BAILII is celebrating 24 years of free online access to the law! Would you
consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it
will have a significant impact on BAILII's ability to continue providing free
access to the law.
Thank you very much for your support!
[New search]
[Printable PDF version]
[Help]
Page 1 ⇓
OUTER HOUSE, COURT OF SESSION
[2019] CSOH 110
CA116/19
OPINION OF LORD DOHERTY
in the cause
BABCOCK MARINE (CLYDE) LIMITED
against
HS BARRIER COATINGS LIMITED
Pursuer
Defender
Pursuer: Richardson QC; Morton Fraser LLP
Defender: Walker QC, Steel; Balfour + Manson LLP (for Hill Dickinson LLP)
27 December 2019
Introduction
[1] In this commercial action the pursuer seeks payment of sums which an adjudicator
has ordered the defender to pay to it. The defender resists payment on four grounds. Each
party has a preliminary plea to the relevancy of the other party’s averments. The matter
came before me for a debate which was conducted having regard to the pleadings, the
adjudicator’s decision, and the other documents forming part of the adjudication process.
Page 2 ⇓
2
The contract
[2] In December 2014 the pursuer contracted with the defender for the defender to carry
out re-preservation of shiplift docking cradles at HM Naval Base Clyde. The work was to
involve dismantling cradle components, removing legacy coating, preparing the metal
surface for painting, and painting and reassembling the components. The total contract
price was £800,000. The contract incorporated the NEC3 Engineering and Construction
Short Contract (June 2005) with bespoke Z clause amendments. It made provision
(clauses 60 to 63) for the price to be increased on the occurrence of specified compensation
events. It is a "construction contract" as defined by Section 104 of the Housing Grants,
Construction and Regeneration Act 1996 ("the 1996 Act"). Clause Z17 provided for any
dispute to be referred to adjudication in accordance with clauses 93.2, 93.3 and 93.4 of the
contract conditions.
[3] Clauses 90 and 92 of the contract conditions provide:
“90 Termination and reasons for termination
...
90.2 Either Party may terminate if the other Party has become insolvent or its
equivalent (Reason 1).
90.3 The Employer may terminate if the Employer has notified the Contractor that the
Contractor has defaulted in one of the following ways and the Contractor has not
stopped defaulting within two weeks of the notification.
Substantially failed to comply with this contract (Reason 2).
Substantially hindered the Employer (Reason 3).
Substantially broken a health or safety regulation (Reason 4).
The Employer may terminate for any other reason (Reason 5).
...
Page 3 ⇓
3
92 Payment on termination
92.1 The amount due on termination includes
an amount due assessed as for normal payments
the cost of Plant and Materials provided by the Contractor which are on
the site or of which the Contractor has to accept delivery and
any amounts retained by the Employer.
...
92.3 If ... the Employer terminates for Reason 5, the amount due on termination also
includes 5% of any excess of a forecast of the amount due at Completion had there
been no termination over the amount due on termination assessed as for normal
payments.
...”
Clause 93.1 (as replaced by clause Z 17) provides for a tiered dispute resolution process:
"A dispute arising under or in connection with this contract is notified to the
Employer's and Contractor's commercial management organisations who shall use all
reasonable endeavours to resolve through negotiation. If the dispute is not resolved
within three days the matter shall be escalated to commercial senior management
who shall have 3 days to resolve. If the dispute is not resolved the matter shall be
escalated to commercial directors, who shall have 3 days to resolve. If resolution
fails, the dispute shall be decided by the Adjudicator in accordance with clauses 93.2,
93.3, 93.4 (and 94.1 if specified in the Contract Data)."
Clause 93.2 provides:
“(1) The parties appoint the Adjudicator under the NEC Adjudicator’s Contract
current at the starting date...
...”
Clause 94.1 provides for the parties to refer a dispute to adjudication at any time where the
1996 Act applies. It is common ground that the NEC Adjudicator’s Contract which was
current at the starting date was the April 2013 edition.
The NEC Adjudicator’s Contract
[4] Clause 2.3 of the NEC Adjudicator’s Contract (April 2013 edition) provided:
“After notifying the parties of his intention, the Adjudicator may obtain from others
help that he considers necessary in reaching his decision. Before making his
Page 4 ⇓
4
decision, the Adjudicator provides the parties with a copy of any information or
advice from others and invites their comments on it.”
The adjudicator’s letter of 11 February 2019
[5] On being appointed the adjudicator wrote to the parties by letter dated 11 February
2019 confirming acceptance of the appointment. He enclosed with the letter a document
headed “Terms and Conditions of Appointment” (“the Terms”). Paragraph 14 of the Terms
stated:
“14. If I require quantity surveying input during the Adjudication I will utilise the
resources of Bunton Consulting Partnership. This matter is at my absolute discretion
and I will not require the consent of the parties. A senior QS will be charged
at £85 per hour plus expenses and a junior QS at £55 per hour plus expenses.”
