Scottish Court of Session Decisions |
||
You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> Castle Inns (Stirling) Ltd (t/a Castle Leisure Group) v. Clark Cotnracts Ltd [2009] ScotCS CSOH_174 (22 December 2009) URL: http://www.bailii.org/scot/cases/ScotCS/2009/2009CSOH174.html Cite as: [2009] ScotCS CSOH_174, [2009] CSOH 174 |
[New search] [Help]
OUTER HOUSE, COURT OF SESSION
[2009] CSOH 174
|
|
CA50/04
|
OPINION OF LORD DRUMMOND YOUNG
in the cause
CASTLE INNS (STIRLING) LIMITED t/a CASTLE LEISURE GROUP
Pursuers;
against
CLARK CONTRACTS LIMITED
Defenders:
ннннннннннннннннн________________
|
Pursuers: Lake; Dundas & Wilson CS LLP
Defenders: Higgins; MacRoberts
22 December 2009
[1] The pursuers are the proprietors of premises at 6-8 South Methven Street, Perth. Those premises were originally a school, built in Victorian times;
subsequently they were converted into council offices. They were acquired by
the pursuers with a view to converting them into licensed premises. The work
of conversion took place in two stages. The first stage consisted of shell
construction works, comprising downtakings, demolitions, the formation of new
structural floors and stairs and the construction of new walls, roof works and
below ground drainage. The second stage consisted of the work of fitting out
to enable the building to be used as licensed premises comprising bars, a
restaurant and other rooms. The two stages were referred to in the contract
documentation as phase 1 and phase 2. The pursuers were appointed contractor
for phase 1, the shell construction works. The fit-out contractor for phase 2
was a company called Dimension Shopfitters. The contract architect for both
stages was Davidson Design Partnership Ltd. The phase 1 contract between the
pursuers and the defenders was contained in a tender by the defenders dated 26 January 2001 as revised by a further letter dated 12 March 2001. It incorporated the terms and conditions of the
Scottish Building Contract Without Quantities Contractors Design Portion
(January 2000 Revision), subject to certain amendments and modifications.
[2] The contract works began on 7 May 2001. Disputes arose between the parties in the course of
the works, and as a result two separate referrals to adjudication were made by
the defenders. Thereafter the pursuers raised the present proceedings against
the defenders, in which they originally claimed for a series of declarators and
decrees for payment relating to the contract works. The defenders
counterclaimed for payment of retention monies. Following sundry procedure,
including two debates, all of those claims except one have been settled. The
only remaining matter in dispute is a claim by the pursuers for loss of profits
caused by the fact that the opening of the premises was delayed by 28 days; the
pursuers aver that that delay was caused by breaches of contract on the part of
the defenders. The present opinion is concerned solely with that claim.
[3] The dispute that remains live is not particularly well focused
in the pleadings, which are largely concerned with other issues, but as they
emerged in evidence the pursuers' allegations can be summarised as follows.
First, stonework performed by the pursuers' masonry subcontractor had been
delayed and had caused delay and disruption to the fit-out works. Secondly,
the defenders' workmen had left debris on site, which had to be cleared by
Dimension Shopfitters to enable them to proceed with the fit-out works. That
too had caused delay and disruption at the start of Dimension's time on site.
Thirdly, the underground drainage works carried out by the defenders both
inside and outside the building had not been executed properly. Inside the
building it is said that the drains failed testing and in consequence had to be
replaced. Outside the building the intention was to retain the existing
Victorian drains with new connections added, but the drains had been damaged in
the course of the works carried out by the defenders. As a result substantial
remedial works were required, including the relaying of the drainage outside
the building. That caused delay and disruption to Dimension Shopfitters
because they had to arrange for all of the necessary remedial work and that
work delayed their own contract. The defenders deny that the drainage work was
carried out defectively apart from a small number of minor matters that were
easily remedied. The defenders further deny that any of the matters complained
of delayed Dimension to any material extent. Finally, the defenders claim that
the pursuers have failed to prove that any amount has been lost as a result of
the alleged delay. The three principal issues that arise are accordingly: (1)
whether there were any material defects in the drainage works carried out by
the defenders; (2) if there were any such defects, whether they caused material
delay in the completion of the phase 2 contract and the opening of the
premises; and (3) if there was such delay, whether loss has been proved in
consequence. I will deal with each of these matters in turn. Before doing so,
however, it is appropriate that I should say something about the general
evidence led in the case.
Evidence
[4] For the pursuers evidence was led from Mr Stewart Davidson,
the principal director of the contract architect and the individual who was
responsible for the architectural aspects of the project, and from Mr Peter
Graham, a chartered accountant with Grant Thornton UK LLP, who prepared a
report on the losses claimed by the pursuers. For the defenders, evidence was led
from Mr David Cooper, the defenders' construction director, Mr Iain Reid, who
had been the defenders' project manager, and Mr John Keenan, a civil engineer
who was now a contracts manager with the defenders but at the time of the
contract had been seconded as a consultant by his then employers, Bullen
Consultants. Mr Keenan had been site engineer and manager between July 2001
and January 2002, leaving after all the major construction works by the
defenders were complete.
[5] In addition to the oral evidence, extensive documentation
relating to the contract was lodged in process. This included a comprehensive
set of minutes of site meetings, which contains a detailed record of events,
and also the correspondence relating to the parties' dispute. As with almost
any building contract, the issues in dispute involved a large number of points
of detail, and on such matters the contemporaneous record contained in site
minutes and correspondence is obviously likely to be more reliable than the
unaided recollection of any witness. For this reason I have generally relied
on the documentation in reaching a view as to what happened. I have, however,
taken into account the fact that the site minutes were prepared by Mr Davidson,
whose evidence was not in all respects satisfactory; consequently I have used
the minutes with some circumspection, especially in relation to whether any
defects were present in the work carried out by the defenders. The minutes were
nevertheless of great assistance in determining whether any defects in the
drainage work caused the completion of the phase 2 works to be delayed. The
evidence of the witnesses was of assistance in giving a general view of events
and guiding me through the details of the documentation. In addition, I should
record that documentary evidence was not available as to the testing carried
out by the defenders on the drainage in about January 2002. On this matter I
have accepted the evidence of Mr Keenan, who was present during the
testing and whose evidence on the matter seemed to me to be both clear and
reliable.
[6] I found all of the defenders' witnesses to be clearly both
credible and reliable. Mr Cooper and Mr Keenan had a good recollection of
events and gave clear evidence. Mr Reid was perhaps less clear, but frankly
admitted occasions when he could not remember what happened. I had greater
doubts about Mr Davidson, whose evidence appeared to change as it developed.
