BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just ┬г5, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
Scottish Court of Session Decisions |
||
You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> Autolink Concessionaires (M6) Plc v Amey Construction Ltd & Ors [2007] ScotCS CSOH_81 (04 May 2007) URL: http://www.bailii.org/scot/cases/ScotCS/2007/CSOH_81.html Cite as: [2007] ScotCS CSOH_81, [2007] CSOH 81, 2007 GWD 37-640 |
[New search] [Help]
OUTER HOUSE, COURT OF SESSION [2007] CSOH 81 |
|
CA23/06 |
OPINION OF LORD CLARKE in the cause AUTOLINK CONCESSIONAIRES (M6) PLC Pursuers; against (FIRST) AMEY CONSTRUCTION LIMITED AND OTHERS Defenders: ннннннннннннннннн________________ |
Pursuers: Keen, Q.C., Mure; Fyfe
Defenders: Cullen, Q.C., Richardson; Pinsent Masons
4 May 2007
Introduction
"special road to be constructed in Scotland ... in accordance with the New Works Requirements between Paddy's Rickle Bridge and Cleuchbrae, together with the junctions and slip roads relating thereto, being all the roads other than the Existing Scottish Motorway situated within the O & M site in Scotland for which the Secretary of State will become the roads authority following their completion". - (See Part 1 of Schedule 1 of the DBFO Agreement).
The obligations undertaken by the
pursuers in terms of the DBFO Agreement were wider in scope than the "works"
undertaken by the defenders in terms of the construction contract, as that
expression, "works", is defined in that contract. In addition to the DBFO Agreement and the Construction
Contract, there were certain other related agreements. The first of these is what was described as
the "Routine Operation and Maintenance Contract" (hereinafter referred to as
"the ROM contract") between the pursuers and the defenders (7/4 of
process), a contract described as the Major Maintenance Call-Off Contract
between the pursuers and the defenders (7/5 of process) and certain
appointments on behalf of the defenders of designers and consultants (7/6
and 7/7 of process). Among others
things, these contractual arrangements were to provide not only for the
construction of a new section of roadway, but the maintenance thereof and the
maintenance of an existing roadway of which it formed the extension. In terms of clause 9 of the DBFO
Agreement, the pursuers' obligations (originally to the Secretary of State for
"In performing its obligations under Clause 6.1.1 the Contractor shall design the Works (including the specification of materials and Plant where required) with reasonable skill and care and in accordance with practice conventionally accepted as appropriate at the time of the execution of the Works having regard to the size, scope and complexity of the Works".
"all works of repair and maintenance and any improvements required in respect of the Project Facilities other than defects repairs under the Construction Contract or routine operation and maintenance to be performed under the Routine Operating (sic) and Maintenance Contract".
In terms of the Major Maintenance Call-Off Contract, the pursuers were obliged to pay for the carrying out of any Major Maintenance Works.
"Since the Final Completion of the Phases of the New Scottish Motorway, the pursuers have identified major and important Defects within the pavement of the road, namely the absence of a, et separatim the inadequacy of the, bond between the upper and lower roadbase courses. The performance, structural integrity and longevity of the pavement depends upon the stiffness of the roadbase within it".
The averments go on to provide more specification about the problem and its consequences. In particular, in Article 6 of Condescendence they aver:
"The Defects have to date caused visible problems in several areas of the New Scottish Motorway, necessitating repair works, and will continue to do so until such time as the Defects themselves are remedied in terms of Clause 51.1. The Defects have caused a very significant reduction in the residual life of the pavement."
In the first conclusion of the summons, the pursuers seek a declarator in the following terms:
"For declarator that the defenders are liable in terms of Clause 51 of the contract between the parties dated 30 April 1997 ('Construction Contract M6 DBFO Project') to remedy the lack of et separatim inadequacy of, bond between the upper and lower roadbase courses in the New Scottish Motorway (as defined in the said Contract)".
