BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd [2006] EWHC 1341 (TCC) (05 June 2006) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2006/1341.html Cite as: [2006] EWHC 1341 (TCC) |
[New search] [Printable RTF version] [Help]
QUEENS BENCH DIVISION
TECHNOLOGY & CONSTRUCTION COURT
St Dunstan's House 133-137 Fetter Lane London EC4A 1HD |
||
B e f o r e :
____________________
MULTIPLEX CONSTRUCTIONS (UK) LIMITED | Claimant/Part 20 Defendant | |
-v- | ||
CLEVELAND BRIDGE UK LIMITED | ||
First Defendant/Part 20 Claimant | ||
CLEVELAND BRIDGE DORMAN LONG ENGINEERING LIMITED | ||
Second Defendants |
____________________
Smith Bernal, 190 Fleet Street, London EC4
Telephone 020-7421 4040
(Official Shorthand Writers to the Court)
HUGH TOMLINSON QC, SIMON HARGREAVES & THOMAS GRANT (instructed by Walker Morris) appeared on behalf of the First and Second Defendants.
____________________
Crown Copyright ©
Part 1. | Introduction. |
Part 2. | The facts. |
Part 3. | The present proceedings. |
Part 4. | Multiplex's evidence. |
Part 5. | CB's evidence. |
Part 6. | Issue 1. |
Part 7. | Issue 2. |
Part 8. | Issue 3. |
Part 9. | Issue 4. |
Part 10. | Issue 5. |
Part 11. | Issue 6. |
Part 12. | Issue 7. |
Part 13. | Issue 8. |
Part 14. | Issue 9. |
Part 15. | Issue 10. |
Part 16. | Conclusion. |
"The Sub-Contractor shall for the consideration payable in accordance with clause 21 carry out and complete the Sub-Contract Works and perform all its other Sub-Contract Obligations in compliance with the Sub-Contract Documents and the Contract [and for that purpose shall complete the design for the Sub-Contract works including the selection of materials, goods and workmanship to be used in the construction of the Sub-Contract Works] and in conformity with all reasonable directions and requirements of the Contractor (so far as they may apply) regulating for the time being the due carrying out of the works."
"The Sub-Contractor shall carry out and complete the subcontract works in accordance with the details in Appendix Part 4 and reasonably in accordance with the progress of the Works but subject to receipt of the notice to commence work onsite as stated in Appendix Part 4 and the operation of clauses 11 and 38A and/or 38C and any revision to the period or periods for the completion of the Sub-Contract Works in respect of a Variation for which a Variation Notice has been issued."
"The aggregate monetary liability of the Sub-Contractor under this sub-Contract for each right or remedy to the Contractor for any matters arising in connection with the performance of its obligations under the Sub-Contract shall not exceed £6 million (Six million pounds) and the Contractor releases the Sub-Contractor from any liability in excess thereof."
"The programme contained within volume 2 of the numbered documents listed as item p in Appendix Part 2 hereof is provided for information only, to indicate anticipated sequence of the subcontract works and interface with other subcontract packages. Dates and the sequence contained within the programme do not form part of the subcontract."(1) Date for commencement of the subcontract works onsite will be:
"between 7th July 2003.
"and 10th August 2003.
"(2) Period(s) for carrying out and completion of the subcontract works onsite:
"81 No. calendar weeks.
"(3) Period required for notice(s) to commence work onsite:
"2 No. calendar weeks.
"(4) Period required for subcontract works off site and prior to commencement onsite:
"44 No. calendar weeks."
"Whilst we cannot agree at this stage to all the contents of your letters and the quantum of your claim we do agree in principal [sic] that you are entitled to an extension of time and that we have instructed you to proceed with acceleration measures in order to mitigate the delay to both the arch and bowl structures.We will also work with you to agree a revised cash flow as discussed. In order to progress and agree your entitlement to an extension of time and the cost of the acceleration measures it is essential to receive the information as requested in our letter dated 11th April 2003, reference 000240 as soon as possible."
"It is our opinion, therefore, that the steelwork package subcontract is now without any effective contractual control. As a consequence we consider the subcontract, in terms of its time for completion and its valuation, to be at large."
"It was RESOLVED that legal advice be taken as to MPX's behaviour in administering the contract with a view to establishing whether MPX could be deemed to have repudiated the contract.Response to Cleveland Bridge's proposal was awaited. It was noted that Cleveland Bridge's options were as follows:
"1. Take/negotiate fair deal with MPX; failing that;"2. Subject to suitably strong legal advice, stop work on the basis that MPX have repudiated the contract and that the contract is at large."3. Negotiate an orderly withdrawal from the contract after a minimum of, say three months; or"4. Continue to work under the existing contract to a January 2006 finish."Shekhar Shetty outlined that Option 4 did not have the support of the principal shareholder, leaving only options 1-3 ...