This can be illustrated by four issues that arose in the course of his
evidence. First, during examination in chief he stated that delay had been
caused by the need to complete the stonework and to carry out remedial works
where it had been defectively performed by the defenders' subcontractor,
Balmoral Stone. That was in accordance with the pursuers' pleadings. In
cross-examination, he was taken through the documentation, and conceded that
the works carried out by Balmoral were relatively small in relation to the
total works. Ultimately, the site minutes revealed that the scaffolding had
come down according to the contract programme and that Balmoral were
progressing the works and not causing difficulties for phase 2. Finally, the
minutes of the site meeting that occurred on 18 June 2002 indicated that the quantity surveyor was to speak to
Balmoral to ensure completion by 24 July. At this point Mr Davidson accepted
that the stonework was not critical to progress and would not stop the opening
of the premises to the public. That itself indicates that Mr Davidson's
initial position was unsustainable. Secondly, further problems arose in
relation to Mr Davidson's evidence regarding a critical path analysis that he
had prepared in connection with the contract. Initially, he suggested that the
critical path analysis indicated that the defenders' breaches of contract had
produced a delay of three to four weeks. Subsequently, however, the extended
this to four to five weeks. There was no obvious reason for
this extension in the period of delay that is said to have been disclosed by
the critical path analysis. The actual critical path analysis was not
produced, although in evidence Mr Davidson said that he had looked at it in
connection with the extension of time claim. In these circumstances I do not
think that reliance can be placed on the evidence relating to the critical path
analysis, and the whole exercise to some extent undermines the general
reliability of Mr Davidson's evidence. Thirdly, a considerable amount of
evidence was led in relation to causes of delay other than drainage work, stonework
and the clearance of debris. When he was asked about these Mr Davidson was
inclined to minimize their significance, on occasion describing them as "snagging".
It became clear, however, that the other delays were highly significant, and it
seems to me that the tendency of Mr Davidson to discount them cast considerable
doubt on his reliability as a witness. Fourthly, in relation to the clearance
of debris, Mr Davidson started by suggesting that a delay of one week had been
caused, but was ultimately forced to concede that the work involved was minor.
I deal with this matter at paragraph [10] below. I should add that counsel for
the defenders invited me to hold that Mr Davidson was not a credible witness.
I found no indication in his evidence that he was doing anything other than
attempting to tell the truth, and accordingly I decline to make such a
finding. Finally, in relation to Mr Graham, I found him to be a credible and
generally reliable witness, although there were serious problems with the information
that was made available to him and some parts of his calculations were opened
to criticism; I deal with this aspect of his evidence when I discuss the issue
of quantum.
[7] Next, I must deal with an objection that was taken to certain
evidence for the defenders. Witnesses, in particular Mr Keenan (day 10, 2.50),
gave evidence of a video survey of the external drainage system that was
carried out by a firm called Martin at the outset of phase 1 of the contract
works. The video itself was not produced, and no explanation was given as to
why it was unavailable. Nevertheless a report (production 158) was
available in which a firm of engineering consultants, Bullen Consultants,
compared that video with a report based on a subsequent video taken at the
start of the phase 2 works by a firm called Drain-Cure. Mr Keenan (who was
employed by Bullen) gave evidence based on the Bullen report and stated that he
agreed with it. Objection was taken to any reference to the contents of the
video and to the report based on it on the basis that these were not the best
evidence; not only was the video unavailable but the maker of the report was
not available to be cross-examined. The Bullen report is highly qualified.
Thus in part 1.0 the author states that the Drain-Cure hardcopy report cannot
be relied on without the backup of video evidence, which was not available. At
paragraph 2.0 it is pointed out that the two video surveys travelled in
opposite directions, which meant that a direct comparison was impossible.
Nevertheless, the author was able to state that in general the two surveys
appeared to show the drain in a similar condition. Ultimately, however, at
part 3.0, the author stated that the existing sewer appeared to be in very poor
form structurally as most of the joints were either displaced or open. It
seems to me that the Bullen's report might be of value in demonstrating that
the Victorian drain was in poor condition. It does not, however, appear to me
to be of any real assistance in determining the critical question of whether
the condition of the drain had deteriorated in the course of the phase 1
works. For that reason I do not think that the objection is ultimately of
great significance. Nevertheless, I am of opinion that it is well founded; it
seems to me that the video taken by Martin is the primary evidence, and without
it the Bullen report is only secondary. This is exacerbated by the fact that
the author of the Bullen report did not give evidence. Consequently I sustain
the objection. I should add, however, that counsel for the defenders did not
rely on the Bullen report in her submissions, and she pointed out that the lack
of the video simply made it more difficult to prove that deterioration had
taken place during the phase 1 works; to that extent excluding the video favours
the defenders rather than the pursuers. I am inclined to agree with the latter
observation. Counsel for the pursuers attempted to rely on a passage in the
evidence of Mr Davidson where he stated that the defenders had passed him the
Martin video and stated that it showed the drain to be clear at the start of
the phase 1 works. For the reasons given in paragraph [19] below, however, I
do not think that any such admission can be relied upon; on this matter I
accept the evidence of Mr Cooper in particular that the defenders did not
examine the video but merely passed it on.
[8] I will now turn to the three main topics that form the subject
matter of the proof, starting with the question of whether there were any material
defects in the work performed by the defenders and their subcontractors.
Although ultimately the main issue was whether there were any defects in the
drainage work, the pursuers' original case involved delays caused by alleged
defects in the stonework and the need to clear debris from site, which was said
to be a breach of the contractual obligation to leave the site in a clean and
tidy condition. In his submissions counsel for the pursuers suggested that I
should allow one or two days delay for the clearance of debris. I will
accordingly deal briefly with these before turning to the question of the
alleged defects in the drainage work.
Stonework and debris.
[9] The stonework forming part of phase 1 was carried out by the
defenders' subcontractors, Balmoral Stone. The relevant work was about 1/13 of
the overall contractual works and, while some delay does appear to have
occurred, it was clear that the scaffolding was taken down on programme. This
was important, because the scaffolding would obviously have had an impact on
the ability of the pursuers to open the premises. Moreover, the minutes of the
site meeting held on 18 June
2002 indicated that the
stonework should be completed by 24 July. At that point the stonework was
clearly not critical to completion and would not stop opening of the premises.
