OUTER HOUSE, COURT OF SESSION
[2006] CSOH 20
|
P1504/05
|
OPINION OF LORD HODGE
in the Petition of
SHETLAND
ISLANDS COUNCIL
Petitioners;
for
Judicial Review of
(1) a decision by the Lerwick Port Authority to revise its dredging proposals
for a navigation channel in the Lerwick North Harbour and a failure to carry
out an environmental assessment in connection with said proposals; (2) a failure of the Scottish Ministers to
consider whether the aforementioned decision of the Lerwick Port Authority
required an environmental statement
ннннннннннннннннн________________
|
Petitioners: Williamson; Shepherd & Wedderburn,
W.S.
Respondents: Davidson, Q.C.; Digby Brown
5 August 2005
[1] This
was an application for first order and interim interdict which I heard on 4 and
5 August 2005. The respondents did not reclaim against my
decision to grant interim interdict but some considerable time after my
decision the parties requested me to write a note explaining that decision in
order to assist them in future discussions.
I agreed to do so.
[2] The
application arose out of a dispute between Shetland Islands Council ("SIC") and
Lerwick Port Authority ("LPA") over SIC's proposal to construct a bridge to the
island of Bressay over the North entrance to Lerwick harbour. This is one of two entrances to Lerwick
harbour, the other entrance being from the South. The circumstance which precipitated the
application for judicial review and the application for interim interdict was
the decision by LPA to instruct dredging works in the channel of the North
entrance to Lerwick harbour. SIC alleged that that the dredging works would interfere with their
proposals for the location of the central piers of the bridge which by this
stage had been designed.
[3] SIC
appointed a project team, including Halcrow Crouch, consulting engineers,
("Halcrow"), to design the bridge and to discuss with LPA the alignment of a
dredged channel within the proposed bridge supports. The proposed bridge was designed taking
account of LPA's representations to SIC's professional advisers of their
requirements for navigation in the North entrance to Lerwick harbour. The height of the bridge was designed as
40 metres above Mean High Water Springs to allow large vessels to pass
underneath and the spans of the bridge were designed to allow a dredged
navigation channel of 120 metres in width under the bridge. LPA, which had commissioned Arch Henderson
& Partners to advise them on the effect of the proposed bridge on the
operation and future development of the port, had taken the view that they
required a minimum navigational channel of 100 metres in width
(10 metres wider than the existing channel) and a dredged channel of
120 metres in width and 9 metres in depth. To accommodate this the
foundation supports of the central piers of the proposed bridge required to be
at least 160 metres apart.
[4] SIC
averred that in the course of 2003 they and LPA agreed that the depth of the
dredged channel would be 9 metres, that its width would be 120 metres
aligned between the two piers that would support the central span of the
proposed bridge and that the bridge would have an air draft of 40 metres
to cater for larger vessels. They
averred that they used that agreement as the basis for fixing the positions of
the relevant piers in their applications for the necessary statutory consents
for the construction of the bridge.
Under planning legislation SIC, which were both the planning authority
and the proposed developer, required to prepare a notice of intention to
develop for consideration by the Scottish Ministers. They published the notice in December 2003
and produced, advertised and made available for inspection an environmental
impact assessment in relation to the bridge.
Under roads legislation SIC required to promote a roads scheme, which
they did on June 2004. Finally, to
acquire the necessary land for the construction of the bridge SIC made a
compulsory purchase order in March 2005.
[5] SIC
averred that LPA objected to the notice of intention to develop and the
environmental statement but did not indicate in their objections that they
intended to revise their proposals for the navigable channel. Similarly LPA objected to the roads scheme
but did not indicate any intention to revise those proposals. The Scottish Ministers did not call in the
notice of intention to develop but in August 2004 LPA raised proceedings for
judicial review to challenge that decision and in June 2005 parties agreed that
that decision was flawed and that the Court should quash the decision. The Court of Session annulled the
decision. When I heard this motion, the
Scottish Ministers had yet to decide whether to call in the notice of intention
to develop. LPA's objection to the roads
scheme if not withdrawn will result in a public local inquiry under the roads
legislation.
[6] SIC
averred that in about December 2004 LPA applied to the Scottish Ministers for a
harbour revision order seeking authority to use dredged material for land
reclamation as part of a project to deepen and widen the North access to
Lerwick harbour. The environmental
statement, which accompanied the application, revealed that LPA proposed
significantly more extensive dredging than the proposals which they had agreed
with SIC. SIC objected to the
application for the harbour revision order and the Scottish Ministers had not
determined whether to hold a public local inquiry as required by the relevant
harbours legislation.
