BAILII is celebrating 24 years of free online access to the law! Would you
consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it
will have a significant impact on BAILII's ability to continue providing free
access to the law.
Thank you very much for your support!
[New search]
[Printable RTF version]
[Help]
Vogelaar v. Callaghan [1998] IESC 9 (13th July, 1998)
THE
SUPREME COURT
306/97
Keane,
J.
Murphy,
J.
Lynch,
J.
S.
VOGELAAR & ANOR.
Plaintiff
V.
D.
CALLAGHAN
Defendant
Ex
Tempore Judgment delivered the 13th day of July 1998, by Keane, J.
1. This
is an appeal from a judgment and order of the High Court (O’Sullivan J)
which was given on the 28th July last year and it is what one might describe as
the penultimate act in a very long, unfortunate and protracted saga arising out
of a building contract which went to arbitration. The plaintiffs, whom for the
sake of clarity I shall call the owners, and the defendant whom I shall call
the builder had several disputes in relation to a building and what was owed by
the owner to the builder. It is unnecessary to go into all those matters. They
were referred, the issues in dispute, to the arbitration of Mr. Padraig Murray,
a well known and experienced architect, of
-2-
course.
He conducted what in the event turned out to be an extremely protracted
arbitration and one which certainly in terms of the costs which were incurred
was out of all proportion to the sums involved, or significantly out of
proportion to the sums involved and as a result of that arbitration the
arbitrator found that the builder was owed a sum of some thirteen thousand
pounds, by the owners and if matters had ended there, then further litigation
mightn’t have resulted but he also directed that the owners were to pay
the builder’s costs. The difficulty which that created was that, as is
now quite clear, there had been an open offer on the 15th April 1992 made by
the owners to the builder to dispose of the whole matter for the sum of
£20,000. So that in accordance with the well established law and practice
as to costs in arbitrations, that should have had the same effect in general
terms as if a lodgment had been made in civil proceedings and the plaintiff in
the action had failed to recover damages in a sum in excess of the lodgment.
However, as I have said, the arbitrator decided, notwithstanding that fact, to
award the costs of the entire arbitration to the builder, and that led to
proceedings being instituted in the High Court which came before Mr. Justice
Barron, in 1996, in which the plaintiffs sought to set aside the arbitration
award on a number of grounds.
2. The
only ground with which we are now concerned is the matter as to costs, because
one of the issues which was raised was that the arbitrator failed to take into
account the open offer of £20,000 made by the owners when he
-3-
decided
to award costs to the builder and in relation to that matter it is important to
cite what the learned High Court judge said. He said, in relation to the award
of costs, that the arbitrator had in his affidavit indicated that he awarded
the costs of the hearing including the preliminary hearing from the costs of
the application to amend the counterclaim to the defendant, i.e. to the
builder, upon the basis that he had succeeded in obtaining an award in his
favour. He appears to have been unaware that costs normally follow the event
which in a case where an offer or a lodgment has not been exceeded by the award
favours the party making such offer or lodgment. Had he taken into account the
fact that the plaintiffs had made an open offer of £20,000 which was in
excess of the sum awarded to the defendant, he would not necessarily have made
the same award as to costs. Towards the end of his judgment, he goes on to say:
“it
seems to me that to allow the award to stand with the direction as to costs
would be to create a severe injustice. The arbitrator has not considered the
question of costs in the light of the fact that the event was in fact in favour
of the plaint ifs and not of the defendant, that is, in favour of the owners
and not of the builder The matter will be remitted to him to make such award as
he considers to be proper having regard to that factor.”
-4-
3. The
matter thereupon came back before the arbitrator and counsel appeared before
him at the hearing in relation to the matter of costs and it appears, and is
not indeed disputed by Mr. Kilty BL on behalf of the builder, that at that
hearing before the arbitrator there were a lengthy submissions and discussions
concerning the effect of an open offer and indeed what an open offer was, or
what constituted an open offer. It appears that there was in fact no discussion
of the principle matter which arose, namely the effect if any on the order as
to costs, of any residual discretion that there might be in the arbitrator, as
to how he was to deal with the costs, because while, as Barron J found there
had been an open offer and as he further found, costs normally follow the
event, there would clearly be a discretion in the arbitrator remaining as to
how he should approach the costs and that would clearly arise in this case. It
is not disputed that there was a relatively significant amendment of the claim
being brought by the owner, or the counterclaim being brought by the owner in
response to the builder’s claim, to him, and it was not in dispute that
the builder hadn’t contributed in any way to that and that this was a
matter which was really had to be laid at the door of the owners and the real
question the arbitrator had to deal with, when the matter came back before him,
was not whether there had been an open offer or not. There had been, because of
there having been an open offer the effect was quite clear, namely, that the
costs should follow the event, the event in this case being that the award had
been
-5-
less
than the amount of the open offer. Accordingly the event, as lawyers would
understand it, was that the builder had lost the case because if he had
accepted the offer as he should have done, there would have been no need for
any arbitration at all, so that in that sense, the costs should follow the
event. That was the finding of the High Court in general terms, that the costs
should follow the event but the arbitrator would, like any court dealing with
the matter, have a residual discretion remaining in him to deal with the costs,
so as to reflect any contribution that the owner’s conduct of the
litigation had made to unnecessarily prolonging it, because it would clearly
be unjust that the builder should have to bear the costs of an unnecessarily
protracted arbitration.