[10] In relation to debris, Mr Davidson gave evidence that the
defenders had left the site in an untidy condition at the end of phase 1, and
that this would cause delay at the outset of phase 2. He appeared to indicate
that that had resulted in delay to the whole of the phase 2 works. The minutes
of the site meetings, however, indicated that the clearance of debris was not a
major issue. At the phase 2 pre-contract meeting, held on 21 February 2002
(production 27, paragraph 3.3 .1), Mr O'Donnell, the individual principally
involved on behalf of Dimension Shopfitting, stated that he had carried out an
inspection of the site. There was no mention of debris, however, which would
be unusual if the problem was serious. At site meeting no 2, held on 12 March
(production 29, paragraph 20.1), Mr O'Donnell mentioned that site setup
procedures were now completed, and once again there was no mention of debris.
The work involved in clearing any debris appears in the quantity surveyor's
draft final account (production 284, page 117), where it is stated that
clearing building debris in the basement took two labourers two days. That
contrasts with Mr Davidson's initial estimate that clearing debris delayed the
works by one week. Mr Davidson eventually agreed that clearing the debris was
not a big job, and that it could be done along with the other works. The entry
from the quantity surveyor's account related to debris in the basement, but no
evidence was led as to any delay caused by other debris. Overall I conclude
that the need to clear debris was of minor significance, and did not delay
completion in any way.
Defects in drainage work
Internal drainage
[11] The drainage work performed within the premises and that
performed externally were distinct, in that the internal drainage was entirely
new whereas the external drainage works sought to make use of the existing
drains so far as that was possible. The work was carried out by a
subcontractor, Dicon. Its later stages were supervised by Mr Keenan, whom I
found to be a convincing witness and I accept his account of what happened. He
gave evidence that he had left the site in January 2002, prior to final
snagging. He had not been aware of any complaints regarding the internal
drainage. The whole of the internal pipes had been tested successfully. Those
tests were witnessed by Mr Tainsh, the official of the Building Control
Department of Perth and Kinross Council who was responsible for approval of the
drainage system, and he had approved of them. Mr Tainsh had marked up a plan
of the drainage with records of his site visits. Mr Keenan had asked Mr Tainsh
for a copy of that plan, but Mr Tainsh had declined to provide one; he gave
evidence (and Mr Cooper concurred in this) that documentation and certification
would not normally be given until the completion of the entire project, not
merely phase 1. In correspondence that passed after the start of the phase 2
works (for example, production 294, page 10) Mr Davidson had suggested that he
had been told by Mr Tainsh that one section in the north wing, where the pipe
was suspended under a floor, had not been tested in Mr Tainsh's presence. This
was put to Mr Keenan both in chief (day 10, 11.59) and towards the start of his
cross-examination (day 10, 3.25), and he was adamant that that section was
tested and the tests were witnessed. Mr Tainsh did not give evidence. On this
matter I accept the evidence of Mr Keenan. Consequently I conclude that the
whole of the internal drainage had been satisfactorily tested prior to the
point when Mr Keenan left the site in January 2001.
[12] In February and March 2001 the handover to phase 2 took
place. The question of drainage was raised by Dimension Shopfitting at
the pre-contract meeting for phase 2, held on 21 February 2001, and was discussed at the site meetings that took
place thereafter. In the minutes of the first contract meeting for phase 2,
which was held on 5 March 2002 (production 28), it was noted (by Mr Davidson,
at paragraph 20.2.1.1) that the external drainage connections were in poor
condition, particularly where new pipework was connected to the existing
manholes. In relation to the internal drainage, it was noted (paragraph 20.2.1.1)
that testing was currently taking place to ascertain the extent of the works
required to rectify the drainage system. At the second phase 2 contract
meeting, held on 12 March 2002 (production 29), it was reported
(paragraphs 27.11 and .12) that the drainage lines were not standing to
test. A number of alleged defects in the drainage system were recorded. On 13
March Mr Davidson wrote to the defenders (production 284, pages 12 and 13)
expressing highly critical views on the drainage; he stated that the system had
been tested on 12 March by the phase 2 plumbing subcontractors and the system
had failed. Mr Reid, the recipient of that letter, then contacted Mr Tainsh
(production 296, page 26) and obtained his confirmation that he was satisfied
with the drainage system apart from the need for rebenching at two external
manholes. The rebenching was a procedure that was fairly easily carried out;
one manhole was rebenched on 21 March and the other required to be realigned to
satisfy building control and was rebenched at that point; the realignment was
not in any way attributable to the defenders' work (Mr Cooper, day 7, 2.30).
Mr Reid also gave evidence that he had contacted Mr Keenan at this point and Mr
Keenan had told him that the whole system had been satisfactorily tested before
he went off site.
[13]
Thereafter Mr Cooper and Mr Keenan visited the site on 18 March. Both Mr Cooper
and Mr Keenan gave evidence that Dimension had started opening up sections of
the existing drains, in particular sections where it ran through or under
concrete floors (day 7, 2.52; day 10, 12.14). That caused both men great
concern, because in order to obtain access to a pipe running under concrete it
was necessary to use jackhammers and electric saws. That was likely to cause
significant damage to the pipes. Indeed, Mr Davidson in cross-examination (day
6, 12.27-12.35) accepted that, if jackhammers were used to remove concrete and
the concrete was bonded to the drainage pipe, that would cause damage to the
pipe. He further agreed that the areas exposed by Dimension were in the area
of the pop ups (sections of pipe coming through the floor with a view to
connection to sinks, wash hand basins, lavatories and the like); those were
areas where the floor was concrete. Despite those concessions, Mr Davidson's
view was that the work carried out by Dimension was performed carefully and
would not have caused damage to the drainage system. On this matter I prefer
the evidence of Mr Keenan and Mr Cooper, who both clearly thought that damage
would be caused. That seems to me to be obvious, in view of the vibration that
devices such as jackhammers set up. Mr Cooper and Mr Keenan further give
evidence that it became apparent to them that additional branches to the
drainage system had been added by Dimension, and that that might further
compromise its integrity (day 10, 12.19).
[14] Mr Davidson gave evidence that, by the time of the visit by Mr
Cooper and Mr Keenan on 18 March, the drainage had not been worked on. In
view of the clear evidence of Mr Cooper and Mr Keenan I reject that evidence.
Moreover, the contract programme for phase 2 (production 319) makes clear that
first fix plumbing was scheduled to start on 4 March. Dimension's site
set up took longer than was originally anticipated, and consequently that date
probably slipped by some days. Nevertheless, it seems clear that the plumbing
works would have started prior to 18 March, and there was no suggestion
that there had been a particularly late start with the first fix plumbing.
Furthermore, Mr Davidson made reference to the testing carried out on 12 March,
but he did not take part in those tests and no evidence was led from anyone who
did in fact conduct the tests. The failure to lead such evidence clearly
prejudiced the defenders, because they were unable to cross-examine anyone who
took part in the testing. For these reasons I am unable to attach weight to Mr
Davidson's evidence about those tests. I prefer the defenders' evidence, that
by 18 March significant work had been carried out on the drainage system
and that that work had given rise to a major risk that the integrity of the
system would be compromised.