The carrying out of the contract works and the agreement to vary the contract
[6] After the works commenced on site there were several disagreements between the
parties. The pursuer was dissatisfied with progress. For its part, the defender claimed that it
was entitled to additional payment under the contract for compensation events. By
22 December 2016 the defender had intimated claims for seven compensation events (CE1
to CE7). Before that date the parties had agreed that the total contract price be increased
by £20,056.11 in respect of CE7. On 22 December 2016 they entered into a Settlement
Agreement (“the Agreement”) which settled disputed matters up to that date (including the
compensation events) apart from the extra over cost of treating six larger strongbacks. In
terms of the Agreement the total contract price was revised from £820,056.11 to £1,070.056.11.
The revised value included a £20,000 provisional sum in respect of the additional cost of the
six larger strongbacks.
Page 5 ⇓
5
Termination
[7] Although progress was slow the sums claimed by the defender escalated. The
pursuer terminated the contract on 15 June 2018 on the ground of Reason 5. On 25 June 2018
the defender prepared and submitted a Termination Application (Payment Notice 31) (7/5 of
process) which applied for payment of £967,549.42 plus VAT. On 10 September 2019 the
pursuer certified £NIL in respect of that application.
The first adjudication
[8] On 10 September 2018 the defender served notice of intention to refer a dispute to
adjudication. The principal issues to be adjudicated upon were (i) whether the Termination
Application was a valid payment notice in terms of the contract; and (ii) whether notices issued
by the pursuer dated 19 July 2018 and 9 August 2018 were valid pay less notices. The wider
question of “the veracity of either party’s assessments” (see para 11.4 of Mr Donny Mackinnon’s
decision dated 14 November 2018 (7/8 of process)) had not been referred to adjudication.
Mr Mackinnon held that the Termination Application was a valid payment notice and that the
notices of 19 July 2018 and 9 August 2018 were not valid pay less notices. The defender was
entitled to payment in full of the sum claimed plus interest and fees. On 3 December 2018
Mr Mackinnon amended the decision (reducing the interest payable by the pursuer). On 7 and
13 December 2018 the pursuer paid the defender the sums awarded. Both parties issued notices
of dissatisfaction in respect of the decision.
Page 6 ⇓
6
The second adjudication
Introduction
[9] The parties remained in dispute as to the true and proper valuation of the works as at
the date of termination. In February 2019 the pursuer referred that dispute to adjudication
and requested that the adjudicator give reasons for his decision. Mr Len C H Bunton was
appointed as adjudicator.
[10] The three principal elements of the valuation which were in dispute were (i) the
value of the base scope works; (ii) what, if any, value should be attributed to compensation
events CE8 to CE13; and (iii) the value of termination costs.
Base scope works
[11] The pursuer maintained that the value of the base scope works at the date of
termination was £447,263.62. The defender maintained it was £643,101.47. In arriving at its
figure the defender relied upon a report (7/7 of process) prepared by Mr Cookson, who is a
chartered quantity surveyor and a chartered builder. Mr Cookson’s figure was only very
slightly higher (0.7%) than the base scope works figure of £638,553.21 which the defender
had advanced in the Termination Application.
Compensation events
[12] The pursuer’s primary position was that no sum was due in respect of the claimed
compensation events CE8-CE13. Its fall-back position was that only a total of £130,384.15
was due (ie £24,713.38 for CE8; £13,083.76 for CE9; £78,021.18 for CE12; and £14,565.43
for CE13 (which, in fact, resulted in a total of £130,383.75)). In the Termination Application
the defender had claimed that a total of £690,155.18 was due for compensation events
Page 7 ⇓
7
CE8-CE13, whereas in the second adjudication it relied on Mr Cookson’s valuation
of CE8-CE13 and it claimed £1,003,498.22 (on the basis of a price list assessment)
or £1,032,583.68 (on the basis of a defined cost assessment).
Termination costs
[13] The pursuer’s primary position was that the sum for demobilisation costs
was £39,064.02, and that £32,807.80 was due for excess of forecast at completion. In the
Termination Application the defender had claimed £160,446.75 for demobilisation costs
and £75,773.59 for excess of forecast at completion; whereas in the adjudication it advanced
Mr Cookson’s valuations (which were £87,350.63 for demobilisation costs, and £90,436.26
(on a price list assessment basis) or £100,599.01 (on a defined cost assessment basis) for
excess of forecast at completion).
Mr Bunton’s decision
[14] Mr Bunton issued his decision on 22 March 2019. The decision incorporated a note of
reasons and a Scott Schedule (in the form of an Excel spreadsheet). For present purposes it
is sufficient to indicate what Mr Bunton decided in relation to base scope works,
compensation events and termination costs. He held that the value of the base scope works
was £447,263.62. He decided that the price should be increased by £690,155.18 because of
compensation events CE8-CE13. In relation to termination costs, he decided that
demobilisation costs were £39,064.02 and that the excess of forecast at completion
was £93,867.67.
[15] Mr Bunton sent the parties his decision under cover of a letter dated 22 March 2019.
