BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
Scottish Court of Session Decisions |
||
You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> Telfer v The Buccleuch Estates Ltd [2013] ScotCS CSIH_47 (31 May 2013) URL: http://www.bailii.org/scot/cases/ScotCS/2013/2013CSIH47.html Cite as: [2013] ScotCS CSIH_47 |
[New search] [Help]
EXTRA DIVISION, INNER HOUSE, COURT OF SESSION
|
|
Lord MenziesLord BrodieLord Malcolm
|
|
Respondents: Sir Crispin Agnew, QC; Anderson Strathern
31 May 2013
[1] I have had
the advantage of reading and considering in draft the Opinion of
Lord Brodie, and I am in complete agreement with the views expressed
therein.
[2] For the
avoidance of doubt, I agree that the argument which the appellant sought to
advance before us based on the principle of unity of contract must be refused
because the grounds of appeal contain no hint of such an argument. On the
second day of the hearing before us the appellant sought to amend his grounds
of appeal to introduce a fifth ground, founded on the principle of unity of
contract. This motion was opposed on behalf of the respondents on several
grounds, including that the issue of who was responsible for the state of the
Duntercleuch fence in 2007 was not explored at the proof before the Land Court,
that the issue was a pure question of law which could have been raised earlier
in the proceedings but was not, that the respondents had been given no notice
of such a line of argument and had not addressed it, and that the attempt to
introduce it came far too late. Essentially for the reasons advanced on behalf
of the respondents the court refused the appellant's motion. The argument
which he sought to introduce was not free from difficulty, and we considered
that it would not be fair to the respondents to allow it to be advanced at such
a late stage, without prior notice having been given to them.
[3] I agree
that ground of appeal 3 falls to be refused for the reasons explained by
Lord Brodie. The Land Court made findings of primary facts which entitled
it to draw the conclusion which it reached that the Duntercleuch fence was a
separate item. It cannot be argued that there was a material legal flaw in
their approach. I would answer the third question raised by the appellant in
the grounds of appeal in the negative. I too consider that the approach of the
Land Court in considering individual items of fixed equipment rather than
looking at the equipment as a whole was correct, and I would answer the fourth
question in the negative.
[4] For the
reasons given by Lord Brodie, I would answer the first and second questions in
the affirmative. It does not appear to me that the distinction between
"renewal" and "replacement" in this context is the material issue. The
Duntercleuch fence was a readily understood item of fixed equipment as at the date
of the PLA in 1971, and remained a readily understood item of fixed equipment
as at the date of the appellant's notice in October 2007. It performed (or was
intended to perform) the same function at both these dates; it forms the match
with the farm of Clenries in the Duntercleuch valley. Whether the whole of the
Duntercleuch fence was renewed between 1971 and 2007, or whether parts of it
were renewed, or a number of stobs or strainers or wires were replaced (and if
so, how many) appears to me to be beside the point. The point is that the
Duntercleuch fence was understood and identifiable and was intended to perform
the same function at both dates. In these circumstances the exercise of
comparison required by section 5(4B)(b)(ii) must be carried out.
[5] I confess
that I have had more difficulty with the issue of competency than your
Lordships, and I found Sir Crispin's submissions on this point initially
attractive. Section 88 of the 2003 Act provides inter alia that any
party to a matter determined by the Land Court by virtue of the 1991 Act or the
2003 Act may appeal against the determination on a question of law within
28 days of the determination. The legal issues which are raised by the
appellant in the present grounds of appeal as to the proper construction of the
new provisions added to section 5 of the 1991 Act by section 60 of the
2003 Act were the subject of debate before the Land Court in 2009 and
2010, and the Land Court determined these issues in its orders dated 6 May
2009 and 3 November 2010. The appellant did not appeal against these
determinations within 28 days of them, but instead allowed the dispute to
proceed to a proof lasting in total 9 days in January and
February 2012. It followed, Sir Crispin submitted, that the Land Court's
determinations as to these legal issues could not now be competently appealed.
[6] The Land
Court itself was clearly aware of the terms of section 88 of the
2003 Act, and of the possibility that an appeal might be taken against its
construction of the new statutory provisions. At paragraph [143] of the
court's Note attached to the order dated 6 May 2009 it stated as follows:
"Decision
[143] Counsel
invited us to have in mind the decision of the Inner House on 3 February
2009 in the appeal in SLC/119/07. The court decided that an appeal could not
proceed where it could not identify any determination or definitive decision in
the Land Court's note. It will be for the Appellate Court considering its own
jurisdiction to decide what type or types of findings are properly to be
regarded as 'determinations' within the meaning of section 88. We,
accordingly, avoid use of that word. However, we consider it appropriate to
make the following findings based on the foregoing discussion. Our intention
in making these findings is to express a concluded view on certain matters of
law for the purposes of litigation between the present parties. It may be, of
course, that other expressions of view in the Discussion above should
also properly be regarded as 'determinations' for the purposes of
section 88. We make the following explicit findings purely for the
avoidance of doubt".
[7] In the
Note attached to the order dated 3 November 2010 the Land Court preceded its
findings [100]-[103], which are central to the issues argued before us, with
the following:
"Decision
[99] It
is appropriate to summarise our answers to the four questions in more formal
findings or determinations..."
[8] It seems
clear from the above that the Land Court was alive to the possibility that an appeal
would be taken within 28 days of each of these determinations, and had the
terms of section 88 of the 2003 Act in mind. For my part, I consider that an
appeal could probably have been competently taken within 28 days of each of the
decisions dated 6 May 2009 and 3 November 2010. The question now comes to be
whether the appellant was bound to appeal at that time, or whether he was
entitled to await the outcome of the proof and appeal within 28 days of the
decision following proof?
[9] On
reflection, I have reached the view that it is competent for the appellant, in
the circumstances of this case, to refrain from appealing the earlier
decisions, but to await the outcome of the proof. (It is not disputed that the
appellant appealed to this court within 28 days of the decision dated 25 April
2012). Just because it was open to the appellant to appeal against the earlier
decisions within 28 days of their being made, it does not follow that he was
obliged to do so. The issues which form the basis of his appeal to this court
were the issues which formed the substance of the decision of 25 April
2012. As part of that decision, the Land Court decided (at paragraph [66]
of its Note) that the Duntercleuch march fence was not in a reasonable state of
repair on the specified date and that, as the fence as it stood on that date
was a replacement fence erected in 1972, it cannot be said that it was in a
worse state when the PLA was made. This was an integral part of the Land
Court's decision of 25 April 2012, and the appellant is in my view
entitled, by reason of section 88 of the 2003 Act, to appeal against that
decision "in all its parts", to use Lord Osborne's phraseology in Harvey
v McTaggart and Mickel. Having regard to that authority, I am persuaded
that Sir Crispin's attack on the competency of this appeal is misconceived, and
that the appeal is competently before this court.
[10] I agree
that this appeal should be disposed of as proposed by Lord Brodie.
EXTRA DIVISION, INNER HOUSE, COURT OF SESSION
|
|
Lord MenziesLord BrodieLord Malcolm
|
|
Respondents: Sir Crispin Agnew, QC; Anderson Strathern
31 May 2013
Introduction
The parties
[11] This
is an appeal to the Court of Session on a question of law against a determination
by the Land Court by virtue of the Agricultural Holdings (Scotland) Act 1991.
The appellant is Thomas Gordon Telfer. The respondents are The Buccleuch
Estates Limited. The appeal is brought under section 88 of the Agricultural
Holdings (Scotland) Act 2003. The appellant is tenant and the respondents are
landlords under a lease executed on 30 November 1970 and 29 March 1971, as
varied by a post-lease agreement executed on 29 March and 3 April 1971
(the "PLA"). The subjects of the lease are the lands and farm of Auchengruith
(including Glenim), extending to 5149 acres, lying near Wanlockhead in the
parish of Sanquhar. The subjects are illustrated in the copy plan 7/4 of
process. The lease is a lease of an agricultural holding.
The issue
[12] The
appeal is concerned with the re-allocation, as between the appellant, as
tenant, and the respondents, as landlords, of liability for the cost of
replacement or renewal of fixed equipment on the holding, by nullification of
the PLA in terms of section 5(4B) of the 1991 Act.
[13] As from 1
November 1948, in terms of the Agricultural Holdings (Scotland) Act 1949 and,
in particular, section 5(2)(a) of that Act, there has deemed to be incorporated
in every lease for the letting of an agricultural holding an undertaking by the
landlord that, at the commencement of the tenancy or as soon as is reasonably
practicable thereafter, he will put the fixed equipment on the holding into a
thorough state of repair, and will provide such buildings and other fixed
equipment as will enable an occupier reasonably skilled in husbandry to
maintain efficient production and, further, that he will during the tenancy
effect such replacement or renewal of the buildings or other fixed equipment as
may be rendered necessary by natural decay or by fair wear and tear. This
deeming provision was re-enacted, in substantially the same terms, on
consolidation of the legislation, by section 5(2)(a) of the 1991 Act. It
operates to impose an obligation on the landlord to renew and replace fixed
equipment as this becomes necessary. This is so irrespective of what the lease
may say; there can be no contracting out: Secretary of State v
Sinclair 1959 SLCR 10. However, notwithstanding the effect of section
5(2) on the lease, section 5(3) of the 1949 Act specifically provided that
section 5(2) did not prohibit any agreement made after the lease has been
entered into between the landlord and the tenant (otherwise, a "post-lease
agreement") whereby one of the parties undertakes to execute on behalf of the
other, and wholly at his own expense or wholly or partly at the expense of the
other party, any work which the other party is required to execute in order to
fulfil his obligations under the lease. Again, this provision permitting the
liability for the cost of renewal and replacement of fixed equipment to be
contractually allocated as between landlord and tenant by a post-lease
agreement was substantially re-enacted in section 5(3) of the 1991 Act.