"[Post Meeting Note: Sheikh Abdullah Al Rushaid confirmed that funding for only Option 2, essentially a four week period, would be available, and no funding should be directed specifically to Wembley. This decision was made on the basis that MPX could be shown to have repudiated the contract. Under these circumstances it was concluded that only options 1 and 2 remain and legal advice should be sought as a matter of urgency.]
"It was FURTHER RESOLVED that a business plan for option 2 be developed over the next 10 days to manage the business, and maximise asset valuation ...
"It was FURTHER RESOLVED that Roddy Grant plan how to handle the media, government and local MPs and staff for any actions contemplated.
"It was RESOLVED that such a plan be code named PROJECT TRAFALGAR."
"HEADS OF AGREEMENT
Preamble
(A) CBUK have claimed 1 year EOT for late delivery of design information. Multiplex dispute the extent of the claim, however late changes to the PPT design has delayed the project. Any delay is unacceptable to Multiplex.
(B) CBUK have offered to settle the EOT claim by altering the contract to cost reimbursable. This alteration of the risk profile is not acceptable to Multiplex.
(C) MPX and CBUK have agreed to settle the Claim as described below. This proposal allows for acceleration of fabrication, the ability for MPX to accelerate erection and reversion to a fixed price.
The deal
1. The current CBUK contractual responsibilities remain untouched except for outsourcing of certain future fabrication (including cost and delivery) and the cost of erection including certain bought out items and subcontracts.
2. Intent of the parties is that a Supplemental Agreement (formally adjusting contract), with an effective date of 15 February 04, incorporating the points below be concluded by end February.
3. Settlement of all claims and disputes to date. The only exception is a dispute as specifically contemplated by Clause 11.
4. Future Fabrication is to be outsourced by MPX as per schedules handed by B Rogan (BR) to A Muldoon (AM) on 11/02/04 with any changes to be agreed by them. CBUK value rates to be taken out of existing contract value with an extra/over costs incurred by MPX in outsourcing as per the existing contract to be the responsibility of MPX.
5. CBUK retain responsibility for remaining fabrication as per the contract, subject to Items 7 & 9.
6. CBUK retain responsibility for design and fabrication drawings, Bought Out Materials and Subcontracts according to schedule handed by BR to AM (11/02/04), with any changes to be agreed by them.
7. CBUK new fixed price in respect of items 1,5-6 above from 15 February is GBP12 million, based on design status as at 15/02/04 and subject to any changes agreed by BR/AM - following a detailed review of the schedule handed by BR to AM on 11-02-04.
8. MPX to re-imburse CBUK (weekly/monthly on a basis to be agreed) at cost for erection and site-works (site staff, direct labour, cranes and other site-related costs) for period of three months; i.e. ending 15/05/04. Plus £80,000 per month for off-site administration and overheads.
9. During these three months CBUK is to complete the works in accordance with the attached programme (named: projected CBUK programme) and complete the raising of the arch by 21st April 2004 (subject to EOT's). In addition MPX/CBUK will re-programme erection works beyond the 3 months, and determine a new fixed price and programme for completion (price to include 10% contribution to CBUK overheads and profit).
10. If at the end of these three months, no agreement to fixed price and/or programme, CBUK to agree orderly handover with no premium or additional cost to MPX. Four weeks notice will be given to CBUK. This notice can be given up to 2 weeks in advance of 15-05-04.
11. A valuation will be compiled up to 15-2-04, (After which the arrangements described in the foregoing will apply). Including £25k for overtime for week ending 15-02-04. This valuation will be checked by an independent QS. Payment will be made on the basis of this valuation, less paid to date. The valuation will include an appropriate deduction for site office rent. Should CBUK dispute any deductions made by MPX, in this valuation, then the value of the deduction, only, may be referred to Dispute Resolution.
12. MPX to make payments to CBUK of GBP 4 million on execution of this Heads of Agreement, an additional GBP 1.25 million on completing the lifting of the Arch and a further GBP 0,5 million if a fixed price arrangement, as detailed in Item 9, is entered into with CBUK.
13. Payment to CBUK of all costs (the sum of £75,000) is included in respect of the Provisional Sum, for painting, is included above.
14. CBUK warrant that they have paid (or will Pay) for all works done or materials purchased up to 16-2-04, including settlement of any outstanding disputes or claims.