They then, in the second conclusion seek the following order:
"For an order ordaining the defenders to remedy the lack of, et separatim inadequacy of, bond between the upper and lower roadbase courses in the New Scottish Motorway (as defined in the said Contract) at their own cost and to the pursuers' reasonable satisfaction, and that within the period of two years from the date of decree to follow hereon, or within such other reasonable period as the Court shall seem fit."
The Dispute focuses, accordingly, in the first place, on the proper construction and effect of clause 51 of the Construction Contract which is in the following terms:
"51 MAINTENANCE PERIOD
51.1 Rectification of Defects
The contractor shall complete the work, if any, outstanding on the date in the Permit to Use as soon as practicable after such date and remedy to the Employer's reasonable satisfaction, and within such reasonable time as the Employer may specify having regard to the nature of the Defect, all Defects (whenever arising or manifesting themselves) in the New Works insofar as notified to the Contractor by the Employer within 60 months of Final Completion of all Phases of the Scottish Works and of the English Works part of the New Works (each of which 60 month periods are referred to in this Contract as the 'Maintenance Period' for such part and in the case of the Ancillary Works and the Accommodation Works, subject to clause 17.1(b) of the M6 DBFO agreement).
51.2 Cost of Remedying Defects
51.2.1 All work referred to in clause 51.1 shall be executed by the Contractor at its own cost unless the necessity thereof is a direct result of a wilful act or breach of this Contract by the Employer.
51.2.2 If in the opinion of the Employer's Agent such necessity is a direct result of a wilful act or breach of this Contract by the Employer, it shall determine an addition to the Contract Sum in accordance with Clause 54 and notify the Contractor accordingly."
In the definition clause of the Construction Contract "Defect" is defined as meaning:
"any defect howsoever arising including without limitation:
(a) any defect that is the result of defective design or defective materials or defective workmanship;
(b) any failure of the New Works to meet, or to continue to meet (except to the extent permitted in the O & M Requirements), the New Works Requirements; or
(c) any damage, destruction or other effect consequential on any such defect;"
The defenders, relying on their general plea to the relevancy, plea-in-law 2, sought to have the action dismissed on the basis that the pursuers had failed to aver the cause of any defect upon which they rely, in particular, that any such defect arose as the result of a breach of contract by the defenders and more specifically, if so, whether any such breach arose in respect of the defenders' contractual obligations regarding workmanship, materials or design.
Discussion
"Without prejudice to Clause 10(b), the remedying to the Secretary of State's reasonable satisfaction, and within such reasonable times as the Secretary of State may specify having regard to the nature of the Defect, of all Defects (whenever arising or manifesting themselves) in the following parts of the New Works -
(i) each part of the New Scottish APR which forms part of a Phase;
(ii) the New English APR if constructed under this Agreement;
(iii) the Ancillary Works;
(iv) the Accommodation Works; and
(v) all other parts (if any) of the New Works not covered by the Company's obligations under Clause 10(b) in respect of the O & M works,
insofar as notified to the Company by the Secretary of State within 12 months of Final Completion of such part of the New Works (each of which 12 month periods are referred to in this Agreement as the 'Defects Correction Period' for such part and in the case of the Ancillary Works and the Accommodation Works, subject to Clause 17.1(b)); ..."
In schedule 1 to the DBFO Agreement "Defect" is defined as meaning
"any defect howsoever arising including without limitation -
(a) any defect that is the result of defective design or defective materials or defective workmanship;
(b) any failure of the New Works to meet, or to continue to meet (except to the extent permitted in the O & M Requirements), the New Works Requirements; or
(c) any damage, destruction or other effect consequential on any such defect."
