BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just ┬г1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
Scottish Court of Session Decisions |
||
You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> Morgan Utilities Ltd v. Scottish Water Solutions Ltd [2011] ScotCS CSOH_112 (28 June 2011) URL: http://www.bailii.org/scot/cases/ScotCS/2011/2011CSOH112.html Cite as: [2011] ScotCS CSOH_112 |
[New search] [Help]
OUTER HOUSE, COURT OF SESSION
[2011] CSOH 112
|
|
CA86/08
|
OPINION OF LORD HODGE
in the cause
MORGAN UTILITIES LIMITED
Pursuers;
against
SCOTTISH WATER SOLUTIONS LIMITED
Defenders:
ннннннннннннннннн________________
|
Pursuer: Howie Q.C.; Pinsent Masons LLP
Defender: Borland; Dundas and Wilson CS LLP
28 June 2011
[1] The pursuer ("MUL") is part of the group of companies
ultimately controlled by Morgan Sindall plc and provides utility services.
The defender ("SWS"), as described in paragraph [8]
below, was established by a consortium of companies to provide infrastructure
and other works to the water industry in Scotland.
[2] MUL asserts that it and SWS entered into an oral agreement,
which was to govern the terms on which it was to carry out work for SWS, at a
meeting on 3 or 4 September
2003. Unfortunately for the
parties, no one took a minute of the meeting or agreed in writing what, if
anything, had been decided. As a result for some time the parties have been at
odds as to the basis on which MUL carried out work in Lothian and Borders. MUL
carried out most of the work at a time when there was significant uncertainty
on this issue. In this action MUL claims payment of г3,520,255.50 from
SWS, which it asserts is the differential between what it has been paid and the
sum to which it is entitled under the alleged agreement.
[3] The proof which I heard was confined to the question of
liability. To understand the circumstances in which the meeting took place, it
is necessary to consider both the prior contractual arrangements between MUL
and Scottish Water ("SW") and the circumstances in which SW and other parties
set up SWS. SW is a body corporate established under section 20 of the Water
Industry (Scotland) Act 2002.
Factual background
(i) MUL's prior contractual arrangements
[4] From 1999 MUL carried out civil engineering works in Lothian
and Borders for East of Scotland Water, one of the statutory predecessors of
SW, under a contract which was governed by the standard terms contained in the
Conditions of Contract for use in connection with Works of Civil Engineering
Construction, Sixth Edition (January 1991) ("ICE 6") as amended by the parties' contract. That work
involved site investigation and the design, construction, repair, renewal and
refurbishment of clean water pipes. In 2001 MUL entered into a contract
on similar terms with West of Scotland Water, of which SW is the statutory
successor, to provide services of a similar nature in Dumfriesshire and
Galloway. In each case MUL contracted to undertake such works as might be
ordered by the employing utility company from time to time during the term of
each contract.
[5] In early 2003 the parties entered into negotiations to extend
the two contracts. By this time, the rates which MUL was entitled to charge
for work in Lothian and Borders had become increasingly unprofitable as the
majority of the work which remained to be carried out was located within towns
rather than in the countryside and urban works were more complex and expensive
to perform than rural works. MUL therefore needed to procure an arrangement
with SW which allowed it to carry out works in both Lothian and Borders and
also in Dumfriesshire and Galloway at rates which would enable the combination
of the works in the two areas to be profitable.
[6] In the summer of 2003 MUL and SW negotiated a new amalgamated
contract which covered works in both areas and involved more favourable rates
than had previously been allowed in Lothian and Borders. It also held out the
prospect to MUL that predominantly rural works in Dumfriesshire and Galloway would make up for the more expensive works in Lothian
and Borders and thereby allow the amalgamated contract to be profitable. The
amalgamated contract, which extended and revised the previous contract
governing works in the East of Scotland and incorporated within it the works to
be carried out in Dumfriesshire and Galloway, was agreed in letters dated 25
June and 1, 22 and 28 July 2003. It took effect from 1 July 2003.
[7] Under the amalgamated contract, which subject to further
extension was to last until 30
June 2004, there was no
guarantee that SW would give a particular amount of work to MUL. But it was
the shared understanding of the parties that the contract would enable MUL to
receive not less than г5.5 million in the year to 30 June 2004 and it was MUL's understanding that it would carry
out any work which SW instructed in Lothian and Borders outside Edinburgh or in Dumfriesshire and Galloway. Mr Howie QC
for MUL submitted that that understanding was correct. The amalgamated
contract incorporated the terms of ICE 6. He submitted, and it was not
disputed, that under ICE 6 the employer was not empowered to give any part of
the contract works to another contractor once a contract was awarded: Carr v
J. A. Berriman Pty Ltd [1953] 89 CLR 327; Commissioner for Main
Roads v Reed and Stuart Pty Ltd 1974 12 BLR 58. In May 2003 SW had
instructed MUL to carry out works in Dumfriesshire and Galloway and by 28 July 2003 had brought those works under the amalgamated
contract during the period of that contract. Thereafter SW had no right
unilaterally to alter that arrangement.
(ii) The establishment of SWS
[8] While MUL was securing the viability of its future works in Scotland by negotiating the amalgamated contract, SW was
involved in a radical reorganisation of the way in which it would deliver parts
of its capital investment programme in future. This involved the creation of a
new company, SWS, whose shareholders were (i) SW, (ii) Stirling Water
(2003) Ltd ("Stirling") and (iii) UUGM Ltd ("UUGM"). Stirling and UUGM were consortia of utility companies. UUGM
comprised (i) United Utilities Contract Solutions Ltd, (ii) Morgan Est plc and
(iii) Galliford (UK) Ltd. Morgan Est plc was an associated company of MUL. Stirling comprised (i) Thames Water Services Ltd, (ii) Alfred
McAlpine Utility Services Ltd, (iii) M J Gleeson Group plc and (iv) Kellogg
Brown and Root Ltd.