[15] In the course of the visit of 18 March Dimension's
subcontractor carried out certain testing, which disclosed a failure in one section
of pipe. The defenders wanted to carry out their own testing, and returned to
site on 21 March to do that. The system of testing used by the defenders'
representatives was different from that used by the pursuers' representatives.
The defenders' representatives used balloons filled with air to block off
sections of the system for testing. The pursuers' representatives, by
contrast, used plastic stoppers. The defenders' witnesses were adamant that
plastic stoppers were not a satisfactory means of isolating sections of the
system because they did not achieve a particularly tight connection and leakage
was liable to occur (for example, Mr Cooper, day 6, 2.50; Mr Keenan, day
10, 12.25). I accept the defenders' evidence on this matter; it seems to me
that a balloon is likely, because of its inherent flexibility, to achieve
significantly tighter connection than a plastic stopper. This is a further
reason for doubting the results of tests carried out by the pursuers'
representatives. The result of the tests carried out by the defenders on 21
March was that every section of internal piping bar one passed the test (Mr
Keenan, day 10, 12.21). Mr Keenan and Mr Reid indicated that the intended to
return in order to investigate that section further. They returned to site on
27 March accompanied by Mr Tainsh, but by then Dimension had already started to
replace the internal drainage.
[16] The decision to replace the whole of the internal drainage had
been taken by Mr Davidson by 19 March at latest. The matter is mentioned in
the minutes of the phase 2 contract meeting held on that date (production
30, paragraph 33.11), where Dimension were instructed to proceed with an
amended and realigned system as discussed with the Architect and with their
plumbing subcontractor. It is further apparent from a fax of 20 March that Mr
Davidson sent to Dimension (production 105), in which Dimension were
instructed to "commence with the agreed strategy to relay the system". Mr
Davidson gave evidence (day 6, 11.30) that the strategy to relay the system was
adopted because the tests had been unsatisfactory; if the defenders' tests had
been satisfactory he would not have proceeded with the instruction to relay.
He did not suggest that relaying was the only option open to the pursuers, and
he further agreed in cross-examination that the defenders had not been given
sufficient time to remedy the position. Mr Davidson further gave evidence that
the phase 2 plumbing subcontractor had carried out a test on 27 March, which
had shown the system to fail. In this case, however, it is clear that the test
was carried out after the opening up of the drainage, and no witness was called
who carried out that test. As with the earlier testing, the failure to call
such a witness prevented the defenders from cross-examining on what actually
took place. For these reasons I am of opinion that no weight can be placed on
the testing on 27 March.
[17] The defenders accepted that some defects existed in the
internal drainage system. As already mentioned, two manholes where the
internal system connected with the external drainage required rebenching; one
of these required a new cover. In one area pea gravel had been omitted under a
run of pipe, and some work was required on suspended pipe underneath a timber
floor. The defenders offered to repair or pay for the repair of all of these.
It was a matter of agreement that not much work was involved in any of these
tasks (for example, Mr Davidson, day 6, 1.57-2.25), and that the work of repair
would not take long. Apart from these matters, I am of opinion that the
pursuers have failed to prove any defects in the internal drainage system. I
reach this conclusion for two reasons: first, no evidence was led from anyone
who was actually involved in the tests carried out on 12 and 27 March, and
secondly, it is likely that significant work had been carried out on the system
by Dimension's subcontractors prior to those dates and that such work was
likely to cause defects to emerge in the system. Once the work of opening up
had started, I am of opinion that no reliance can be placed on any testing
because it was probable that the work carried out to concrete floors, using
jackhammers and the like, would produce cracking in the system.
External drainage
[18] The external drainage work made use of an existing Victorian
fireclay pipe which ran to the east of the building and connected to the public
sewer in Mill Street. Connections were to be made to the
existing manholes, but one of these was to be replaced. In addition, work was
required on a section to the north of the property, running between manholes 1
and 2. The pursuers' case on the external drainage was in summary that in May
2002 it was discovered that a significant number of defects existed. Some of
these were said to have arisen from new connections made into the drain by the
defenders, which were said to be faulty. Others involved cracks and displaced
joints in the existing drain, which were said to have been caused by the phase
1 works, and in particular by heavy plant which crossed the line of the drain.
[19] At the start of the phase 1 works Mr Davidson instructed the
defenders to obtain a camera survey of the existing drain (minuted in
production 5). The defenders did so, and provided a copy to Mr Davidson. Mr
Davidson's evidence was that, when the video was handed over, the defenders
told him that the drain was intact and clear. The evidence of Mr Cooper,
however, was that no one at the defenders had actually watched the video. It
had been obtained from a specialist firm, Martin, and all that the defenders
did was to obtain the survey and pass the results to Mr Davidson (day 7,
12.16). On this matter I prefer the evidence of Mr Cooper; I think that he is
more likely to recall whether or not the defenders actually looked at the
video. Moreover, Mr Davidson's evidence was not supported by any reference in
the documentation, whether in the site minutes or elsewhere. Mr Davidson also
gave evidence (day 6, 2.25) that he had seen the video and had been satisfied
with the condition of the drain. The video itself was not produced.
[20] When the phase 2 works were under way, it became apparent that
a new section of external drain laid between manholes 1 and 2 had slumped; this
was accepted by the defenders and remedial work was in due course carried out.
As a result of this defect, a further video survey was commissioned from
Drain-Cure. A copy of this was sent by Mr Davidson to the defenders on 26 May
(production 284, page 34). It was accompanied by a lengthy fax in which Mr
Davidson set out the defects that he thought the video revealed in the drainage
system. No witness from Drain-Cure was led to speak to the report, and the
accompanying video was not available. Mr Davidson had not inspected the drain
himself; he had relied entirely on interpretation of the Drain-Cure video. For
this reason Mr Davidson's evidence on this matter must, I think, be approached
with some care.
[21] The fax of 26 May indicated that the connections between the
internal and external drainage were defective. In relation to this matter, the
only evidence available for the pursuers was that of Mr Davidson, who, as
explained in the last paragraph, relied entirely on the Drain-Cure video. Mr
Keenan, however, gave evidence that Mr Tainsh had inspected and approved all
the connections with the existing drain; moreover, when those connections were
made, Mr Keenan himself had not been aware of any damage to the drain. On this
matter I prefer the evidence of Mr Keenan, who was a careful witness and
who had been directly involved in the works at first hand.