Counsel for the defenders stressed, in their submissions, that the pursuers' obligations under clause 10(c) of the DBFO Agreement were not, in terms, transferred to the defenders under the Construction Contract. The period of maintenance in terms of clause 51 of the Construction Contract was 60 months whereas that in clause 10(c) of the DBFO Agreement was 12 months. The context of these provisions, it was submitted, made clear that the obligations undertaken by the pursuers, on the one hand, in terms of the DBFO Agreement and, on the other hand by the defenders in terms of the Construction Contract were quite different. The court's attention was drawn to paragraph (E) in the preamble to the Construction Contract where it is stated that:
"The Employer has reached agreement with the Contractor whereunder the Contractor undertakes and each member of the Contractor jointly and severally undertakes that it will design, construct, test, complete and maintain the Works in accordance with this Contract to enable the Employer to discharge its obligations to the Secretary of State for Scotland in respect of the Works in accordance with the terms of the M6 DBFO Agreement and the Employer undertakes to exercise any right or power granted to it under the M6 DBFO Agreement, on request by the Contractor, which may be necessary to enable the Contractor to discharge its obligations to the Employer in accordance with the terms of this Contract."
In the definition clause contained in the Construction Contract 1.1 the "works" are defined as meaning:
"the New Works, the Maintenance and the Relevant O & M Works and any works which are a necessary or ancillary part of these works and, where the context requires, any works carried out as a Variation;"
"New Works" are defined as having "the meaning given in clause 10(a) of the M6 DBFO Agreement". The word "maintenance" is defined as meaning "all works to be carried out in accordance with Clause 51". The "Relevant O & M works" are defined as meaning "such of the O & M Works as are applicable to the obligations of the Contractor under this Contract and which are generally described in Schedule 17". Schedule 17 is in the following terms:
"RELEVANT O & M WORKS
Those elements of the Planned Maintenance Works described in the ROM Agreement which are on the line of the New Works".
The ROM contract was entered into between the parties. Under it the defenders undertook certain of the obligations of the pursuers, regarding maintenance of the roadway for an initial period of 5 years with the possibility of subsequent renewals. Counsel for the defenders commented that, in accordance with these contractual arrangements, it was only part of the pursuers' obligations in relation to operation and maintenance contained in the DBFO Agreement which were passed on contractually to the defenders.
"The Contractor shall be responsible for the design, construction, completion, commissioning and testing of the Works, which shall be carried out in strict accordance with the New Works Requirements, the Certification Procedure, the Review Procedure and all other requirements of this Contract".
Clause 6.1.2, as has already been noted, provides that
"in performing its obligations under Clause 6.1.1 the Contractor shall design the Works (including the specification of materials and Plant where required) with reasonable skill and care and in accordance with practice conventionally accepted as appropriate at the time of the execution of the Works having regard to the size, scope and complexity of the Works."
The expression "New Works Requirements" appearing in clause 6.1 is defined in clause 1.1 as meaning:
"the conditions, procedures, standards, specifications and requirements for design and construction set out or identified in Schedule 2 as amended from time to time in accordance with this Contract."
Clause 9.1.3 also provides:
"the Works when constructed and the Maintenance when completed will comply in all respects with the New Works Requirements."
Schedule 2 provides:
"NEW WORKS
REQUIREMENTS
This Schedule shall be deemed to consist of the provisions of Schedule 2
of the M6 DBFO Agreement as if the same has been incorporated at length herein
but declaring that:
(i) the provisions so incorporated shall be deemed applicable only to the scope of work under this Contract as set out in the Conditions and the Schedules and so far as relevant to the description of the Works;
(ii) the definitions used in the M6 DBFO Agreement shall apply to provisions incorporated herein as aforesaid;
(iii) Clause references contained in the provisions incorporated herein as aforesaid shall be taken to be to references to the applicable clauses within the M6 DBFO Agreement;
(iv) information contained in the provisions incorporated herein as aforesaid which, when read in conjunction with the M6 DBFO Agreement is relevant only to that Agreement, shall be treated as irrelevant to this Contract."
Under reference to these provisions, the defenders once again stressed that the pursuers' obligations under the DBFO Agreement were not transferred "wholesale" to the defenders. They particularly emphasised that clause 6.1 of the Construction Contract provided for design obligations which were qualified by reference to certain standards and requirements.
