BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
Scottish Court of Session Decisions |
||
You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> APC v Amey Construction Ltd & Ors [2004] ScotCS 182 (23 July 2004) URL: http://www.bailii.org/scot/cases/ScotCS/2004/182.html Cite as: [2004] ScotCS 182 |
[New search] [Help]
OUTER HOUSE, COURT OF SESSION |
|
CA79/02
|
OPINION OF LORD MACKAY OF DRUMADOON in the cause APC LIMITED (in receivership) Pursuers; against (FIRST) AMEY CONSTRUCTION LIMITED, (SECOND) SIR ROBERT McALPINE LIMITED, (THIRD) TAYLOR WOODROW CIVIL ENGINEERING LIMITED and (FOURTH) BARR LIMITED, together trading as "AMEY-ROBERT McALPINE-TAYLOR WOODROW-BARR M6 JOINT VENTURE" Defenders:
________________ |
Pursuers: Keen, Q.C., Mure; Maclay Murray and Spens
Defenders: Moynihan, Q.C., Borland; Masons
23 July 2004
[1] The pursuers are a limited company, which is in receivership. The defenders are also limited companies. All four of the defenders are active in the construction industry. For the purposes of carrying out the works of road construction, to which this action relates, the defenders have traded together as the "Amey-Robert McAlpine-Taylor Woodrow-Barr M6 Joint Venture". It is as constituting the members of that trading entity that the defenders are parties to the present proceedings. [2] In 1997, Autolink Concessionaires (M6) plc ("the Employer") entered into a Design Build Fund Operate Contract with the Secretary of State for Scotland, for the upgrading, operation and maintenance of the M6/M74 motorway from Millbank to Junction 44 on the M6 ("the DBFO Contract"). On 30 April 1997 the Employer entered into a contract with the defenders, for the design, construction and completion of the works involved in upgrading the sections of the motorway covered by the DFBO Contract and certain ancillary and accommodation works ("the Main Contract"). Under the Main Contract, the Operations Commencement Date was 29 July 1997. [3] On 28 July 1997, the defenders issued an Official Order No. TWC/S 87156 ("the Official Order") to the pursuers. The Official Order related to the earthworks and site clearance required in the construction of a section of the motorway in Scotland and ancillary works in Scotland, which were collectively referred to as "Scotland North". That section of motorway ran between Paddy's Rickle and Marchhouse Bridge. The Official Order stated that the pursuers would "Provide all necessary Labour, Supervision, Plant and Materials and carry out the Site Clearance, Excavation, Earthworks, Topsoiling, Structures Excavations, Capping Layer and disposal of Drainage arisings in Scotland North for the sum of £9,000.000". The Official Order was placed subject to various conditions, including that the pursuers would complete and execute a Form of Sub-Contract, incorporating a number of Appendices, to which I will refer later. In this Opinion I intend to refer to the earthworks covered by the Official Order as "Scotland North Earthworks", without in any pre-judging the questions of (a) when and on what terms the pursuers and the defenders first entered into a contractual relationship and (b) the terms of the Sub-Contract, which it is agreed existed between the parties, following the execution, on 4 February 1998, of a Form of Sub-Contract, together with the Appendices and other documents referred to therein ("the Form of Sub-Contract Agreement"). It will be appreciated that once the parties entered into the contractual relationship of Main Contractor and Sub-Contractor, the earthworks that required to be undertaken by the pursuers fell to be regarded as being "Sub-Contract Works". On any view that had occurred by 4 February 1998. Later in this Opinion, I will deal further with the question of whether there may have been a contractual relationship between the parties from an earlier date. [4] During July 1997, and it would appear some days before 29 July 1997, the pursuers began carrying out the Scotland North Earthworks. From that month onwards, interim applications for payment were submitted to the defenders and paid by the defenders. Whilst the first of those applications was submitted on notepaper in the name of APC (Civils) Scotland Limited, subsequent applications appear to have been in the name of the pursuers. From July 1997, the pursuers continued to carry out the Scotland North Earthworks (and such further earthworks as may have been instructed and ordered by the defenders) until 24 September 1998, on which date Joint Receivers were appointed to the pursuers. The pursuers and the Joint Receivers were only prepared to complete the Scotland North Earthworks (and the further earthworks that had been instructed and ordered by the defenders), on the basis of a re-negotiated sub-contract between the pursuers and the defenders. Such a proposal was not acceptable to the defenders. The defenders held the pursuers to be in repudiatory breach of the Sub-Contract that existed between them. On 30 September 1998, the defenders determined that Sub-Contract. [5] Following the determination of the Sub-Contract, the pursuers submitted a claim for payment to the defenders. That claim