[9] In an attempt to set up SWS
in an orderly manner SW in about May 2003 issued a Letter of Intent to the
companies which comprised Stirling and UUGM. The letter set out transitional
arrangements for the funding and carrying out of activities by a transition
team to establish SWS. Under that arrangement the chief
operating officer required to obtain the approval of the interim transition
board before the transition team incurred costs in excess of г10,000 and
the transition team required to obtain the written consent of the chief
operating officer to activities which cost less than that sum. The interim
transition board had no authority to instruct works on behalf of SWS. The interim arrangements took effect from about
March 2003 and the interim transition board met from around that time until 9 September 2003 when SWS commenced its operations.
[10] Under the transitional arrangements, Mr Martin Bradbury
was appointed chief operating officer, Mr Nick Sumption was head of
commercial services and Mr George Sloss was head of project delivery.
Mr Sumption's responsibility included the negotiation and agreement of
commercial contracts. Mr Sloss's responsibilities included the
coordination of the project management activities which SWS staff were to
undertake through area delivery managers and project managers. It was not
envisaged that he would have responsibility within SWS for the negotiation and
conclusion of commercial contracts.
[11] The participants in SWS entered into a
Shareholders Agreement on 9
September 2003 which governed
their relationship and on that date shares in SWS
were allocated or transferred to its participants. Until 9 September 2003 SWS was not trading and had no employees.
[12] The entities involved in the creation of SWS spent several
months in 2003 in the negotiation of a Services Agreement
which, among other things, identified the projects which SW was to retain and
those which it transferred to the responsibility of SWS. While it was
envisaged that SWS would take over responsibility for all of SW's capital
programme, there were projects which were in the course of execution and which
SW was managing. The parties had to negotiate between themselves and with the
Water Industry Commissioner for Scotland ("WICS"),
among other things, which projects were to be transferred to SWS and which were
to remain the responsibility of SW. It had initially been envisaged that the
parties would sign the Services Agreement in March 2003 but repeated delays in
the completion of the negotiation forced the parties to operate under the
Letter of Intent until the Services Agreement was signed on 9 September 2003.
[13] The Services Agreement provided for three categories of
contract, namely allocated contracts, managed contracts and legacy contracts. Allocated
contracts were contracts which SWS would place with a contractor which was a
member of one of the consortia involved in SWS.
The contract was a generic self-delivery contract which contained a target
price and provided for a management fee. Managed contracts were contracts
which SW had already placed and for which SWS
took over responsibility for administration. SW remained the employer of the
contractor under such a contract and paid SWS
a fee for its administration. Legacy contracts were contracts which SW had
placed and for which it retained responsibility without any involvement on the
part of SWS.
[14] Even in early September 2003 there was considerable uncertainty
as to the categorisation of particular contracts within the Services Agreement.
That uncertainty appears to have continued after the signature of that
agreement. There was also considerable uncertainty as to which hats certain
officials were wearing as several SW officials found themselves dealing with outside
bodies, including MUL, both in their capacity as representatives of SW and also
as representatives of SWS. The failure of those who organised and implemented
the transfer of responsibility to SWS adequately to address and inform MUL of
its position provides the backdrop to the unfortunate circumstances of this
case.
(iii) Comments on the
credibility and reliability of witnesses
[15] Before turning to MUL's response to the emergence of SWS it is
appropriate that I comment on the credibility and reliability of the principal
witnesses in relation to disputed matters of fact. Most of the witnesses were
no longer involved with the companies which employed them in 2003 and 2004 and
had no commercial or financial interest in this action. I formed the view that
the witnesses were doing their best to recall events truthfully. Inevitably
there was a measure of retrospective rationalisation in the evidence of several
witnesses. While that did not militate against their credibility, it did
affect their reliability.
[16] I accept the evidence of Mr Charles Brien, who was at the
material time a senior commercial solicitor in SW, about the interim
arrangements to establish SWS. His evidence about the transitional
arrangements and the eventual execution of the Services Agreement was not
contested. It was helpful in clarifying the circumstances and timing of the
transfer of responsibility from SW to SWS. But matters which were known to
those within SW and SWS but not to MUL do not form part of the shared knowledge
which provides the factual matrix to the alleged contract.
[17] Mr Graham Carr, who was operations director and acting
managing director of MUL, was a credible witness. He was straightforward in
his evidence and answered questions in an open manner. He clearly believed
that he had reached a deal with Mr Sloss on about 3 September 2003 and
correspondence from MUL in the months following the contested meeting supports
the conclusion that he held that belief at that time. Some of his detailed
evidence of events leading up to the meeting with Mr Sloss was less
accurate and appeared to have been derived from reviewing the documents much
later. It was not clear from the evidence as a whole whether Mr Carr attended
a meeting with Mr Sloss in mid August 2003 or whether they were briefly
introduced when he met other people who were seconded to SWS. But nothing turns on that. Mr Bill Leach, who
was a regional director of Morgan Est plc and was working for MUL, accompanied
him to the meeting with Mr Sloss on 3 or 4 September 2003. Mr Leach also was a credible witness. He
understood that Mr Carr had reached an understanding with Mr Sloss at
the meeting but that the agreement was more of an agreement in principle rather
than a legally binding contract.
[18] Mr George Sloss also did his best to tell the truth. He
was clear in his evidence that he had understood the meeting with Mr Carr
and Mr Leach to be an informal "chat" about future arrangements and that
he was aware at the time that he had no power to bind SWS.
I accept that he was not aware of the structure of the amalgamated contract
between SW and MUL and of the problems which MUL had with the Lothian and
Borders work other than what Mr Carr told him at that meeting. In his
evidence he said that he had made it clear that MUL should raise any problems
concerning the Lothian and Borders work with SW and that he had no authority to
make any offers in that regard on behalf of SWS.