[7] SIC
averred that on or around 25 June 2005 LPA intimated to them that they were
amending their dredging proposals and sent them drawings numbers 204516-91 and
204516-92 illustrating their revised proposals.
The effect of the revised proposals would be to locate the west pier of
the central span of the proposed bridge within the revised navigational
channel, causing an obstruction and danger to navigation. SIC averred that this
prejudiced the outcome of any public local inquiry that might be held into the
roads scheme.
Grounds
of challenge
[8] In
their petition for judicial review SIC sought (1) reduction of LPA's amended
dredging proposals, (2) interdict and interim interdict prohibiting LPA from
implementing the amended dredging proposals, (3) an order on LPA to serve
notice of their dredging proposals on the Scottish Ministers, (4) declarator
that the dredging proposals constituted a project which fell within Annexes I
and II of Council Directive 85/337/EEC and (6) declarator that the Scottish
Ministers should require LPA to carry out an environmental impact assessment of
the dredging proposals.
[9] The
grounds of challenge were, first, that the decision of LPA to revise their
dredging proposals and change the alignment of the navigable channel was Wednesbury unreasonable. In essence the averred unreasonableness
consisted in the awareness that on the altered alignment the west pier of the
proposed bridge would be within the navigable channel and that that would
entail danger both vessels and bridge users.
Miss Williamson however in her submissions founded on the knowledge of
LPA that their decision would make the proposed bridge impossible to construct
as designed. Secondly, SIC averred that
LPA acted unreasonably in the Wednesbury sense
in refusing to provide SIC with a copy of the report from Eagle Lyon Pope which
LPA had represented showed ship simulations that justified their decision to
realign the navigable channel. In this
context I was referred to James Aitken
& Sons (Meat Producers) Ltd v
City of Edinburgh
District Council 1990 SLT 241. Thirdly, SIC averred that
LPA were personally barred from altering their dredging proposals because of
the agreement which they reached with SIC on their original dredging proposals
and thereby the alignment of the navigable channel. SIC averred that they had taken forward the
necessary planning and roads applications and compulsory purchase order in
reliance on that agreement and that the LPA's new proposals prejudiced those
applications. I was referred to Cairncross v Lorimer (1860) 3 Macq 827 and Gatty
v MacLaine 1921 SC (HL) 1. Relying on the same facts and essentially the
same reasons, SIC argued, fourthly, that they had a legitimate expectation that
LPA would not alter their dredging proposals which had been agreed.
[10] Fifthly, SIC averred that LPA required and had failed to notify
and obtain approval from the Scottish Ministers under section 9(5) of the
Lerwick Harbour Order Confirmation Act 1974 ("the 1974 Act") in relation to the
deposit of reclaimed materials below the high water mark. Sixthly, it was asserted that because their
dredging proposals constituted development and the authorisation of a harbour
revision order to use the dredged material to reclaim land constituted
development consent, LPA were under an obligation to carry out an environmental
assessment under Council Directive 85/337/EEC which was directly
effective. I was referred to Marshall v Southampton & South West Hampshire Area
Health Authority (Case 152/84) [1986] 1 CMLR 688. SIC averred that LPA's environmental
statement was inadequate as it was confined to the land reclamation works;
Council Directive 85/337/EEC required an assessment of the proposed dredging
works. Seventhly and finally, SIC
averred that in any event because LPA had not notified the dredging proposals
to the Scottish Ministers under section 9(5) of the 1974 Act, the Council
Directive 85/337/EEC was directly effective and LPA had failed to carry out the
required environmental impact assessment.
Miss Williamson submitted that the revised dredging proposals were a
project either under paragraph 8(a) of Annex I of that Directive or in any
event under one or more of paragraphs 2c, 10c, 10k or 13 of Annex II of that
Directive.
[11] Miss Williamson submitted that SIC had made out a prima facie case against LPA for interim
interdict. SIC
understood that LPA had placed a contract for dredging and that operations
would begin on Tuesday 9 August.
The dredging works would prejudice the construction of the bridge and
the consents sought in relation to it.
The balance of convenience favoured the preservation of the status quo pending resolution of the
application for judicial review.