is set out in documentation which is extensive and complicated. For the purposes of the debate before me the discussion proceeded on the basis that the pursuers' claim was contained in the Final Account Submission Version 2.1 (dated 9 September 2002) and an Addendum thereto, Version 2.1 (Nos. 6/18 and 6/19 of process). Various Appendices and other documents relevant to the quantification of the pursuers' claim against the defenders have also been lodged as productions. [6] The present action was raised on 22 February 2002. In the summons, the pursuers conclude for payment of two sums, £10,441,754 and £2,450,617. The defenders, for their part, have counterclaimed for payment of five sums, £2,955,845.83, £404,496.71, £264,151.17, £429,345 and £1,716,147. After the pleadings were adjusted, a hearing was sought by the parties at which the Court was to be invited to answer a number of questions, the terms of which had been agreed by the parties. I understand that the parties seek answers to those questions, in the hope that such answers may assist in negotiating a settlement of some or all of the financial disputes between them. [7] The questions posed are as follows:Question A
What are the documents that form the Sub-Contract between the parties?
Question B
Do the pursuers have a relevant case for payment of a bonus in terms of Clause 22 of Appendix 1 to the Sub-Contract as averred in Condescendence 8?
Question C.1
Can the pursuers claim under both clause 10 of the Sub-Contract conditions and clause 20 of Appendix 1 in respect of increased quantities of excavated earthworks?
Question C.2
If yes, what elements of such claim fall to be valued under (i) clause 10 of the Sub-Contract conditions and (ii) clause 20 of Appendix 1?
Question C.3
Is the programme TARGET2.PMA 17/Jun/97 listed in Appendix 8 to the Sub-Contract a contractually binding programme, such that, in respect of the earthworks specified therein, the pursuers were obliged to carry out the work specified in respect of material type, quantity, timing and location, all as set out therein?
Question D
Do the pursuers have a relevant claim in respect of those alleged changes for which they have averred no written instruction or written confirmation?
Question E
Do the pursuers have a relevant claim for finance charges as averred in Condescendence 10?
Question F
Is the counterclaim relevant, or pled (whether in the pleadings or in the discs or documents lodged in process) with sufficient specification, to allow it to proceed to probation?
By agreement between the parties, Questions E and F are not to be answered in this Opinion.
[8] It is important to note that during the course of the hearing I was not invited to sustain any pleas in law. All that I was asked to do was to answer those questions as I considered to be capable of answer, on the basis of the submissions I had received. It was recognised by senior counsel for both parties that I might reach the view that certain questions were not susceptible of answer, on the basis of submissions alone and that evidence might be required. [9] In anticipation of the hearing, both parties lodged written Notes of Argument. During the course of the submissions extensive reference was made to certain of the productions that have been lodged. That occurred because both senior counsel found it appropriate to expand upon the factual averments in the written pleadings of their respective parties. Towards the end of the initial hearing I indicated that senior counsel should feel free to lodge written summaries of their respective positions, as to how the questions should be answered, having regard to the submissions and discussions during that hearing. Subsequently the defenders lodged a written Note, to which certain other documents were attached. That Note was subsequently revised on 10 February 2004. The Note summarised the defenders' position during the hearing. However, under reference to the documents attached to the Note, the Note also sought to expand on the factual and legal arguments advanced during the hearing. That was taken a stage further, by additional oral submissions, which senior counsel for the defenders delivered on 11 February 2004. The pursuers for their part lodged a written Response in reply to the defenders' Note. The initial version of that written Response was lodged before I heard the additional oral submissions from senior counsel on 11 February 2004. Subsequently, the written Response on behalf of the pursuers was adjusted to 10 March 2004. Both the Note for the defenders and the Response for the pursuers both contain detailed factual information relating to certain aspects of the Sub-Contract Works, which were mentioned during the course of the oral submissions, including ISC 37, Earthworks Schedules, Mass Haul Charts issued by the defenders, and road box excavations. The terms of the defenders' Note, the further submissions I heard on 11 February 2004, and to a lesser extent the terms of the pursuers' Response, all serve to illustrate the difficulty of focussing questions, whether of law or of fact, that are susceptible of answer, before the full facts of a complicated dispute have been established in evidence. [10] During the course of the original hearing, I raised with counsel for both parties the general approach I might take to answering to the questions that had been posed. Both counsel were agreed that what the parties were looking for were the answers themselves, rather than summaries of the submissions I heard, extensive reference to authority or detailed explanation of the reasoning behind such conclusions as I felt able to reach. As best I can, I have sought to follow that approach.