He also said that he was very clear that he could not make any commitment on
behalf of SWS. While I do not question Mr Sloss's
credibility, I am not satisfied that he is reliable in his recollection of what
he made clear to Mr Carr and Mr Leach. As I have said,
correspondence which officials of MUL wrote shortly after the meeting support
the view that there was an understanding within MUL that the parties had
reached an understanding or deal at the meeting of which MUL then sought
confirmation from SWS. Had Mr Sloss made his position as
clear as he suggested, it is not likely that employees of MUL would have
written the letters in the terms which they did. Nonetheless, I accept that at
the time he did not think that he had entered into any binding agreement. I
accept the evidence of Mr Bradbury and Mr Michael Beirne that Mr Sloss never told them that he had done any deal with
MUL in relation to work in Lothian and Borders.
[19] Mr Martin Bradbury also was a credible witness. He spoke
to the genesis of SWS and the transitional arrangements. I
consider that his evidence in that regard was both credible and generally reliable.
He recalled meeting Mr Carr with Mr Sumption and Mr Sloss in
August 2003 to discuss how the establishment of SWS
would affect MUL's existing contract with SW and saw it as a simply a meeting
to explore possibilities. He had no recollection of inviting Mr Carr to
speak to Mr Sloss. I am satisfied from the evidence of Mr Carr and Mr Sloss
that, contrary to Mr Bradbury's recollection, Mr Sloss did not attend
that meeting in August. At most he may have met Mr Carr briefly when he
entered the room in which a meeting was taking place. I did not hear from Mr Nick
Sumption, who could have cast considerable light on this matter and on the
circumstances in which Mr Carr and Mr Leach came to meet Mr Sloss.
While Mr Bradbury had no recollection of it, I am prepared to accept Mr Carr's
evidence that Mr Bradbury did invite him to speak to Mr Sloss and
that it was because of that invitation that Mr Carr arranged to meet Mr Sloss.
Mr Bradbury's lack of recollection on this matter did not however affect
my generally favourable assessment of his credibility and reliability on other
matters of fact.
(iv) MUL's response to
the emergence of SWS
[20] In about August 2003 Mr Graham Carr became increasingly
concerned to establish how MUL's contractual arrangements would fit in with
SW's proposals that its infrastructure works would be provided through SWS. MUL was not involved in the
discussions concerning the establishment of SWS which SW was having with, among others,
its associated company Morgan Est plc. At some stage in mid to late August
2003 he had a meeting with Mr Martin Bradbury and Mr Nick Sumption to
discuss the work which MUL was undertaking for SW and ultimately to ascertain
MUL's position when the contracts were to be with SWS. Mr Bradbury advised him to speak
to Mr Sloss.
[21] After a regular progress meeting on about 22 August 2003, Mr Carr
wrote to Mr Fraser Purves of SW on 26 August 2003 seeking to clarify the
rates at which MUL would undertake feasibility studies and the design and
construction of water main rehabilitation schemes in Dumfriesshire and Galloway.
After summarising correspondence between MUL and SW he stated:
"MUL consider that negotiations between SW and MUL in respect of the amalgamation of the WOSW and EOSW contracts, by way of an agreed extension to the EOSW contract up to 30 June 2004, clearly envisaged and linked the undertaking of feasibility, design and construction works in the Dumfriesshire and Galloway areas, with the agreement of rates for the existing works in the Lothian and Borders areas, which provided SW with a tangible saving."
He referred to a variation order number 143801-39 dated 21 May 2003 and asked for confirmation that the works which MUL was to undertake in Dumfriesshire and Galloway would be valued at the rates agreed in the amalgamated contract.
[22] Mr Carr and his colleagues in MUL had very limited
knowledge of the status of SWS or of the programme for the transfer of
responsibility from SW to SWS. They were aware that SWS was to manage SW's capital programmes and had seen
organograms showing the intended management structure of SWS. While the consortia of contractors, including MUL's
associated company Morgan Est plc, were negotiating with SW, Mr Carr was
concerned that MUL might be disadvantaged by the establishment of SWS and might lose work to companies directly involved in
the consortia. He had spoken to his colleagues, Mr James Tyson and Mr Bill
Leach, in July 2003 and had understood that MUL would receive all of the clean
water rehabilitation work in Dumfriesshire and Galloway. He had learned from Mr Fraser
Purves that SWS was managing "everything" and needed to
ensure that MUL was allowed to carry out the work in that area and in Lothian
and Borders in a way which was economically viable for it. He considered that
it was not viable that MUL should be paid on what he understood as a "cost
plus" basis for work in Dumfriesshire and Galloway while working in Lothian and
Borders for the rates agreed in the amalgamated contract. He discussed this
with Mr Bill Leach before the meeting on 3 or 4 September. The possible
solutions for MUL were either that all works were to be paid on a "cost plus"
basis or that all works would remain governed by the rates in the amalgamated
contract.
(v) The meeting of 3 or
4
September 2003
[23] On either 3 or 4
September 2003 Mr Carr
and Mr Leach had a meeting with Mr George Sloss at SW's office at
Pentland Gait, Edinburgh, where SWS was occupying the bottom floor. It is unfortunate
that no record was kept of the discussion as the exchanges at this meeting form
the basis of this legal action. It was not disputed that at the meeting Mr Carr
did most of the speaking for MUL and that Mr Leach said little. The
recollection of witnesses as to what was said is not detailed; they did not
recall the words used. But it is possible to reach certain conclusions.
[24] First, I accept Mr Carr's evidence that he understood that
Mr Sloss represented SWS. Mr Leach had the same view.
[25] Secondly, I accept that Mr Carr explained to Mr Sloss
the nature of the amalgamated contract and also the difficulties which MUL
would face if it were to be remunerated for work in Dumfriesshire and Galloway
on one basis and for work in Lothian and Borders on another, because of the
relatively costly nature of the residual urban works in the latter area.