He also sent each party a Fee Account. One of the entries in the Fee Account was:
Page 8 ⇓
8
“QS assistance – 28 hours @ £95 £2,660”
Proceedings in England and Wales
[16] The pursuer raised proceedings in England and Wales to enforce Mr Bunton’s award
(on the basis that the defender was domiciled there). The defender resisted enforcement,
pleading inter alia that the court did not have jurisdiction; and that if it did the action should
be stayed on the ground of forum non conveniens. On 28 June 2019 Mrs Justice O’Farrell held
that while the courts in Scotland and England and Wales both had jurisdiction, Scotland was
the more appropriate forum. She granted a stay of the English proceedings (Babcock Marine
The present action
[17] The present action was raised on 31 July 2019. Defences were lodged on 29 August
2019. At the preliminary hearing on 13 September 2019 I allowed the pursuer seven days to
adjust its pleadings, seven days for the defender to adjust in response, and a further seven
days mutual adjustment. The debate was fixed for 25 October 2019. On 21 October I
granted the pursuer’s unopposed motion to extend the period of mutual adjustment until
21 October 2019.
[18] In the defences the defender avers that the adjudicator failed to exhaust his
jurisdiction; and that because of the way that the adjudication was conducted there has been
a breach of natural justice. Since the alleged failures are all set out in my summary of
Mr Walker’s submissions I do not repeat them here. The defender maintains that it is not
bound by the decision, which should be reduced ope exceptionis.
Page 9 ⇓
9
[19] By adjustment intimated on 27 September 2019 the defender made reference for the
first time to the adjudicator having engaged the services of a quantity surveyor who
“purportedly provided 28 hours assistance to the Adjudicator”. By further adjustment
intimated on 4 October 2019 the defender averred:
“To the extent that the defender was not advised of the appointment of the QS and
the nature of the assistance provided by him, an opportunity has been afforded for
injustice to be done and there is a breach of natural justice. The decision should be
held as unenforceable and falls to be reduced ope exceptionis.”
Recent correspondence with the adjudicator
[20] On 1 October 2019, shortly after the defender intimated its adjustments raising the
issue of the quantity surveyor assistance, the pursuer’s solicitors sought to obtain
clarification from the adjudicator of the nature of that assistance. By email dated 2 October
2019 the adjudicator replied that in terms of paragraph 14 of the Terms the engagement of
quantity surveying assistance had been entirely at his discretion and that he had not
required to advise the parties of it. He pointed out that the parties had known since
22 March 2019 that he had obtained such assistance and that no issue had been taken with it.
While at the time of reply he was out of his office and was not able to review the
adjudication papers, he observed:
“I cannot, at this stage ... recall exactly what assistance was provided. However,
based on my past and extensive experience as an Adjudicator, this would probably
involve clerical and administrative assistance, checking that the parties (sic)
submissions contained the documents set out in any inventory, checking the parties
(sic) calculations in relation to variations etc, assisting me in checking if the parties
have submitted vouching information in relation to variations etc, double checking
figures after my calculations, and populating the Scott Schedule with values I had
decided, and assistance in proof reading, (sic) a very lengthy and detailed Decision.
For example, I can see that on 19 and 22 March 2019, the day before my decision was
issued, 14 hours were taken up in checking that the figures from my Decision were
Page 10 ⇓
10
populated into the Scott Schedule, and this would be checked by me, and an assistant
to ensure there were no arithmetical slips...”
Counsel for the defender’s submissions
[21] Mr Walker recognised that decisions of adjudicators should be enforced unless there
is good reason to refuse enforcement (Atholl Developments (Slackbuie) Ltd, Petitioners 2011
SCLR 637, per Lord Glennie at para 17). He submitted that there were good reasons here.
[22] First, while it was clear that the adjudicator had preferred the pursuer’s base scope
works valuation to the valuation put forward by the defender, he had not explained why he
had preferred it. The defender was entitled to know why the adjudicator had decided the
matter the way that he had. Reference was made to Atholl Developments (Slackbuie) Ltd,
Petitioners, supra, per Lord Glennie at para 17; Balfour Beatty Engineering Services (HY) Ltd v
DC Community Partnerships Limited v Renfrewshire Council [2017] CSOH 143, per
Lord Doherty at para 26; Gillies Ramsay Diamond v PJW Enterprises Ltd 2004 SC 430, per
Lord Justice-Clerk Gill at para 31. The failure to give reasons was a material failure. By
failing to give adequate reasons the adjudicator had failed to exhaust his jurisdiction.
[23] Second, the adjudicator had failed to consider a material line of defence (Pilon Limited
v Breyer Group plc [2010] BLR 452, per Coulson J at para 22; Connaught Partnerships Limited v
Perth and Kinross Council 2014 SLT 608, per Lord Malcolm at paras 18-21). He had refused to
consider the Cookson report’s position on base scope works because he thought
(erroneously) that it was not competent for the defender to advance a base scope works
valuation which was higher than the base scope works valuation in the Termination
Application. Accordingly, he had failed to consider a material defence. Separatim, he had
Page 11 ⇓
11
failed to give proper reasons for deciding as he did. Those were failures to exhaust his
jurisdiction. Separatim, in deciding it was incompetent for the defender to rely on the
Cookson report the adjudicator acted in breach of natural justice because that possibility had
not been put in issue (Costain Limited v Strathclyde Builders Limited 2004 SLT 102, per
Lord Drummond Young at paras 23-24; Corebuild Ltd v Cleaver [2019] BLR 505;
[24] Third, the adjudicator had not explained the basis upon which he had arrived at his
termination costs figure. In relation to demobilisation costs it might be inferred (para 292)
that he had rejected the project leader claim because it was not something which had been
included in the price list and there was no vouching of the sum claimed. However, there
was no further explanation of why he had preferred the pursuer’s demobilisation costs
figure. The excess of forecast figure at completion of £93,867.67 seemed to have been based
on 5% of £1,877,353.40 (para 295), but the adjudicator had not said how that latter figure had
been calculated. Once again he had failed to give reasons. That was a material failure. In
that regard he had failed to exhaust his jurisdiction.