[11] Before I turn to deal with the individual questions, it may be helpful if I indicate that in addressing the issues that have been raised, I found considerable assistance in what was said by Lord Hoffman in Investors Compensation Scheme Limited v West Bromwich Building Society [1998] 1 All E R at pp.114e - 115 f and Lord President Rodger in Bank of Scotland v Dunedin Property Investment Co Ltd 1998 SC 657 at p 661d-e and 665d-g. I refrain from quoting those passages verbatim. They both emphasise that when interpreting the provisions of a written contract a court is entitled to have regard to the full factual background and circumstances in which the language in the contract was agreed to.
Question A What are the documents that form the Sub-Contract between the parties?
[12] This question raises the issue of which documents "form the Sub-Contract between the parties". That question unfortunately begs a number of other questions, which have not been formally posed, but which were touched upon during the course of argument. Those questions arose despite the fact that the written pleadings of neither party assert that the parties had entered into a contractual relationship prior to 4 February 1994. The additional questions include (i) when the parties first entered into a contractual relationship with each other, (ii) if they did so prior to 4 February 1998, when that occurred and on what terms did the parties contract, (iii) whether the terms of any initial sub-contract were amended before 4 February 1998 and (iv) whether the terms of any sub-contract between them were amended when the parties executed the Form of Sub-Contract Agreement on 4 February 1998. [13] In their written pleadings the pursuers aver that in February 1998 the parties entered into a "written Sub-Contract" for the provision by the pursuers, as sub-contractors, to the defenders, as main contractors, of labour, supervision, plant and materials and the carrying out by the pursuers for the defenders of site clearance, excavation, earthworks, top soiling, structures excavations, capping layer and disposal of drainage arising in relation to the M6/M74 motorway. The pursuers aver that the Sub-Contract was constituted by (i) a written order (No. TWC/S 87156) dated 28 July 1997 issued to the pursuers by Taylor Woodrow Construction Limited on behalf of the defenders ("the Official Order"), (ii) the Conditions of Order attached thereto, (iii) minutes of meetings among representatives of the pursuers and the defenders held on 14 August 1997 and 7 September 1997 and (iv) a Form of Sub-Contract entitled "M6 CONSTRUCTION WORKS/Form of Sub-Contract Agreement SUB/M6/Sub-Contract Ref:- EARTHWORKS 2 / (PADDY'S RICKLE TO MARCHHOUSE BRIDGE)" dated 4 February 1998, together with the appendices thereto. [14] The defenders, for their part, aver that the Sub-Contract was constituted by the Form of Sub-Contract Agreement executed on 4 February 1998 alone, that document having incorporated the terms of the documents specified in its Second Schedule, which include the minutes of the meetings on 14 August 1997 and 14 September 1997. In an effort to avoid confusion, I shall refer to the document executed 4 February 1998, including all the appendices and other documents referred to in its Second Schedule, as being "the Form of Sub-Contract Agreement", that being a term which appears on its front cover. All of the documents referred to in the pursuers' pleadings were lodged as productions. [15] Taking the documents in chronological order, the Official Order is dated 28 July 1997. It was sent on that date to the pursuers, together with a version of the Form of Sub-Contract. As I have indicated, that Order was to the effect that the pursuers should "provide all necessary Labour, Supervision, Plant and Materials and carry out the Site Clearance, Excavation, Earthworks, Topsoiling, Structures Excavations, Capping Layer and disposal of Drainage arising in Scotland North for the sum of £9,000,000." The Official Order provided that it was subject to certain conditions, which included the "due and proper conclusion of the enclosed Form of Sub-Contract", incorporating the various appendices referred to therein. The Official Order provided that the pursuers were required to confirm acceptance of the Agreement by returning the Form of Sub-Contract to Taylor Woodrow Construction Limited, duly completed. Paragraph 3 of the Official Order provided that:"3. The works are to be carried out in accordance with the Programme ref. TARGET2.PMA17/JUN/97 and all other documentation listed in Appendix 8 of the enclosed Sub-Contract Agreement."