[14] Section 5
of the 1991 Act was amended by section 60 of the 2003 Act. Section 5(3)
was repealed (as was section 5(5)). New subsections: (4A), (4B), (4C) and (4D),
were introduced. Subsection (4D) provided that post-lease agreements made after
the subsection came into force which purport to provide for the tenant to bear
any expense of any work which the landlord is required to execute (which
formerly were specifically permitted by the now repealed section 5(3)) shall be
null and void. Subsections (4A), (4B) and (4C) relate to post-lease agreements
made before the coming into force of the new provisions. In terms of subsection
(4A) any agreement between the landlord and tenant, made before the coming into
force of the subsection, which purports to provide for the tenant to execute on
behalf of the landlord (whether wholly at his expense or wholly or partly at
the expense of the landlord) any work effecting such replacement or renewal of
fixed equipment on the holding as is rendered necessary by natural decay or by
fair wear and tear, shall be nullified provided that the requirements of
subsection (4B) are complied with. Subsection (4C) applies subsections (4A) and
(4B) to post-lease agreements which provide that the tenant bear any of the
expense of any work of replacement or renewal which is required to be done by
the landlord.
[15] The PLA in
the present case makes provision for the maintenance of the fixed equipment on
the subjects and the renewal, and the payment for renewal, of fences et
cetera and land drainage. The respondents are obliged to renew fences and
entitled to renew land drainage but the appellant is obliged to contribute to
the cost. In addition the appellant is obliged to provide haulage. Accordingly,
the PLA is an agreement such as is referred to in section 5(4A) of the 1991 Act
and therefore is subject to nullification on the appellant giving notice as
provided by section 5(4B)(a) and the other requirements of section 5(4B) being
complied with.
[16] The
appellant gave notice by letter to the respondents' agent dated 22 October
2007 that the PLA be nullified as from that date. No question arises as to the
formal validity of the notice but, by letter dated 9 November 2007, the
respondents' agent objected to the notice on the ground that the fixed
equipment on the holding did not comply with the requirements of section
5(4B).
[17] The
respondents' objection put in issue the state of repair of the fixed equipment
on the holding as at 22 October 2007. Included in the fixed equipment of the
holding was the Duntercleuch march fence ("the Duntercleuch fence"). The
Duntercleuch fence is delineated in blue on the plan 7/4 of process. It runs
for some 2.5 miles. It forms the march with the farm of Clenries at the
Duntercleuch valley, running north from Stood Hill down into the valley,
turning north west along the south side of the water-course, then north east
across the water and then east up to Sowen Dod where the march with the
Hopetoun estate begins. The Duntercleuch fence is part (but only part) of the
boundary of the appellant's IACS (Integrated Administration and Control System)
field, number 36. Field 36 designates the whole of the hill ground of
Auchengruith.
[18] The
appellant applied to the Land Court for an order declaring that his notice that
the PLA or any other agreement made during the lease be nullified as from 22 October
2007 was valid (application number SLC/225/07). In the procedure which
followed the Land Court issued, inter alia, orders dated 6 May 2009, 3
November 2010, and 25 April 2012. It is the decision expressed in the order of
25 April 2012 which is appealed to this court. That decision determines, inter
alia, that the Duntercleuch fence was a distinct and significant item of
fixed equipment; that it was not in a reasonable state of repair as at 22
October 2007; and that as the fence as it stood on that date was a replacement
fence erected in 1972, and therefore something different than what was there in
1971, it cannot be said that the Duntercleuch fence was not in a worse state
than it was when the PLA was entered into. As a result it could not be said
that the requirements of section 5 (4B) were complied with. The appellant's
application to have the PLA held to have been nullified therefore fell to be
refused. It is against that refusal that the appellant appeals.
The statutory provisions
[19] As
between 27 November 2003 and 21 March 2011 (the relevant period for present
purposes) the Agricultural Holdings (Scotland) Act 1991 provided, inter alia,
as follows:
"5 - Fixed equipment and insurance premiums
(1) When a lease of an agricultural holding to which this section applies is entered into, a record of the condition of the fixed equipment on the holding shall be made forthwith, and on being so made shall be deemed to form part of the lease; and section 8 of this Act shall apply to the making of such a record and to the cost thereof as it applies to a record made under that section.
(2) There shall be deemed to be incorporated in every lease of an agricultural holding to which this section applies-
(a) an undertaking by the landlord that, at the commencement of the tenancy or as soon as is reasonably practicable thereafter, he will put the fixed equipment on the holding into a thorough state of repair, and will provide such buildings and other fixed equipment as will enable an occupier reasonably skilled in husbandry to maintain efficient production as respects both-
(i) the kind of produce specified in the lease, or (failing such specification) in use to be produced on the holding, and
(ii) the quality and quantity thereof,
and that he will during the tenancy effect such replacement or renewal of the buildings or other fixed equipment as may be rendered necessary by natural decay or by fair wear and tear; and
(b) a provision that the liability of the tenant in relation to the maintenance of fixed equipment shall extend only to a liability to maintain the fixed equipment on the holding in as good a state of repair (natural decay and fair wear and tear excepted) as it was in-
(i) immediately after it was put in repair as aforesaid, or
(ii) in the case of equipment provided, improved, replaced or renewed during the tenancy, immediately after it was so provided, improved, replaced or renewed.
...
(4A) Any agreement between the landlord and tenant made before the coming into force of this subsection which purports to provide for the tenant to execute on behalf of the landlord (whether wholly at his expense or wholly or partly at the expense of the landlord) any work effecting such replacement or renewal of the building or other fixed equipment on the holding as is rendered necessary by natural decay or by fair wear and tear shall be nullified provided that subsection (4B) below is complied with.
(4B) This subsection is complied with if-
(a) following a determination (in accordance with section 13 of this Act) of the rent payable in respect of the holding, the tenant gives notice to the landlord that the agreement be nullified as from a date specified in the notice ; and
(b) on that date
(i) the buildings and other fixed equipment are in a reasonable state of repair; or
(ii) if the buildings and other fixed equipment were in an unreasonable state of repair when the agreement was made, they are not in a worse state of repair than they were then."
(4C) Any agreement between the landlord and tenant made before the coming into force of this subsection which purports to provide for the tenant to bear any expense of any work effecting such replacement or renewal of the building or other fixed equipment on the holding as is rendered necessary by natural decay or by fair wear and tear shall be subject to subsections (4A) and (4B) above.
(4D) Any agreement between the landlord and tenant made on or after this subsection comes into force which purports to provide for the tenant to bear any expense of any work which the landlord is required to execute in order to fulfil his obligations under the lease shall be null and void."
...
60 Resolution of disputes by Land Court
(1) The Land Court shall have jurisdiction to hear and determine any of the matters referred to in subsection (2) below.
(2) Those matters are-
...
(b) any question or difference between the landlord and tenant of such a holding arising out of the tenancy or in connection with the holding, whether such question or difference arises during the currency of or on or after the termination of the tenancy;
...
(d) any other issue of fact or law relating to-
(i) a tenancy of such a holding or any other type of agricultural tenancy; or
(ii) agriculture,
which the landlord or tenant reasonably require to have resolved.
...
(6) Any application to the Land Court for a matter to be determined by the Court under this Act may be made by either party or by them jointly.
...
85.- Interpretation.
(1) In this Act, unless the context otherwise requires-
...
'building' includes any part of a building;
...
'fixed equipment' includes any building or structure affixed to land and any works on, in, over or under land, and also includes anything grown on land for a purpose other than use after severance from the land, consumption of the thing grown or of produce thereof, or amenity, and, without prejudice to the foregoing generality, includes the following things, that is to say-
(a) all permanent buildings, including farm houses and farm cottages, necessary for the proper conduct of the agricultural holding;
(b) all permanent fences, including hedges, stone dykes, gate posts and gates;
(c) all ditches, open drains and tile drains, conduits and culverts, ponds, sluices, flood banks and main water courses;
(d) stells, fanks, folds, dippers, pens and bughts necessary for the proper conduct of the holding;
(e) farm access or service roads, bridges and fords;
(f) water and sewerage systems;
(g) electrical installations including generating plant, fixed motors, wiring systems, switches and plug sockets;
(h) shelter belts,
and references to fixed equipment on land shall be construed accordingly;"
[20] Section 88
of the Agricultural Holdings (Scotland) Act 2003 provides:
"
(1) Subject to subsection (2), any party to a matter determined by the Land Court by virtue of the 1991 Act or this Act may appeal to the Court of Session against the determination on a question of law within 28 days of the determination; and in an appeal under this section the Court of Session may-
(a) quash, confirm or vary the determination or any part of it; and
(b) where the Court quashes the determination or any part of it-
(i) remit the case to the Land Court for further procedure; and
(ii) direct the Land Court on any question of law relevant to the case.
(2)A determination by the Land Court in an appeal may not be appealed against under subsection (1).
(3)The decision of the Court of Session in any appeal made under subsection (1) is final."
Procedure before the Land Court
[21] The
Land Court's order of 25 April 2012 was made after a proof, held in February 2012,
on the state of repair of five items of fixed equipment, including the
Duntercleuch fence. The proof had been allowed by order of the Court dated 21 November
2011 as a proof before answer in relation to the equipment listed. Having
considered the evidence led by parties over seven days, the Court concluded
that as at 22 October 2007, other than one section referred to as the "Rylock",
the Duntercleuch fence was not in a reasonable state of repair but that it was
in no worse state of repair than the then existing fence (the "old fence") had
been in 1971, when the PLA had been executed (see Note dated 25 April 2012,
paragraph [30]). However, the Court went on to find that the whole of the old
fence had been replaced in 1972, shortly after the PLA was made and therefore
the Duntercleuch fence was something different from the old fence. The Land
Court emphasised that finding in its Note dated 25 April 2012, paragraph 38:
"[38]. In our Note of 3 November 2010 we discussed the issues which might arise where an item of equipment was replaced. We did not attempt to define the circumstances necessary to demonstrate the distinction between renewal and complete replacement. We were satisfied that Parliament would not have intended the matter to turn on a careful analysis of how many old parts were used. A broad approach was required. If a fence was replaced but a significant number of old posts remained in position or if existing wires or netting [were] still used, it would fall to be treated as a renewal. However, the circumstances disclosed in the present case seem far from such a situation. An insignificantly small percentage of the old fencing material may have been used. No one looking at the fence in 1972 would have been in any doubt that the old one had been replaced. We are satisfied that there is no justification for comparing the state of the Duntercleuch fence in 2007 with the fence which there in 1971. It is simply not the same piece of equipment - even if it serves the same purpose and is located on or very close to the one which it replaced."