[22] Further defects identified in the fax of 26 May were displaced
joints and circumferential cracking. The pursuers submitted that these
resulted from inadequate protection of the drainage during the phase 1 works,
which was a breach of the contractual duty to protect the existing drainage.
In his evidence Mr Davidson gave evidence to that effect; he suggested in
particular that excessive loading had been placed on the drains as a result of
plant brought on to site by the defenders. It is notable, however, that in the
documentation relating to the phase 1 works there is no indication that that Mr
Davidson at any time commented on the loadings on the drain, or claimed that
there was inadequate protection from such loading. Moreover, in
cross-examination (day 6, 2.10) Mr Davidson explained his view as based on an
attempt to explain the difference between the two camera surveys. He took the
view that the plant used in carrying out the works, including lorries,
contributed to the defects in the second survey. He was asked whether there
was inadequate protection at that stage and replied that it was difficult to
say, as he had only been on site once per week. Nevertheless, the works were
major; the whole car park at the front of the building had been covered with
plant and spoil heaps and had been very congested. He was asked whether he was
aware that the works were without adequate protection and replied that he was
not looking for that and was not aware of it. He felt that he would probably
have said something if he had noticed it. Against that background, it seems to
me that Mr Davidson's evidence on this matter is essentially speculation; a
difference existed in the condition of the drain in the two surveys; there must
be an explanation; and the only possible explanation was loading with plant.
Moreover, Mr Davidson's evidence must be set against clear evidence from
Mr Cooper and Mr Keenan (day 10, 2.31) to the effect that there was no
major loading above the drain. The drain was at a depth of between 1.5 and 2.5
m, and when cranes were on site appropriate protection was provided above it,
in the form of spreader plates which came with the crane. These were used on
top of timbers. That evidence appeared to me to be very clear, and I prefer it
to that of Mr Davidson. On that basis, I find that it has not been proved that
anything occurred during the phase 1 works that might involve undue weight on
the old fireclay pipes; instead, I conclude that the defenders took proper
steps to protect the pipes from plant. On this basis I am unable to draw the
inference that the phase 1 works caused damage to the old pipes. In an
appropriate case it is clearly possible to draw an inference of causation from
the fact of damage. In the present case, however, there was uncontested
evidence (Mr Keenan, day 10, 2.42, 3.02), that the condition of fireclay
pipes deteriorates with age, and that in a Victorian pipe defects are likely to
exist to some extent. It seems to me that that factor makes it difficult to
draw any inference of causation from the existence of damage and in view of the
evidence that I have accepted about the care that the defenders took to protect
the pipe I find such an inference to be unwarranted.
[23] In any event, the evidence relied on by the pursuers as showing
damage to the pipe was the comparison of the two videos, that taken by Martin
at the start of the phase 1 works and that taken by Drain-Cure at the start of
the phase 2 works. Neither of these was produced, although the report that
accompanied the Drain-Cure video was available. Nevertheless, it is the
comparison between the two that is critical to the pursuers' case. As
mentioned above at paragraph [7], counsel for the pursuers objected to any
evidence about the contents of the Martin video, on the basis that anything
other than the video was not best evidence, and I have sustained that
objection. Nevertheless, as mentioned at paragraph [7], it seems to me that if
anything the absence of the video undermines the pursuers' case, because a
comparison of the two videos would be the most convincing evidence that
deterioration had occurred. In fact, the only evidence that suggested that the
Victorian drain was in good condition at the start of phase 1 was the evidence
of Mr Davidson that he had been told by the defenders' representatives
that the drain was intact and clear. This was contrary to the evidence of Mr
Cooper, and I have declined to find that any such statement was made. I am
accordingly of opinion that the pursuers have failed to make out a critical
element in their case, namely that at the start of the phase 1 works the
Victorian drain was intact. I reach this conclusion without any reference to
the report from Bullen Consultants (production 158) based on a comparison of
the Martin video and the Drain-Cure survey report (see paragraph [7]).
[24] In the foregoing circumstances I conclude that the pursuers
have failed to establish that any deterioration in the condition of the
Victorian drain occurred during the course of the phase 1 works. I further
conclude that, even if there was any such deterioration, the pursuers have
failed to establish that it was caused by the actings of the defenders.
Indeed, for the reasons explained previously, I consider that the defenders
took reasonable care to protect the existing drainage line during the phase 1
works.
Delay
[25] The second main issue in the case is whether, if the pursuers
have established that defects existed in the drainage system, such defects
caused material delay in the completion of the phase 2 contract and the opening
of the premises. For the pursuers it was submitted that I should find that the
opening of the premises was delayed by four weeks or such lesser period as
could be attributed to the delays caused by defects in the internal and
external drainage. The premises in fact opened 28 days later than was provided
for in Dimension's phase 2 programme (production 319). In my opinion the
pursuers have wholly failed to make out this aspect of their claim, for three
main reasons. First, it is very clear from the minutes of the site meetings
for the phase 2 contract that major delays occurred as a result of the
performance of two contractors employed directly by the pursuers, Arthur McKay,
who were the electrical contractors, and The Music Company, who were
responsible for installing sound and lighting systems in the premises. Even if
some delay resulted from the drainage works, it was insignificant compared with
the delays caused by the work of those two contractors. Secondly, further
delays occurred as a result of the installation works carried out by Dimension
Shopfitters during the phase 2 contract. These related to a number of matters,
notably the kitchen equipment. It is obvious that none of the foregoing delays
was in any way attributable to the defenders. Thirdly, the pursuers have
failed to provide any systematic analysis of the effect that the various causes
of delay had on the date of opening of the premises. This is important in view
of a submission by the pursuers that the court should apportion the losses
sustained by the pursuers among the various causes of delay in the manner
suggested in John Doyle Construction Ltd v Laing Management
(Scotland) Ltd, 2004 SC 713, at paragraphs [16]-[20]. If that is to be
done, it is important that there should be some sort of evidential basis for
the apportionment exercise, and in my opinion this was wholly lacking in the
present case.
[26] I propose first to consider the minutes of the site meetings
relating to the phase 2 project in order to explain how delays caused by
Arthur McKay and The Music Company and delays in Dimension's own work impacted
on the progress of the works. Thereafter I will consider the pursuers' analysis
of delay, including its relationship to the events disclosed in the site
minutes. In considering the site minutes, what is in my opinion of great
significance is, first, the relatively small number of references to the
drainage works, which disclose that the drainage was complete well before the
end of the phase 2 works, and secondly, the large number of references to
delays caused by the matters mentioned in the last paragraph.