[12] Mr Davidson QC for LPA invited me to refuse interim interdict
or in any event to accept an undertaking which LPA had offered and SIC
refused. He explained that SIC had been
aware since about December 2004 of the broad outline of LPA's revised thinking
on the dredged channel in the Northern approach to Lerwick harbour. Thus, he submitted, the factual position
which SIC presented in their petition was not the whole picture.
[13] He invited me in my consideration of the application for interim
interdict to have regard to the relative strength of the parties' cases: Toynar Ltd v Whitbread & Co plc 1988 SLT 433, 434. He submitted that there were matters which
had not been disclosed in the petition which could not be treated as SIC's
final position and that SIC's case was not likely ultimately to succeed. In any event, he submitted that the balance
of convenience did not favour the grant of interim interdict.
[14] On the merits of the various grounds of challenge Mr Davidson
addressed me systematically on each of the relevant paragraphs of the
petition. First, he submitted that there
was nothing irrational about LPA's decision to revise the dimensions of the
channel as the decision was motivated by concerns for navigational safety and
as neither the existence nor the final positioning of the bridge was a
certainty. Secondly, LPA were under no obligation
to show SIC the Eagle Lyon Pope report but had shown them the proposed dredging
plans which were informed by that report.
SIC had known that LPA's dredging plans were not
immutable. Thus the refusal to
disclose the report could not of itself be
irrational. Thirdly, there was no
factual basis for the case of personal bar.
All that had been agreed by the parties was the location of the existing
channel; there was no agreement as to the future alignment of the channel. For personal bar there required to be a clear
and unambiguous representation and this was lacking. The chief executive officer of SIC who had
attended the meeting with LPA on 13
December 2004 had not suggested that LPA were barred by any
agreement from altering their dredging plans.
The documents on which SIC founded were communings
between professional advisers and not the authorities themselves. There was no representation by LPA that a
drawing showed the proposed dredging channel and that its alignment and
dimensions were fixed thereafter.
Fourthly, there was no basis for a case of legitimate expectation as
there was no express promise or established practice disclosed in the facts on
which SIC relied: CCSU v Minister for the Civil Service [1985] AC 374, Lord Fraser at 401B, Clyde and Edwards "Judicial Review" para 19.09f.
[15] Fifthly, Mr Davidson explained that there was no failure to
notify the Scottish Ministers under section 9(5) of the 1974 Act. LPA required two licences, one for dredging
and one for land reclamation. The
applications included drawings setting out the proposed dredging works. The Scottish Ministers had granted both
licences to the LPA. Sixthly and
seventhly, SIC had not pleaded the environmental impact of the dredging which,
he submitted, did not fall within any of the relevant paragraphs of Annex I or
Annex II of Council Directive 85/337/EEC.
[16] In relation to the balance of convenience, Mr Davidson
submitted that the only prejudice SIC could assert was prejudice to the
proposed bridge in its current form and that form was not immutable. LPA had placed a contract to dredge for a
period of eight weeks at a price of г6.5 million and demurrage would run at
г2,250 per hour. The vessel was due to
arrive on 9 August and dredging would commence shortly thereafter. Cancellation costs would be in the region of
250,000 Euros. The harbour was a
significant employer as about 2,000 jobs depended on it. The status quo in the Northern approach was
not desirable and there was a real issue of the safety of navigation. Without the improvements to that approach,
Lerwick harbour might not be able to attract larger vessels which would go
elsewhere. He renewed the offer of the
undertaking.
Decision
[17] In considering the application for interim interdict I was aware
that the petition had been prepared at short notice and that LPA had not had an
opportunity to prepare detailed Answers to it as they became aware of the
application only by the operation of a caveat on 3 August. I also took account of the fact that the
undertaking was tendered by LPA on the morning of 5 August in discussions
between the parties in an attempt to resolve their dispute. Miss Williamson represented to me that SIC
were not able to determine whether the undertaking was appropriate in the absence
of the Eagle Lyon Pope report and that the drawing submitted with the
undertaking was in any event too inspecific to allow SIC to reach a view on
it. In the circumstances I was not able
to reach a view on the desirability of the undertaking and therefore I accepted
SIC's representation that the undertaking was not a sufficient alternative to
the interim interdict which they sought.