Question B
Do the pursuers have a relevant case for payment of a bonus in terms of Clause 22 of Appendix 1 to the Sub-Contract as averred in Condescendence 8?
[28] The relevant provisions in the Form of Sub- Contract Agreement are as follows:Appendix 1
Clause 20 End of Contract Bonus
If the Contractor earns a bonus from the Employer for completing the Contract early then the Contractor will pay the Sub-Contractor a corresponding bonus in accordance with the attached schedule. This will only be payable to the Sub-Contractor if and when the Contractor receives payment."
....
Appendix 7
SCHEDULE OF POTENTIAL SUB-CONTRACTORS BONUS PAYMENTS
Further to clause 22 of Appendix 1 the Sub-Contractor will be paid a bonus if and when the Contractor receives payment calculated from the following schedule. The Sub-Contractor shall only be paid if the Contractor receives payment. No claim will be made by the Sub-Contractor for whatever reason if they do not receive payment.
POTENTIAL BONUS EARNING |
EARTHWORKS |
SUBCONTRACT |
SCOTTISH NEW WORKS |
|||||
BONUS DETAIL |
CONTRACT |
TARGET |
NO OF WEEKS |
NO OF DAYS |
BONUS |
BONUS |
||
PROGRAMME |
PROGRAMME |
EARLY |
EARLY |
PAYMENT |
DUE |
|||
PERIOD (WEEKS) |
PERIOD (WEEKS) |
PER DAY |
£ |
|||||
1. Early Completion of New Scottish |
||||||||
Works |
121 |
92 |
29 |
203 |
201 |
40,803 |
||
2. Early Permit to Use Paddies (sic) |
||||||||
Rickle to Beattock |
115 |
92 |
23 |
161 |
1,290 |
207,690 |
||
3. Early Permit to Use Beattock to |
||||||||
Cluechbrae |
96 |
73 |
23 |
161 |
356 |
57,316 |
||
4. Additional Bonus for Scot North |
||||||||
PTU achieved before Scot South |
0 |
0 |
0 |
0 |
378 |
0 |
||
TOTAL POTENTIAL |
305,809 |
"When a party to a simple contract, upon a breach by the other contracting party of a condition of the contract, elects to treat the contract as no longer binding upon him, the contract is not rescinded as from the beginning. Both parties are discharged from further performance of the contract, but rights are not divested or discharged which have been unconditionally acquired. Rights and obligations which arise from partial execution of the contract and causes of action which have accrued from its breach alike continue unaffected."
Question C.1 Can the pursuers claim under both clause 10 of the sub-contract conditions and clause 20 of Appendix 1 in respect of increased quantities of excavated earthworks?
[45] The provisions of the Form of Sub-Contract Agreement that are relevant to this Question are as follows:
"Clause 1(1)(a)
'Change' means a variation in the design, quality or quantity of the Sub-Contract Works and may include but not be limited to additions, substitutions, alterations in design, properly ordered by the Secretary of State for Scotland or the Department's Agent, or the employer or a contractor.
....
Clause 1(1)(bb)
'Sub-Contract Works' means the works described in the documents specified in the Second Schedule hereto and any further works instructed as a change in accordance with the sub-contract.
....
Clause 9(1)
A Sub-Contractor shall make such Changes to the Sub-Contract works, whether by way of addition, modification or omission as may be:-
(a) ordered by the Secretary of State for Scotland's Agent or the Employer under the main contract and confirmed in writing to the Sub-Contractor by the contractor; or
(b) agreed to be made by the Employer and the Contractor and confirmed in writing to the Sub-Contractor by the contractor; or
(c) ordered in writing by the Contractor.
....
Clause 9(3)
Save as aforesaid a Sub-Contractor shall not make any alteration in or modification to the Sub-Contract Works.