[25] Fourth, the adjudicator had engaged the services of a quantity surveyor who, it seemed,
had provided 28 hours of assistance to him in the adjudication. The parties were not informed
during the adjudication of the fact that quantity surveying assistance had been engaged, nor
was the nature of the assistance disclosed. An opportunity had been afforded for injustice to be
done (Barrs v British Wool Marketing Board 1957 SC 72, per Lord President Clyde at p 82). The
defender would insist on this ground if none of the other grounds of challenge was successful.
In that event it would be necessary to inquire into the precise nature of the services provided by
the quantity surveyor in order to determine whether the breach of natural justice had in fact
been material.
Page 12 ⇓
12
Counsel for the pursuer’s submissions
[26] Mr Richardson submitted that the defender’s averments were irrelevant and that
decree de plano should be pronounced.
[27] It was well settled that one of the purposes of the 1996 Act was to enable parties to
obtain a speedy decision from an adjudicator. The courts should lend their assistance to the
prompt enforcement of decisions made by adjudicators within the scope of their jurisdiction
(The Construction Centre Group Limited v Highland Council 2003 SC 464, per the Opinion of the
Court delivered by Lord Hamilton at para 14). Paragraphs 85 to 87 of the judgment of the
court in Carillion Construction Ltd v Devonport Royal Dockyard Ltd [2006] BLR 15 (delivered by
Chadwick LJ) set out the correct approach:
“85. The objective which underlies the Act and the statutory scheme requires the
courts to respect and enforce the adjudicator's decision unless it is plain that the
question which he has decided was not the question referred to him or the manner in
which he has gone about his task is obviously unfair. It should be only in rare
circumstances that the courts will interfere with the decision of an adjudicator. The
courts should give no encouragement to the approach adopted by DML in the
present case; which ... may, indeed, aptly be described as ‘simply scrabbling around
to find some argument, however tenuous, to resist payment’.
86. It is only too easy in a complex case for a party who is dissatisfied with the
decision of an adjudicator to comb through the adjudicator's reasons and identify
points upon which to present a challenge under the labels ‘excess of jurisdiction’ or
‘breach of natural justice’. It must be kept in mind that the majority of adjudicators
are not chosen for their expertise as lawyers. Their skills are as likely (if not more
likely) to lie in other disciplines. The task of the adjudicator is not to act as arbitrator
or judge. The time constraints within which he is expected to operate are proof of
that. The task of the adjudicator is to find an interim solution which meets the needs
of the case...
87. In short, in the overwhelming majority of cases, the proper course for the party
who is unsuccessful in adjudication under the scheme must be to pay the amount
that he has been ordered to pay by the adjudicator. If he does not accept the
adjudicator's decision as correct (whether on the facts or in law), he can take legal or
arbitration proceedings in order to establish the true position. To seek to challenge
the adjudicator's decision on the ground that he has exceeded his jurisdiction or
breached the rules of natural justice (save in the plainest cases) is likely to lead to a
Page 13 ⇓
13
substantial waste of time and expense — as, we suspect, the costs incurred in the
present case will demonstrate only too clearly.”
[28] The court should allow considerable leeway in relation to an adjudicator’s reasons
(Miller Construction (UK) Limited v Building Design Partnership Limited [2014] CSOH 80, per
Lord Malcolm at para 17). Brief reasons will suffice. In Carillion Construction Ltd v Devonport
Royal Dockyard Ltd, supra, the Court of Appeal set out (at para 53) Jackson J’s observations at
“53. The judge then went on, at paragraph 81 of his judgment, to state five
propositions which, as he said, bore upon the issues which he had to decide:
‘1. If an adjudicator declines to consider evidence which, on his analysis of
the facts or the law, is irrelevant, that is neither (a) a breach of the rules of
natural justice nor (b) a failure to consider relevant material which
undermines his decision on Wednesbury grounds or for breach of
paragraph 17 of the Scheme. If the adjudicator's analysis of the facts or the
law was erroneous, it may follow that he ought to have considered the
evidence in question. The possibility of such error is inherent in the
adjudication system. It is not a ground for refusing to enforce the
adjudicator's decision. I reach this conclusion on the basis of the Court of
Appeal decisions mentioned earlier. This conclusion is also supported by the
reasoning of Mr Justice Steyn in the context of arbitration in Bill Biakh v
Hyundai Corporation [1988] 1 Lloyds Reports 187.
...