[18] I was not satisfied that the decisions to alter the alignment
of the dredged channel and place a contract to dredge the altered channel were
unreasonable on the basis of LPA's awareness that the altered channel would not
be compatible with the design of the proposed bridge. In the absence of any agreement between the
two public authorities as to the location of the proposed dredged channel or an
understanding which would support a submission of personal bar or legitimate
expectation, I did not consider that it was Wednesbury
unreasonable for LPA to change their proposals for the location of the
dredged channel. Absent such agreement
or understanding, it would simply be the case that one public body's proposed
works were not compatible with those of another public body and I was not
persuaded that administrative law requires one body to defer to the other in
this context. Similarly, while one might
expect responsible public bodies to cooperate by disclosing to each other
information such as the Eagle Lyon Pope report to enable them to conduct their
discussions in an economic and efficient manner, I was not able to categorise
LPA's refusal to release the report, which it had obtained for its purposes, as
unreasonable.
[19] Nonetheless there appeared to me to be a prima facie case either that LPA were personally barred from
altering their proposals or that their behaviour had given rise to a legitimate
expectation that they would not do so.
To explain this I must set out the events upon which SIC relied to
support these grounds of challenge. Initially
in April 1999 Halcrow produced a feasibility study for a link to Bressay and
recommended as a preferred option a fixed bridge. In response, Arch Henderson produced a report
for LPA in January 2003 recommending that the minimum navigational channel
required for the future development of the port should be of the dimensions
mentioned at the end of paragraph 3 above and including drawings showing the
location of the then proposed channel.
The report stated that the anticipated distance between bridge pier foundation supports corresponded to the minimum 160 metres
but that this dimension could be finalised and agreed only once future site
investigation information confirmed the side slope characteristics of the
dredged channel. In April 2003 Arch
Henderson sent estimated dredging costs to LPA for the dredging works on a
channel illustrated on drawing 202512-03.
Following discussions in late 2003 which SIC aver gave rise to the
agreement, a further meeting was held on 9
January 2004 between Arch Henderson on behalf of LPA and a
representative of SIC at which agreement was reached or confirmed as to the
alignment of the existing dredged channel.
On the same day Arch Henderson sent SIC an e-mail with a plan showing
both the existing channel and the boundaries of the new dredged channel which
LPA wished to create. Arch Henderson
in that e-mail asked SIC to incorporate the drawing into all existing and
future bridge drawings. Thereafter on 13
April 2004 Arch Henderson sent SIC the contract drawings and tender documents
that they had prepared for the proposed dredging and land reclamation works and
attached to the letter a plan which showed the proposed dredged channel which
was in all material respects the same as that shown on the plan that
accompanied the e-mail of 9 January 2004.
On 17 May 2004 LPA
sent an e-mail to Mr Nicholson of SIC's project team in response to
queries from the latter. The e-mail
contained a representation that the new channel alignment had not been changed.
[20] The cases of personal bar and legitimate expectation were as
follows. Miss Williamson submitted
that the agreement reached in late 2003, and evidenced by the later e-mail and
correspondence, was binding on LPA. She
founded in particular on the e-mail of 9
January 2004 and Arch Henderson's letter of 13 April 2004.
If there were no binding agreement, she submitted that there was a
representation that LPA would not depart from the alignment of the channel
which they had indicated. That
representation bound LPA as they knew that SIC would rely on it to their detriment
and SIC did so in working up and progressing the notice of intention to develop
(in December 2003), the roads scheme (in June 2004) and their compulsory
purchase order (in March 2005). It was
not until 26 June 2005 that
LPA intimated to SIC that they were to amend the alignment of the dredged
channel. She submitted that at the
meeting on 13 December 2004
LPA did not specify the changes to the dredged channel which they were
considering, that the chief executive of SIC was not aware of the effect of such
changes on the bridge design and that the SIC's project team did not attend the
meeting. That meeting did not support
the inference that there had not been and there was not detrimental reliance by
SIC.
[21] In my opinion, it appeared from the documents produced in court
that Arch Henderson and LPA, since January 2003 at the latest, knew that SIC
were seeking to accommodate LPA's proposals for the future dredged channel in
their design of the bridge and that SIC were seeking to reach agreement, or at
least an understanding, with LPA as to those proposals which would inform their
design of the bridge. Whether one
categorised a representation by a public authority as personal bar, where it is
followed by detrimental reliance by the representee, or as a species of breach
of a legitimate expectation (see R v Jockey Club, ex parte RAM Racecourses
[1993] 2 All ER 225, Stuart Smith LJ at 236), I considered that the
documentation produced to me supported the view that there was such a
representation and reliance. In
particular I considered (i) that there was a clear and unambiguous
representation as to LPA's proposals for the dredged channel, (ii) that this
representation was made in a context in which LPA and their advisers would have
known that SIC and its advisers would reasonably rely on it, (iii) that SIC did
so rely on the representation, and (iv) that there was detriment to SIC in the
sense that, were LPA to depart from the representation by altering their plans
materially and dredging a different channel, SIC would suffer substantial financial
loss through wasted expenditure in taking forward proposals which would then
have to be altered radically. See William Grant & Sons Ltd v Glen Catrine Bonded Warehouse Ltd 2001 SC 901, 921, where Lord President Rodger cites a luminous passage from the
judgment of Dixon J in Grundt v Great Boulder Pty Gold Mines Ltd (1937)