....
Clause 10
.... "
Clauses 12 and 20 of Appendix 1 provide:
"12 Schedule of Rates
When written changes are issued pursuant to the terms of the Sub-Contractor (sic) by the Contractor they shall be valued at the rates included within the schedule of rates attached to this sub-contract where ever possible. These rates are total rates and are deemed to be fully inclusive rates which shall require no payment whatsoever for the works concerned.
20 Changes in Quantities
If the total final volume of excavations carried out by the Sub-Contractor increases or decreases by more than 10% from the attached earthwork schedules, the Sub-Contract price will be increased or decreased respectively, any adjustment in the Sub-Contract Price by way of increase or decrease shall be shared equally by the Contractor and the Sub-Contractor, as follows:
i) Sub-Contract sum divided by the excavation quantity in attached earthwork schedule = rate of m3 of excavation.
ii) Rate for m3 of excavation x increase or decrease in volume excavation (over the 10%) = value of adjustment.
iii) Increase or decrease in the Sub-Contract Price = value of adjustment x 50%.
This adjustment will be fully inclusive of all costs whatsoever."
Question C.2 If yes, what elements of such claim fall to be valued under (i) clause 10 of the sub-contract conditions and (ii) clause 20 of Appendix 1?
[60] This question proceeds on the premise that I have answered Question C.1 in the affirmative. The earlier question relates to "increased quantities of excavated earthworks". The pursuers' starting position in relation to the present question is that it is for them to establish that the additional works claimed for, in respect of increased quantities of excavation, were included within "authorised Changes" or should be deemed to be treated as "authorised Changes". The pursuers concede that when those issues are addressed, it will be open to the defenders to argue that, having regard to the provisions of Clause 2.(8)(a) and Clause 11.(1)(d), or indeed other provisions of the Sub-Contract between them, particular Items or constituent parts of the Items in the Final Account Submission should not be held to be "Changes", within the meaning of Clause 1.(1)(a), that have been "authorised" under reference to the provisions of Clause 9. Issuing "detailed design information", as envisaged by Clause 11.(1).(d), is one thing. Ordering an "authorised Change", constituting a variation in the design, quality or quantity of the Sub-Contract Works is another.
[61] Complex issues of fact may arise in determining whether an "authorised Change" has been ordered, or should be deemed to have been ordered, in terms of Clause 9 of the Sub-Contract. In respect of those issues the onus of proof will be on the pursuers. It certainly should not be assumed that the Court will be satisfied that every difference as to the quantities of materials, the movement of materials and the timings of particular item of earthworks specified in Mass Haul documentation will be sufficient to constitute an "authorised Change", ordered in terms of the provisions of Clause 9. Unless an item of work has been, or falls to be treated as having been, ordered by the defenders, as an "authorised Change" in terms of the provisions of Clause 9, the provisions of Clause 10 will have no application. [62] In my opinion, the pursuers were also correct to concede that a valuation of an authorised Change, in accordance with the provisions of Clause 10, would require to take account of any reduction in the Sub-Contract Works. [63] The defenders responded to the pursuers' position by asserting that the pursuers have not made clear which elements of their claim they have valued under each of the clauses upon which they seek to rely. The defenders submit that no consistent explanation had been advanced by the pursuers as to the manner in which the Pursuers' claim has been valued and that Item 3 of the pursuers' Final Account Submission (No. 6/18 of Process) "remains a mystery". Those submissions were developed by attacking the approach to valuation that the pursuers have adopted in Item 3 of their Final Account Submission (No. 6/18 of Process). [64] Having read through the Final Account Submission Version 2.1 (No.6/18 of Process) more than once, I have reached the view that, at this stage in the action, I could not, and indeed should not, hold that the pursuers' statement of claim, as set out in the Final Account Submission, with its accompanying Addendum and Appendices, is irrelevant. Apart from any other considerations I am not being invited to sustain any pleas-in-law. In my opinion, the pursuers' pleadings and the Final Account Submission provides adequate notice of the legal and factual bases of the individual Items making up the pursuers' claim, the extent to which individual Items in the claim are based on the provisions of Clauses 9 and 10 of the Form of Sub-Contract and the extent to which, if at all, the claim is based on the provisions of Clause 20 of Appendix 1 to the Form of Sub-Contract. In that regard it is important to bear in mind that this action has been raised as a Commercial Action, to