BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £5, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
Scottish Court of Session Decisions |
||
You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> Wiltshier Construction (Scotland) Ltd v. Drumchapel Housing Co-operative Ltd [2003] ScotCS 21 (29 January 2003) URL: http://www.bailii.org/scot/cases/ScotCS/2003/21.html Cite as: [2003] ScotCS 21, 2003 SCLR 188 |
[New search] [Help]
FIRST DIVISION, INNER HOUSE, COURT OF SESSION |
|
Lord President Lord Marnoch Lord Macfadyen
|
XA28/02 OPINION OF THE COURT delivered by LORD MACFADYEN in THE CASE FOR THE OPINION OF THE COURT OF SESSION under the Administration of Justice (Scotland) Act 1972, section 3 between WILTSHIER CONSTRUCTION (SCOTLAND) LIMITED Appellant; and DRUMCHAPEL HOUSING CO-OPERATIVE LIMITED Respondent: _______ |
Act: Glennie, Q.C., Masons; for the Appellant
Alt: Howie, Q.C., MacRoberts; for the Respondent
29 January 2003
Introduction
The Contract
"The Contractor shall be responsible for the security of the site and of all work done by him from the Date of Possession of the Site until the date of handover of the site or any such sections."
Paragraph d. then sets out certain minimum (but not limiting) measures to be taken by the contractor. Among the sub-paragraphs of paragraph d. particular reference was made in argument to 7 and 8. Sub-paragraph 7 indicates that in some instances security 24 hours a day may be appropriate, and states:
"The Contractor should make allowance for this level of security if this proves necessary".
Sub-paragraph 8 refers to closed circuit television and in that connection repeats the language quoted above from sub-paragraph 7. Similar language is again used in sub-paragraph a) of a later passage setting out the employer's specific requirement that security services be provided "at all times". The clause ends with the following passage:
"The Contractor is recommended to visit the site: examine and ascertain for himself the specific nature and level of security requirements which may influence or affect his tender. Any monetary or other claims made by the Contractor on the grounds of want of knowledge of any or all of the matters noted under Site Security will not be entertained by the Employer."
The Appellant's Pleadings
"... the time taken to carry out the Works and the manner and cost of their being carried out was radically altered as a result of vandalism, theft, damage and fire-raising greatly in excess of what could reasonably have been foreseen by an experienced contractor in the position of the [appellant], and greatly in excess of what was foreseen by the [appellant], as a reasonable and experienced contractor."
There follows specification of the level of vandalism experienced at the site. It is then averred:
"Despite the [appellant's] best efforts, due to the nature and extent of the vandalism, theft, damage and fire-raising experienced on site, it is both impractical and impossible for the [appellant] to identify the nexus between the said incidents of lawlessness and corresponding heads of loss suffered by it."
"... the actings of the respondent, and its funder, Scottish Homes, were such that it was clear that they wished the [appellant] to remain on site and carry out the works, notwithstanding this change in the time, manner and cost of carrying them out."
Re-phasing was proposed, but rejected by the respondent. The problem was raised with a Mr Hastie of Scottish Homes. He was told that the appellant was considering determination of the contract. It is not said under which provision of the contract they were considering taking that step, or whether that was made clear to Mr Hastie. It is averred that he:
"... noted that Scottish Homes could provide additional funding for the ... project in the same way as they had on another problematic site ...".
It is averred that at a meeting representatives of the appellant expressed concern about the problem, and advised the architect of the possibility of their determining the contract. Again there is no further specification of the provision under which the appellant was contemplating acting. At a later meeting the appellant's representatives were "given to understand" by a representative of the respondent:
"... that the issue of significant losses being incurred by the [appellant] on the project could be addressed by the involvement of Scottish Homes."
The contention is then advanced that:
"In the whole circumstances, the respondent thereby effectively requested that the [appellant] remain on site and carry out the works notwithstanding the radical change in the time, manner and cost of doing so. ... The [appellants] carried out the said radically different works."
"The parties did not, however, address the terms on which the [appellant] would be paid in respect of these radically different works, nor the time for completion of those works. Accordingly, in substitution for the original provisions of the Contract as to time for completion and remuneration, there was implied into the Contract an entitlement that the [appellant] would be required to complete the said radically different works within a reasonable time, and that the [appellant] would be paid reasonable remuneration in respect thereof."
There then follows an alternative contention that in the circumstances the respondent has been unjustly enriched by the appellant's execution of the "radically different" works, and that it is equitable that that enrichment should be reversed.
