BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
High Court of Ireland Decisions |
||
You are here: BAILII >> Databases >> High Court of Ireland Decisions >> P. Elliot and Co. Ltd. v. Mardown Ltd. [2000] IEHC 201 (24th November, 2000) URL: http://www.bailii.org/ie/cases/IEHC/2000/201.html Cite as: [2000] IEHC 201 |
[New search] [Printable RTF version] [Help]
1. These
proceedings were issued to enforce an alleged settlement of earlier proceedings
between the Plaintiff and the Defendant which bore record number 1996 No. 686S.
These were proceedings taken by the Plaintiff, which carries on business as a
building contractor, against the Defendant, which was the employer of the
Plaintiff under a contract for the construction of a fitness centre. The
original proceedings constituted a claim for payment pursuant to Architect's
Certificates issued under the building contract.
2. While
the Plaintiffs were the contractors under the building contract, there were two
subcontracts entered into between the Plaintiff and a Northern Ireland firm
called Stothers (M&E) Limited (herein called "Stothers"), one for the
mechanical work and one for the electrical work. While, as between the
Plaintiff and the Defendant, Stothers were described as domestic
subcontractors, the fact is that the Plaintiff was directed by the Defendant's
Architect to engage Stothers, and to enter into subcontracts with Stothers on
the same terms as the main contract. It also appears that Stothers were
treated as the nominated subcontractor in the certifying of payments by the
Defendant's Architect, and it is quite clear that Stothers were, in everything
but name, nominated subcontractors. It also emerged in the course of these
proceedings that there was an action pending in Northern Ireland in which
Stothers were Plaintiffs and the Defendants were Defendants, and that there had
been a preliminary ruling in that case dealing with the relationship between
the Defendant and Stothers. While the Defendant maintains that the existence
of this ruling made it vital for the Defendant to establish the connection
between the main contract and the subcontracts, I am satisfied that the
Plaintiff was in fact unaware of this ruling at all relevant times, although it
was aware that the relationship between the main contract and the subcontracts
was a matter of concern to the Defendant.
3. The
original action was listed for hearing on 29th June, 1999, and on the previous
day lengthy negotiations took place between Counsel for the Plaintiff and
Counsel for the Defendant. I have heard evidence from Mr Dermot Gleeson SC,
who conducted the negotiations on the part of the Plaintiff, and his account of
the negotiations and of what transpired leading up to the matter being called
on in Court on 29th June has not been seriously contested. He gave evidence
that by the evening of the 28th June there were only two matters on which
agreement had not been reached. These were, firstly the form of words to deal
with Stothers, and secondly, the amount to be paid by the Defendant to the
Plaintiff as an immediate payment. At about 8.50 pm on that evening Counsel
for the Defendant telephoned Mr Gleeson and agreed the form of words in
relation to Stothers which had been suggested by Mr Gleeson, but could not
agree to any further immediate payment. Mr Gleeson got immediate instructions
to accept both these matters, and as far as he was concerned, and indeed as far
as Counsel for the Defendant was concerned, agreement was reached, subject to
the respective Junior Counsel writing out formal terms of settlement.
4. Later
that evening Counsel for the Defendant telephoned Mr Gleeson on several
occasions, intimating that he was having difficulties, but, very properly,
stressing that he was not repudiating the agreement which had been reached. A
further telephone call took place on the morning of 29th June, in which the
Defendant's Counsel said he still did not have full instructions but repeated
that he was not repudiating the agreement. He subsequently produced a document
which set out an alternative agreement, which included a clause stating:-
5. It
is quite clear, however, that this document was not the Defendant's account of
the agreement that had been reached, as it was only given to Mr Gleeson
conditional on the approval of one of the Directors of the Defendant. The
Counsel then went into Court, and upon Mr Gleeson announcing that the case was
settled, the Defendant's Counsel said
“I
am instructed that the case is not settled”
.
6. Shortly
afterwards, he told Mr Gleeson that the document had not been approved and that
the case was not settled.
7. Mr
Gleeson accepts that there was discussion about the relationship between the
main contract and the subcontract. His evidence is that what was agreed was
that no amount claimed by the Defendant in relation to the mechanical and
electrical items regarding Stothers were included in the agreed sum to be paid
and should not be deducted therefrom. He also accepts that this was on the
basis that the main contract and the subcontracts were identical, and in effect
was subject to a proviso that this was so. However, he strongly denies that
there was any suggestion that there was a condition precedent to the entire
agreement, and I accept his evidence in this regard.