[10] In the Major Maintenance Call-Off Contract, paragraph E of the preamble provides:
"The Employer (i.e. the pursuers) has reached agreement with the Contractor (i.e. the defenders) in the terms set out below with regard to the works of Major Maintenance required for the Project so as to enable the Employer to discharge its obligations to the Secretary of State for Scotland in respect of the Project in accordance with the terms of the M6 DBFO Agreement and the Employer undertakes to exercise any right or power granted to it under the M6 DBFO Agreement, on request by the Contractor, which may be necessary to enable the Contractor to discharge its obligations to the Employer in accordance with the terms hereof."
Clause 1.1.4 of the same agreement defines "Major Maintenance" as meaning:
"all works of repair and maintenance and any improvements required in respect of the Project Facilities other than defects repairs under the Construction Contract or routine operation and maintenance to be performed under the Routine Operating (sic) and Maintenance Contract" (emphasis added).
Again clause 3 of the same contract sets out the procedure for instructing major maintenance works including machinery for agreeing the contract sums. Clause 4 provides for payment of the contractor.
[11] The ROM contract between the parties states in paragraph E of its preamble as follows:
"The Employer (i.e. the pursuers) has reached agreement with the Contractor (i.e. the defenders) whereunder the Contractor undertakes and each member of the Contractor jointly and severally undertakes that it will carry out the routine operation and maintenance of the Project Road in accordance with this Contract to enable the Employer to discharge its obligations to the Secretary of State for Scotland in respect of the Works in accordance with the terms of the M6 DBFO Agreement and the Employer undertakes to exercise any right or power granted to it under the M6 DBFO Agreement, on request by the Contractor, which may be necessary to enable the Contractor to discharge its obligations to the Employer in accordance with the terms of this Contract."
As has been noted, the combined effects of clause 6 of the ROM contract and the definition of "contract period" contained in that contract is that the ROM contract was agreed to endure for 5 years with the possibility of renewals for a further 5 years up until the end of the project period which is 30 years. The "works" to be carried out under the ROM contract are defined in the definition clause as meaning:
"subject to the provisions of Clause 43.4 the Planned Maintenance Works, the Minor Call-Off Maintenance Works carried out under a Works Order and Defects Repairs and, where the context requires, any works carried out as a Variation."
Clause 43 provides for the commencement of the carrying out of the works in respect of various areas according to various dates. In respect of the Existing Scottish Motorway, commencement date is said to be the:
"Operations Commencement Date" and in respect of 'each part of the New Scottish Motorway which forms part of a Phase from the date of issue from the Permit to Use for such Phase'".
In schedule 4 of the ROM contract there are certain exceptions from the O & M work, undertaken by the pursuers under the DBFO Agreement, which the defenders are obliged to carry out as Planned Maintenance Works. The most significant of these exceptions, for present purposes, is that there is excepted "rectification of defects in road pavement". The responsibility for such defects remains with the pursuers under the DBFO Agreement. Counsel for the defenders pointed out that in terms of the DBFO Agreement, there was no express requirement of any bond to be part of the road pavement.
"the works of Routine Operation and Maintenance (other than the Planned Maintenance Works) to be carried out by the Contractor as specified in a Works Order."
In the definition of "Works Order" it is provided that it:
"means an order issued by the Employer's Agent in accordance with Clause 45 requiring the Contractor to carry out works other than Planned Maintenance Works and shall include those works expressly excluded from the scope of the Planned Maintenance Works in Schedule 4."
Counsel for the defenders pointed out that the remedying of a defect in the road pavement could be covered by those provisions and, if those provisions were employed by the pursuers, then, the contractor, i.e. the defenders would require to be paid for any such work by virtue of the provisions of clause 45 of the ROM agreement.
"DEFECTS CORRECTION
51.1 Duration of Defects Correction Period
In this Contract, 'Defects Correction Period' shall mean a period of 12 months from the issue of the Certificate of Completion and shall apply solely in respect of Works carried out under a Works Order.
51.2 Remedying Defects
The contractor shall execute to the reasonable satisfaction of the Employer's
Agent all such work of amendment, reconstruction, and remedying of defects,
shrinkages or other faults as the Employer's Agent may instruct and at such
times as the Employer's Agent may instruct the Contractor to execute either
during the Defects Correction Period or within 14 days after its
expiration, as a result of an inspection made by or on behalf of the Employer's
Agent prior to its expiration and shall agree a programme for the Defects
Repairs with the Employer's Agent.
