BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £5, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
Scottish Court of Session Decisions |
||
You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> Mowlem (Scotland) Ltd v. Inverclyde Council [2003] ScotCS 248 (01 October 2003) URL: http://www.bailii.org/scot/cases/ScotCS/2003/248.html Cite as: [2003] ScotCS 248 |
[New search] [Help]
FIRST DIVISION, INNER HOUSE, COURT OF SESSION |
|
Lord President Lord Marnoch Lord Wheatley
|
XA29/02 OPINION OF THE COURT delivered by THE LORD PRESIDENT in CASE FOR THE OPINION OF THE COURT OF SESSION under the Administration of Justice (Scotland) Act 1972, Section 3 in arbitration between MOWLEM (SCOTLAND) LIMITED Claimant and Respondent; against INVERCLYDE COUNCIL Respondent and Appellant: _______ |
Act: Currie, Q.C.; DLA (Claimant and Respondent)
Alt: Reid, Q.C.; Masons (Respondent and Appellant)
1 October 2003
[1] This arbitration arises out of a building contract for the construction of a local authority leisure complex in Greenock. The appellant, to whom we will refer as "Inverclyde", was the employer and the respondent in the arbitration. The respondent in this court, to whom we will refer as "Mowlem", was the main contractor and the claimant in the arbitration. In the case which has been brought before us at the instance of Inverclyde, the arbiter has stated questions of law for the opinion of this court in two parts. Part A relates to the competency of the case. Part B relates to substantive issues in the arbitration. [2] We deal first with the procedural questions to which Part A relates. At the outset we should point out, while it might be argued that it would have been more appropriate for these questions to have been the subject of a separate hearing directed to whether the court should entertain the case, parties were agreed, and the court was content to accept, that these questions should be argued and decided along with the substantive issues to which Part B relates. [3] Following the hearing on the substantive matters in this section of the arbitration, the arbiter issued a draft part award on 7 February 2001 and allowed parties until 23 February to make representations. Both parties did so. On 2 March 2001 Inverclyde submitted a Minute requesting that the arbiter state a case in terms of section 3 of the Administration of Justice (Scotland) Act 1972 (the 1972 Act), indicating that they would reassess their position should a further draft decision be issued. The arbiter issued a revised draft award on 6 May 2001. On 21 May 2001 Inverclyde again submitted a Minute asking that the arbiter state a case, on questions which were virtually identical to those contained in their first Minute. The questions related to some of the issues subsequently covered in the present stated case. On 29 June 2001 Inverclyde asked the arbiter whether he intended to state a case or whether they should infer that the arbiter was refusing to do so. In the meantime parties made representations in respect of the draft award issued on 6 May 2001, and in the light of these the arbiter made certain alterations and issued a further draft award dated 2 July 2001. On the same date the arbiter also wrote to parties indicating the detail of the questions he was prepared to state on the issues in the arbitration and requested comments. On 9 July 2001 Inverclyde indicated by fax that in the light of the re-issued draft they would propose to present a further Minute requesting the arbiter to state a case on certain specified questions. The fax continued:-"These questions are essentially the same as those included in our previous Minute. We would request that you clarify that you are prepared to state a case on these questions. If you are not so prepared to state a case on these questions we shall forward the Minute on behalf of the Respondent and it will be then for you to comply with the relevant rules of court in respect of any refusal to state a case on the terms requested."
The arbiter responded on 13 August 2001, saying that he would state questions as stated in his fax dated 2 July 2001 to the parties and not in the form requested by Inverclyde in their fax dated 9 July 2001. On 3 October 2001 Inverclyde submitted a further Minute craving that the arbiter state a case for the Opinion of the Court in terms of section 3 of the 1972 Act, in identical terms to the request dated 9 July 2001. Mowlem asked that the arbiter delay a decision on this request and on 8 October 2001 wrote to the arbiter stating that as the arbiter had on 13 August 2001 refused to state a case on the terms set out in Inverclyde's fax of 9 July 2001, and as Inverclyde had thereafter failed to make an application in terms of Rule of Court 41.8 of the Rules of the Court of Session within fourteen days, the arbiter should now issue his part award in its final form. On 9 October 2001 Inverclyde wrote to the arbiter stating that the arbiter's letter of 13 August was not a refusal to state a case but rather was concerned to query the form of the questions proposed in Inverclyde's fax of 9 July. In these circumstances the arbiter did not sign his part award but stated the present case for the opinion of this court. It is with the status of the fax from Inverclyde dated 9 July 2001 and the arbiter's response dated 13 August 2001 that we are principally concerned.