8. On
6th July, 1999 the Plaintiff wrote to the Defendant setting out the terms of
the settlement which it was alleging. Included in that letter as part of the
settlement was the following paragraph:-
9. It
appears there is one clear inaccuracy in this statement, in that the
instructions given by the Defendant's Architects were not to enter into a
contract with Stothers as nominated subcontractors, but rather to enter into
the contract with them as domestic subcontractors. While the Defendant has
highlighted this error, I do not think it is of any real significance, and it
is notable that the Defendant did not seek to correct it in correspondence at
the time. Indeed, the Defendant's response was quite clear, and was contained
in a letter from them dated 9th July which stated:-
10. There
is no mention of any of the specific clauses in the Plaintiffs' letter of 6th
July, nor were any queries raised with regard to the relationship between the
main contract and the subcontracts.
11. Considerable
further correspondence took place between the parties and their respective
legal advisors, in the course of which the Defendant consistently maintained
that there was no agreement, and indeed sought to invite the Plaintiff to
renegotiate. On 14th July the Plaintiff enquired whether the Defendant would
instruct Solicitors in Dublin to accept service of these proceedings, but the
Defendant failed to do so, and by order dated 19th July the Plaintiff was given
leave to serve notice of the proposed summons on the Defendant as its
registered office in the Isle of Man. In due course, proceedings were issued
on 30th July, and the Statement of Claim was delivered in August in these
proceedings seeking Judgment in the sum of £350,000, which was the initial
sum to be paid on foot of the agreement, an order for specific performance of
the terms of the agreement and damages for breach
thereof
together with interest and costs.
12. Paragraph
5 of the Statement of Claim set out the alleged terms of the settlement,
including the following:-
13. On
19th and 20th October
there
were exchanges of correspondence
between
the Defendant's and the Plaintiffs' Solicitors in which
,
rather
bizarrely, the Defendant sought confirmation that Mr Gleeson had approved the
terms of the settlement agreement as set out in the Statement of Claim and
sought confirmation that Mr Gleeson would not, in giving evidence, seek to
expand on, adjust or vary the extent or meaning of the terms alleged.
Understandably, the Plaintiffs' Solicitors refused to deal with this point, and
the Defendant again reiterated that it was their position
“that there was no such agreement as alleged or at all”.
In a further letter dated 20th October the Defendant, in a letter marked
“without prejudice”, but which both parties have agreed should be
open to me, referred to the Statement of Claim, and in particular the paragraph
quoted above, and commented:-
14. The
Defendant then sought confirmation that this version would be accepted by the
Plaintiff. When queried by the Plaintiffs' Solicitors, the Defendant stated
that the letter had been written without prejudice on the basis that the
Defendant did not accept that there was a settlement agreement. It should be
said that it is most unfortunate that the Defendant, even at this stage, had
not instructed a Solicitor, and indeed had not entered an appearance. The
correspondence on the Defendant's behalf was carried out largely by one of its
Directors, Mr Peter Willers, who it appears is a qualified barrister in the
United Kingdom.
15. In
due course the Defendant did instruct Solicitors in this jurisdiction, and a
defence was duly filed on 28th January. Paragraph 1 of the defence read:-
16. The
Defence then continued to plead,
inter
alia
,
that the parties had not been
ad
idem
,
that the Defendant's representatives had no authority to enter into a
settlement, and denied in particular that any agreement entered into had
contained the clause set forth at paragraph 5(5) of the Statement of Claim.
The Defence then continued:-
17. It
should be noted that nowhere in the correspondence which took place had this
contention been put forward by or on behalf of the Defendant. A reply was
delivered on behalf of the Plaintiff on 15th February in which it was denied
that the agreement was provisional upon the main contract and the subcontracts
being back to back, and further denied that it was a fundamental term of the
agreement that such contracts were back to back. The reply then pleaded:-
18. In
April and May, 2000 there were further exchanges of correspondence
in
which the Defendant's Solicitor again raised the question of whether the main
contract and the subcontracts were back to back, and some, what I can only
describe as rather testy correspondence, took place and ultimately on 7th June
the Defendant's Solicitor wrote to the Plaintiffs' Solicitors saying:-
21. As
a result of this confirmation the initial payment on foot of the settlement
agreement has been paid by the Defendant, and the only issue now before me is
the question of interest on that payment and the question of the costs of these
proceedings.
22. I
felt it necessary to quote at some length from some of the correspondence which
took place, and from the pleadings. The following facts appear to me to be
quite clearly established:-
23. I
can find no justification for the attitude of the Defendant in the present
case. I have no doubt that there was a binding and valid agreement between the
parties Counsel which was reached on 28th June, 1999, and which was binding on
the parties. There was no justification for the attitudes subsequently taken
up on the part of the Defendant, and I will order that the Defendant pay to the
Plaintiff interest at Courts Act rates from 29th June, 1999 to 3rd August,
2000, being the date in which the payment was ultimately made, on the sum of
£350,000 and I further order that the Defendant pay the Plaintiffs' costs
of these proceedings.