In its Note of 25 April 2012, prior to its discussion of the Duntercleuch fence, the Court had considered the condition of Muirhead Cottage and the Coshogle water-gate. Having made its findings in relation to the Duntercleuch fence, the Court went on in its Note to consider the state of the drainage in fields 7 and 23, these being the other instances of unreasonable state of repair founded on by the respondents. The Court summarises its findings in relation to four of the five items of fixed equipment at paragraph [65] of its Note. Two items (Muirhead Cottage and the drainage of field 7) were in a reasonable state of repair as at 22 October 2007, and two (Coshogle water-gate and the drainage of field 23) were not in a worse state of repair than they were at the date of making the PLA. Thus, by reference only to these four items, section 5(4B) was complied with. However, the Court's overall conclusion on the consequences of what it had found at the proof, appears at paragraph [66] of its Note:
"[66]. The Duntercleuch march fence is a substantial piece of the fixed equipment. We are satisfied that it was not in a reasonable state of repair on the specified date and that, as the fence as it stood on that date was a replacement fence erected in 1972, it cannot be said that it was in a worse state when the PLA was made. We determined in our Note of 3 November 2010 that it would be sufficient to prevent a tenant from setting aside a PLA if one significant item or part of the relevant fixed equipment was not in a reasonable state of repair at the date selected by him for nullification. It follows that our findings in relation to the Duntercleuch march fence prevent Mr Telfer from setting aside his PLA from 22 October 2007. For reasons discussed in the Note, this may well seem an unsatisfactory result. We have little doubt - having visited the farm in May 2009 - that Mr Telfer has been attentive to his own repairing obligations. Renewal of the fence was a matter for the landlord. However, the provisions of (4B) do not appear to us to allow examination of questions of responsibility for the state of the equipment. We find that the application must be refused."
[22] The
Court's approach to the evidence led at the proof and its decision refusing the
application, as stated at paragraph 66 of its Note, proceeded on a construction
of section 5(4B) whereby "the buildings and other fixed equipment" meant such
of the buildings and other fixed equipment which were made subject of the
tenant's obligation to replace or renew in terms of the PLA. Therefore all of
the fixed equipment subject to the PLA had to be in a reasonable state of
repair at the relevant date if the appellant was to comply with section
5(4B)(b)(i), or in no worse state than as the date of the PLA being made, if
the appellant was to comply with section 5(4B)(b)(ii). However, on the Land
Court's approach, all of the fixed equipment subject to the PLA was not to be
looked at as a whole but rather, leaving aside insignificant pieces of
equipment, was to be considered on an item-by-item basis, with the result that
if one significant item of fixed equipment was found not to be in a reasonable
state of affairs then section 5(4B)(b)(i) would not be complied with.
Similarly, section 5(4B)(b)(ii) would not be complied with unless each
significant item of fixed equipment was not in a worse state of repair than it
was when the PLA was made. Moreover, on the Court's construction of the
subsection, where an item of fixed equipment had been replaced subsequent to
the making of the PLA (but not where it had been renewed) it could not be said
to be "not in a worse state of repair" than the equivalent item at the time of
the PLA and therefore, in such circumstances, section 5(4B)(b)(ii) had no
application.
[23] The Land
Court acknowledges this approach and explains how it came to adopt it in
paragraph [1] of its Note dated 25 April 2012:
"We heard debates in 2009 and 2010 on issues relating to the proper construction of the new provisions. We concluded that the fixed equipment was not to be looked at as a whole. Regard had to be had to individual items though minor parts could be ignored. Even if a landlord could show that a significant item, or part, of the fixed equipment was not in reasonable state of repair on the specified date, the tenant would still be entitled to succeed if he could show that it was not then in a worse state of repair than it was when the PLA was made. This was in terms of the provisions of sec 5(4B)(b)(ii). But, where the equipment had been installed after the PLA was made, the tenant would not be able to take advantage of these provisions. The equipment in question would not have been there when the PLA was made and it would not be relevant to point to the condition of earlier equipment which had been replaced. We also determined that the concept of 'a reasonable state of repair', in the context of these provisions, was an objective one to be determined by looking at the state of the equipment without regard to the parties' respective responsibilities for maintenance."
Thus, while it was only on 25 April 2012 that the Land Court determined the appellant's application, the construction of the critical statutory provision which informed its approach to determination of the application had been arrived at by the Land Court as a result of earlier procedure, namely the debate which preceded the Court's order and Note dated 6 May 2009 and the debate which preceded the Court's order and Note dated 3 November 2010.
[24] In its Note
of 6 May 2009 the Land Court expressed its opinion on a number of matters which
had been the subject of debate between parties. For present purposes it is only
necessary to note what it said about two matters and that is at paragraphs
[147] and [149] of the Note:
"[147] Section 5(4B)(b) should be construed as implicitly limited to relevant buildings and other fixed equipment; in other words to items of equipment affected by the terms of the agreement to be nullified.
[149] The concept of a 'reasonable
state of repair' in section 5(4B)(b)(i) is an objective one, to be determined
by looking at the state of the equipment without regard to the issue of which
party is responsible for its condition. "
The Land Court referred to this as a finding. The making of findings, including the finding set out paragraph [149], is part of the Court's order of 6 May 2009. It is relevant to record what it said, at paragraph [143] of its Note, of the findings that it was about to record:
"Counsel invited us to have in mind the decision of the Inner House on 3 February 2009 in the appeal in SLC/119/07. The Court decided that an appeal could not proceed where it could not identify any determination or definitive decision in the Land Court's Note. It will be for the Appellate Court considering its own jurisdiction to decide what type or types of findings are properly to be regarded as 'determinations' within the meaning of section 88. We, accordingly, avoid use of that word. However, we consider it appropriate to make the following findings based on the foregoing discussion. Our intention in making these findings is to express a concluded view on certain matters of law for the purposes of litigation between the present parties. It may be, of course, that other expressions of view in the Discussion above should also properly be regarded as 'determinations' for the purposes of section 88. We make the following explicit findings purely for avoidance of doubt."
[25] Similarly,
the Land Court made findings in terms of its order of 3 November 2010. These
are the findings set out in paragraphs [99] to [107] of its Note of the same
date. The findings followed a debate on four questions which had been proposed
by the Court as a way of focusing certain issues of law outstanding between the
parties. After a discussion of these questions, at paragraph [99] of its Note
dated 3 November 2010 the Court explains, "it is appropriate to summarise our
answers to the four questions in more formal findings or determinations". Among
the findings set out in the following paragraphs are these:
"[100] We have concluded that the nature of work done on fixed equipment between the date of the agreement and the date in the tenant's notice is irrelevant to the question of a tenant's entitlement to nullify or set aside a PLA agreement. It does not matter who paid for the work. The test of entitlement depends on objective assessment of the state of particular items of equipment at the two dates.
[101]
If an item of equipment, present at the date of nullification, was not present
at the date when the agreement was made, [section
5(4B)(b)(ii)]
will have no application.
[102]
Even if an item of equipment, present at the date when the agreement was made,
has been substantially renewed before the date of nullification it will
normally fall to be regarded as the same equipment for the purposes of [section 5(4B)(b)(ii)]
[103]
If an item of equipment, present at the date when the agreement was made, has
been wholly replaced, it will not be available for comparison for the purposes
of [section 5(4B)(b)(ii)].
[106] In considering the state of repair of buildings and fixed equipment it is necessary to have regard to each individual item. Although a broad approach to the question may have been intended, that approach must have regard to individual items. Where any significant item is not in a reasonable state of repair, it cannot be said the fixed equipment is in a reasonable state of repair for the purposes of [section 5 (4B)(b)(i)]
[107]
When considering [section 5(4B)(b)(ii)] it is necessary to carry out a direct
comparison of individual items. In broad terms, if an original item has been
replaced by a radically different piece of equipment, [section 5(4B)(b)(ii)] will not come into play in relation to
that particular equipment. In other words if such a piece of equipment is not
in a reasonable state of repair there will be nothing with which to compare it."
[26] Having set out the Court's
findings the Note proceeds to a discussion of future procedure. In terms of
that discussion parties are required to lodge pleadings as a basis for the
resolution of questions of fact relevant to a determination of the application
on the Court's construction of section
5(4B)(b). On finalisation of the pleadings that parties lodged in obedience to
what was required by the Note dated 3 November 2010, the Court appointed the proof in terms of order and Note dated 21 November
2011.
The grounds of appeal
[27] The
appellant appeals the decision of the Scottish Land Court dated 25 April 2012
on the following grounds:
"The points of law upon which the appeal is to proceed is that the Scottish Land Court erred in law by finding
1. 'that as the relevant equipment' (Duntercleuch March Fence) 'had been put in place after the making of the Post Lease Agreement, no comparison fell to be made under section 5(4B)(ii)' of the Agricultural Holdings (Scotland) Act [1991, as amended]
2. At paragraph (66) of the order dated 25 April 2012 the Land Court compares the Duntercleuch March Fence at 22 October 2007 with the refurbished fence in 1972, instead of the Duntercleuch March Fence when the lease was signed in 1971 contrary to the law stated at section 5(4B)(b)(ii) - 'if the buildings and other fixed equipment were in an unreasonable state of repair when the agreement was made, they are not in a worse state of repair than they were then'.
3. That they could consider part of the fence in field 36, ie two parts of the Duntercleuch March Fence as a separate unit of fixed equipment. The unit of fixed equipment was the whole of the fence in field 36 or alternatively the whole of the fences on the farm.
