Oct 2004 | £ 1,857.14 | £ 0 | £ 1,857.14 |
a. The accounts for the year ending 2001 were not based on the amounts actually paid in that year. The amount actually paid was £31,222.30, whereas the apportionment took the figure as 90% of £59,711 less deductions.
b. In the case of the Finch Associates percentage fees, the fees used in the accounts were not based on actual fees paid by reference to dates of payment, but took a percentage approach.
c. The percentage assumptions made (90% in the case of the split of Phase 1 between years ending 2000 and 2001, and 68.93% as the amount of the Phase 2 contract which could be passed on to tenants) should not have been made, but the actual costs should have been ascertained.
d. In the case of the year ending 31st October 2002, the amount paid under the contract was £120,877.97 plus VAT (£ £142,031.62 in total) whereas the amount used in the accounts was £141,697.28 plus VAT. Even if the delay in paying £3,116.30 plus VAT (£3,661.65 in total) does not take that payment outside the relevant year, the inclusion of sums certified on 5th November, and not due for payment until 14 days thereafter, was contrary to the clear words of the contract.
Conclusions
Final Account (before VAT) | £ 59,711.00 |
Less paid for by neighbour | £ (800.00) |
Less works not relevant to recovery | £ (12,242.00) |
(Total deduction) | £ (13,042.00) |
Balance (78%) | £ 46,669.00 |
78% of amount certified and due for payment | |
before 1st Nov 2000 (£24,390.30) | £ 19,024.43 |
Barrington %age (24.24) | £ 4,611.52 |
Vat @17.5% | £ 807.02 |
Fees @10% incl VAT | £ 541.85 |
24.24% of disbursements (£368.74) | £ 105.02 |
24.24% of planning supervisor fees (£ 500) | £ 142.41 |
TOTAL | £ 6,207.82 |
Final Account (before VAT) | £ 59,711.00 |
Less paid for by neighbour | £ (800.00) |
Less works not relevant to recovery | £ (12,242.00) |
(Total deduction) | £ (13,042.00) |
Balance (78%) | £ 46,669.00 |
78% of amount (£ 33,819.31) | |
certified for payment after 1st Nov 2000 | £ 26,379.06 |
Barrington %age (24.24) | £ 6,394.28 |
Vat @17.5% | £ 1,119.00 |
Fees @10% incl VAT | £ 751.33 |
24.24% of disbursements (£368.74) | £ 105.02 |
24.24% of planning supervisor fees (£ 500) | £ 142.41 |
TOTAL | £ 8,512.04 |
(I have not adjusted the above calculations of the 78% figure for the very minor reduction in the overall contract value when the final certificate was issued in September 2001).
Final Account Contract no 2 | £ 148,571.39 |
Proportion of final account on which | |
E Barrington percentage to be based | |
£ 102, 416.01/£148,571.39 = 68.93% | |
Amount to be certified and due for payment | |
before 1st Nov 2002 | £ 123,994.27 |
At 68.93% | £ 85,469.25 |
At 24.24% | £ 20,717.75 |
VAT @17.5% | £ 3,625.61 |
Total | £ 24,343.36 |
Fees @10% | £ 2,434.34 |
24.24% of Finch Assocs disbursements | £ 347.96 |
24.24% of Planning Supervisors Fees | £ 185.13 |
Total due from E Barrington for year to 31.10.02 | £ 27,310.79 |
"So in questions in which the parties have entrusted the power of decision to a valuer or other decision-maker, the courts will not interfere either before or after the decision. This is because the courts' views about the right answer to the question are irrelevant. On the other hand, the court will intervene if the decision-maker has gone outside the limits of his decision-making authority.
One must be careful about what is meant by "the decision-making authority". By "decision-making authority" I mean the power to make the wrong decision, in the sense of a decision different to that which the court would have made. Where the decision-maker is asked to decide in accordance with certain principles, he must obviously inform himself of those principles and this may mean having, in a trivial sense, to "decide" what they mean. It does not follow that the question of what the principles mean is a matter within his decision- making authority in the sense that the parties have agreed to be bound by his views. Even if the language used by the parties is ambiguous, it must (unless void for uncertainty) have a meaning.
Accordingly, if the decision-maker has acted upon what in the court's view was the wrong meaning, he has gone outside his decision-making authority."
Year ending | Date of demand | Amount claimed | Amount determined by Lands Tribunal |
31st October 2000 | 6th June 2001 | £ 13,406.76 | £ 6,207.82 |
31st October 2001 | 24th Sept 2003 | £ 1,117.64 | £ 8,512.04 |
31st October 2002 | 24th Sept 2003 | £ 31,133.89 | £ 27,310.79 |
Total | £ 42,030.65 |
Formal decision
Dated: 12th April 2007
Signed: His Honour Judge Gilbart QC