The Arbiter's Proposed Decision
"1. |
Notwithstanding the [appellant's] arguments to the contrary, Site Security, as called for and presented in the contract documents, is a risk item to be borne fully by the contractor. Specifically, Clause 9.17(c) in the preliminaries in the Bill of Quantities places the risk expressly on the contractor. This absolute nature of the responsibility for this risk is not restricted by the wording of Appendix iii, including the handwritten insertion of the phrase 'as required', nor by the wording of clause 9.17(d). |
|
2. |
It follows that, irrespective of the allegedly higher than normal incidence of vandalism and lawlessness - and it is said that this was of an extreme nature - delays, loss and expense arising therefrom and not otherwise reimbursable under the contract, are and remain the responsibility of the contractor." |
"In the first place I do not accept that in the absence of a breach or termination of the contract a change in the time, manner and cost of carrying out the contract work is a change, which entitles the [appellant] to any payment, which goes beyond what is expressly provided under the contract. I do not accept that there is any basis for an implied right to reasonable time and reasonable remuneration in favour of the contractor in these circumstances. I am persuaded of this in particular by [certain authorities] and by the express contractual allocation in this case of responsibility for security risk to the contractor.
In the second place, I do not consider that there are averments in the pleadings, which form the foundation for any case that there was express alteration to the contract. The [appellant] made numerous representations to the Respondent both by letter and at meetings. The most encouraging response it received according to the pleadings was that the issue could be addressed by the involvement of Scottish Homes. That does not amount to an averment of an agreement to alter the contract. The [appellant] says that the Respondent effectively requested it to remain on site and carry out the contract works. In the circumstances that was no more than its existing contractual duty."
The arbiter then proceeded to reject the contentions that what the appellant had to do was outside the scope of the contract, or that there was any renegotiation of the contract, or that any new terms as to time and payment were implied into the contract.
"The contract works remained the contract works and, standing my decision on responsibility for the risk associated with site security, it follows that the 'changed circumstances' narrated by the [appellant] were matters which fell to be dealt with within the framework of the contract. ... There is no room for the application of the principle of unjust enrichment."
In section 5 the arbiter rejects the claim that time became "at large".
The Questions of Law
"10.1 |
On its true construction, does the responsibility for security imposed on the Appellant by Clause 9.17 of the preliminaries preclude it, in the circumstances condescended upon, from claiming for payment for the works quantum meruit, et separatim claiming that it was entitled to "a reasonable time" as the period for completion of the contract works et separatim claiming on the basis of unjust enrichment? |
|
10.2 |
Does the fact that the contract was not terminated preclude, in the circumstances condescended upon, the claims made on record by the Appellant for a reasonable time to complete the work et separatim an entitlement to be paid for the works on a quantum meruit basis et separatim payment on the basis of unjust enrichment? If it precludes any of those claims, which does it preclude?" |
The Appellant's Submissions
The Respondent's Submissions
The Appellant's Response
Discussion
(a) The Scope of the Case
(b) Question 1
"The Contractor shall be responsible for the security of the site and of all work done by him from the Date of Possession of the Site until the date of handover of the site ...".
In our opinion, that is an unequivocal and unlimited allocation of responsibility to the appellant for the provision and maintenance of site security. It is true, as Mr Glennie pointed out, that other parts of the clause are concerned in one way or another with the obtaining of information about security requirements. Paragraph b. obliges the contractor to obtain a crime profile of the area from the police "in order that he is fully [cognisant] of the crime level in the area". The last paragraph of the clause contains a recommendation that the contractor visit the site and "ascertain for himself the specific nature and level of security requirements which may influence or affect his tender". It is also true that the last paragraph of the clause contains a declaration that claims made by the contractor "on the ground of want of knowledge" of security matters "will not be entertained by the Employer". We do not consider, however, that it is correct to infer from those references to the acquisition of knowledge and the consequences of want of knowledge that the contractor's responsibility is limited to making provision for security measures against risks reasonably foreseeable by an experienced contractor. Other parts of the clause set minimum requirements which are expressly said not to limit the measures which the contractor must take (paragraph d.), and within that paragraph certain of the requirements emphasise that the contractor must make allowance for such level of security as proves necessary (sub-paragraphs 7 and 8). When account is taken of the whole provisions of clause 9.17, we are of opinion that it contains nothing which limits the responsibility of the contractor for site security. We do not consider that that involves requiring the contractor to perform the impossible by taking measures which will prevent all breaches of security, however unforeseeable. On the contrary, the clause functions as a provision allocating risk. The contractor can protect himself to some extent by obtaining as much information as he can about what measures are likely to be necessary to maintain site security. The cost to him of those measures will no doubt inform the amount which he enters in the tender summary as "cost of preliminaries" (although how far it is reflected therein is, in the context of competitive tendering, a matter for his judgment). But once his tender has been accepted and the contract has been entered into, the risk of loss and expense caused by breaches of site security in our opinion remains with him in terms of clause 9.17c., whether the loss or expense results from foreseeable events or unforeseeable events.
(c) Question 2