51.3 Cost of Remedying Defects
All work referred to in Clause 51.2 shall be executed by the Contractor at its own cost if the necessity thereof is in the opinion of the Employer's Agent, due to:
51.3.1 the use of materials Plant or workmanship not in accordance with this Contract or the specific requirements of any Works Order; or
51.3.2 any fault in design where such design has been exclusively prepared by the Contractor or where the design was not so prepared where the Contractor could reasonably have been expected to detect that fault; or
51.3.3 the neglect or failure on the part of the Contractor to comply with any obligation, express or implied, on the Contractor's part under this Contract; or
51.3.4 any breach of the Contractor's warranties.
If the remedial works are not required as a consequence of any of the reasons specified in Clauses 51.3.1 to 51.3.4 above then an addition to the Contract Sum shall be calculated in accordance with the provisions of Clause 54."
In clause 50.1.1 of the Construction Contract, it is provided:
"Not later than 25 Working Days prior to the date upon which the Contractor expects the issues of a Substantial Completion Certificate for a Phase, the Contractor shall issue to the Employer a notice to that effect, and the Contractor shall deliver to the Employer such Substantial Completion Certificate as soon as it is available in the form required to enable the Employer to comply with clause 14.1(a) of the M6 DBFO Agreement. If the Substantial Completion Certificate is in the form required by the M6 DBFO Agreement the Employer shall forthwith deliver the Substantial Completion Certificate to the Secretary of State ..."
50.1.2 provides:
"Following the decision of the Secretary of State under clause 14.1(b) of the M6 DBFO Agreement, and within five Working Days of such decision, the Employer shall either:
50.1.2.1 issue a notice to the Contractor acknowledging the issue of such Substantial Completion Certificate (a 'Permit to Use'); or
50.1.2.2 notify the Contractor that in the opinion of the Secretary of State notwithstanding issue of the Substantial Completion Certificate the Phase has not reached Substantial Completion. In that event the Employer shall state in such notice the respects in which the Secretary of State considers such Phase has not reached Substantial Completion."
Substantial completion is defined as follows in the definition clause:
"substantial completion" of a Phase means Final Completion of such Phase except for incomplete items which do not prejudice the operation, or safe use by Users of such Phase, and in the case of all Phases other than the Accommodation Works, shall not be earlier than the date of satisfactory completion of the Stage 3 Audit Procedure for such Phase and the date on which all Lanes are available to traffic."
Final Completion is defined as:
"'Final Completion' of a Phase or of any part of the New Works means completion of such Phase or such part of the New Works fully in accordance with the New Works Requirements except for outstanding or incomplete works to a value not exceeding:
(a) г200,000 in the case of the
Paddy's
(b) г200,000 in the case of the Beattock to Cleuchbrae Phase; and
(c) г200,000 in the case of the New English Motorway and the New English APR,
which do not materially affect Users or Third Parties."
The significance of these provisions, it was said, by junior counsel for the defenders, was that they indicated that the first part of clause 51.1 in the Construction Contract was concerned with completion of outstanding work. Moreover once a Permit to Use was issued, the provisions of the ROM contract were activated. As has been seen clause 51.1. provides that the maintenance period is 60 months from final completion of all phases of the "Scottish Works" and of the "English Works part of the New Works". Clause 50.5 of the Construction Contract provides as follows:
"Subject to the requirements of this Clause 50 and Clause 51 the Contractor's liability under this Contract for any failure to comply with this Contract which becomes apparent after the end of the Maintenance Period or for any defect in the Works which becomes apparent after the end of the Maintenance Period shall be in damages. Such liability shall be limited to:
50.5.1 the direct Loss suffered by the Employer arising out of such failure or defect: and
50.5.2 any Consequential Loss suffered by the Employer but subject to Clause 69."