[27] At the beginning of the phase 2 contract Dimension's programme
was delayed by one week because an extra week was required as lead-in time, and
all dates in that programme have to be adjusted accordingly. The programme
contemplated that first fixed electrical work would be completed by 28 April,
adjusted to 5 May; the second fixed electrical work by 22 May, adjusted to 29
May, and sound and light by 26 May, adjusted to 2 June. Mr Davidson agreed
that the work of the two direct contractors dealing with these items, Arthur McKay
and The Music Company, was a cause of the ultimate delay in opening (day 2,
2.59). Moreover, as early as 28 March Dimension had given notice under clause
25 of the contract (production 108) that the progress of the works was likely
to be delayed, and identified the work by Arthur McKay and The Music Company as
causes of the delay, as well as the drainage works. At site meeting no 5, held
on 2 April, Dimension's site manager, Mr O'Donnell, stated that Dimension were
maintaining their programme despite drainage issues, but expressed concerns at
the progress that was being made by Arthur McKay and The Music Company, and in
particular the hours that were being worked by those contractors (production
31, paragraph 46.9.1). That entry forms the pattern for a number of subsequent
site minutes. In these it became clear that Dimension were greatly concerned
at the progress that was made on site by Arthur McKay and The Music Company,
and at the failure of the employees of those companies to work full site hours.
That concern was shared by Mr Davidson. For example, on 3 April he wrote to
Dimension (production 110) to state that both he and the pursuers were
stressing the importance of the contract programme to the pursuers' directly
employed contractors and that both Arthur McKay and The Music Company had been
advised to rectify their manpower levels on site. At the next site meeting,
held on 9 April (production 32), concerns were raised by Dimension regarding
the programming and working practices of Arthur McKay (paragraph 53.1.4).
Dimension also stated that they had lost time because both The Music Company
and Arthur McKay were behind their respective programmes (paragraph 55.8.1).
Arthur McKay were not working site hours, and The Music Company had started one
week late; delays had occurred in cabling work, and the result was that wall
and ceiling sheeting trades were prevented from working properly. This
indicates the way in which the electrical and sound and light work carried out
by Arthur McKay and The Music Company was critical to the overall programme.
The problems with the hours worked by Arthur McKay and the consequent
delay to the general site programme were highlighted again at paragraph 57.2.1.
The manpower available on site from The Music Company was also criticised at
paragraph 52.1.6.
[28] At the next site meeting, held on 16 April (production 33,
paragraph 61.2.4), it was noted that The Music Company had increased their
manpower but (at paragraph 61.12.1) that delays had been caused by lack of
manpower on the part of both Arthur McKay and The Music Company, with the
latter contractor being a week late in starting on site. On 18 April Dimension
wrote to the Architect to apply under clause 25 of the contract for an
extension of time of two weeks (production 115). The delay was attributed to
both lack of progress by Arthur McKay and The Music Company and the additional
drainage works. Two weeks delay was attributed to the former and 11/2 weeks to
the latter, the two obviously running concurrently.
[29] At site meeting no 9, held on 30 April, Dimension once again
expressed concern at the progress being made by Arthur McKay (production 35,
paragraph 72.21.1); this matter was considered at some length, and clearly
provoked significant discussion. At the same meeting (paragraph 73.1.1) the
issue was raised of the programme and installation dates for Stanguard, the
designated supplier of certain kitchen fittings. The concern about lack of
progress regarding the kitchen fittings was repeated at site meeting no 10,
held on 14 May (production 37, paragraph 84.9), and at site meeting no 11, held
on 21 May, it was noted (production 38, paragraph 91.8) that Stanguard was no
longer involved with the project and that the quantity surveyor was to advise
on the appointment of a replacement supplier of kitchen fittings. At the next
site meeting, no 11, held on 28 May, the programme analysis was referred to
(production 39, paragraph 97.7), and it was noted that the external works were
two weeks behind schedule; it was also noted (paragraph 98.2) that the drainage
system had passed tests. At the same meeting it was noted that The Music
Company were having difficulty in ordering certain items of equipment, which
were on a two to four week lead in time; this had implications for the
programme. The following site meeting, no 12, was held on 4 June (production
40). In the programme analysis section of the minute, it was noted (paragraph,
103.7) that The Music Company would not complete on time. It was further noted
(paragraph 103.19.1) that information was required regarding the refrigeration
equipment and (paragraph 104.2.3) that the pursuers had to supply fittings for
the lavatories. At the next site meeting, no 13, held on 11 June, the minute
recorded the fitting programme for The Music Company (production 41, paragraph
109.2): television units (about 30 in total) were to be installed from 18 June
onwards, and the lighting fittings were to be installed by 3 July. The
stainless still fittings in the kitchens were to be installed by 23 June and
the second fix of the refrigeration equipment was to be at a date still to be
confirmed (paragraph 109.6). Fixed seating was still being installed
(paragraph 109.8.1). It was further noted that the main drainage had now been
completed and tested in full, and backfilling was taking place. Drainage was
being installed to the outbuildings (a laundry) (paragraph 109.11); Mr Davidson
stated that the drainage to the laundry did not cause any delay.
[30] Site meeting no 14 was held on 18 June (production 42). Arthur
McKay were not represented (paragraph 114.3), which was described as "not
helpful or acceptable". So far as The Music Company was concerned, it was
noted (paragraph 115.2) that the programme had slipped approximately 1 week,
and that this had a significant impact on the pursuers' ability to open and
trade. The Music Company were directed to complete installation by 27 June and
to carry out programming between 27 June and 3 July, supplementing manpower as
necessary. Lifts were to be installed between 24 and 27 June (paragraph
115.5.1) and kitchen equipment was to be delivered on 21 June (paragraph
115.6.2). The date for kitchen equipment should be compared with the programme
(paragraph the 19), which indicated that, allowing for one week of slippage,
kitchen equipment should have been delivered by 20 May. External drainage was
recorded as complete (paragraph 115.10). The site manager for Arthur
McKay was once again not present (paragraph 115.16). At paragraph 115.16.3 it
was recorded that Arthur McKay were now behind programme by 10 days, holding up
finishing work, particularly painters. Disruption was being caused to paint
finishes by wires being pulled through, incorrect locations, and holes cut
incorrectly requiring patching. Areas available for completion were not being
completed. Despite being behind programme, Arthur McKay were not working
overtime; this was recorded as unacceptable, and Arthur McKay were instructed
to issue a full report on programme. A complaint about cabling and further
concerns about inadequate manpower were recorded at paragraph 115.16.4.