4. Alternatively, the Court should in considering sections 5(4B)(i) and (ii) have assessed the fixed equipment as a whole and not by a random approach of individual items.
The questions of law for the opinion of the court are:
1. Can the Duntercleuch March Fence as it stood in 1971 be compared with the fence at the date of the purported termination of the Post Lease Agreement?
2. Were the court wrong to compare the Duntercleuch March Fence at the purported termination of the Post Lease Agreement with the refurbished fence in 1972?
3. Were the court wrong in regarding two parts of the Duntercleuch March Fence as a separate unit of fixed equipment instead of the whole of the fence in field 36?
4. Were the court wrong to consider individual items of fixed equipment rather than looking at the fixed equipment as a whole?"
Submissions of parties
Appellant
[28] Mr Telfer
submitted that the Land Court had erred in adopting, for the purpose of
determining the application, the construction of section 5(4B)(ii) which it set
out at paragraphs [96] and [101] to [103] of the Note attached to its order of
3 November 2010: that the state of the fixed equipment is to be assessed
by looking at the individual items making up the relevant fixed equipment; that
if an item of equipment, present at the date of nullification, was not present
at the date when the agreement was made, section 5(4B)(ii) will have no
application; and that if an item of equipment, present at the date when the
agreement was made, has been wholly replaced, it will not be available for
comparison for the purposes of section 5(4B)(ii). In Mr Telfer's submission,
when determining, in terms of section 5(4B)(ii), whether the buildings and
other fixed equipment were not in a worse state of repair than they were when
the PLA was made, on a proper construction of the subsection one should
consider the respective states of all the buildings and other fixed equipment
on the holding as at the relevant date and the date of the making of the PLA.
Moreover, where an item of fixed equipment had either been renewed or replaced
(it mattered not which) subsequent to the date of the PLA, and that item
remained in existence as at the relevant date, then the state of that item fell
to be compared with the state of the equivalent item as at the date of the PLA.
In any event, the principle of unity of contract meant that the landlord was
not entitled to rely on its failure (the obligation to renew or replace being
on the landlord albeit the tenant had an obligation to meet part of the cost).
It was inconsistent of the Land Court to regard the Duntercleuch fence as a
separate unit of fixed equipment and yet not to identify and treat separately
the stretches of the fence that were in good order at the relevant date. The
Land Court's approach was unrealistic. It would be unusual, particularly on a
large holding, for at least some items of fixed equipment not to be in poor
repair.
Respondents
[29] On
behalf of the respondents, Sir Crispin Agnew QC submitted that the appeal was
incompetent insofar as relying on grounds 1, 2 and 4 in that the relevant
points of law had been determined by the Land Court in its decision of 3
November 2010 which had not been appealed. As far as grounds 1 and 2 were
concerned, reference was made to paragraphs [101] to [103] and [107] of the
Land Court's Note. Ground 3 did not raise any point of law. As far as ground 4 was
concerned reference was made to paragraphs [106] and [107] of the Land Court's
Note. In developing his submission, Sir Crispin referred to and adopted the
written Note of Argument and Supplementary Note of Argument for the
respondents. The appeal was incompetent, being brought out of time in respect
of matters which had been determined on 6 May 2009 and 3 November 2010.
Section 88 of the 2003 Act replaced the former procedure under section 1(7) of
the 1993 Act whereby the Land Court might be required to state a special case
on point of law within one month of the relevant decision. There was no further
means of challenging what was determined before the Court went on to further
procedure. Reference was made to Harvey v MacTaggart & Mickel Ltd
2000 SC 137. The simplified procedure introduced by section 88 of the 2003
Act was not intended to change that. Sir Crispin reminded the court that there
was no equivalent in relation to the Land Court of RCS 38.8 (1) which provided,
in the Court of Session, that a reclaiming motion shall have the effect of
submitting to the review of the Inner House all previous interlocutors of the
Lord Ordinary. Esto the appeal was not incompetent, it should
nevertheless be refused because the appellant, by proceeding to proof, must be
taken to have acquiesced in the decisions which he now sought to appeal.
Reference was made to Maclaren Court of Session Practice, p947, Copeland
v Lord Wimbourne 1912 SC 355 and Macaskill v Nicol
1943 SC ll. In any event ground 3 did not raise a question of law. It was
entirely a matter of fact as to whether the Duntercleuch fence was identifiable
as a separate unit of fixed equipment. There was no suggestion that no court
could reasonably have come to the Land Court's conclusions. As to the merits
of the remaining grounds of appeal, it was Sir Crispin's position that the Land
Court had been correct in its construction of section 5(4B). He referred to
paragraphs [5] to [27] and [78] to [98] of the Court's Note of 3 November 2010
and, in particular adopted the submissions recorded at paragraph [5] to [8],
[20], [79] and [80] and the Court's reasoning at paragraphs [20], [21],[25],
[26], and [84] to [96] albeit he did not accept the Court's distinction as
between "replace" and "renew" set out in paragraphs [22] to [25] of its Note.
The appeal should be refused.
Discussion
Summary of the argument
[30] The
appellant appeals a decision of the Scottish Land Court expressed in an order
dated 25 April 2012. The critical part of that order is in the following terms:
"FIND that the fixed equipment comprising the Duntercleuch march fence was not in a reasonable state of repair on the date specified by the tenant for nullification of the Post Lease Agreement in terms of sec 5(4A) of the Agricultural Holdings (Scotland) Act 1991, as amended, and that as the relevant equipment had been put in place after the making of the Post Lease Agreement, no comparison fell to be made under sec 5(4B)(ii), and accordingly FIND that the tenant was not entitled to nullify the Post Lease Agreement as at 22 October 2007;"
In support of his appeal, in oral submission the appellant advanced essentially four lines of argument: (first) the Land Court erred in law in having regard to the condition of the Duntercleuch fence because given that contractual responsibility for carrying out the work of renewal of that fence lay with the landlord, this was to allow the landlord to found on its own failures, contrary to the principle of unity of contract; (second) in any event, the Land Court erred in law when considering the state of repair of "the buildings and other fixed equipment" for the purposes either of section 5(4B)(b)(i) or section 5(4B)(b)(ii), by assessing or comparing the fixed equipment item by item rather than assessing or comparing the state of the buildings and other fixed equipment on the holding (insofar as subject to the PLA) as a whole (ground of appeal and question of law 4); (third) even if it were correct to assess or compare the fixed equipment item by item, the Land Court erred in law in identifying the Duntercleuch fence as a separate item as opposed to either all the fencing of field 36 or all the fencing on the holding (ground of appeal and question of law 3); and (fourth) even if it were correct to assess or compare the fixed equipment item by item, the Land Court erred in law, when considering the application of section 5(4B)(b)(ii), by not comparing the state of the Duntercleuch fence with that of the "old fence" which had been in position in 1971 when the PLA was made but had been replaced by the Duntercleuch fence in 1972 (grounds of appeal and questions of law 1 and 2).
The argument not included in the grounds of appeal
[31] I
can dispose of what I have described as the first line of argument relatively
shortly. As appears from the final paragraph of its Note dated 25 April 2012,
the Land Court saw it as somewhat unsatisfactory that a tenant who had been
attentive to his own repairing obligations was denied the opportunity offered
by section 5(4A) of the 1991 Act by reason of the state of repair of a fence,
renewal of which was a matter for the landlord (subject only to a contribution
to the cost by the tenant together with the provision of haulage and laying out
of materials). On one view the landlords by failing duly to carry out their
obligations had deprived the tenant of a benefit that the Scottish Parliament
had intended to confer on him by amendment of the 1991 Act. However the Land
Court did not see a way open to it to translate its sympathy for the appellant's
position into a legal basis for eliding the plain meaning of the statutory
provision. No more do I. The application of the principle of mutuality is by no
means free from difficulty and while I have endeavoured to articulate the
appellant's point as favourably as I can from his perspective, I have not been
able to identify a legal proposition which, if applied, would have allowed the
Land Court to ignore the state of the Duntercleuch fence at the relevant date.
I observe that although the appellant was critical of what he would see as
failure on the part of the respondents to carry out their obligations, there is
no finding here of breach of contract by the respondents. However, there is a
further objection to this line of argument and that is that it is not even
hinted at in the grounds of appeal. Each of the other lines of argument
advanced by the appellant can be ascribed to one or to more than one of the
appellant's grounds of appeal and questions of law as set out in the Form
41.25. The first line of argument is not, and for that reason alone it cannot
be entertained.
The competency of grounds of appeal 1, 2 and 4
[32] While
the appellant's other arguments support the grounds which appear in his form of
appeal, the respondents submit that they also cannot be entertained and that is
because the grounds of appeal are said to be incompetent being presented
outwith the period of 28 days from the relevant determination which is provided
by section 88 of the 2003 Act. Now, the present appeal was lodged with the
Court of Session on 22 May 2012. That was within 28 days of 25 April 2012 (and
therefore equally within 28 days of the Land Court's decision being
communicated to the appellant on 26 April 2012). The respondents do not contend
otherwise. Their position, however, is that the points of law on which the Land
Court's decision is challenged in the appellant's grounds of appeal were all
determined, following debate, in terms of the Court's order and Note dated 3
November 2010. Accordingly, if the appellant had wished to appeal on these
points he had 28 days from receipt of the Court's decision dated 3 November
2010. He had not done so. He could not do so now.
[33] RCS
41.5(2)(b) requires a party who wishes to object to the competency of an appeal
made under chapter 41 of the Rules of Court to do so by lodging in process and
serving on the appellant a note of objection in Form 41.5 at any time before
the expiry of the period of 14 days from the date of service of the appeal. The
respondents appreciated this but late, necessitating their application in terms
of RCS 2.1 for the respondents to be relieved from the consequences of
their failure to lodge a note of objection timeously. The application came
before Lord Carloway who refused it for the reasons given in his Note of 19
July 2012. Lord Carloway was not persuaded that the appeal was indeed
incompetent but indicated that if there was merit in the respondents'
contentions they could be addressed by the court at the summar roll hearing.