[4] Thereafter, on 23 October 2001 the arbiter sent Mowlem a copy of the Minute submitted by Inverclyde on 23 October 2001 and indicated that in terms of Rule of Court 41.6(2) it was for Mowlem to decide within fourteen days whether to propose any additional questions for the case. On 30 October 2001 Mowlem replied, repeating their view that Inverclyde's application was out of time, but stating that if that view were wrong they sought to have additional questions stated. Those questions were in general terms directed to the question of the competence and validity of Inverclyde's request for a stated case. [5] Rule of Court 41.5 provides:-"(1) An application for a case for the opinion of the court on any question shall be made by minute setting out the question on which the case is applied for.(2) ...
(a) where the application must be made before the issue of the decision of the tribunal, at any time before the issue of the decision; or
(b) where the application may be made-
(i) after the issue of the decision of the tribunal, ...
within the period mentioned in paragraph (3).
(3) The period referred to in paragraph (2)(b) is -
(a) ...
(b) ... within 14 days after the issue of the decision or statement of reasons, as the case may be."
Further, Rule of Court 41.8 provides that, where the tribunal has refused to state a case, the party whose application has been refused may lodge an application in the Court of Session within fourteen days of the refusal. Rule of Court 41.7 provides that in the event of a refusal there should be sent to the applicant a certificate specifying the date of the refusal and the reasons for the refusal.
[6] Section 3 of the 1972 Act provides:-"(1) Subject to express provision to the contrary in an agreement to refer to arbitration, the arbiter or oversman may, on the application of a party to the arbitration, and shall, if the Court of Session in such an application so directs, at any stage in the arbitration state a case for the opinion of that court on any question of law arising in the arbitration."
".1 Where the Contract Bills provide that certain work measured or otherwise described in those Bills and priced by the Contractor must be carried out by persons named in a list in or annexed to the Contract Bills and selected therefrom by and at the sole discretion of the Contractor the provisions of clause 19.3 shall apply in respect of that list.
.2.1 The list referred to in clause 19.3.1 must comprise not less than three persons. Either the Employer (or the Architect/the Contract Administrator on his behalf) or the Contractor shall be entitled with the consent of the other, which consent shall not be unreasonably withheld, to add additional persons to the list at any time prior to the execution of a binding sub-contract agreement.
.2.2 If at any time prior to the execution of a binding sub-contract agreement and for whatever reason less than three persons named in the list are able and willing to carry out the relevant work then
either the Employer and the Contractor shall by agreement (which agreement shall not be unreasonably withheld) add the names of other persons so that the list comprises not less than three such persons
or the work shall be carried out by the Contractor who may sub-let to a Domestic Sub-Contractor in accordance with clause 19.2.
.3 A person selected by the Contractor under clause 19.3 from the aforesaid list shall be a Domestic Sub-Contractor".
Bill No. 1 provided, at page 1/28, for the notification of the Contract Administrator in the event of there being less than three persons able and willing to carry out the relevant work. It also provided that before the start of the work to which the list related, the contractor must enter into a binding sub-contract agreement and confirm to the Contract Administrator that this had been done, giving the name of the selected sub-contractor.
[21] The part of the specification to which we have referred in paragraph [19] was headed as follows:"H11 CURTAIN WALLING - STRUCTAL (U.K.) LTD.