Finally, it was recorded (paragraph 115.17.2) that another subcontractor, Bell
Security, were still to fix a Redcare line (a security device which Mr Davidson
thought was perhaps relevant to insurance). The following day the Quantity
Surveyor wrote to The Music Company (production 133) to complain that excessive
holes and damage were being caused in the walls and ceilings in a part of the
building that had already been fully painted; this would cause problems with
making good.
[31] The next site meeting, no 15, was held on 26 June (production
43). The Music Company were now to complete by 3 July, with programming of
their installation thereafter (paragraph 121.2). All kitchen equipment
was to be installed by 2 July (paragraph 121.5.3). Dimension again
complained that Arthur McKay were not using sufficient manpower (paragraph
121.11), and it was recorded that there was a disagreement between Dimension and
Arthur McKay as to the labour required on site. The works were behind
programme, and there had been difficulties on site between Arthur McKay and The
Music Company. A substantial number of specific items requiring attention of Arthur
McKay were recorded in paragraph 121.11. At paragraph 121.13.1 it was
noted that certain work was required to complete the stairs; Mr Davidson stated
(day 5, 11.54) that a certificate of practical completion would not be issued
by the Building Control Department until such work was completed. Floors were
still being installed, and were to be completed by 30 June (paragraph 122.2).
[32] Site meeting no 16 was held on 2 July (production 44). As
would perhaps be expected at this stage in a fit-out contract, a large number of
uncompleted items were discussed. The kitchen manifold and gas fitting works
were to be completed by 3 or 4 July (paragraph 128.1), and the
subcontractor fitting out the kitchen was to return to site on 4 July to
complete its work following the manifold alterations (paragraph 128.5.1).
The restaurant seating was completed and available for delivery (paragraph
128.5.3). Building Control had required that a fan be relocated in order to
obtain a completion certificate (paragraph 128.8.2, explained by Mr Davidson at
day 5, 12.22). Arthur McKay's progress was discussed at length at
paragraph 128.10. Progress was not as agreed at the previous site meeting, and
now all bars and public areas were to be completed by 5 July. The Architect
further directed Arthur McKay to ensure that all works were completed by that
date in order to permit follow-on trades to proceed. Concern was also
expressed regarding cabling, and completed cable routes required to be
addressed. Building Control had also instructed the insertion of window
barriers at certain locations (paragraph 128.11.2). Arthur McKay required to
relocate seven of the sounders (paragraph 128.15.1). At paragraph 129.1.1 it
was noted that, because of the requirement to install additional electrical
detectors and the number of outstanding items of work, the programme was
currently unachievable. The cleaners who would move in on completion of the
works were accordingly put off until 8 July. At paragraph 129.3 it was
recorded that The Music Company were concerned at the load imposed on certain
circuits that were not designed for the purpose. As a result delays would be
caused, but that section of work should be complete by 5 July. The procedure
for handover to the pursuers was considered at paragraph 130.1.1, where it was
noted that the Architect confirmed that he would arrange a final inspection
with the Building Control Officer and the Firemaster for about 9 July. For
this purpose certification was required from Arthur McKay. In the event, the
pursuers took possession of the premises on Friday, 12 July.
[33] Even after completion problems continued with the electrical
work. On 26 July, following complaints by the pursuers, Mr Davidson wrote to
Arthur McKay (production 136) to state that the electrical installation was
still not complete and that defects were not being dealt with with sufficient
urgency; particular defects were set out. Further correspondence passed
thereafter. The pursuers employed Hawthorne Boyle, consulting engineers, to
investigate Arthur McKay's work, and concerns were raised about the standard of
workmanship and design of the electrical works. Thereafter they refused to
make full payment to Arthur McKay for the works carried out.
[34] In evidence Mr Davidson expressed the opinion that a delay of
four or five weeks was attributable to the drainage works carried out by the
defenders. In my opinion that view was quite unsupported by the evidence. The
site minutes and correspondence indicate very clearly that the drainage works
were complete well before the end of the phase 2 works. Moreover, the latter
part of the drainage works consisted of external works, where the effect on
programming was clearly less than the effect of internal works. By contrast,
the pursuers' difficulties with Arthur McKay and of the Music Company continued
right to the end of the phase 2 works and, in the case of Arthur McKay, even
beyond that. Clearly the effect of the drainage works carried out during phase
2 could still be relevant to overall completion in that it could have delayed
or hindered the electrical and sound and lighting works. In the minutes,
however, there is no indication that I have been referred to that any such
event occurred. Had this been a significant problem, I would have expected a
specific reference at one of the earlier site meetings, but there is no such
reference.
[35] Moreover, if it were to be established that the drainage works
in phase 2 had caused delay to overall completion, one would normally expect
some sort of critical path analysis to be available. Mr Davidson indicated
that he had carried out such an analysis as part of his time review process,
and that that formed the basis of his view on delay (day 7, 12.49, at the end
of re-examination). The difficulty with that evidence is that no critical path
analysis was produced, and it is quite impossible to subject such an analysis
to critical scrutiny without seeing the whole document. In particular, the
linkage between activities is of crucial importance in such an analysis, and
the actual delays that are recorded in the analysis must be tested against the
site minutes and other documentation. Indeed, proper cross-examination of Mr
Davidson on such an analysis would be wholly impossible without having the
document available. In addition to that, the analysis that Mr Davidson spoke
to was carried out for the purposes of an extension of time claim, which is
conducted under specific contractual terms. These do not apply in their
entirety to an analysis of the overall delay caused to the phase 2 contract (an
analysis in which delays caused by other factors, notably the electrical works
and the sound and lighting works, must clearly be taken into account).
Furthermore, Mr Davidson expressly agreed at the start of his cross-examination
(day 5, 2.59) that other works caused delay, and these were recorded in the
site minutes; he specifically mentioned Arthur McKay and The Music Company.
[36] Both counsel referred me to the analysis of global claims in
John Doyle Construction Ltd v Laing Management (Scotland) Ltd,
supra, at 2004 SC paragraphs [15]-[16]. Counsel for the pursuers
submitted that I should make an award of damages based on the daily loss
suffered by the pursuers as a result of the late opening of the premises, apportioning
that loss between delays caused by the drainage works and delays caused by
other matters. It is clear from the Court's analysis in John Doyle
Construction that if apportionment is to take place, two conditions must be
satisfied. First, it must be possible to hold that the events for which each
party is responsible are a material cause of the loss. Secondly, the causes of
the loss must be "truly concurrent, in the sense that both operate together at
the same time to produce a single consequence". In the present case, I am of
opinion that neither of these conditions has been satisfied. The history of
the phase 2 contract, as described in the site minutes and summarized at
paragraphs [27]-[32] above, indicates that the dominant causes of the late
opening were the delays in the work performed by the two contractors employed
directly by the pursuers, Arthur McKay and The Music Company, and to a lesser
extent the delays that arose during the phase 2 contract in relation to, for
example, kitchen fittings. Such delay as was caused by the additional drainage
works in phase 2 was, by contrast, of lesser significance and occurred at a
fairly early stage in the phase 2 works. In that situation, if delay caused by
drainage works is to be regarded as a concurrent cause of the final delay, some
form of analysis of causation, normally in the form of a critical path
analysis, is essential. It is not particularly difficult to perform such
analyses; they are used commonly in the construction industry, and indeed Mr
Davidson indicated that he had used one in considering an extension of time.