[34] Consistent
with Lord Carloway's opinion, I do not see a failure to serve a note of
objection in terms of RCS 41.5 (2) (b) as foreclosing the question of
competency of an appeal; the rule simply provides a mechanism whereby
competency can be dealt with as a preliminary issue by the procedural judge or,
on a reference by the procedural judge, by a bench of three or more judges. I
therefore turn to address the respondents' argument that the appeal is
incompetent as being out of time.
[35] Section 88
of the 2003 Act provides that any party to a matter determined by the Land
Court by virtue of the 1991 Act may appeal to the Court of Session against the
determination on a point of law within 28 days. On the face of it that is just
what the appellant has done. The measure of what in any particular instance was
"the matter determined" by the Land Court must be the order which it
pronounces. I take that to be acknowledged by the Land Court in paragraph [143]
of its Note dated 6 May 2009. What the Land Court was discussing in that
paragraph was the fate of an appeal in another process between the same
parties, SLC/119/07. In that process Buccleuch Estates Ltd had appealed to this
court (Court of Session reference XA33/08). Sir Crispin, who had appeared
in that case also, confirmed that the problem he had encountered in attempting
to advance the appeal was that while he wished to challenge the Land Court's
interpretation of the law, he did not dispute the correctness of its disposal
following a debate, that being to allow proof before answer. This court
dismissed the appeal on the grounds that properly understood there was no
determination to appeal against. No opinion was issued but that Sir Crispin's
recollection is accurate is confirmed by the terms of the interlocutor
pronounced by this court on 3 February 2009 in the appeal reference XA33/08:
"The Lords having heard counsel for the appellants and the party respondent personally on the Summar Roll; considering that the 'determination' of the Land Court was that there should be a proof before answer, and given that the appellants now accept that a proof before answer is the appropriate disposal, and given also that the court is not persuaded that it could be said that the Land Court made any other 'determination' or indeed reached any concluded or definitive view on any aspect of the law or as to the proper interpretation of the lease in question; dismiss the appeal and decern."
[36] As I would
understand it, it was because the Land Court appreciated that its
determinations for the purposes of section 88 of the 2003 Act were what was to
be found in its orders and not in mere expressions of opinion in its Notes,
that it said what it said in paragraph [143] of its Note of 6 May 2009. It
recognised that it would ultimately be for the Court of Session, in exercise of
the jurisdiction conferred by section 88, to identify what was and what was not
a "determination". However, the Land Court indicated that it was its intention
to signal, to the extent that it was able to do so, its concluded views on
matters of law for the purposes of litigation between the parties. The
expedient adopted by the Land Court was to express its views on matters of law
in the form of findings set out in its Notes but then to make these findings by
means of its orders.
[37] It is the
making of the findings set out at paragraphs [99] to [107] the Land Court's
Note of 3 November 2010 that Sir Crispin founded on in support of his
submission on competency but if, as must be the case, one looks to the court's
order of 25 April 2012 in order to discover what was determined on that day,
one finds that the court determined: that the fixed equipment comprising the
Duntercleuch fence was not in a reasonable state of repair on the relevant
date; that as the fence had been put in place after the making of the PLA, no
comparison fell to be made under section 5(4B)(ii); and that accordingly
the tenant was not entitled to nullify the PLA as at 22 October 2007. These are
precisely the matters which the appellant complains about in his appeal as
having been determined by reason of error of law. Accepting that the Land Court
expressed its concluded views on the relevant matters of law for the purposes
of the litigation between the parties by means of the findings made in its
order of 3 November 2010, it was only on 25 April 2012 that it made the
determinations that the appellant is interested in challenging. It may be
inferred from paragraph [143] of its Note of 6 May 2009 that the Land Court
intended to express its decisions in such as way as to allow parties to appeal
points of law as they arise in the course of an application, rather than having
to wait until the application is concluded. I recognise the value of such a
facility. I am prepared to accept that what the Land Court did on 3 November
2010 was to make a determination. It does not however necessarily follow that,
just because the appellant could have appealed the court's findings as set out
at paragraphs [99] to [107] of its Note dated 6 May 2009 within 28 days of that
Note being communicated to him but did not, he is prevented from appealing a
later determination by the court, albeit that the later determination was made
by applying the interpretation of the law which had been set out in the Note of
6 May 2009.
[38] Sir Crispin
cited Harvey v MacTaggart & Mickel Ltd in support of his
submission that any determination of the Land Court, including a determination
as to what was the proper construction of statute, effectively became final if
not challenged within the period allowed for an appeal. Harvey is a case
to which section 1(7) of the 1991 Act and rule 88 of the Scottish Land
Court Rules 1992 applied. The leading opinion on the question of competency was
that delivered by Lord Osborne. Section 1(7) and rule 88 allowed challenge
to a determination by the Land Court by requiring a special case to be stated
for the opinion of a Division of the Court of Session on a question of law. The
applicant had applied to the Land Court for an order finding and declaring that
she was the tenant of an agricultural holding, the lease of which was said to
have been bequeathed to her by her late father. The respondents resisted the
application. While there was no dispute that the Land Court had jurisdiction to
determine one of these issues (the suitability of the applicant as a tenant),
the parties were in dispute as to whether the Land Court had jurisdiction to
determine the other issues. That position was reflected in a plea of no
jurisdiction being taken by the respondents. They enrolled a motion to sist the
applicant's application to the Land Court, pending determination of the matters
in dispute, other than the one issue in respect of which it was accepted the
Court had jurisdiction, in another court. That motion was refused on the basis
that the Land Court was satisfied that all of the matters in issue in the case
fell within its jurisdiction. Following upon that decision, the respondents did
not lodge a requisition for the Land Court to state a special case. The
application went to proof on all issues. The Land Court determined the
application in favour of the applicant. Following intimation of the decision
the respondents requisitioned the stating of a special case. One of the
questions was whether the Scottish Land Court had jurisdiction to deal with all
questions arising in the case? The applicant stated two questions of law, one
of which was whether the special case was competent in respect of the question
directed at jurisdiction in that the respondents had failed to request a
special case within one month of the decision following the application to
sist. Answering the applicant's question on jurisdiction in the affirmative,
the court held that the special case was competent notwithstanding the
respondents' failure to requisition a special case when the point was first
decided against them on refusal of the motion to sist. Sir Crispin pointed to
the fact that in Harvey, in contrast to the position in the present
case, at the proof the respondents' representative had formally restated the
submission that the court did not have jurisdiction to deal with all of the
matters concerned and the Land Court had expressly found in its most recent
decision that it did not find the additional submissions to be persuasive in
changing its views to any extent.
[39] Harvey
was a decision in relation to different provisions than apply here but rather
than supporting the position of the respondents in the present case, as Sir
Crispin argued, I would see the opinion of Lord Osborne, with which the other
two members of the court agreed, as supporting that of the appellant. The
critical passage, which I would see as being the nub of the decision, found at supra
149I to 150A is as follows:
"Having regard to the contents of the Land Court's decision [following proof], which I have described, it appears to me clear that a decision on the issue of the Land Court's jurisdiction to deal with all the questions arising in the case was part of their decision ... Against that decision, in all its parts, including that part, the present special case has been timeously requisitioned."
[40] Applying
that approach (considering what "was part of their decision", in other words
what it was that was determined in the most recent decision with a view to
identifying what may be the subject of challenge on point of law) here,
reinforces me in the view previously expressed that what the appellant is
seeking to appeal is a matter which was determined by the Land Court's decision
of 25 April 2012 and that therefore his appeal is timeous and therefore
competent. In my opinion it is not possible to disentangle "how it was decided"
from "what was decided". It may be that the Land Court by making the findings
it did on 3 November 2010 committed itself to a particular construction of
section 5(4A) and (4B) of the 1991 Act and thereby determined how it would
decide the issues which emerged in the subsequent proceedings, but on these
issues being determined on 25 April 2012 on an application of that
construction, the "how it was decided" (the statutory construction adopted by
the Land Court on 3 November 2010) becomes part of the "what was decided" on 25
April 2012, or to use the language of section 88 of the 2003 Act, part of
"the determination". The determination "in all its parts" may be appealed within
28 days. In my opinion this appeal is competent. Just because much the same
points could have been taken on an appeal from the order of 3 November 2010,
does not prevent them being taken on an appeal from the order of 25 April 2012.
[41] Sir Crispin
further argued that even if the appeal was competent it should not be allowed
to proceed because, by implication, the Land Court's order of 3 November
2010 was intended to be a final interlocutor and by participating in the
subsequent proof the appellant must be held to have acquiesced in it. He
referred to Copeland v Lord Wimbourne and Macaskill v
Nicol.
[42] In putting
forward this argument Sir Crispin was relying on the proposition that an
interlocutor, once acted upon as a basis for future proceedings, may not
competently be reviewed. That proposition was considered, in the context of
proceedings in the Court of Session, in McCue v The Scottish Daily
Record 1998 SC 811 (a five judge decision). In an opinion
delivered by Lord Justice-Clerk Cullen the court expressed its conclusion in
these terms (supra at 824C):
"It remains for us to say that in so far as the opinions in the decisions dealing with the actings of parties after a prior interlocutor have indicated that subsequent review was excluded as not being 'competent', those observations are disapproved, for the reasons which we have already given. The true question in such cases is not one of competency but of whether the court should exercise the power of review which is available."
Earlier, the Lord Justice-Clerk had said this (supra at 820G):
"Given that there is a competent reclaiming motion, we are unable to accept that the actings of the parties, and of the reclaimer in particular, consequent upon a prior interlocutor, could have the effect of disabling the court from reviewing that interlocutor. It would mean that an interlocutor which was not beyond subsequent review immediately after the expiry of the reclaiming days acquired that quality over the course of time. However, such actings could lead the court to the conclusion that the prior interlocutor should not be interfered with."