To be read with Preliminaries/General Conditions
SCOPE OF WORK
The design, supply and installation of curtain walling including structural steel support elements where indicated in the documentation using Structal (U.K.) Ltd. Systems throughout ... "
"Additional preliminaries related to items 0014-0016 (refer Mowlem's letter of 21 DEC 1994).
Defined Provisional Sum for additional steelwork supports to head of cladding at south elevation (refer Statement of Revised Tender - 22 December 1994)".
decided to carry out the remaining work. Mowlem did not at any stage ask the Contract Administrator to take any steps under clause 35 of the contract conditions (which relate to nominated sub-contractors).
[37] In paragraph 42 of the case the arbiter states that the initial question for him was whether, from the outset, the provisions of the contract in relation to curtain walling were such that the curtain walling sub-contract was to be performed by "a named but domestic sub-contractor or by a nominated sub-contractor". The arbiter's view was that, in the light of the fact that none of the named sub-contractors was in a position to carry out the whole of the work involved in the sub-contract "the Contract Administrator by stipulating that Structal (U.K.) systems be used throughout had effectively named the sub-contractor in the contract bills". In paragraph 43 the arbiter states that it was for the Contract Administrator to put into effect the nomination procedure but this had not been done. Having considered what happened after Structal withdrew its tender, the arbiter states the following conclusions in paragraphs 50 and 51:"50. I conclude that upon the withdrawal of Structal the existing provisions as to curtain walling including the purported list of sub-contractors were rendered inappropriate for the purposes of the Contract. By agreement between the Contractor Administrator and Nelson changes were made to the provisions in relation to curtain walling so as to enable it to be carried out by Nelson using a Schuco system and agreement reached as to the price at which Nelson would do the relevant (varied) works. The claimant was only informed after that agreement had been reached as to the identity of the sub-contractor and as to the pricing provision. The Statement of Revised Tender Amount provided by the Quantity Surveyor to the Claimant stated 'Omit' in relation to Curtain Walling Works by Structal UK Limited and 'Add' in relation to Curtain Walling Works by Nelson Tectonics Limited. The acceptance dated 6 January 1995 by the Respondent refers to that acceptance as subject to the terms of the correspondence referred to in the schedule attached hereto. The schedule (B/132) describes its last item of correspondence against the date 21/12/94 as 'Confirmation of revised Tender amount incorporating Nelson Tectonics Limited in lieu of Structal (U.K.) Limited' and is signed by the Director of Administration of the Respondent Mr. John Thompson. This constitutes a naming by the Contract Administrator of the sub-contractor within the meaning of clause 35.1
51. In any event, if the alterations made are not to be taken as the naming of the sub-contractor in the Contract Bills, the Contract Administrator in the verbal agreements and Statement of Revised Tender Amount named Nelson as the sub-contractor and the claimant agreed to that being done signing and returning the Statement of Revised Tender Amount and letter of 21 December 1994".
"Where
.1 in the Contract Bills; or
...
.4 by agreement (which agreement shall not be unreasonably withheld) between the Contractor and the Architect/the Contract Administrator on behalf of the Employer
...
The Architect/the Contract Administrator has, whether by the use of a prime cost sum or by naming a sub-contractor, reserved to himself the final selection and approval of the sub-contractor to the Contractor who shall supply and fix any materials or goods or execute work, the sub-contractor so named or to be selected and approved shall be nominated in accordance with the provisions of clause 35 and a sub-contractor so nominated shall be a Nominated Sub-Contractor for all the purposes of this Contract ... ".
"9. There was a valid agreement between the Contract Administrator and (Mowlem) naming Nelson Tectonics Limited as sub-contractor within the meaning of clause 35.1.4 of the Conditions of Contract?
10. Nelson Tectonics Limited was named as a sub-contractor within the meaning of clause 35 of the Conditions of Contract?
"Performance Specified Work pursuant to clause 42 shall not be provided by a Nominated Sub-Contractor under a Nominated Sub-Contract or by a Nominated Supplier under a contract of sale to which clause 38 refers."