4. During argument, my attention has been drawn to certain decisions on the
duty to give reasons in a planning context. See in particular Save Britain's
Heritage v No 1 Poultry Limited, [1991] 1 WLR 153 and South Bucks DC and
these cases are only of limited relevance to adjudicators' decisions. I reach
this conclusion for three reasons:
(a) Adjudicators' decisions do not finally determine the rights of the parties
(unless all parties so wish).
(b) If reasons are given and they prove to be erroneous, that does not
generally enable the adjudicator's decision to be challenged.
(c) Adjudicators often are not required to give reasons at all.
Page 14 ⇓
14
5. If an adjudicator is requested to give reasons pursuant to paragraph 22 of
the Scheme, in my view a brief statement of those reasons will suffice. The
reasons should be sufficient to show that the adjudicator has dealt with the
issues remitted to him and what his conclusions are on those issues. It will
only be in extreme circumstances, such as those described by [the]
Lord Justice Clerk in Gillies Ramsay [Diamond], that the court will decline to
enforce an otherwise valid adjudicator's decision because of the inadequacy
of the reasons given. The complainant would need to show that the reasons
were absent or unintelligible and that, as a result, he had suffered substantial
prejudice.’”
The Court of Appeal went on (at para 84) to approve Jackson J’s observations:
“84. It will be apparent, from what we have said in giving our reasons for refusing
permission to appeal, that we are in broad agreement with the propositions which
the judge set out at paragraph 81 of his judgment and which we have ourselves set
out at paragraph 53 in this judgment. Those propositions are indicative of the
approach which courts should adopt when required to address a challenge to the
decision of an adjudicator appointed under the 1996 Act...”
Reasons will be sufficient if they show that the adjudicator has dealt with the issues. Unless
reasons are absent or unintelligible and that causes substantial prejudice the court should
not interfere. In some cases the acceptance by an adjudicator of one position will be
sufficient to indicate the reasons for rejecting the other position (DC Community Partnerships
Limited v Renfrewshire Council, supra, per Lord Doherty at para 26; SW Global Resourcing Ltd v
[29] The difference between the parties in relation to the valuation of the base scope
works had not been to the fore at the adjudication. The defender’s figures had been set out
in appendices 55 and 56 to Mr Cookson’s report. There had been no discussion of them in
the body of the report. However, the difference had been focussed for the adjudicator (eg in
the pursuer’s Reply (7/14 of process) at paragraphs 5.4 to 5.7 and in the defender’s rejoinder
(7/15 of process)). The pursuer’s position had been that the difference arose because before
termination the defender had been overpaid for preliminaries. The defender denied that
there had been overpayment, or (if there had been) that the pursuer was entitled to take
Page 15 ⇓
15
account of it when valuing the base scope works. The adjudicator accepted the pursuer’s
figures. It was implicit that he had accepted that there had been overpayment before
termination. In the circumstances acceptance by the adjudicator of the pursuer’s position
had sufficiently disclosed his reasoning for rejecting the defender’s alternative position.
[30] It was erroneous to suggest that the adjudicator had failed to consider the position
advanced in the Cookson report and appendices when he was valuing the base scope works.
It was clear from his decision and reasons that he had fully considered the Cookson report
and appendices in relation to all of the disputed matters. The foundation for this aspect of
the defender’s argument was paragraph 183 of the adjudicator’s note of reasons. That
paragraph occurred during the adjudicator’s consideration of the parties’ opposing positions
on quantification of the CE8 claim. The adjudicator had been critical of the absence of
records and vouching supporting Mr Cookson’s assessments. Those were the circumstances
in which he had decided not to go beyond what the defender had claimed for the
compensation events in the Termination Application. He had not failed to consider
Mr Cookson’s report in the context of compensation events, and there was no basis
whatsoever for concluding that he had failed to consider the report and appendices in
relation to the base scope works. He had not considered himself capped by each of the
elements in the Termination Application. His base scope excess of forecast at completion
figure (£93,867.67) was higher than the corresponding figure in the Termination Application
(£75,773.59). In any case, even if on a fair reading of paragraph 183 the adjudicator was
saying that he considered claims were capped at the claims which had been made in the
Termination Application, the cap for the base scope works (£638,553.21) would have been
very far in excess of the adjudicator’s view of the value of those works (£447,263.62).
Page 16 ⇓
16
[31] The criticism of the adjudicator’s reasons relating to termination costs was
unwarranted. The dispute in relation to demobilisation costs had been clearly focussed in
the adjudication. The pursuer had itemised the build-up of its valuation. It had proposed a
total value of £39,064.02. Mr Cookson had not supported parts of the claim for £160,446.75
which the defender had submitted in the Termination Application (paragraphs 16.35
to 16.47 of his report). He had maintained that this aspect of the claim should be £87,350.63
(being £27,443.50 for redundancy notice and £59,907.13 for other demobilisation costs).