[26] Thirdly, I accept Mr Sloss's evidence that Mr Carr
explained that he had heard that SWS was to be responsible for the delivery of
work in Dumfriesshire and Galloway and he had a problem if he received the
rates under the amalgamated contract only for the expensive Lothian and Borders
work.
[27] Fourthly, I accept Mr Carr's evidence that Mr Sloss
explained that contractors working for SWS
were to be in house delivery partners and that they would work under a self-delivery
contract, which Mr Carr understood to be a "cost plus" basis. It appears
that Mr Sloss equated MUL with Morgan Est plc as it was part of the same
group of companies. Mr Sloss's understanding in this regard was
understandable as MUL's printed paper which it used for its correspondence
described MUL as a division of Morgan Est plc.
[28] Fifthly, I accept the evidence of Mr Carr and Mr Leach
that they both understood Mr Sloss to have agreed that MUL would have the
status of a self-delivery partner both in relation to the works (except for
design works) in Dumfriesshire and Galloway and in relation to the works in
Lothian and Borders. In accepting this evidence I reject Mr Sloss's recollection
that he explained that he was clear that SWS
had nothing to do with the Lothian and Borders work. That in my opinion is a
retrospective rationalisation of his position.
[29] But, sixthly, I prefer Mr Leach's characterisation of the
discussion to that of Mr Carr. In his oral evidence Mr Leach said
that he understood that the purpose of the meeting was to obtain guidance on
the future organisation of the contracts and that it was not a contractual
negotiation. He said that the purpose of the meeting was to discuss principles.
He saw the principle under discussion as being whether MUL would be an in house
delivery partner on the Lothian and Borders works once the SWS regime was in
place. He was aware that Mr Sloss did not have a good grasp of the detail
of the contractual arrangements which MUL had or of the differentiation between
work in the East and the West of Scotland. On cross-examination when he was
referred to MUL's position that Mr Sloss had instructed that MUL would be
an in house delivery partner, Mr Leach said that "instructed" was not the
word; it was more a discussion and an understanding.
[30] In my opinion, the most that MUL can claim from the meeting was
that its officials understood from what Mr Sloss said that it was agreed in
principle that MUL would be an in house delivery partner in respect of the
works which it carried out, in both areas, except for the already commissioned
design works in Dumfriesshire and Galloway. I am satisfied that Mr Sloss
did not intend to create that impression. This is both because he was aware
that he had no authority to enter into contracts before the completion of the
Shareholders' Agreement and the Services Agreement and because he did not know
whether it was intended that SWS would take responsibility in any form for
the works which MUL was carrying out in Lothian and Borders. I am also
satisfied that both Mr Carr and Mr Leach came away from the meeting
satisfied that they had an understanding with Mr Sloss that MUL would in
future undertake work in both areas under self-delivery contracts. Had they
not had that understanding, they would have sought to raise the issue at a
higher level within SWS as they were aware that it was not
commercially viable to separate the contractual terms governing the works in
Lothian and Borders from those which applied in Dumfriesshire & Galloway.
[31] Seventhly, while Mr Carr asserted in his written witness
statement that Mr Sloss had instructed that MUL were to undertake all work
as an in house delivery partner from 1 July 2003 onwards, he was more guarded in his oral evidence
when he recalled what had been discussed. He accepted that he was not
authorised to negotiate the detail of an arrangement and that those discussions
would be conducted by commercial personnel within MUL such as Mr James
Tyson, its divisional commercial manager, and Mr Paul Else, its contracts
manager. He had not agreed a cut off date from which work which MUL had
carried out would shift from the amalgamated contract to a self-delivery
contract with SWS. Similarly, he accepted that he had not
agreed with Mr Sloss whether, in relation to work which MUL had already
carried out and for which it had been paid, MUL would (i) reimburse SW the sums
which it had paid and claim from SWS the whole sum due
under the self- delivery contract for that work, or (ii) claim only the
differential from SWS.
(vi) Subsequent
correspondence
[32] Mr James Tyson gave evidence, which I accept, that Mr Carr
had understood at the time that he had an agreement with Mr Sloss. He
recalled Mr Carr telephoning him from his car immediately after the
meeting with Mr Sloss and confirming what had been agreed. He had taken
notes of the conversation at the time but unfortunately had not been able to
find those notes when preparing to give evidence. He understood that it had
been agreed that the Dumfriesshire and Galloway works and the Lothian and
Borders works were to be tied together as MUL required.
[33] He used his notes and further discussions with Mr Carr to
draft a letter which Mr Leach sent on MUL's behalf to SWS on 18 September 2003. The letter was marked for the attention of Mr Sloss
and copied to Mr Sumption. It referred to the meeting on 3 September and
stated:
"Outlined below is our confirmation of the agreements reached therein.
With regards to all Works undertaken for Scottish Water since 1st of July 2003, it is our understanding that these will be undertaken in accordance with the generic self-delivery contract."
It then referred, as an exception to that rule, to ten design schemes in Dumfriesshire and Galloway which had been instructed on the agreed rates in the amalgamated contract and which it listed. The letter went on to refer to a letter from Mr Nick Sumption of SWS dated 11 September 2003, which appears to have been a response to MUL's letter of 26 August. See paragraph [15] above. In that letter SWS awarded MUL a contract to carry out works in Dumfriesshire and Galloway on the Quhytewoolen SR WSZ with an agreed target cost of г1,074,722 in accordance with an attached Scope of Works. Mr Sumption's letter had concluded as follows:
"Notwithstanding any previous contractual arrangements or negotiations with Scottish Water, as Morgan Utilities are categorised as an In-House Delivery Team (IHDT) partner within Scottish Water Solutions, the subject works shall be carried out and reimbursed in accordance with the generic self-delivery contract."