The Lord Justice-Clerk also quoted with approval observations by Sheriff Principal Caplan (as he then was) in Newcastle Building Society v White 1987 SLT (Sh Ct) 81 (supra at 821E):
"An interlocutor which holds a defence relevant is intrinsically related to a later judgment which sustains that defence. Viewed another way, if a party fails to appeal a procedural determination in time, such failure may readily be held to be unequivocally referable to acceptance of the procedure in question, because once procedure has flowed it cannot be retrieved. The matter is different when the merits are in issue."
The Lord Justice-Clerk then continued (supra at 821F):
"No general statement can be made as to the facts which will be relevant on either side of the question whether the court should review a prior interlocutor, let alone what facts will be determinative on that question. However, it is plain that, during the course of the proceedings, importance may attach to actings which have followed on the prior interlocutor; and in the end of the day, to the relationship between the prior interlocutor and the final judgment which is the subject of the reclaiming motion or appeal."
Thus, on the appeal of a final judgment, a prior interlocutor may or may not be open to review. It is not a matter of competency. It is a matter of whether the appellate court considers the interlocutor should be subject to review in all the circumstances. If it is purely procedural or otherwise seen to be final or spent it may be that it will be held not subject to review. On the other hand, if it continues to be linked to, or is directly influential in the order which is the subject of a timeous challenge then it may be subject to review. I would see the example given by Sheriff Principal Caplan in Newcastle Building Society v White to be apposite in the present case. Just as an interlocutor which holds a defence relevant is intrinsically related to a later judgment which sustains that defence, a determination that a particular statutory construction is to be adopted is intrinsically related to a later determination which applies that construction to facts found at proof. I would reject Sir Crispin's submission on this point. This is not a case of acquiescence (whatever precisely that might mean) in a purely procedural matter. What the appellant wishes to put in issue is central to the determination which he has timeously appealed.
[43] Accordingly,
in my opinion, grounds 1, 2 and 4 are competently before the court.
The competency of ground of appeal 3
[44] In
support of ground of appeal 4 the appellant argued that for the purposes of
section 5(4B)(c) of the 1991 Act, "the buildings and other fixed equipment" of
the holding should be considered as a whole (or at least those subject to the
PLA should be considered as a whole) and not as a series of individual items
and I shall address that argument presently. However, ground of appeal 3
proceeds on the hypothesis that, contrary to the position taken in ground of
appeal 4, it is correct to assess or compare the buildings and other fixed
equipment item-by-item with a view to determining whether they are in a
reasonable state of repair. On that hypothesis the contention for the appellant
is that the Land Court erred in identifying the Duntercleuch fence as a
separate item rather than taking as an item either all the fencing of field 36
or all of the fencing on the holding. The ground of appeal asserts that this is
an error of law. The respondents in their Note of Argument dispute that.
According to the respondents, all the ground of appeal does is to challenge a
factual determination; no question of law arises.
[45] I agree
with the respondents on this point. It does not admit of much in the way of
elaboration. Where an appeal is restricted to a point of law, unless the
argument is pitched as high as a contention that no reasonable finder of fact
could have come to a particular conclusion, "[it] is not", as Lord Malcolm said
in Jardine v Murray 2012 SC 185 at para 80, "a question of
whether this Court agrees or disagrees with the decisions taken in the Land
Court, but whether there is a material legal flaw in their approach." What is
in issue here is whether, assuming it is appropriate to split the totality of
the buildings and other fixed equipment on the holding into a number of
distinct items for the purposes of assessing their state of repair, the
Duntercleuch fence could meaningfully be taken as one such distinct or separate
item. That is a factual conclusion to be drawn from the primary facts found by
the Land Court on the basis of the evidence led and, importantly, its
inspection of Auchengruith. Drawing that conclusion does not require the
application of any legal rule or principle beyond the requirement that the
conclusion must have a basis in the primary findings of fact. As is pointed out
in the Note of Argument for the respondents, it is clear from paragraphs [20],
[22] and [39] in the Land Court's Note dated 25 April 2012, that the Land Court
did have such a basis. Essentially the appellant's argument was that taking the
Duntercleuch fence as a separate item of fixed equipment was no more valid than
taking all the fencing of field 36 or all of the fencing on the holding as a
separate item. That might be an entirely tenable point of view but it was not
the point of view adopted by the Land Court and, given that there were primary
facts to support its conclusion, it cannot be said by this court that the Land
Court was wrong. I see this as properly a matter of the competency of this
ground of appeal. In my opinion, it does not raise a question of law. It is
therefore incompetent.
Ground of appeal 4
[46] The
Land Court held that for the purposes of section 5(4B)(c) of the 1991 Act, "the
buildings and other fixed equipment" under consideration were those subject to
the PLA, as opposed to the remainder of the fixed equipment on the holding.
That would seem to be right and, in any event, that approach is not challenged
in any of the grounds of appeal. I have to confess that I was not entirely
clear from what the appellant said as to what he considers to be the fixed
equipment which is subject to the PLA but for present purposes that is not
important in that there is no question but that the Duntercleuch fence is part
of the fixed equipment of the holding which is subject to the PLA and therefore
potentially is, as the Land Court held it to be, a separate item within the
totality comprehended by "the buildings and other fixed equipment" of
Auchengruith. However, in his ground of appeal 4, the appellant argues that for
the purposes either of section 5(4B)(b)(i) or section 5(4B)(b)(ii) of the 1991
Act, the condition of the fixed equipment of the holding should, as a matter of
law, be considered as a whole and not "by a random approach of individual
items".
[47] As
previously noted, the Land Court expresses its conclusion on this matter at
paragraph [106] of its Note dated 3 November 2010:
"In considering the state of repair of buildings and fixed equipment it is necessary to have regard to each individual item. Although a broad approach to the question may have been intended, that approach must have regard to individual items. Where any significant item is not in a reasonable state of repair, it cannot be said the fixed equipment is in a reasonable state of repair for the purposes of [section 5](4B)(b)(i)."
[48] Before
going further it is important to acknowledge the special status of the Scottish
Land Court and therefore the status of its decisions when they are brought
before this court on an appeal on a question of law in terms of section 88 of
the 2003 Act. In paragraph 46 of his opinion in Jardine v Murray
supra, the then Lord Justice-Clerk observed, already famously: "The Land
Court is not an ordinary court of law." Lord Gill went on to explain that it is
a specialist court whose members have expert knowledge. That expert knowledge
includes not just the law relating to agriculture but also the practice of
agriculture in Scotland. It is informed, inter alia, by frequent
inspections of agricultural holdings of the sort that was carried out in this
case. In Jardine v Murray the importance of the Land Court's
special status related to the respect that this court will accord to its
findings in fact but in my opinion the deference which this court should show
towards the Land Court goes further than that. What is in issue here when
considering ground of appeal 4, and indeed when considering grounds of appeal 1
and 2, is the construction of relatively recently enacted statutory provisions,
the application of which fall particularly within the jurisdiction of the Land
Court and which relate, at the practical level, to matters of which the Land
Court has an expert knowledge which this court does not profess: cf Jardine v
Murray supra at para 49. Thus, while this court might regard itself as
entirely competent in the techniques associated with the generality of
statutory construction, it appears to me that it should exercise a degree of caution
in differing from a construction adopted by the Land Court where that
construction has been informed by the Land Court's understanding of the
practical effect of the construction not only in the case under consideration
but in other cases.
[49] Returning
then to section 5(4B)(b) of the 1991 Act, the Land Court's reasoning which led
to the construction that the state of the fixed equipment was to be assessed by
looking at the individual items making up the relevant fixed equipment rather
than looking at the equipment as a whole is set out at paragraphs [84] to [96]
of its Note dated 3 November 2010. In my opinion, that reasoning is compelling.
I agree with the conclusion.
[50] The
proper objective when construing a statutory provision is to arrive at its
legal meaning, the legal meaning being that which correctly conveys the
legislative intention: Bennion On Statutory Interpretation (5th
edit) pp24 and 441. That is of course not to say much more than that the
provision means what the Scottish Parliament intended it to mean, which might
be said simply to be a restatement of the objective rather than an explanation
of how one gets there. There will be cases where Parliament's purpose in
enacting the legislation can be identified from extrinsic material, including
the Explanatory Notes which are, in the majority of cases, now published
together with bills. Once the legislative purpose is known it becomes possible
to adopt a purposive approach to construction. This, however, was not a case
where either party made reference to extrinsic material or, indeed, except
insofar as it could be inferred from the text of the statutory provisions
themselves, to what was the purpose of Parliament in enacting the 2003
legislation. That placed the focus on the grammatical or linguistic meaning of
section 5(4B)(b) and therefore the ordinary meaning of the phrase "the
buildings and other fixed equipment", in its proper and most known
signification, read in the context of the statute taken as a whole:
cf Bennion supra pp441, 443, 1181. As I have said, neither party
put anything before either the Land Court or this court with a view to
identifying the purpose or policy which the 2003 Act was intended to put into
effect but a certain amount is readily apparent from the text. The 1991
consolidation of the legislation had re-enacted the prohibition against
contracting out, by way of the terms of the lease, of the landlord's deemed
obligation to put the fixed equipment on the holding into a thorough state of
repair and thereafter to replace and renew it as that became necessary.