While the contract programme had allowed for about one week demobilisation, Mr Cookson
had considered it appropriate to allow five weeks. He allowed £25,250 for project leader
costs. The pursuer’s criticisms of the defender’s claim had been set out in, eg, the Reply at
paragraph 2.7; paragraph 5.1(f), (j), (k) and (l); and paragraphs 5.10 to 5.15. It was clear that
the adjudicator had taken the criticisms on board because he had found in favour of the
pursuer’s demobilisation figure. It was reasonably clear from paragraph 295 that he had not
accepted that any sum ought to be due for project leader costs, and that he thought
demobilisation claims ought to have been vouched to show actual costs incurred. In the
whole circumstances it had not been necessary for him to say more than he did in relation to
demobilisation costs.
[32] Nor had the adjudicator needed to say more than he did about excess of forecast to
completion. There was no dispute as to the methodology to be used - that was clearly set
out in clause 92.3. This was not a case of a method being used which was a surprise for the
parties. Rather, the formula had been applied in light of the other findings which the
adjudicator had made. The sum awarded under this head had been higher than the sum for
which the pursuer had contended because the adjudicator had awarded considerably more
for compensation events than the pursuer had suggested. There was no mystery about the
Page 17 ⇓
17
calculation of the excess of forecast sum. The multiplicand was £1,877,353.40
(paragraph 295). How that figure had been arrived at was apparent from the Scott Schedule.
The forecast of the amount due at completion had there been no termination
was £3,053,836.21. The amount due on termination which was to be deducted was the sum
of three figures - £447,263.62 (base scope works), £690,155.18 (compensation events)
and £39,064.02 (demobilisation costs). Five per cent of £1,877,353.40 was £93,867.67.
[33] The defender’s averments about the assistance which the adjudicator obtained from
a quantity surveyor were irrelevant. The presumption of propriety ought to be applied
(Atholl Developments (Slackbuie) Limited, Petitioner, supra, at para 17, and SW Global Resourcing
Ltd v Morris & Spottiswood Limited, supra, at para 13). Where an adjudicator obtained
assistance of a clerical or administrative nature without telling the parties that did not result
in a breach of natural justice (Dickie & Moore Limited v Trustees of The Lauren McLeish
Discretionary Trust [2019] CSOH 71 and John Sisk & Son Limited v Duro Felguera UK Limited
Adjudicator’s Contract the adjudicator was entitled to obtain such help as he considered
necessary provided that he notified the parties. Here, the adjudicator had notified the
parties by sending them the Terms. Paragraph 14 of the Terms had alerted them to the fact
that the adjudicator could obtain quantity surveying input without further notice. Neither
party had queried the Terms. Accordingly, contrary to the defender’s averments, the
defender had been advised of the adjudicator’s intentions. It may reasonably be inferred
from the fact that the adjudicator did not provide any information or advice to the parties
that the quantity surveyor assistance was merely clerical and/or administrative.
Page 18 ⇓
18
Counsel for the defender’s response
[34] Mr Walker responded to Mr Richardson’s submissions on Ground 4. The defender’s
averments were not irrelevant. On the face of things matters had not been done properly.
The adjudicator had not complied with either of the requirements of clause 2.3 of the NEC
Adjudicator’s Agreement. There had not been notification of his intention to obtain the
assistance which he obtained from the quantity surveyor. Paragraph 14 of the Terms had
not been notification of his intention to obtain that assistance. In any case, he had not
provided the parties with a copy of any information or advice from the quantity surveyor
and invited their comments on it. Inquiry was necessary to ascertain the nature of the
assistance which had been given in order to determine the materiality or otherwise of the
breach of natural justice which had occurred.
Decision and reasons
Base scope works: Ground 1
[35] There was no real dispute as to the relevant law. Where, as here, an adjudicator was
required to give reasons they could be brief, and they need not deal with every point.
Adjudicators’ reasons are not to be judged by the standards applied to judges or arbiters. A
reasonable person informed as to the context of the dispute who reads the decision ought to
be able to discern from it what the adjudicator has decided, and why he has decided it.
Here, there is no doubt that the reasonable reader would be clear that the adjudicator had
decided that the value of the base scope works was £447,263.62. Would he be able to discern
why the adjudicator had decided that? In my opinion he would.
[36] The reasonable reader would know that the difference between the parties’
valuations for base scope works had been focussed in the material before the adjudicator
Page 19 ⇓
19
(eg in the Referral at paragraph 10.7(a)(iii) (7/12 of process), in the pursuer’s Reply (7/14 of
process) at paragraphs 5.4 to 5.7, and in the defender’s Rejoinder (7/15 of process)). The
pursuer’s position had been that the difference arose because before termination the
defender had been overpaid for preliminaries. The defender denied that there had been
overpayment or, if there had been, that the pursuer was entitled to take account of it when
valuing the base scope works. The adjudicator accepted the pursuer’s figures. In my
opinion this is an instance of an issue where the acceptance by an adjudicator of one position
is sufficient to indicate the reasons for rejecting the other position (SW Global Resourcing Ltd
v Morris & Spottiswood Limited, supra, per Lord Hodge at para 17; DC Community Partnerships
Limited v Renfrewshire Council, supra, per Lord Doherty at para 26). I think it is implicit that
the adjudicator accepted that there had been overpayment before termination and that
account ought to be taken of that. In my view, acceptance by the adjudicator of the
pursuer’s position sufficiently disclosed his reasoning for rejecting the defender’s alternative
position.