No such analysis was available, however. In those circumstances I do not think
that the pursuers have established that the drainage works were a material
cause of the delay in opening. In relation to the second requirement, I
consider that the pursuers have not established that delays caused by the
drainage work continued to operate in the latter stages of the phase 2
contract, and have certainly not established what delay to the works was the
defenders' responsibility. In these circumstances it is impossible to hold
that the effect of the drainage works on the programme operated concurrently
during the latter stages with the delays caused by the client direct
contractors and elements in Dimension's own work. Once again, the absence of a
critical path analysis is of the greatest importance; it is simply impossible
to form a view on the relative significance of the various possible causes of
delay. In addition, the present case as presented by the pursuers does not
appear to be one of mere delay caused by the phase 2 drainage works, but rather
one involving a significant amount of disruption. As indicated in John
Doyle Construction at paragraph [17], disruption cases are inherently more
complex than cases of mere delay. In such cases an appropriate analysis of the
causes of delay is essential, but no such analysis was available. That makes
the attribution of delay to the various different causes even more difficult.
In all the circumstances I conclude that the pursuers have failed to establish
that any delay was caused by works for which the defenders were responsible,
and that in any event they have failed to provide a sufficient basis in
evidence for apportioning delay between those works and other causes of delay.
Quantification of the pursuers' claim
[37] The third element in the pursuers' case is the quantification
of their claim. The only evidence on this matter came from Mr Graham, who
prepared a report (production 309). The report itself is a conventional
calculation of loss of profits and additional and wasted costs caused by the
late opening. These were calculated at г72,680, consisting of г32,726 in
respect of loss of profits, г37,974 in respect of additional and wasted costs,
and г1,980 in respect of financing costs. The loss of profit calculation was
based on the trading figures for the premises disclosed in the management
accounts for the first 11 months of trading, but excluding periods such as
Christmas and the first 15 weeks of trading when conditions could not be
described as normal. In that way a figure for "normal" monthly trading was
obtained, and this was attributed to the period of delay, bringing out the
figure of г32,726. The additional and wasted costs were the cost of employing
the staff for the premises during a 28 day period of delay. This included the
cost of renting a flat in Perth for the manager of the nightclub during
that period and certain travelling costs. It also included costs incurred in
relation to telephone rental, insurance, and heat, light and power. Finally,
finance costs in relation to the two previous elements were calculated, based
on the rate of overdraft interest charged to the pursuers at the time.
[38] As I have indicated, the calculation in the report is of a
fairly conventional nature. Nevertheless, a number of defects became apparent
in the information relied on and in certain elements included in the report.
First, the loss of profit calculation was based entirely on figures derived
from the management accounts of the pursuers. These had not been prepared by
Mr Graham or audited by him, and he could not vouch for the accuracy of any of
the figures that he used. The supporting material was not made available. The
accuracy of the figures used is clearly of critical importance, and the failure
to provide the necessary vouching appears to me to be a serious defect in the
calculation of loss. Secondly, counsel for the defenders made various
criticisms of the additional and wasted costs included in Mr Graham's
calculation. In relation to the cost of employing staff, she pointed out that
the premises were ready for occupation by the pursuers after they were taken
over on 12 July. Mr Graham's calculation of the wasted cost of employing
staff was, however, based on the period of 28 days ending on 19 July. That may
have been the point when the premises were ready for opening, but staff would
have been required to make them ready, and wages paid during the period between
12 July and 19 July cannot be regarded as wasted. I agree with that criticism
of Mr Graham's calculation. Counsel for the defenders further criticised the
fact that Mr Graham made an allowance for one month's rent on a flat in Perth occupied by the manager of the premises, on the basis
that there was no information as to why he required a flat there.
Nevertheless, it seems to me that a manager moving from elsewhere might well
require accommodation in Perth during the set-up period, and if opening
was delayed those expenses would be required over a longer period.
[39] Counsel for the defenders also criticised the travelling costs
that are included for one employee, on the basis that no explanation was given
as to why they were incurred. In my opinion that is correct, and the
calculation would require to be amended on that ground. Criticism was also
directed at the telephone charges; in addition to line rental, which the
pursuers claim was incurred for a longer period than would otherwise have been necessary,
telephone calls were included. It is difficult to see how those calls can be a
consequence of the delay in completion; they were no doubt made for good
reasons which have no obvious connection with that delay. For that reason the
calls would have to be deleted from Mr Graham's calculation. Even in relation
to the rental of the telephone line, it appears that it was used for calls
during the relevant period. For that reason I do not think that it can be
considered as wasted expenditure. I accordingly agree with this ground of
criticism. So far as insurance premiums are concerned, no documentation was
available, and on this ground I do not think that insurance can be a legitimate
head of claim. In relation to heat, light and power, it is clear that
electricity or gas was actually used, and accordingly this appears to be in the
same position as the telephone calls and rental charges. In any event, no
documentation was available to explain precisely what was involved in this head
of claim, and that by itself is in my opinion sufficient ground for rejecting
it. Finally, counsel for the pursuers intimated that he did not seek financing
costs.
[40] In general, however, I am of opinion that the pursuers'
calculation of compensation is not well founded. The primary ground is the
lack of supporting documentation, but in addition I sustain the specific
criticisms of aspects of Mr Graham's calculations that are mentioned in
the last two paragraphs.
Conclusion
[41] I accordingly conclude that the pursuers have failed to make
out any of the three essential elements of their claim. They have failed to
establish any delay in completion of the phase 2 works resulting from defects
in the drainage works carried out by the defenders; even if such defects existed,
they have failed to establish that they caused any delay in the completion of
the premises; and in any event they have failed to establish the amount of any
loss sustained by them in consequence of the late opening of the premises. In
the circumstances I will repel the pursuers' twelfth plea in law (the plea
dealing with entitlement to damages as a result of the defenders' breach of
contract), sustain the defenders' third and 10th pleas in law, and assoilzie
the defenders from the tenth conclusion of the summons, the only conclusion in
the action that remains live.