59 CLR 641, 674-675.
[22] Turning to Mr Davidson's submission that there was no factual
basis for the cases of personal bar and breach of legitimate expectation, three
points may be made. First, while the
correspondence in the main comprised exchanges between professional advisers
and not their clients, I was not persuaded that this was material in the
context in which the exchanges (and in particular the e-mail of 9 January 2004) took place. It appeared that LPA could have been in no
doubt why SIC were seeking to ascertain their proposals for the dredged channel
or as to the reliance that SIC would place on a representation in that regard. Secondly, while the documentation did not
contain an express statement that LPA would not alter materially the alignment
of the proposed dredged channel in future, I considered that the context in
which the exchanges took place between the parties suggested that this was
implicit in what SIC sought and what LPA represented. Thirdly, while the documentation suggested
that the chief executive of SIC who met with representatives of LPA on 13 December
2004 did not assert that LPA were barred from altering their plans, it was not
clear how well informed he was of the discussions between the two public
authorities' officials and advisers when he attended that meeting. In the absence of more detailed information
about the lead up to and circumstances of the meeting I was not persuaded that
that what occurred at that meeting undermined SIC's case of detrimental
reliance. In relation to Mr Davidson's
submission that there could be a legitimate expectation only if there were an
express promise or established practice, I did not consider that Lord Fraser's
reference in CCSU (above) to an
express promise excluded a representation which in English law might ground an
estoppel or in Scots law a personal bar (R
v Board of Inland Revenue ex p MFK
Underwriting Agents Ltd [1990] 1 WLR 1545, Bingham LJ at 1569-1570).
[23] In granting the motion for interim interdict I upheld Miss
Williamson's submissions that the understanding reached in about December 2003
and January 2004 grounded a prima facie case
of personal bar or breach of legitimate expectations.
[24] In relation to the balance of convenience I considered that the
preservation of the status quo was
the predominant consideration having regard to the likelihood that the dredging
works if carried out would undermine much of the work that SIC had carried out
since late 2003. I recognised that
interim interdict might force LPA to cancel or curtail their dredging contract
at considerable cost to the public but was not persuaded that that
consideration should outweigh prejudice to SIC where LPA appeared knowingly to
have sought to alter the status quo. I also had regard to the fact that, before
placing the dredging contract, LPA had been unwilling to discuss with SIC's
advisers the technical basis on which they had altered their proposals when
they must have known that the proposed alteration would prejudice the
development of the bridge on which SIC and their advisers had been working for
several years. While that may not have
been Wednesbury unreasonable, it did
not appear to be a laudable way for a public body charged with the use of
public money to deal with another public body.
I was not persuaded that concerns about the long term future of the
harbour if the Northern channel were not improved were a weighty factor in the
balance of convenience at this interim stage.
[25] When granting interim interdict I stated that I had made my
decision on the limited material available, that I recognised there would have
been much material that had not been disclosed to the court which might cast
light on parties' understanding of each other's position during 2004, and that
I would have been prepared to sit again on the following week to reconsider
matters in the light of a fuller discussion of the background.
[26] I can deal briefly with the other grounds of challenge listed
in paragraph 10 above as they were not material to my decision. There was a factual dispute as to whether LPA
had obtained the approvals from the Scottish Ministers in relation to the
deposit of reclaimed materials that the 1974 Act required. Similarly there was a dispute whether the
dredging works fell within any of the paragraphs of the Annexes to Council
Directive 85/337/EEC to which I referred in paragraph 10 above. I did not consider that I had sufficient
information to form a clear view on the merits of these disputes. Having decided to pronounce interim interdict
on the basis of the cases of personal bar and breach of legitimate expectation,
I concluded that there was no need for me to attempt to do so.