Base scope works: Ground 2
[37] I am not persuaded that the adjudicator failed to consider the position advanced in
the Cookson report and appendices when he was valuing base scope works. On the
contrary, in my view his reasons suggest that he considered the Cookson report and
appendices when deciding all of the disputed matters.
[38] I do not think that Mr Walker’s suggested reading of paragraph 183 is correct. The
context of that paragraph, of course, was not the base scope works. It was part of the
adjudicator’s discussion of the quantification of the CE8 claim. In the immediately
preceding paragraphs the adjudicator had been critical of the absence of records and
Page 20 ⇓
20
vouching supporting Mr Cookson’s assessments. Those were the circumstances in which he
decided not to go beyond what the defender had assessed for the compensation events in
the Termination Application. So in relation to compensation events the adjudicator did not
fail to consider Mr Cookson’s report. Rather, he did not find it to be of much assistance
because Mr Cookson’s opinions were not based upon the sort of evidence (site
records/actual costs) he would have expected in the circumstances.
[39] It is no part of the defender’s case that the adjudicator failed to have regard to the
Cookson report in the context of compensation events. The adjudicator is not said to have
failed to exhaust his jurisdiction in respect of that part of his decision. Yet, paradoxically,
Mr Walker seeks to rely upon something said in relation to that aspect of the case to support
the proposition that the adjudicator treated the Cookson report as being forbidden territory
(at least in so far as the base scope works sum in the report exceeded the base scope works
sum in the Termination Application) when he came to consider the base scope works.
[40] I reject Mr Walker’s proposition. First, as already noted, I disagree with his reading
of paragraph 183. Second, as a matter of fact, the adjudicator cannot have considered
himself capped by each of the elements in the Termination Application because his base
scope excess of forecast at completion figure (£93,867.67) is higher than the corresponding
figure in the Termination Application (£75,773.59). Third, there was really no material
difference (about 0.7%) between the Termination Application base scope works
figure (£638,553.21) and the Cookson base scope works figure (£643,101.47). Even if on a fair
reading of paragraph 183 the adjudicator was saying that he considered all claims were
capped at the claims which had been made in the Termination Application, the cap for the
base scope works would have been very far in excess of the adjudicator’s view of the value
of those works.
Page 21 ⇓
21
[41] It follows from my rejection of Mr Walker’s proposition that I reject the contentions
which were based upon it viz that the adjudicator (i) failed to consider a material defence;
and (ii) acted in material breach of natural justice by not raising with the parties that he
proposed to cap values to those in the Termination Application.
Termination costs: Ground 3
[42] It seems clear that the dispute in relation to demobilisation costs was well focussed
during the adjudication. The pursuer itemised the elements it accepted - its total value for
demobilisation costs was £39,064.02. Mr Cookson departed materially from the
demobilisation costs claim which the defender had submitted in the Termination
Application (paragraphs 16.35 to 16.47 of his report). He maintained that the demobilisation
costs element of the termination costs should be £87,350.63 (£27,443.50 for redundancy
notice and £59,907.13 for other demobilisation costs). He recognised the contract
programme had allowed about one week for demobilisation, but he considered five weeks
to be justified. He allowed £25,250 for project leader costs, notwithstanding that no sum for
a project leader had been included in the contract price list. The pursuer’s criticisms of the
defender’s demobilisation costs claim were set out in the Reply at paragraphs 2.7, 5.1(f), (j),
(k) and (l), and 5.10 to 5.15.
[43] The adjudicator valued demobilisation costs at the figure suggested by the pursuer.
Once again, in my opinion it is implicit that the adjudicator agreed with the pursuer’s
criticisms of the defender’s figure. I think it is tolerably clear from paragraph 295 (i) that he
did not accept that any sum ought to be due for project leader costs (which were a
substantial part of the difference between the figures of £39,064.02 and £87,350.63); and
(ii) that he thought demobilisation claims ought to have been vouched and based on actual
Page 22 ⇓
22
costs incurred. In my opinion in the whole circumstances it was not necessary for the
adjudicator to say more than he did in relation to demobilisation costs.
[44] I am also satisfied that the adjudicator did not require to say more than he did about
excess of forecast to completion. There was no dispute as to the methodology. Clause 92.3
prescribed that. The adjudicator’s calculation and the result were no more than the
application of that methodology to the relevant findings which he had made. There was no
mystery about the calculation. The multiplicand was £1,877,353.40 (paragraph 295). The
Scott Schedule showed the constituent elements of that sum. The forecast of the amount due
at completion had there been no termination was £3,053,836.21. The payments deducted
from that sum were £447,263.62 (base scope works), £690,155.18 (compensation events)
and £39,064.02 (demobilisation costs). Five per cent of £1,877,353.40 was £93,867.67.
[45] It follows that I reject ground 3.