which the more traditional strictures of written pleading do not apply. The defenders may well wish to challenge much that is set out in Items 3 and 4 of the Final Account Submission (No. 6/18 of Process), but in my opinion it cannot be said that the pursuers have not given an appropriate level of notice as to the legal and factual bases for their claim and, in particular, how they identify and seek payment in respect of the individual Items that make up that claim. [65] As I have already observed, the question whether the issue to the pursuers of particular documents, such as Mass Haul Revisions and Revised Target Programmes, added to, altered or otherwise modified the Sub-Contract Works, which the pursuers had undertaken to carry out, involves questions of fact and questions of law that could not be determined after a hearing of the nature that has taken place. In particular, I could not at this stage determine whether the pursuers are correct to assert, as they do at page 25 of No.6/18 of Process, that various documents, which they detail there, constitute orders in writing in terms of Clause 9(1)(c) of the Form of Sub-Contract Agreement. Likewise, it would not be appropriate for me to hold that because documents issued by the defenders contained details of what could be described as "detailed design information" that automatically means that the works involved in implementing the development of the detailed design could not and did not fall within the scope of the provisions of Clause 9 and Clause 10 of the Form of Sub-Contract Agreement. [66] As I have indicated, how the pursuers have chosen to quantify or value the various items of work constituting their claim involves questions of law and fact. Such questions are additional to those as to whether the items making up the pursuers' claim attract payment under Clause 9, which is to be valued under the provisions of Clause 10. That such additional questions arise is well illustrated by the approach to valuation that the pursuers outline, on page 35 of their Final Account Submission, under reference to Clause 10, for the haulage of materials and by the detailed criticisms of that approach that the defenders have raised as to use made by the pursuers of the rates contained within the Schedule of Sub-Contractors Rates, set out in Appendix 6. The pursuers submit that when they could use Schedule 6 rates they have done so. On the other hand, they contend that there are items of work to which such rates are not applicable. In respect of those they have set out their approach to determining valuations that are "fair and reasonable". [67] There is clearly a dispute between the parties as to the particular items of work to which the Schedule 6 rates could be applied. Accordingly, even when it has been resolved (by agreement between the parties or by decision of the Court) which particular items of work fall be to valued in terms of Clause 10, important questions of fact and law will remain as to the extent to which the Appendix 6 rates could or should be applied in the valuation of individual items of work. On the basis of the information placed before me, by way of submission and reference to the productions, I do not consider that it would be appropriate for me to consider issues such as the procedure by which and the basis upon which the Court should determine the additional payment, if any, which the pursuers would be entitled to receive for items of work such as (a) the haulage, between two points specified in an Earthworks Schedule, of a greater quantity of material than was provided for in the Schedule, when it was originally issued, or (b) the haulage of a quantity of material, provided for in an Earthworks Schedule, over a greater distance than that specified in the Schedule, when it was originally issued. [68] If such questions of law and fact remain in dispute, then proof will be necessary. In my opinion, the questions that arise could not be resolved without evidence being heard. The submissions made by both senior counsel in respect of the Item of Work CN1, on Page 47 of No. 6/18 of Process, confirm that view. Under reference to various documents placed before me, including an Instruction to Sub-Contractor (ISC.37), dated 28 October 1997, (No. 6/33 of Process), I was taken through what was alleged to have happened following the excavation of 121,000 m of peat between Chainages 2,800 to 4,800 and invited by the defenders to determine that particular element of the pursuers' claim was irrelevant, on the basis that it was unclear whether the claim was one for an addition to the Sub-Contract price or one based on additional costs, which had been calculated on Schedule 6 rates, relating to price. As the submissions of both senior counsel included assertions of fact, which the other did not accept, I am very firmly of the view that I should not accede to the defenders' submission. Like all of the individual elements of their claim, which are set out in Item 3 of No. 16/18 of Process, the determination of whether the pursuers are entitled to recover the sum they claim in respect of the works referred to in ISC.37 involve questions of