BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
High Court of Ireland Decisions |
||
You are here: BAILII >> Databases >> High Court of Ireland Decisions >> Lynch Roofing Systems (Ballaghaderreen) Ltd. v. Bennet and Son (Construction) Ltd. [1998] IEHC 216; [1999] 2 IR 450 (26th June, 1998) URL: http://www.bailii.org/ie/cases/IEHC/1998/216.html Cite as: [1998] IEHC 216, [1999] 2 IR 450 |
[New search] [Printable RTF version] [Help]
1. This
matter comes before the court as a motion brought by the defendant seeking an
order pursuant to section 5 of the Arbitration Act 1980 staying the within
proceedings pending arbitration.
In
summary the issues between the parties can be stated as follows. The defendants
are a building company who were engaged to develop a site in Mullingar, Co
Westmeath and the defendants subcontracted the roofing aspect of the contract
to the plaintiff company. The plaintiff company claims in the summary summons
that there is the sum of £59,799.25 due on foot of this contract in
respect of works carried out on the premises. The defendants say that the
plaintiffs are estopped from maintaining these proceedings by reason of an
arbitration clause contained in the contract entered into between them.
On
behalf of the defendants it is submitted that the plaintiff company is one of
the largest roofing contractors in the Midlands and in November 1996 an
enquiry, for tenders for the job, was sent to Mr Noel Deane of the plaintiff
company and the plaintiff company furnished a tender in writing. There then
followed a meeting in December of 1996 between Mr Deane and Mr Bruton a
Quantity Surveyor employed by the defendants.
It
is alleged on behalf of the defendants that at that meeting the parties agreed
on the price and terms on which the roofing subcontract would be awarded by the
defendants to the plaintiff company and it is stated in Mr Bruton's affidavit
that;
"it
was perfectly clear to Mr Deane at that meeting that the conditions of contract
would be as per the main conditions of contract RIAI (April, 1998 Edition)
which includes a standard arbitration clause. We would not have had a detailed
discussion on the individual terms of that contract at that meeting as Mr Noel
Deane was an experienced man in the business, very familiar with the form of
sub-contract documents and it would have been sufficient for us to agree that
the standard conditions of contract RIAI (April, 1998 Edition) would apply to
the job. This was specifically agreed between us".
On
the 18 December, 1996 Mr Bruton sent a letter to the defendants for the
attention of Mr Deane stating that the defendants (erroneously referred to as
the plaintiffs in the affidavit) wished to enter into a domestic subcontract in
respect of the roofing work and stating that the same would be subject to a
written receipt of the conditions and terms detailed on form CBS/ACC which he
had attached to the letter. Paragraph 38 of this Contract contains the
arbitration clause upon which the defendants rely in this case.
No
reply was received to this letter but Mr Deane of the plaintiff company
attended on site and commenced the job on foot of the terms which, Mr Bruton
says, they had agreed in December of 1996 and confirmed in the letter of the 18
December, 1996.
Problems
arose in the performance of the contract terminating in a letter from the
plaintiff's solicitors on the 19 January, 1998 seeking payment of the amount
now claimed.
It
is the defendants case that the conditions of the contract are as set out in
form CBS which incorporates into the said contract the standard conditions of
contract RIAI (April, 1998 Edition). The letter of the 18 December, 1996
written by Mr Bruton concludes with the words "failure to respond will deem
your full acceptance of all conditions herein".
No
response was received to this letter and the plaintiffs commenced work shortly
after the receipt of the letter.
The
defendants submit that the plaintiffs are bound by the terms of this contract
which incorporate the arbitration clause and seek to have the within
proceedings set aside on that basis.
The
defendants have relied on British Crane Hire Corporation Limited v Ipswich
Plant Hire Limited [1975] QB 303 in support of their case that the plaintiffs
are bound by the terms of the agreement which require them to seek any relief
which they claim by way of arbitration. In that case the facts shortly were
that a crane was delivered on site for the carrying out of engineering works on
marsh land and subsequently the plaintiff sent a printed form setting out the
conditions of hire including the condition that the defendants should be
responsible for the recovery of the crane from soft ground and the defendants
should be responsible for and indemnify the plaintiffs against all expense
arising out of the use of the crane. The defendants neither signed or returned
the form to the plaintiffs.
The
crane having sunk on soft ground and the issue arising as to whether the
"printed form" formed part of the contract, it was held that "where parties to
a contract of hire were both in the trade and of equal bargaining power the
conditions habitually imposed in such contracts would be incorporated into the
contract on the basis of common understanding of the parties that the usual
conditions would apply; and that since the conditions set out in the plaintiffs
printed form form part of the contract the plaintiffs were entitled under these
conditions to the cost of recovering the crane . . .".
I
respectfully agree with the principal enunciated by the Court of Appeal and two
issues therefore appear to me to arise in this case. Firstly did the parties
habitually trade under contracts which incorporated arbitration clauses so that
a court would be forced to conclude that the parties expected and knew that
this clause would govern their contract. Put another way, as Lord Denning said
was there evidence that "it was clear that both parties knew quite well that
conditions were habitually imposed by the supply of these machines and both
parties knew the substance of these conditions".
In
the present case I am satisfied that each party was sufficiently familiar with
the trade so as to lead a court to conclude that, as Lord Denning put it in the
British Crane Hire Case the defendants would be understood and presumed to say
"of course that is quite understood". I would find it hard to believe that a
large roofing contractor would undertake this contract without the benefit of a
building contract.
Apart
from the foregoing there is also the fact that a meeting was held between the
parties on the 18 December, 1996 when the parties "agreed on the price and the
terms on which the roofing subcontract would be awarded by (the defendants) to
the plaintiff company" (see paragraph 5 of Mr Bruton's affidavit). He goes on
to say that "it was perfectly clear to Mr Noel Deane at that meeting that the
conditions of the contract would be as per the conditions of contract RIAI
(April, 1998 Edition) which includes a standard arbitration clause . . . This
was specifically agreed between us".
In
the affidavit in reply by Mr Coleman Lynch on behalf of the plaintiffs he says
that at no stage during the negotiations for the contract was an arbitration
ever mentioned or brought to his attention however Mr Bruton sent a letter to
the plaintiffs the second paragraph of which reads
"The
above is subject to receipt of your written acceptance of the conditions and
terms detailed on form CBS/ACC attached [subcontractor meeting form (QD/13)
should also be filled out and returned]. We draw your attention to the special
conditions on page 5 of this form. Failure to respond will deem your full
acceptance of all conditions thereon".
There
was no response to this letter. The work simply proceeded.
In
my view the contract for this work was entered into between the parties on the
occasion when the meeting was held between Mr Deane of the plaintiff company
and Mr Bruton. This meeting was held at the defendants premises at Milltown
Pass in County Westmeath when the plaintiffs representative discussed the job
with Mr Pierce Murphy the project manager and Mr Bruton. At that meeting they
agreed the price and the terms on which the roofing subcontract would be
awarded by the defendants to the plaintiff company.
Having
agreed that "the terms on which the roofing subcontract would be awarded" in my
view it would be extremely unlikely that experienced contractors would have
contemplated a contract such as this would be performed otherwise than being
governed by the appropriate building contract and I accept the evidence of Mr
Bruton.
Accordingly
that being so the contract entered into between the parties provided for an
arbitration clause and accordingly I grant the relief sought.