Mr Leach's letter of 18 September referred to this letter, confirmed its terms, asked for confirmation that it was
"in accordance with the previously detailed agreements reached at our meeting of the 3/9/03, namely the generic self delivery contract,"
and requested a meeting to discuss the process for measurement and valuation of the works and payment.
[34] While it was a substantial overstatement to describe the
discussions at the meeting on 3 or 4 September as involving "detailed
agreements", there was little room for doubt that MUL was asserting that an
agreement had been reached at that meeting. Mr Borland for SWS submitted
that MUL's letter of 18
September 2003 was ambiguous
as it appeared to relate only to the particular works in Dumfriesshire and
Galloway; but I do not see that ambiguity in the words which I quoted in the
previous paragraph which were not so confined.
[35] In his oral evidence Mr Sloss explained that he was
annoyed by the assertion that there had been an agreement reached at the
meeting and that he had discussed the matter with Mr Sumption and had
asked him to speak to Mr Stuart Marshall while he would speak to Mr Michael Beirne to arrange that SWS
responded to the letter. Mr Beirne gave evidence, which I accept, that he
had not seen the letter until he was preparing to give evidence in this proof
and that he was never asked to respond to it. Mr Steven Downie, who was
seconded from SW to SWS in September 2003, gave evidence that he
also was not asked to reply to the letter and that he had not seen it before he
prepared for this action. I also accept his evidence on that matter. It is remarkable
that SWS never sent a proper response. This served
to add to the misunderstanding between the parties.
[36] Mr Steven Downie issued a variation order dated 13 October 2003 in the name of SW ordering that design work on
certain schemes in Dumfriesshire and Galloway cease with immediate effect as
SWS was to issue a new design specification. In response Mr James Tyson
of MUL wrote a letter dated 15
October 2003 to Mr Downie
at SW and copied it to Mr Sumption and Mr Sloss among others. In
that letter he sought clarification of the use of and payment for MUL's design
staff. He sought confirmation that the works which MUL had been instructed to
cease had been ordered on 21
May 2003 during the
negotiation of the amalgamated contract. He continued:
"Subsequent discussion with Mr George Slosh (sic), of Scottish Water Solutions, have removed on site construction activities from this agreed Framework Extension, and these are now valued in accordance with the generic self delivery contract. Design, however, was specifically ring fenced and not incorporated into this arrangement. Confirmation of these discussions was communicated via our correspondence of the 18/09/03, to Mr Slosh (sic)."
Mr Downie in his evidence recalled reading the letter at the time but did not recall responding to it. No response was produced in evidence.
[37] On 29 October
2003 Mr Tyson sent SWS a
letter for the attention of Mr Sloss and copied the letter to, among
others, Mr Sumption of SWS and Mr Carr and Mr Leach of MUL. In
that letter he stated:
"Further to our letter of the 18/09/03 regarding agreements reached at our meeting of the 3/09/03, please be advised that Morgan Utilities are continuing to work and operate in accordance with the conditions laid down within said correspondence.
We are currently in the process of preparing statements of cost to enable reimbursement in line with the agreements, and these will be submitted in due course.
We trust this to be to your satisfaction, but should you require any further information, please do not hesitate to contact the undersigned."
[38] On 31 October
2003 Mr Steven Downie
wrote a letter under an SW letterhead to MUL for the attention of Mr Keith
Troughton, who was an area manager, concerning the submission of costs in
relation to water mains rehabilitation in Dumfriesshire and Galloway. Under
his signature he placed an email address which suggested that he was working
for SWS. In the letter he complained that he had been requesting MUL's costs
for work in Dumfriesshire and Galloway for several weeks and he informed MUL
that he would refer the matter to Mr Michael Beirne if it did not submit
the information by end of business on Monday 3 November 2003. Mr Downie explained that he acted
for SWS after 9 September 2003 but that he also retained his role as
project manager and employer's representative on behalf of SW in relation to
the Lothian and Borders contract with MUL. He was later replaced in that role
by Montgomery Watson Harza in early 2004. Again, there was no clear evidence
that anyone in SW or SWS took care to explain to MUL employees the capacity in
which he was acting.
[39] Mr Tyson replied by letter dated 3 November 2003. He apologised for any confusion relating to the
submission of costs and stated that MUL had always intended to provide cost
information in November for work undertaken in October. He stated that MUL was
paying similar attention to the formulation of costs for the Lothian and
Borders works so that full reimbursement could also be made for that work. SWS
replied by letter from Mr Allan Falconer, a Senior Project Manager, dated 6 November 2003. In that letter Mr Falconer emphasised the
importance of the prompt receipt of accurate costs. In relation to Mr Tyson's
reference to the Lothian and Borders work he stated:
"Additionally, your letter of 3rd November relates to commercial matters associated with your Borders and Lothian works. This matter will be addressed separately by Mike Beirne and Nick Sumption."
In his oral evidence Mr Sloss explained that he had requested his team to respond to MUL's assertions about what he had agreed and that this letter was his team's response. If that was the purpose of this letter, it did not give MUL notice of the disagreement which later became apparent.
[40] In a letter dated 13 November 2003 MUL submitted to SW its
statement of costs for works which it had undertaken in Lothian and Borders in
the period from 1 July 2003 and 26 September 2003. The letter was stated to be
for the attention of Mr Steven Downie and was copied to Mr Sumption
and Mr Sloss of SWS. In that letter Mr Tyson again referred to the
agreement with Mr Sloss of SWS at the meeting of 3 September 2003 and to MUL's letters of 18 September and 29 October 2003.
[41] Mr Downie wrote to Mr Troughton of MUL on 25 November 2003 instructing him to recommence feasibility and design
works on five projects in Dumfriesshire and Galloway. He stated that the
payment mechanism for all work on the schemes had to comply with contractual
agreements with SWS. Again, he wrote under an SW letterhead but included under
his signature an email address at SWS. Further instructions to carry out water
mains rehabilitation works in Dumfriesshire and Galloway were sent by Mr Stewart
Marshall, a Commercial Manager Infrastructure of SWS, on SWS letterhead on 5
and 19 December 2003 and on 10 March 2004.