It was important, it was submitted on behalf of the defenders, to read clauses 50.5 and 51 together. In clause 51.1 the remedying of defects required was not linked to any technical standard. It was simply to be done to "the reasonable satisfaction of the employer". The clause, it was submitted, should be read as imposing an obligation on the defenders to remedy any breach of contract on their part notified to them within the 60 month maintenance period. Junior counsel for the defenders submitted that the pursuers had failed to aver that the problem in the road arose from a defect as defined in either (a) or (b) or as the consequence of such, under (c) of the definition of "Defect" in the Construction Contract. In Article 4 of Condescendence, the pursuers make no reference at all as to the cause of the absence or inadequacy of the adhesive bond and, in particular, that it arose because of defective design, defective materials or workmanship or any combination of these. The only averment of the pursuers which connected the work of the defenders with the "bond issue" was the averment in Article 4, page 20, c-d to the following effect:
"Full bond between roadbase courses is implicitly assumed in specifying design and construction requirements for such pavements, and is expected to be a characteristic of completed pavements. The Design prepared for the New Scottish Motorway implicitly assumed full bond between roadbase courses. The absence, et separatim the inadequacy, of such a bond in the pavement of the New Scottish Motorway is a Defect in respect of clauses 1.1 and 51.1 of the contract."
The pursuers conspicuously, it was said, do not aver that the absence of bond itself represents non-compliance with the New Works Requirements. The word "bond" did not appear in any of the contract documents. For all the pursuers offered to prove, the defenders may have performed all their obligations in terms of the Construction Contract. The pursuers were contending, on the basis of a bare assertion, that the defenders should rectify the "problem" at their own cost.
"It should be made clear that in clauses of this kind the word 'defects' will today usually be held to indicate any deficiency in the quality of the work, whether structural on the one hand or merely decorative on the other and whether due to faulty materials or workmanship, or even in design or performance, if that is a part of the contractor's obligation. In some cases, the making good or repair obligation may be limited expressly to cases of breach of contract on the part of the contractor, but the modern tendency is to require making good or repair whatever the cause of the defect, but with full compensation to the contractor in cases where he is not in breach of contract. In other less usual cases, the repair obligation may be 'absolute', in the sense that the contractor may be obliged to make good without additional cost to the owner whether or not he is at fault."
At paragraph 5.040 after having stated:
"In building
contracts in
The writer continues:
"The word 'defect' in this particular context may in practice often mean the symptom rather than the cause, which may often be difficult to establish (and so any consequential questions of liability), until work has been demolished, removed or uncovered, or special investigations carried out.
Despite the similarity of many modern clauses, there are in fact different types of wording which may occasionally be met within construction contracts and which may have very different consequences, particularly in those cases where the contractor's obligation is to arise independent of fault on his part, so that he is not entitled to extra payment whatever the cause of the defect. ..."
Junior counsel for the defenders
submitted that before holding that a defects liability clause had the effect last
described in the passage from
"21.1 Care
Subject to Clause 21.4, the Contractor shall be responsible for and shall take the full risk in the care of the Works and materials and Plant for incorporation therein from the date of execution of this Contract or, if earlier, the date when it commences manufacture of materials or Plant until the date of issue of the Permit to Use when such risk and responsibility in the relevant part of the Works shall pass to the Employer or Local Person or the Secretary of State provided that the Contractor shall take full responsibility for the care of and risk in:
21.1.1 any Maintenance and materials and Plant for incorporation therein during the Maintenance Period; and
21.1.2 any Works to be carried out in respect of a Phase remaining to be completed between the issue of the respective Permit to Use for that Phase and the acknowledgement by the Secretary of State pursuant to clause 14.3 of the M6 DBFO Agreement and by the Employer pursuant to clause 50.3.2 of the corresponding Final Completion Certificate and any materials and Plant for incorporation therein until such Final Completion Certificate is issued;
21.2 Responsibility to Rectify Loss or Damage
If any loss or damage happens to the Works, or any part thereof, or materials or Plant for incorporation therein, during the period for which the Contractor is responsible for the care thereof in accordance with clause 21.1, from any cause whatsoever, (subject to Clause 21.4) the Contractor shall, at its own cost, rectify such loss or damage so that the Works conform in every respect with the provisions of this Contract to the satisfaction of the Employer's Agent."