fact as well as questions of law. They cannot be resolved at this stage. What the pursuers are inviting the Court to accept is that Item 3 of No.6/18 of Process constitutes a fair and reasonable valuation, in terms of Clause 10, of items of work that (a) the pursuers carried out, (b) were not within the Sub-Contract Works, as originally defined, (c) constitute "authorised Changes" in terms of Clause 9, either explicitly or implicitly ordered by the defenders, and (d) are not claimed for in Item 4 of No.16/18 of Process. [69] As I have already indicated, I consider that the application of the provisions of Clause 20 of Appendix is a separate exercise to that involving Clauses 9 and 10. In my opinion, that separate exercise falls to be carried once it is possible to reach a determination as to the total volume of excavations that has been carried out by the pursuers. Once that important figure has been determined, it can be compared with the amount specified in the original Earthwork Schedules. Carrying out that exercise does not require checking on whether or not any additional quantities excavated have been authorised or have attracted payment for the pursuers under other provisions of the Sub-Contract. All that requires to be determined is the total quantity of the excavations actually carried out by the pursuers in executing their obligations as Sub-Contractors.Question C.3 Is the programme TARGET2.PMA 17/Jun/97 listed in Appendix 8 to the sub-contract a contractually binding programme such that, in respect of the earthworks specified therein, the pursuers were obliged to carry out the work specified in respect of material type, quantity, timing and location, all as set out therein?
[70] I answer that question in the affirmative.
[71] Whether or not the Official Order, dated 28 July 1997, is part of the Sub-Contract between the parties, the terms of numbered paragraph 3 of that Order are of significance. They provide:"3. The works are to be carried out in accordance with the Programme ref.TARGET2.PMA 17/Jun/97 and all other documentation listed in Appendix 8 of the enclosed Sub-Contract Agreement."
That programme, which parties variously referred to during the submissions as being the "Overall Programme", the "Contract Programme" and the "Target Programme", and I shall, for sake of convenience, refer to as the "Overall Programme", that being the title of the document, when it was originally produced, bearing the reference "TARGET2.PMA17/Jun/97". It should be noted, however, that in the pursuers' Final Account Submission (No. 6/18 of process) the programme is referred to as the "Contract Programme".
[72] The Overall Programme was mentioned in the Form of Sub-Contract that was sent to the pursuers with the Official Order dated 28 July 1997. Moreover, the Official Order explicitly provided that the pursuers were to carry out the "works" in accordance with (emphasis added) that particular programme and all other documentation listed in Appendix 8 of the Form of Sub-Contract. [73] As I have already mentioned, the Sub-Contract Works are defined in Clause 1(1)(bb) of the Form of Sub-Contract Agreement as "the works described in the documents specified in the Second Schedule hereto and any further works instructed as a change in accordance with the Sub-Contract". Appendix 8 is one of the documents specified in the Second Schedule and the Overall Programme is one of the documents specified in Appendix 8. In my opinion, therefore, the Overall Programme is one of the "Further Documents forming part of the Sub-Contract" (cf. the opening words of the Second Schedule). As such, it is one of the documents from which the pursuers, as Sub-Contractors, were responsible for ascertaining the full extent of the Sub-Contract Works (cf. Clause 10.(3)). [74] I agree with the submission made on behalf of the pursuers that the purpose of the Overall Programme was not limited to specifying the total period within which the Sub-Contract Works required to be completed (cf. Third Schedule (C)). It had a part to play, as had other documents, in describing and defining the Sub-Contract Works. In my opinion, that part was not limited to defining when the Sub-Contract Works could begin and by when they should be finished. In my opinion, if, by the issue of Mass Haul Revisions and amended Target Programmes, the pursuers were required to carry out earthworks, which were different from those provided for in the Overall Programme, it is a matter for determination, in each instance, whether the earthworks specified constituted a "Change", ordered, or deemed to have been ordered, in terms of Clause 9, or whether the defenders were entitled to require or direct the pursuers to carry out those earthworks, by virtue of some other provisions of the Sub-Contract, including those to be found in Clause 2.(8), Clause 8.(2), Clause 11.