[42] In summary, SWS failed to respond directly to the repeated
assertion in MUL's letters that an agreement had been reached on 3 September 2003. It and SW did not explain that in their
understanding there were different employers in relation to work in
Dumfriesshire and Galloway on the one hand and work in Lothian and Borders on
the other. As a result, MUL proceeded with the works in Lothian and Borders
without having obtained the confirmation which it sought from SWS.
[43] MUL submitted claims to SW for the works which it carried out
in Lothian and Borders and SW paid for those works. Mr Carr explained
that MUL did so because there appeared to be some uncertainty as to the
contractual arrangements and MUL needed to maintain its cash flow while that
was sorted out. I see no reason to doubt his explanation and do not accept the
suggestion that MUL by so acting showed that it knew that the Lothian and
Borders contract had remained with SW. MUL also submitted claims to SWS for
those works based on its understanding of an agreement with SWS.
(vii) Attempts at
clarification
[44] In an attempt to resolve those uncertainties a meeting between SWS
and MUL was held on 3
February 2004.
Mr Sumption, Mr Sloss, Mr Beirne and Mr Marshall attended
on behalf of SWS and Mr Leach and Mr Tyson on behalf of MUL. The
parties did not agree a formal minute of the meeting and the witnesses who were
able to speak to the meeting had varying recollections. The only contemporary
document which parties produced in the proof was a manuscript note which Mr James
Tyson made at the meeting.
[45] Mr Tyson asserted at that meeting that SWS should be paying MUL for the Lothian and Borders
works under the self-delivery contract. It appears that there was some
uncertainty within the SWS camp as to the status of the Lothian and
Borders contract. The manuscript note, which is the best evidence, records Mr Sumption
as suggesting that the contract should form part of the "managed works" and
asking whether it currently formed part of the "allocated works." The note
showed someone asking the question, "Who is the contract with now?" The note
also recorded an explanation of the differences between managed, legacy and
allocated works. The note showed someone speaking of an instruction from Mr John
Bennett of SW to Mr Bradbury of SWS confirming that it
was a managed project. In his oral evidence Mr Tyson accepted that Mr Sumption
had suggested that SW would have to give such an instruction for the works to
be treated as a managed contract. The note recorded that Mr Sumption
advised Mr Tyson and Mr Leach to liaise with Mr Marshall to
establish precisely what had been paid to date. While it is not possible to
determine in any detail what was discussed and agreed at this meeting, it is
clear that there was uncertainty within SWS
as to the status of the Lothian and Borders contract and that no conclusion was
reached on that matter.
[46] There was no meeting of minds in the following months. SW paid
MUL certain sums for the Lothian and Borders works on the basis of the
amalgamated contract but MUL's submissions to SWS on the basis of cost were not
paid. On 5 August 2004 Mr Martin Broome of MUL sent an email
to Mr John Manners of SW in which he stated that he was clarifying the
situation with the benefit of hindsight. He asserted that at the meeting on 3 September 2003 it had been agreed that the Dumfriesshire and
Galloway contract would be carried out under the allocated programme and that
the Lothian and Borders contract would be carried out under the managed
programme. At a meeting on 17
November 2004 between MUL and
SWS, Mr Tyson and Mr Broome of MUL asserted that the Dumfriesshire
and Galloway contract was part of the generic partnership contract and that the
Lothian and Borders works had been transferred to SWS and were to be paid on a
cost plus basis. Mr Sumption, Mr Marshall and Mr Sullivan
attended the meeting for SWS. Their position was that while the construction
work in the Dumfriesshire and Galloway contract was paid by SWS through a
partnership contract, it was SW and not SWS which was responsible for the
Lothian and Borders contract. In his oral evidence Mr Tyson did not
accept that the assertion in SWS' minutes of the meeting that MUL had accepted
that its contract for the Lothian and Borders works was with SW. But SWS'
position was clear: it was not responsible for those works. It offered to
assist MUL in the submission of a claim to SW.
(viii) The internal treatment of the MUL contracts
by SW and SWS
[47] From the
internal documentation of SWS it became clear in the course of the proof that
the Lothian and Borders contract had not been transferred from SW to SWS either
as an allocated contract or as a managed contract. The contract had an
autocode number 4549, which applied to an SW project. It was not a project
which was transferred to SWS under the Services Agreement. SW employees
authorised payments to MUL in monthly payment certificates. Accordingly,
notwithstanding the uncertainty of senior employees of SWS, there was no
transfer of the contract from SW to SWS. There was no evidence that SW had
requested the transfer of the agreement to SWS. It remained a legacy agreement
in which SW was the contracting party with MUL. The only basis therefore on
which SWS could be liable under the contract was if SWS had undertaken
responsibility to pay MUL for the contract works under a self-delivery contract.
The central issue therefore is whether Mr Sloss entered into a binding
agreement to that effect on 3 or 4 September 2003.
(ix) Other evidence
[48] For
completeness, I record that the parties led evidence about a number of matters
which might have supported the view that SWS
had taken over from SW the responsibility for the Lothian and Borders contract
in September 2003. First, MUL questioned SWS's
assertion that it did not place contracts for infrastructure works before 9 September 2003. Mr Bill Leach gave evidence in his witness
statement that an SWS Monitoring Report dated November 2003 gave
rise to an inference that it had placed two contracts at Stenton and between
Dunkeld and Perth on 14 August and 5 September 2003 respectively. But SWS established by documentary evidence and Mr Leach
accepted in his oral evidence that SW had awarded those contracts.