Breach of natural justice: Ground 4
[46] I did not understand there to be any dispute about the applicable law. In reaching
his decision the adjudicator required to comply with the rules of natural justice (Costain
Limited v Strathclyde Builders Limited 2004 SLT 102; Carillion Utility Services Limited v SP
Power Systems Limited [2011] CSOH 139; Highland and Islands Airports Limited v Shetland
Islands Council [2012] CSOH 12). The test is not “Has an unjust result been reached?” but
“Was there an opportunity afforded for injustice to be done?” (Barrs v British Wool Marketing
Board, supra, per Lord President Clyde at p 82). However, immaterial breaches of natural
justice will not render a decision unenforceable: the provisional nature of an adjudicator’s
decision justifies ignoring non-material breaches (Balfour Beatty Construction Ltd v The Mayor
Page 23 ⇓
23
HH Judge Lloyd QC at para 27; Dickie & Moore Limited v McLeish & Ors, supra, per
Lord Doherty at para 33).
[47] The defender does not accept that the Terms were incorporated into the parties’
contract with the adjudicator. Mr Richardson did not suggest that the court should hold at
this stage that the defender’s averments to that effect are irrelevant. The defender’s case is
that it was incumbent upon the adjudicator to inform the parties during the adjudication
(i) that he was obtaining quantity surveying assistance; and (ii) of the nature of that
assistance. He avers that neither of these things was done, and that as a result there has
been a breach of natural justice. The question is, can it be said at this stage, without inquiry,
that this defence is bound to fail (Jamieson v Jamieson 1952 SC (HL) 44, per Lord Normand at
p 50, Lord Reid at p 63; Henderson v 3052775 Nova Scotia Ltd 2006 SC (HL) 85, per
Lord Rodger of Earlsferry at para 16)?
[48] Mr Richardson maintains that the court should reach that conclusion. He says that
paragraph 14 of the Terms informed the parties that the adjudicator intended to obtain
quantity surveying assistance (and that communication of that paragraph to the parties was
compliance with the first of the adjudicator’s obligations under clause 2.3 of the NEC
Adjudicator’s Contract). Mr Richardson did not suggest that the adjudicator informed the
parties of the nature of the assistance; but he contended that the court should infer from the
absence of such a communication that the assistance provided was merely administrative or
clerical, and not the sort of assistance which called for disclosure and comment by the
parties. That, he submitted, would be an appropriate application of the presumption of
propriety.
[49] In my opinion neither of these submissions is compelling. Paragraph 14 did not
communicate an intention on the part of the adjudicator to employ quantity surveying
Page 24 ⇓
24
assistance. Rather, it purported to make provision for what would happen if it subsequently
transpired that the adjudicator considered that he needed quantity surveying input during
the adjudication. Moreover, in my view it would be going too far too fast to infer at this
stage that the assistance provided by the surveyor was of a type which did not require to be
disclosed.
[50] If the surveyor’s assistance here was indeed merely of a clerical, administrative and
checking nature I think it moot whether that would have engaged the obligations in
clause 2.3 of the NEC Adjudicator’s Contract. It is arguable that clause 2.3 concerns matters
which are likely to be material to the decision-making process (“help that he considers
necessary in reaching his decision”), such as quantity surveying opinion or advice upon
which an adjudicator proposes to rely. It is not hard to see that with material of that sort
fairness requires that it be disclosed to enable the parties to comment on it. However, I
incline to the view that even if the assistance provided by the surveyor was merely clerical
and administrative, natural justice required (i) that the adjudicator ought to have told the
parties that the surveyor had been engaged; and (ii) that while detailed disclosure for
comment would not have been necessary, the adjudicator ought to have indicated (at least in
brief, broad terms) just what it was that the surveyor was doing (Dickie & Moore Limited v
McLeish & Ors, supra, per Lord Doherty at para 33).
[51] Be that as it may, the critical question here is whether there has been a material breach
of natural justice. In my opinion I am not in a position, without inquiry, to conclude that
there has not been a material breach of natural justice. I am not persuaded that I can
determine on the pleadings that this defence is bound to fail even if the defender proves all
that it avers.
Page 25 ⇓
25
[52] Before passing from this ground I observe that it is highly regrettable that, after it
became aware of the fact that a surveyor had been engaged, the defender took six months to
raise the present complaint. It is wholly unsurprising that the adjudicator and the pursuer
have expressed frustration at that delay. I agree with them that the point ought to have been
raised much earlier. Ordinarily, by the stage of an enforcement hearing such as this I would
have expected a defender taking such a point to have investigated the matter by
precognoscing the adjudicator and the surveyor so that it was in a position to make specific
averments as to the nature of the services which the surveyor provided. While I have
concluded that it is in the interests of justice that there should be an inquiry here, I think it
right to stress that objections to an adjudicator’s decision ought to be raised expeditiously. I
also caution that defenders should not assume that the court would reach the same
conclusion as it has here in similar circumstances in the future if, despite these words of
warning, a defence is raised at a very late stage.
Disposal
[53] I shall put the case out by order (i) to discuss an appropriate interlocutor to give
effect to my decision; (ii) to discuss further procedure; and (iii) to consider any motion for
expenses which may be made.
BAILII:
Copyright Policy |
Disclaimers |
Privacy Policy |
Feedback |
Donate to BAILII
URL: http://www.bailii.org/scot/cases/ScotCS/2019/2019_CSOH_110.html