4. Unfortunately
the arbitrator does not seem in the way he dealt with the matter to have
appreciated that, because he embarked on a lengthy and really quite unnecessary
hearing, as to whether there had been an open offer and if so what the effect
of an open unconditional offer was, when there was really no doubt, or should
have been no doubt as to what the position was in relation to this particular
arbitration having regard to the clear and unequivocal finding of the High
Court, that there had been an open offer and that it had to be reflected in the
arbitrator’s award.
5. It
is necessary to refer to the award at this point, i.e. his second award dealing
with the matter of costs. What he did was to set out the history of the matter
in some detail, to refer to the amended counterclaim which has been
-6-
delivered,
and to refer to a earlier ruling that he had made that the costs arising from
the amended pleadings would be payable by the owners and that a decision as to
the amount of the costs should be reserved until the hearing had been
concluded. He went on to find as follows:
“During
the course of the hearing I concluded that had the experts for the Respondent
prepared adequate proper extensive and independent reports and valuations prior
to the commencement of the arbitration in September, not only would there have
been no necessity to amend the counterclaim but the hearing involving claim
defence and counterclaim could have been concluded in a period of six days or
less.”
6. Now
that was clearly an important finding, by the arbitrator, and one that he was
fully entitled to make, and indeed very properly made because it was one that
would undoubtedly affect the way he exercised the residual discretion as to
costs that he had. He goes on to say in paragraph 9 that his award of
£13,270.10 in favour of the builder stands. That again is not challenged
and could not be challenged. He then goes on to deal with the costs in this
manner:
-7-
“The
builder shall pay 6/15 of the owners costs in the arbitration including the
costs of the preliminary hearings and the amended counterclaim on a party and
party basis, such costs failing agreement shall be taxed”
7. If
one pauses there, if that was all we were concerned with there could be no
possible challenge in my view to the arbitrator’s award as being in any
way erroneous in point of law or in any way being susceptible to being set
aside because having regard to his finding that the arbitration, were it not
for the manner in which it had been conducted on behalf of the owner, could
have been concluded in the period of six days or less. He was entitled to come
to the conclusion that the owner should not recover more than six days costs.
That would be a significant loss, of course, to the owners because they would
have to bear the costs of the remaining days of the arbitration themselves. Of
course that could be quite a significant penalty, if I can put it like that but
could be seen as representing no more than justice to the builder who was not
responsible for it being prolonged that long and who should not be asked to pay
for more than the costs of a six days’ arbitration. It is even
unnecessary to express views as to the merits because it was clearly a matter
which the arbitrator was entitled to take into account, that’s what he
was there for. He was the person who conducted the arbitration and heard all
the evidence and
-8-
who
concluded who was at fault in this respect and he was perfectly entitled so to
do. It is the clauses which follow which create the real problem in this case
where he goes on to say that “the owners shall pay 9/15s
of
the builder’s costs in the arbitration including the preliminary costs
etc.” Of course, that finding inevitably meant that not merely were the
owners, who it must be remembered had succeeded in the arbitration, going to
have to pay their own costs of 9 days but they were going to have to pay in
addition the builders’ costs of those 9 days. It was that order as to
costs which led to the present proceedings which were commenced again by
special summons seeking to set aside that part of the award and it came on
before O’Sullivan J on the 28th of July of last year as I have said. In
an ex tempore judgment he said that, having considered the matter, he would
make an order enforcing so much of the award as ordered the builder to pay
6/15s of the plaintiffs’ taxed costs and ancillary orders in respect of
that, but then went on to say and this is the crucial part of his judgment:
“I
make an order remitting so much of the award of the arbitrator as granted costs
to the builder to the arbitrator, because of the High Court judgment delivered
by Mr Justice Barron on the 30th
-9-
April
1996 which has in my view determined the matter and held that, an open offer of
£20, 000 having been made by the owners, it is not open to the arbitrator
to treat that offer as withdrawn. I therefore order that such part of the said
award as determined that the owners should pay 9/15 of the builders’
taxed costs in the arbitration including the costs of preliminary hearings in
the amended counterclaim on a party and party basis and that the owners should
pay 9/15 of the costs of the award of £29,137.82 inclusive of VAT in the
arbitration be and the same are set aside so that this matter be remitted to
the arbitrator to make such award as he considers proper having regard to the
court’s findings herein.