[49] Secondly, SW instructed MUL at a monthly progress meeting on 10 September 2003 to adopt the new format of the SWS monthly report in reporting the progress of the
Lothian and Borders work. Thirdly, there was evidence that health and safety
advisers employed by SWS made site visits in October and November
2003 to sites on which MUL was working at Musselburgh and reported on them in SWS Contractor Performance Summaries. Mr Hall, one
of the health and safety advisers, gave evidence that he had visited the site
because he had understood that it was the subject of a managed contract and
thus under the control of SWS. Fourthly, emails sent on 1 July 2004 by
a person seconded to SWS instructed MUL not to carry out work in
Musselburgh during Gala Week and criticised it for a failure to restore iron
covers on manholes in that area and for other minor matters. There was also,
fifthly, a suggestion that at least one invoice which MUL had submitted before
September 2003 had been processed by SWS. Finally, there
was evidence that SWS included work which MUL carried out in
Lothian and Borders in the outputs which SWS
reported to the WICS. But Mr Bradbury explained that SWS had agreed with SW that it was entitled to include
prior under-measurements of SW work in its returns to the regulator. There
was also evidence of the confusing practice of personnel wearing two hats. For
example, Mr Steven Downie issued instructions in relation to Lothian and
Borders work in his capacity as an employee of SW but issued instructions for
work in Dumfries and Galloway in his capacity as a representative of SWS.
His messages to MUL did not clearly distinguish the capacity in which he was
acting.
[50] In summary there was extensive evidence of uncertainty among
MUL employees in late summer 2003 as to when SWS took over from SW; there was
also evidence of uncertainty within SW and SWS as to who had responsibility for
different projects in the months after the transfer of authority to SWS. But
the evidence in aggregate did not contradict the internal documentation of SW
and SWS which demonstrated that the Lothian and Borders works remained legacy
works which SW managed and for which SW was liable to pay.
Discussion
[51] There were three
central legal issues in this case. The parties disputed (i) whether there was
an intention to contract on 3
September 2003, (ii) whether Mr Sloss
had apparent authority to contract and (iii) if there were an intention to
enter into legal relations, whether there had been sufficient agreement to
create a contract. I set out briefly my understanding of the relevant law
before considering its application to the facts of this case.
Legal issues
(i) An intention to enter a contract
[52] There was no dispute between the parties on the approach which
the court should adopt in deciding whether there was an intention to enter into
a contract. The task of the court can be summarised in four propositions. First,
the court has to decide whether the parties had manifested an intention to be
immediately bound, "there and then": Aisling Developments Ltd v
Persimmon Homes Ltd 2009 SLT 494, Lord Glennie at paragraph 56; Fletcher Challenge Energy Ltd v Electricity
Corporation of New Zealand Ltd [2002] 2 NZLR 433, paragraphs 51-53. Secondly,
the court adopts an objective approach, having regard to what the parties did
and said. It asks what would reasonable and honest men in the position of the
parties and having their shared knowledge of the surrounding circumstances have
understood by the discussion which they had or the communications which passed
between them: Fletcher Challenge Energy Ltd (above) at paragraphs
54-55. In the context of a commercial transaction the court asks what would
have been the reasonable expectations of sensible businessmen: G Percy
Trentham Ltd v Archital Luxfer Ltd [1993] 1 Lloyd's Law Reports 25,
Steyn LJ at p.27. Thirdly, while it is important to consider events as they
unfolded in order to take an objective view of what reasonable people would
have understood the position to be at the time the deal was allegedly
concluded, it is also relevant to look at parties' behaviour after that time to
the extent that that may cast light on what reasonable persons would have understood
at that earlier time: Fletcher Challenge Energy Ltd at paragraph 56.
Communications between the parties after an alleged agreement may help the
court evaluate evidence about what occurred at the time of such an agreement: Australian
Broadcasting Corporation v XIV th Commonwealth Games Ltd (1988) 18
NSWLR 540, Gleeson CJ at p.550. Fourthly, when the court is considering
whether or not the parties intended to enter into a contract at a particular
time, it adopts an entirely neutral approach: Fletcher Challenge Energy Ltd
at paragraph 58. It is only once the court has decided that the
parties did intend to contract that it will seek to give effect to that
intention and uphold the contract if it can: G Scammell and Nephew Ltd v
Ouston [1941] AC 251, at p. 268. See generally, Baillie Estates Ltd v
Du Pont (UK) Ltd [2009] CSOH 95, at paragraphs 25 and 26.
(ii) Apparent authority
[53] The
issue in this case is not the actual authority of Mr Sloss to enter into a
contract on behalf of SWS with MUL. Mr Howie did
not contend that he had such authority. The evidence revealed that he did not.
Instead Mr Howie founded on Mr Sloss's apparent authority.
[54] It is well established that apparent or ostensible authority
arises from a representation by the apparent principal to the contractor that
the agent has authority to enter into a contract of a kind within the scope of
that authority. The agent may be unaware of the representation by the
principal. That representation, when acted on by the contractor by entering
into the contract with the agent, bars the principal from asserting that he is
not bound by the contract: Freeman and Lockyer v Buckhurst Park
Properties (Mangal) Ltd [1964] 2 QB 480, Diplock LJ at pp.503-504.
(iii) The sufficiency of
an agreement
[55] Where
it has been established that the parties intended to enter into a binding
agreement with immediate effect, it is necessary to consider whether they have
agreed enough to enable the court to give effect to their agreement. In his
judgment in Fletcher Challenge Energy Ltd, which Lord Glennie quoted in Aisling,
Blanchard J pointed out (at paragraph 50) that one could not sensibly
divorce the question whether the parties intended to enter into an immediately
binding agreement from a consideration of the terms express or implicit in the
product of their negotiations. A failure by parties to agree terms which are
legally essential elements of a bargain may point to the failure of a
negotiation or to the achievement of no more than an understanding or agreement
in principle which the parties did not intend to be legally binding.