However, the consolidation had also retained a provision (section 5(3)) which
permitted parties to allocate the obligation to replace and renew to the
tenant, through the mechanism of a post-lease agreement. The 2003 legislation
can be seen as reflecting a change in policy towards one that favoured the
obligation of replacing and renewing fixed equipment being borne by the
landlord. That would seem to be clearly articulated by subsections (4C) and
(4D) of section 5. Subsections (4A) and (4B) have something of the nature of a
transitional function: they permit a tenant to transfer the obligation to
replace and renew fixed equipment back to the landlord but subject to the fixed
equipment being in a reasonable state of repair or at least in no worse state
of repair than it was when the tenant assumed the obligation by way of a
post-lease agreement. That context appears to me to fit with the notion of a
"fresh start" referred to by the Land Court (first mentioned at paragraph [13]
of its Note dated 3 November 2010). In other words if the landlord can be
forced to assume an obligation of replacement and renewal, it would seem fair
that that should be in respect of fixed equipment that is in at least
reasonable condition or, if not, in no worse condition than the fixed equipment
was when the tenant took on the obligation under a post-lease agreement. The
Land Court considered that the idea of a "fresh start" fitted better with an
item by item construction of "the buildings and other fixed equipment". I would
agree. The Land Court recognised the force of the appellant's submission that
in a practical sense it might be difficult to ensure that every last item was
in a reasonable state of repair given that a tenant would maintain the fixed
equipment on a cyclical basis. However, that, in the view of the Court, was not
the proper focus. While, as had been argued on behalf of the respondents, a
broad or robust approach to the assessment of the condition of individual items
would be appropriate and might in part address such problems, the critical
context was not one of regulating the practical day to day working of the farm
but one of the setting aside of contractual arrangements negotiated by the
parties to regulate their affairs. Parliament was dealing with a situation
where the existing contractual obligation on the tenant was to effect necessary
replacement or renewal of all the relevant items of equipment. In that context,
it was quite reasonable to require the performance of current obligations to be
up to date. Again, I would agree. An obligation to replace and renew specified
fixed equipment when necessary is an obligation to replace or renew every item
of fixed equipment when necessary. There is no very obvious reason why the
landlord should not require the obligation to have been fully performed by a
tenant who has undertaken it by entering into a post-lease agreement before
having to resume the obligation on a section 5(4A) nullification.
[51] Developing
its idea of a "fresh start", the Land Court drew attention to the consideration
that a tenant may have paid rent over many years fixed on the assumption that
the tenant had onerous commitments. On nullification a landlord might find
these commitments to have become unenforceable. A construction which required
every piece of equipment to be in a reasonable state of repair would tend to
minimise that particular risk. The Land Court thought that approach to be
consistent with what was proper when rights are removed retrospectively. That
seems to me to be valid.
[52] In at least
two respects I would see the Land Court's construction as being reinforced by
it having drawn on its legal and practical expertise. Referring to its previous
decision in another litigation between the parties, Telfer v
Buccleuch Estates Ltd 2005 SLCR 51, the Court was able to say with a
confidence which a non-specialist court would find difficult to emulate that it
was not aware of "any concept of fixed equipment as a totality having been
applied in any case in Scotland relating to repair obligations in an
agricultural context", and "although not free from difficulty in its
application, the practice has been to assess the repair obligation by reference
to identifiable individual items of fixed equipment". The Court added that it
was satisfied that the provisions of section 5(2) have always been understood
in this sense. These are quite powerful statements. The Land Court was in a
good position to make them. I take them to be an accurate summary of the understanding
of the concept of fixed equipment and the approach to the assessment of its
condition in practice and therefore, to revert to Bennion's language, the "proper
and most known signification" of the relevant expression. The second respect in
which the Land Court was able to reinforce its construction by drawing on its
own particular expertise was at paragraph [92] of its Note when it had regard
to the practical implications of the construction urged on it by the appellant.
In the view of the Court it became clear that the appellant's construction did
not in fact provide a robust approach in the sense of being one which is
capable of being easily applied in practice with tolerably consistent results.
Looking at matters as a whole invited attention to fractions or percentages.
The approach would require consideration of the proportion of equipment which
was in a reasonable state of repair as opposed to that which was not. That
raised a number of questions. For example, was the percentage to be assessed by
reference to the value of the whole fixed equipment in question or, perhaps, to
the number of separate identifiable items making up that totality of equipment?
It would, on any view, require consideration initially to be given to the state
of individual items. At any given time the bulk of the fixed equipment on the
farm would be expected to be in a reasonable state of repair. The focus of
attention would not be on the equipment as a whole but on the items needing
renewal.
[53] I would add
this. In the present case it would appear that no record of the condition of
the fixed equipment on the holding was made when the lease of Auchengruith was
entered into. That was a matter of complaint by the appellant, because section
5(1) of the 1949 Act required such a record to be made forthwith with a view to
it being deemed to form part of the lease. The same requirement appears in the
1991 Act. Thus, while in the present case there was no record of the condition
of the fixed equipment and while that may be so in many other cases, the
paradigm that the legislature will have had in view when enacting
section 5(4B)(b) is one where there will be a record of the condition the
fixed equipment as at the date of entering into the lease. While section 8 of
the 1991 Act, which applies to the making of such a record does not expressly
so state, I find it very difficult to imagine a record of the condition of the
fixed equipment on the holding which has not been drawn up on an item-by-item
basis. If I am correct about that then the legislative intention would be best
reflected in an item-by-item approach to the determination of whether the
buildings and fixed equipment are in reasonable or unreasonable state of
repair.
[54] The Land
Court concluded that part of its Note dated 3 November 2010 which gives its
reasoning for the adoption of an item-by-item construction of section 5(4B)(b)
as follows:
"[96] In short, we conclude that the state of the fixed equipment is to be assessed by looking at the individual items making up the relevant fixed equipment. We are satisfied that in the context of the range of the fixed equipment likely to be covered by any PLA it is appropriate to apply a very broad approach. We accept that Parliament must have been intending to address issues of substance. The expression "reasonable state of repair" can be considered broadly. Even if some parts of the fixed equipment are worn out, if they are minor parts, we accept that, in the context of this provision, they can be ignored. But, if there is any significant amount of work to be done to put any individual item into a reasonable state of repair, that will normally prevent the "buildings and fixed equipment" from being in a reasonable state of repair within the meaning of (i)."
As I have already indicated, I consider that to be the correct approach to the subsection. It is consistent with the ordinary meaning of the words. It gives the concept of "the buildings and other fixed equipment" the meaning which was attached to it in agricultural law and practice prior to the amendment of the legislation by the 2003 Act. It is workable and it reflects how assessments and comparisons of fixed equipment are likely to be carried out in real conditions. It is likely more closely to achieve the symmetry as between the situation on entering into a post-lease agreement and the situation on annulment of the agreement which would seem to be the intention of the legislature than would the suggested alternative.
Grounds of appeal 1 and 2
[55] I
would understand grounds of appeal 1 and 2 and the associated questions of law
1 and 2 which appear in the appellant's Appeal, all to relate to one
contention: that, even if it were correct to assess or compare the fixed
equipment item-by-item, the Land Court erred in law, when considering the
application of section 5(4B)(b)(ii), by not comparing the state of the
Duntercleuch fence with that of the "old fence" which had been in position in
1971 when the PLA was made but which had been replaced by the Duntercleuch
fence in 1972.
[56] As
previously noted, the Land Court expresses its conclusion on this matter at
paragraph [107] of its Note dated 3 November 2010:
"When considering [section 5(4B)(b)(ii)] it is necessary to carry out a direct comparison of individual items. In broad terms, if an original item has been replaced by a radically different piece of equipment, [section 5(4B)(b)(ii)] will not come into play in relation to that particular equipment. In other words if such a piece of equipment is not in a reasonable state of repair there will be nothing with which to compare it."
[57] Again,
the point of law raised by the grounds of appeal is one of statutory
construction.
[58] On
the item-by-item approach to the fixed equipment adopted by the Land Court
(which I consider to be correct) there is no question but that the Duntercleuch
fence was not in a reasonable state of repair (and therefore was in an
unreasonable state of repair) as at 22 October 2007. Subsection (4B)(b)(i) is
therefore not complied with. What then about subsection (4B)(b)(ii)? It will be
recollected that there would be compliance with subsection (4B)(b)(ii) for
present purposes if the item of fixed equipment was not in a worse state of
repair than it was on the date when the post-lease agreement was made. The Land
Court said that subsection (4B)(b)(ii) had not been complied with. In its
summary of formal findings in relation to the interpretation of subsection
(4B)(b)(ii) set out in its Note dated 3 November 2010 the court had included
the following:
"[101] If an item of equipment, present at the date of nullification, was not present at the date when the agreement was made, (ii) will have no application.
[102]
Even if an item of equipment, present at the date when the agreement was made,
has been substantially renewed before the date of nullification it will
normally fall to be regarded as the same equipment for the purposes of (ii).
[103]
If an item of equipment, present at the date when the agreement was made, has
been wholly replaced, it will not be available for comparison for the purposes
of (ii)."
I do not see paragraphs [101] or [102] presenting difficulty. Paragraph [103] is perhaps more problematic. At least on the court's approach, it depends upon a distinction between "replacement" and "renewal" which, in this context, I simply do not see to be warranted. It was not supported either by the appellant or Sir Crispin on behalf of the respondents, either before the Land Court or before this court (Sir Crispin's argument being that the Duntercleuch fence was not available for the purpose of comparison irrespective of whether it was to be regarded as a replacement for the old fence or whether it was a renewal of the old fence).
[59] "Replacement"
and "renewal" and their corresponding verbs are clearly capable of having
different meanings or at least different shades of meaning. One need not go
further than section 5(4A) of the 1991 for support for that proposition in that
one there finds the expression "replacement or renewal of the building or other
fixed equipment". That both words are used suggests that they have or may have
different meanings and that that is so in the context of the maintenance of
fixed equipment. Equally, a particular physical operation may be better
described as a "replacement" than as a "renewal". Sometimes that will be very
clearly so, sometimes it will be less clearly so. However, whether legal
significance should be attached to such linguistic subtleties is another
matter.