From
that order the builder has appealed to this court and Mr. Kilty on his behalf
submits in effect that this was an exercise by the arbitrator of his discretion
as to costs and that is it is one that shouldn’t be interfered with by
this court because as he rightly says, of course, the arbitrator is the person
who is seised of this matter. He was the person who heard the whole arbitration
and he refers, of course, to the well known jurisprudence of this court in
relation to arbitrations that this court must under no circumstances act as an
appeal from
-10-
findings
by arbitrators and can only set aside awards by arbitrators, where the parties
have agreed to take that course of going to arbitration or are statutorily
obliged to go to that particular form of dispute resolution in limited and
defined circumstances. It is an inevitable consequence that they must take the
arbitrator’s award as they find it and they can only ask the High Court
to interfere where it appears that the arbitrator has in some way misconducted
himself or made an error as to his jurisdiction or an error of law which is
patent on the face of his award.
For
their part the owners don’t quarrel with the finding of the High Court
judge and they are obviously satisfied with the order setting aside so much of
the award as gave costs against them but it is an important feature of the last
act of this protracted drama, if I can call it, that, that they don’t
claim or contend that the matter should go back to the arbitrator so that they
should be awarded more costs than the six days that he thought proper to award
to them and there is no cross appeal from Mr. Justice O’Sullivan’s
order.
So
we are solely concerned then with whether the High Court judge was right in
setting aside so much of the arbitrator’s award as actually awarded costs
of the nine days to the builder as against the owners. Now I am satisfied that
the arbitrator was in error and it was indeed an error which - in the technical
sense in which that word is used in relation to arbitrations and I want to
emphasise that could be described as misconduct but not, of course, intentional
-11-
misconduct
by the arbitrator. He appears not to have appreciated, it in quite clear, the
significance of the finding by the High Court that the open offer which had
been made was an unconditional open offer and in general should attract the
consequence of costs following the event subject to any discretion there might
be as to the extent of those costs or any penalty the plaintiffs might suffer
because of any contribution they made to a protracted hearing. He doesn’t
appear to have understood that properly because it is quite clear that the
parties didn’t really get an opportunity to address him on that crucial
matter. The hearing before him appears to have been in effect a discussion as
to whether indeed this was an unconditional offer, what the effect of such an
offer was and so on.
In
those circumstances, and bearing in mind that the court should not interfere
with arbitrator’s awards lightly and that the whole disposition of the
court should be against so doing I am nonetheless satisfied that the High Court
was correct in finding that the provision in the award that the owners should
pay 9/15s
of
the costs to the builder, that the owners should bear that very significant
burden of costs was clearly an error, on the face of the award, having regard
to the express finding of the High Court that there had been an unconditional
offer and that the costs were to be determined in the light of that
unconditional offer. Whether it is going too far even in the technical sense to
-12-
describe
that as misconduct in the arbitrator’s part it is probably unnecessary to
say, because when one looks at all the agreed facts it is quite clear that
there was an error on the face of the award in an arbitration the result of
which was that one party succeeded and the other party did not, because that is
the effect of a party failing to beat a lodgment under the law or equally
failing to beat an open offer in an arbitration. It cannot be consistent with
justice that that party should end up paying a significant part of the other
party’s costs of the arbitration which effectively wipes out and more
than wipes out the limited order for costs in his favour. In those
circumstances and on the particular facts of this case I am satisfied that the
High Court was perfectly correct in setting aside that part of the
arbitrator’s award and I would accordingly propose to dispose of the
matter by simply affirming the order of the High Court insofar as it so decided.
The
only other matter that really remains then is as to whether any useful purpose
is to be served by sending it back to the arbitrator to make a final award and
it seems to me, as Mr. Stewart SC has properly and sensibly conceded, that
there is no possible point in its going back to the arbitrator to see can he
get more of the costs of the hearing. Mr. Kilty for his part accepts that,
whatever finding this court makes and, of course, he urges us to set aside that
finding by the High Court and restore the arbitrator’s original award, at
this stage it is in no one’s interest that the matter should return to
the arbitrator. I
-
13 -
am
satisfied that, in a case like this, where the court is doing no more than
simply setting aside part of the arbitrator’s award and confirming it in
all other respects, the situation in this court at all events, whatever the
situation has been in High Court, is that complete finality should be achieved
so far as that is humanly possible, Accordingly, I would dispose of the appeal
by dismissing the appeal but varying the order of the learned High Court judge
by deleting so much of it as remitted the matter to the arbitrator for a
further hearing.
© 1998 Irish Supreme Court
BAILII:
Copyright Policy |
Disclaimers |
Privacy Policy |
Feedback |
Donate to BAILII
URL: http://www.bailii.org/ie/cases/IESC/1998/9.html