[56] Even where the parties intend to enter into a contract, the
result of their discussion or negotiation may not deal with an essential term
and the court may not be able to determine the parties' intention by implying a
term or by referring to an objective standard such as what was reasonable in
the circumstances. The parties require agreement or the objective means of
achieving agreement on every term which is essential to the formation of their
deal.
Whether the parties entered into a contract on 3 or 4
September 2003
[57] I turn to the
three issues, namely (i) whether the circumstances viewed objectively
demonstrated that the parties intended to enter into a binding agreement at the
meeting of 3 or 4 September 2003, (ii) whether Mr Sloss had apparent
authority to contract, and (iii) if issues (i) and (ii) were decided in MUL's
favour, whether there was sufficient agreement of the essential terms to create
a binding agreement.
[58] There are a number of factors which cumulatively persuade me
that the parties did not intend to reach a binding agreement at the meeting on
3 or 4 September 2003. First, there is the informality of the
meeting. No formal minutes were prepared and exchanged. Mr Sloss was not
accompanied by any other officer of SWS. Mr Sloss
spoke of understanding that Mr Carr had come for "a chat." Secondly, Mr Leach
characterised the nature of the discussion as achieving an understanding rather
than a contractual negotiation. While there is scope for a contract to come
into existence without detailed negotiation of its terms, Mr Leach's
characterisation was telling. Thirdly, there is the relative complexity of the
arrangement by which the contract works would be transferred from the
amalgamated contract to the new SWS system of a generic
self-delivery contract. There was no agreement of the scope of the works or a
target cost for those works. The former was perhaps already discernible in
what SW had agreed with MUL in relation to the Lothian and Borders works under
the amalgamated contract but the latter was a crucial component of a generic
self-delivery contract. It was therefore not clear how, on MUL's
understanding, a "cost plus" arrangement would work. Fourthly, there was no
agreement as to the start date of the new arrangement or as to whether MUL
would repay SW sums already paid under the amalgamated contract and obtain the
full sum due for the works under the new arrangement from SWS.
[59] Some light is cast by the subsequent behaviour of the parties.
MUL's correspondence after the event clearly pointed to an understanding that
it had a deal with SWS in relation to the Lothian and Borders works. But the
subsequent behaviour of Mr Sloss and of Mr Steven Downie, the project
manager who was responsible for administering those works, did not demonstrate
such an understanding. Mr Sloss did not inform Mr Bradbury or his
subordinate, Mr Beirne, of any such deal. Mr Downie gave evidence
that SW always intended the Lothian and Borders works to be legacy works and
that he administered the contract on that basis.
[60] Turning to issue (ii), I am not persuaded that Mr Sloss
had apparent authority to enter into a contract with MUL on behalf of SWS. Mr Bradbury's suggestion that Mr Carr
should discuss his concerns about MUL's future contractual position with Mr Sloss
is not sufficient in the circumstances to amount to a representation of
apparent authority to contract. Mr Sloss, as Mr Carr knew, was responsible
for project delivery. I do not accept that Mr Sloss's title contained a
representation of power to contract. Mr Sumption and not he was
responsible for commercial services, which included the negotiation of
contracts. There was no evidence that Mr Bradbury or any other senior SWS employee made any representation to Mr Carr
about Mr Sloss which was sufficient to bestow on him an apparent authority
to enter into a contract on behalf of SWS.
[61] As I have concluded both that the parties did not intend to
reach a binding agreement there and then and also that Mr Sloss did not
have apparent authority to contract, the issue of the sufficiency of the
agreement does not arise. But, in case I am wrong on issues (i) and (ii), I
record my conclusions on issue (iii). In my opinion the understanding was
lacking in one fundamental respect. There was no agreement at the 3 September
meeting or afterwards on a start date at which the works, which were being
carried out under the amalgamated contract, were to become the subject of a
generic self-delivery contract. In the practical context in which
infrastructure works were being carried out in Lothian and Borders and design
work was being undertaken in relation to works in Dumfriesshire and Galloway,
it was essential to any agreement that a start date of the new arrangements had
been agreed. It had not. That was fatal to the existence of a binding
agreement.
[62] Mr Borland submitted that the failure to agree a payment
or repayment mechanism also prevented a binding agreement. I am not persuaded
that that of itself would have been fatal if otherwise the court were satisfied
that there was an intention to contract. MUL could either (i) repay to SW sums
which the latter had paid under the amalgamated contract and seek payment in
full for the works from SWS under a generic self-delivery contract or (ii)
simply obtain from SWS the balance of their entitlement under the latter
contract. Which arrangement would have been made is to my mind a matter of
mechanics and the absence of agreement on such mechanics would not have
invalidated an otherwise sufficient agreement.
Conclusion
[63] I have concluded that MUL has not proved that it entered into a
binding agreement with SWS that SWS would pay it for works in the Lothian and
Borders area under a contract which was to replace the amalgamated contract. The
action therefore fails.
[64] I am left with a sense of disquiet at the outcome. Mr Borland
could not explain how as a matter of law SW had uncoupled the Dumfriesshire and
Galloway works from the amalgamated contract. There was no evidence to support
any agreement between SW and MUL to novate that agreement to separate those
works from the Lothian and Borders works. Given Mr Carr's concerns about
the viability of the Lothian and Borders works on their own, it is very
unlikely that MUL would have agreed to that separation. It appears that,
through pressure of work, inadvertence or otherwise, the people in SW and other
organisations, who were responsible for the establishment of and transfer of
responsibility to SWS, failed to address SW's obligations to MUL
under the amalgamated contract. As a result MUL has been treated rather
shabbily. But that consideration cannot alter the duty of the court to apply
the law relating to the formation of a contract.
[65] I therefore repel the first plea in law for the pursuer,
sustain the fourth plea in law for the defender and grant decree of absolvitor.