[60] The
submission made to the Land Court on behalf of the respondents by
Sir Crispin and renewed before this court is recorded at paragraphs [5] to
[8] of the court's Note dated 3 November 2010. Subsection (4B)(b)(ii) was
dealing with the buildings or fixed equipment that existed at the time the
agreement was made. The use of "the", "they" and "them" where these words
appeared made this clear. This was logical where the tenant had the renewal or
replacement obligation. Under section 5(4B)(b)(i) the tenant had to hand
over the buildings and fixed equipment that he was responsible for in a
"reasonable state of repair", and under section 5(4B)(b) (ii) to hand back
the original buildings and fixed equipment in no worse state of repair. It was
illogical to construe section 5(4B)(b)(ii) to the effect that if the fixed
equipment had been replaced by a new item of fixed equipment, the tenant should
be allowed to let it fall into the same state of disrepair as the former items
of fixed equipment had been at the outset of the lease. The sensible approach
was that, if something new had been interposed, it was reasonable to have
regard to it. That applied even if the new equipment had been provided by the
tenant. The old equipment should be regarded as having been superseded as
redundant. It was no longer part of the fixed equipment. On any view, the
original equipment, as it was at the outset, was no longer there. There was
nothing to compare for the purposes of section 5(4B)(b)(ii). Accordingly, the
tenant could only rely on section 5(4B)(b)(i). Sir Crispin accepted that
this meant that, if a tenant had managed to get by, doing minimum repairs, he
would be able to rely on section 5(4B)(b)(ii). But, if he had actually renewed
existing equipment, he could only rely on section 5(4B)(b)(i) as the old
equipment would not be there for comparison. This was justified because the
tenant should be seen to have done any renewal "on the landlord's behalf". It
did not matter who had actually done the work. It was a landlord's obligation
which had been taken over by the tenant.
[61] The
appellant's submission to the Land Court is recorded in paragraph [10] of the
court's Note.
[62] The
Land Court was not persuaded by the respondents' submission but clearly had
difficulty in identifying a satisfactory alternative approach. At paragraphs to
[11] to [17] of its Note the Court discusses how section 5(4B)(b)(ii) might
impact on different post-lease agreements in differing situations but without
coming to any conclusion which assisted it in construing the provision. At
paragraph [22] the court admits its difficulty in identifying the precise
policy behind section 5(4B)(b)(ii) and at paragraph [24] it rejects
considerations of reasonableness or fairness as a means of discerning the
intention of Parliament. With that by way of background the Court adopted what it
described as "a practical approach to the concept of identity", the
ramifications of which, with the consequent distinction between "replacement"
and "renewal" are explored in paragraphs [21] to [26].
[63] I
agree with the Land Court that central to an understanding of the meaning of section
5(4B)(b)(ii) is the concept of identity. That must be so on the ordinary
meaning of the statutory language, certainly once "the buildings and other
fixed equipment" is construed as a reference to the individual items of fixed
equipment which are subject to the post-lease agreement. That is because the
provision requires a comparison of the state of what, in some sense, is the
same item at different points of time. Only if, in some sense, a particular
item of fixed equipment that exists at the notice date is the same item of
fixed equipment that existed at the post-lease agreement date can the exercise
of comparison required by "not in a worse state of repair" be carried out. For
the Land Court "identity" means that the items of fixed equipment must
constitute one and the same physical object, subject to a degree of leeway
provided by a construction of "renewal" as something less fundamental than
"replacement", albeit that "there is plainly scope for much philosophical discussion
of the concept of continuing identity" (see Note paragraph [20]) as the
component parts of, for example, a fence, are incrementally substituted by new
components as the former components fall into disrepair.
[64] I
find the Land Court's emphasis on physical identity unconvincing and
unnecessary. In my opinion, a more natural reading of section 5(4B)(b)(ii) is
one pointing to identity of function rather than identity (more or less) of
constituent parts as determining whether an item of fixed equipment present at
the notice date is available for comparison with an item of fixed equipment
present at the post-lease agreement date. I am encouraged in coming to that
view by what is said about fixed equipment in sections 5(2) and 85(1) of the
1991 Act. "Fixed equipment" is given a wide definition in section 85(1) as
including various things, from farm houses to plug sockets which, whether the
expression is attached to them (as it is at section 85(1)(a) and (d)) or not
are "necessary for the proper conduct of the ...holding". Similarly, the
obligation on the landlord which is deemed by section 5(2)(a) is to put the
fixed equipment on the holding into a thorough state of repair, and to provide
such buildings and other fixed equipment "as will enable an occupier reasonably
skilled in husbandry to maintain efficient production". As is perhaps no more
than self-evident, the fixed equipment of a holding is made up of items with a
function, the function being, in ways specific to the specific items, to enable
the holding to be used for efficient agricultural production. With that in mind
and remembering also that the legislature envisaged that there would always be
a record of the condition of the fixed equipment on the holding and therefore
something of the nature of a list of the items of fixed equipment available for
various necessary agricultural purposes at the commencement of the lease, I
would regard the natural meaning of "the buildings and other fixed equipment
...when the agreement was made" and "they" where that word second occurs in section
5(4B)(b)(ii) as being those items which, as at the date of the post-lease
agreement, were performing the function associated with such items in such
locations as they were situated. Similarly, I would regard "they" where that
word first occurs in section 5(4B)(b)(ii) as meaning those items which, as at
the notice date are performing the function associated with such items in such
locations. Thus, if, for example, a march fence is located at a particular
boundary at the notice date, for the purposes of section 5(4B)(b)(ii) its state
of repair may be compared with the state of repair of the fence which was in
that location performing that function at the post-lease agreement date. It
will not matter whether the march fence at the notice date is composed of
exactly the same stobs and wires as the march fence at the post-lease agreement
date or whether some of the stobs and wires are different from the originals or
whether all of the stobs and wires are different. In this example I mention
location, which in the case of a fence I would suppose will generally be of
relevance, but what I see as the key to determining identity of items of fixed
equipment is function. If the item of fixed equipment is performing the same
function at the notice date as an item of fixed equipment at the post-lease
agreement date then the items are sufficiently identical to allow comparison of
their respective states of repair for the purposes of section 5(4B)(b)(ii). On
this construction no significance attaches to such distinction as there may be
as between "replacement" and "renewal". That is a consideration which tends to
confirm me in my conclusion. Agreeing with both the appellant and Sir Crispin,
I see the distinction, over which the Land Court agonised, as a distinction
without a difference. As I read the Act, the proper distinction is between
maintenance in the sense of keeping in good repair, on the one hand, and
replacement or renewal, on the other, but, for the purposes of the statute,
"replacement" and "renewal" are the same thing, or at least describe the same
obligation and have the same effect.
[65] I
am conscious that by adopting a different construction of the statute than that
adopted by the Land Court I may be seen to be offending against the principle
that, in this area, this court should accord particular deference to the
undoubted experience and expertise of the specialist court. I would however
observe that in this instance, in adopting the construction that it did, the
Land Court placed no reliance on policy or practical effect. Its analysis would
appear to have been entirely linguistic and philosophical. I have therefore
felt emboldened to substitute what I consider to be the correct interpretation
of the statute.
[66] Given
the Land Court's finding, at paragraph [30] of its Note dated 25 April 2012,
that at the relevant date the Duntercleuch fence was in no worse state than the
old fence had been in 1971, on what I see as the correct construction of the
provision, the requirements of section 5(4B) were complied with in respect of
the items of fixed equipment the condition of which was considered at the
proof. The Land Court's determination must therefore be quashed. I understood
from Sir Crispin that the respondents have reserved their right to challenge
the appellant's entitlement to nullify the PLA by reference to other items of
fixed equipment. That will be a matter for the Land Court when the case is
remitted back.
Disposal
[67] This court
has power in an appeal under section 88 to quash, confirm or vary the
determination complained of or any part of it. Where the court quashes the
determination or any part of it, it may remit the case to the Land Court for
further procedure and direct the Land Court on any question of law relevant to
the case. Consistent with the views expressed in this opinion I would move your
Lordships to quash the determination of the Scottish Land Court of 25 April
2012 insofar as it finds that no comparison falls to be made of the
Duntercleuch fence and the old fence under section 5(4B)(ii) of the
Agricultural Holdings (Scotland) Act 1991 and that accordingly the tenant was
not entitled to nullify the Post Lease Agreement as at 22 October 2007; to
direct the Land Court that a comparison does fall to be made of the
Duntercleuch fence and the old fence under section 5(4B)(ii) of the
Agricultural Holdings (Scotland) Act 1991; and, quoad ultra, to remit
the case to the Land Court for further procedure as accords.
EXTRA DIVISION, INNER HOUSE, COURT OF SESSION
|
|
Lord MenziesLord BrodieLord Malcolm
|
|
Respondents: Sir Crispin Agnew, QC; Anderson Strathern
31 May 2013
[68] I have had
the benefit of reading in draft the opinion prepared by Lord Brodie. I
have reservations as to the "item by item" approach to the construction of the
relevant statutory provisions. However, I do not intend to dissent from the
view taken by his Lordship in the discussion of ground of appeal 4. It
supports the approach adopted by the Land Court, which, as a specialist court,
has given the matter the most careful and anxious consideration. My only
comment is that it is far from clear that the drafters of section 5(4B) of the
1991 Act had in view the potential diversity of post-lease agreements, not
least those which, as here, place a financial liability on the tenant, with the
landlord retaining executive responsibility for repairs. The statutory tests
appear to proceed upon the basis of a relatively simple situation, with the
tenant assuming all duties concerning the replacement or renewal of all the
fixed equipment on the holding. Unfortunately the real world is likely to be
more complex, and this may create difficulties for the Land Court when
attempting to apply the legislation.
[69] I need not
dwell on ground of appeal 4 given that Lord Brodie's views on the other
matters, with which I am in entire agreement, are sufficient to dispose of this
appeal in favour of Mr Telfer. In the course of the hearing, counsel for
the respondents indicated that, if the appeal were to succeed, and
notwithstanding the protracted nature of the proceedings so far, he would be
moving the Land Court to allow an inquiry into whether nullification could be
resisted by reference to other parts of the fixed equipment on the farm. It
seems likely that, when making a selection of certain items for consideration
by the Land Court, the landlords chose those which were most likely to result
in a favourable outcome. In the result they have failed in all of them.
However, if and when an application is made, it will be for the Land Court
to decide whether such further procedure is to be allowed. I agree that the
appeal should be dealt with as proposed by Lord Brodie.