The Norfolk Vanguard Offshore Wind Farm (Amendment) Order 2023 No. 1390


BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?

No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!



BAILII [Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback]

United Kingdom Statutory Instruments


You are here: BAILII >> Databases >> United Kingdom Statutory Instruments >> The Norfolk Vanguard Offshore Wind Farm (Amendment) Order 2023 No. 1390
URL: http://www.bailii.org/uk/legis/num_reg/2023/uksi_20231390_en_1.html

[New search] [Help]


Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Statutory Instruments

2023 No. 1390

Infrastructure Planning

The Norfolk Vanguard Offshore Wind Farm (Amendment) Order 2023

Made

13th December 2023

Coming into force

14th December 2023

An application has been made, under paragraph 2 of Schedule 6 to the Planning Act 2008( 1), to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011( 2) (“ the 2011 Regulations”) for a non-material change to the Norfolk Vanguard Offshore Wind Farm Order 2022( 3).

The Secretary of State, having considered the application, the responses to the publicity and consultation required by regulations 6 and 7 of the 2011 Regulations ( 4), has decided to make the change on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.

Accordingly, the Secretary of State, in exercise of the powers in paragraph 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order:

Citation and commencement

1.  This Order may be cited as the Norfolk Vanguard Offshore Wind Farm (Amendment) Order 2023 and comes into force on 14th December 2023.

Amendment to The Norfolk Vanguard Offshore Wind Farm Order 2022

2.  The Norfolk Vanguard Offshore Wind Farm Order 2022 is amended in accordance with this Order.

Amendment to Part 3 (Requirements) of Schedule 1 (Authorised Project)

3.  In Part 3 (Requirements) of Schedule 1 (Authorised Project), in paragraph 16(18), for “must not exceed two” substitute “must not exceed four”.

Signed by authority of the Secretary of State for Energy, Security and Net Zero

John Wheadon

Head of Energy Infrastructure Planning Delivery

Department for Energy, Security and Net Zero

13th December 2023

EXPLANATORY NOTE

(This note is not part of the Order)

This Order amends the Norfolk Vanguard Offshore Wind Farm Order 2022, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008.

( 1)

2008 c. 29. Paragraph 2 was amended by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23), by paragraphs 1 and 72 of Schedule 13 to the Localism Act 2011 (c. 20), and by section 28 of the Infrastructure Act 2015 (c. 7). There are other amendments to the Act that are not relevant to this Order.

( 3)

S.I. 2022/138, as amended by S.I. 2022/944and S.I. 2022/1004.

( 4)

S.I. 2011/2055. Regulations 6 and 7 were both amended by S.I. 2012/635, S.I. 2015/760, S.I. 2020/1534and S.I. 2020/764.


BAILII: Copyright Policy | Disclaimers | Privacy Policy | Feedback | Donate to BAILII
URL: http://www.bailii.org/uk/legis/num_reg/2023/uksi_20231390_en_1.html