These provisions, it was submitted, incorporated a clear and explicit imposition of absolute liability to be placed on the defenders which fell to be contrasted with the wording of clause 51.1. It was also important to note, it was said, that clause 21.4 removed from the defenders, liability under the clause for damage or loss to the works caused by force majeure as defined. If the pursuers' arguments were correct, regarding the construction of clause 51.1, the defenders would be bound to put right, at their own cost, defects which were caused by force majeure. The width of the obligations which the pursuers' contention involved, was added to by virtue of the provisions of clause 50.5. While the specific performance obligations of the defenders were restricted in time, there was under clause 50.5, a potential liability upon them for damages without limit of time.
"This Contract (including the Schedules) and the Construction Direct Agreement constitutes the whole agreement and understanding of the Parties as to the subject matter hereof and there are no prior or contemporaneous agreements between the Parties with respect thereto."
This established the primacy of the provisions of the Construction Contract for the purposes of the present dispute. The defenders were not party to the DBFO Agreement which related to operations which went far beyond the New Works which were the subject of the Construction Contract. The total length of the motorway was 92 kilometres. Of that total length, 29 kilometres constituted the New Motorway. The DBFO contract was not just concerned with building and maintaining a new road for 30 years, but was concerned with the pursuers taking over an existing motorway and maintaining it. From the commencement of the DBFO Agreement, the pursuers had an obligation to operate and maintain the existing motorway quite apart from the obligations regarding the construction and maintenance of the new motorway. The pursuers entered into the ROM and Major Maintenance Call-Off contracts which related to both the New and Old Motorway. In clause 3 of the DBFO Agreement, certain other agreements were referred to as 'the related documents'. These included the ROM contract but did not include the Major Maintenance Call-Off Contract. The last mentioned contract was concerned only with the existing motorway. Reference in that respect was made to paragraph E of the preamble to the last mentioned contract and clause 1.1.4 and clause 3 thereof. Any major maintenance which was to be instructed under that contract required to be the subject of a works contract. If there was a works contract then there required to be payment made for the works undertaken by the defenders under clause 4 of that contract. The provisions of the Major Maintenance Call-Off Contract, it was submitted, therefore advanced neither parties arguments, particularly because of the express exception of the defenders' defects responsibilities under the Construction Contract.
"Contractor to Search
If any defect, shrinkage or other fault in the Works appears at any time during the Defects Correction Period, the Employer's Agent may instruct the Contractor to search for the cause thereof. The cost of the work carried out in searching as aforesaid shall be borne by the Contractor and it shall remedy such defect, shrinkage or other fault in accordance with the provisions of Clauses 51.2 to 51.4 inclusive."
Clause 51.5 had a purpose when one turned back to look at clause 51.3. There was no equivalent provision in the Construction Contract. The reason for that was obvious. There was no intention, in that provision, to allocate the risk by reference to a cause.
Decision
"which may often be difficult to establish (and so any consequential questions of liability), until work has been demolished, removed or uncovered, or special investigations carried out".
Seen in that light, the ordinary meaning of the words employed in clause 51 does not produce any commercial absurdity. Ultimately, the pursuers' construction of clause 51 appears to me to be more in accordance with the rules of construction as set out in such cases as BCC Iv Ali (2002) 1 AC 251 per Lord Bingham at page 259G, paragraph 8, Melanesiam Mission Trust Board v Australian Mutual Provident Society (1997) 74 PNCR 297 per Lord Hope at page 301 and City Wall Properties (Scotland) Ltd v Pearl Assurance Plc 2004 SC 214 at page 229. The defenders' approach, on the other hand, seems to me to involve an illegitimate re-wording of the provision itself to save them from, what is accepted is, an onerous obligation.
[39] I shall, in the circumstances, have the case put out By Order
for discussion of further procedure.