(1)(d) and Appendix 2. [75] The language of paragraph 3 of the Official Order could be viewed as being couched in more peremptory terms than those to be found in the Third Schedule and Condition 6 of Appendix 1 of the Form of Sub-Contract. Whether that is so, the terms of paragraph 3 support the view that when the pursuers embarked upon the works covered by the Official Order, they began to do so (and from the documentation available may well have agreed to do so) on the basis that they should do so in accordance with the terms of the Overall Programme. Whether the execution of the Form of Sub-Contract Agreement on 4 February 1998 involved the creation of a new contract, where no contract had previously existed, or whether it involved the replacement of an existing contract, with a new contract, or whether it involved the amendment of an existing contract, the factual circumstances in which the Form of Sub-Contract Agreement were signed on 4 February 1998 include (a) that the pursuers had been ordered by the defenders to carry out the earthworks in accordance with what the Overall Programme laid down, (b) that the pursuers appear to have undertaken to do so and (c) that the pursuers had been attempting to do so. [76] In any event Clause 2(1) of the Form of Sub-Contract Agreement provides that the defenders shall execute, complete and maintain the Sub-Contract Works in accordance with the Sub-Contract. Clause 6 of Appendix 1 also provides that "(t)he programme for the Sub-Contract works is in accordance with the enclosed programme schedule". In my opinion, as the Overall Programme formed part of the Sub-Contract, those provisions required the defenders to execute the Sub-Contract Works in accordance with the Overall Programme. I agree with senior counsel for the pursuers that if the pursuers did not comply with the Overall Programme they could have been in breach of contract and could have been liable in damages for any loss suffered by the defenders as a consequence of such breach. Likewise I agree that it was open to the defenders to issue changes to the Overall Programme, which did not constitute "authorised Changes" in terms of Clause 9, but rather the issue of detailed design information in accordance with the provisions of Clause 11.(1)(d) or the exercise of other of their powers in terms of the Sub-Contract. [77] The copies of the Overall Programme that were lodged as productions are difficult to decipher. There is, however, little doubt that when the Overall Programme is read in conjunction with the other programmes referred to in Appendix 8 of the Form of Sub-Contract Agreement, the Overall Programme provides considerable detail as to the various items of work (or tasks) that the pursuers began to carry out during July 1997, including (i) the name of each work task, (ii) the description of each work task, including the chainage at which the task was to be performed, (iii) the type of material involved, (iv) the quantities of material to be excavated, moved or filled, (v) the nature of the work itself, (vi) the duration of each work task, (vii) the daily output during the period relevant for each work task and (viii) by reference to the calendar charts, the dates on or between which the individual tasks were to be carried out. [78] The defenders argue that the scope of the work to be carried out under the sub-contract, including the quantities, haul distances and sequence of the Sub-Contract Works, was not determined by the Overall Programme (and the subsidiary programmes) but simply by reference to Clause 1(ee), the First Schedule, Clause 2 of Appendix 1 and Appendix 2. The provisions of Clause 1(ee) and the First Schedule do not set out in detail the works to be carried out by the Sub-Contractor. Nor do they set out whether any particular items of work are to be carried out at a particular time or in a particular sequence. Clause 2 of Appendix 1 and Appendix 2 equally do not provide such details. Rather the latter define the scope of the works. [79] In my opinion, for the reasons set out in paragraphs 3.1 to 3.8 of the pursuers' skeleton Note of Arguments, the Overall Programme placed obligations upon the pursuers, as Sub-Contractors, which were subject to the defenders' right, as Main Contractors, to issue authorised Changes. In my opinion it is not fatal to the arguments advanced on behalf of the pursuers that the Overall Programme did not refer to all of the works which the pursuers had contracted to undertake. Whether or not the Overall Programme and the original Earthwork Schedules covered all of the works relating to the 'road box', which figure in the defenders' adjusted Note and the pursuers' adjusted Response, remains unclear. It would certainly be inappropriate for me to determine such a factual issue on the basis of the complicated and highly technical written submissions that are now before me. But even if the defenders are correct, and such works were not covered by the Overall Programme and the original Earthwork Schedules, that does not mean, in my opinion, that the issuing of amended Earthwork Schedules, Mass Haul Charts or Target programmes could never constitute the authorising of Change to the Sub-Contract Works, in accordance with the provisions of Clause 9 of the Form of Sub-Contract Agreement.Question D Do the pursuers have a relevant claim in respect of those alleged
Changes for which they have averred no written instruction or written confirmation?