15. If CBUK provide an acceptable unconditional BG, for the retention sum, then MPX will release the cash retention.
16. Both parties agree to ensure that the content of this agreement is strictly confidential. Disclosure has to be agreed with both parties.
Agreed on 18th February 2004."
"THIS AGREEMENT is made 16th day of June 2004BETWEEN:
(1) MULTIPLEX CONSTRUCTIONS (UK) LIMITED (Company Number 03808946) whose registered office is situated at Mayfair Place, 8th Floor, 50 Berkeley Street, London W1J 8BY ("the Contractor")(2) CLEVELAND BRIDGE UK LIMITED (Company Number 03749601) whose registered office is situated at Cleveland House, PO Box 27, Yarm Road, Darlington Co Durham DL1 4DE ("the Sub-Contractor")
(3) THE CLEVELAND GROUP OF COMPANIES LIMITED (Jersey Company Number 75906) whose registered office is situated at PO Box 478, St Helier, Channel Islands, JE2 5SL ("the Guarantor")
WHEREAS;
(A) By a sub-contract ("the Sub-Contract") dated 26 September 2002 made between (1) the Contractor and (2) the Sub-Contractor, the Contractor engaged the Sub-Contractor to carry out the fabrication and erection of structural steel in connection with the design and construction of Wembley National Stadium.(B) The original Sub-Contract Sum (stated in Article 2.1 of the Sub-Contract) was £60,000,000 and original the period for the carrying out and completion of the Sub-Contract Works (stated in Appendix - Part 4 to the Articles of Agreement) was 81 No. calendar weeks, which period commenced on 8 June 2003.(C) The Sub-Contractor has made certain claims under the Sub-Contract and certain disputes have arisen between the Contractor and the Sub-Contractor under and in connection with the Sub-Contract.(D) It has been agreed to resolve and settle all claims and disputes between the Contractor and the Sub-Contractor existing on or before 15 February 2004, and to make consequential amendments to the Sub-Contract on the terms set out in this Agreement.(E) By a deed of guarantee ("the Guarantee") dated 26 September 2002 made between (1) the Guarantor and (2) the Contractor, the Guarantor agreed to guarantee to the Contractor the performance by the Sub-Contractor of the Sub-Contract and the Guarantor hereby consents to the terms of this Agreement.(F) By a performance bond ("the Performance Bond") dated 27 November 2002, Gulf International Bank B.S.C. London ("the Surety") agreed, also, to guarantee to the Contractor the performance of the obligations of the Sub-Contractor under the Sub-Contract, with a maximum aggregate liability of the Surety under the Bond of £6,000,000 and the Surety has consented to the terms of this Agreement and has confirmed that the Performance Bond shall continue in full force and effect in relation to the Sub-Contract as varied by this Agreement.NOW IT IS HEREBY AGREED as follows:-
1. Unless the context otherwise requires, or this Agreement specifically otherwise provides, words and phrases used in this Agreement shall have the meanings (if any) give or ascribed to them by the Sub-Contract.2.1 Subject to Clause 2.2, the provisions of this Agreement are in full and final settlement of all disputes between the Contractor and the Sub-Contractor and all and any claims by the Sub-Contractor to the Contractor and by the Contractor to the Sub-Contractor existing on or before 15 February 2004 under or in connection with the Sub-Contract whether for extension of time, direct loss and/or expense, Variations, other adjustments to the Sub-Contract Sum, damages for breach of contract or otherwise or howsoever arising. Neither the Contractor nor the Sub-Contractor shall be entitled or permitted to make or pursue any claims against the other for any matter arising from any event or circumstance occurring up to and including 15 February 2004 (whether or not known to the Sub-Contractor).2.2 Clause 2.1 shall not apply to any claim that the Contractor might have for design workmanship or materials not being in accordance with the Sub-Contract.3.1 The Sub-Contract Works shall be varied post 15 February 2004 only by the omission of the fabrication and supply to the Site of the items specified in Schedule 3, Part A.3.2 Notwithstanding Clause 3.1, the Sub-Contractor shall retain responsibility under the Sub-Contract for all design and fabrication drawings. In addition, the Sub-Contractor shall retain responsibility under the Sub-Contract for bought out materials and sub-contracts remaining in its scope after execution of this Agreement.3.3 The Sub-Contract Works shall be completed in accordance with the revised programme contained in Schedule 4.4. Save as may be subsequently adjusted in accordance with the terms of the Sub-Contract (any such adjustment being subject to Clause 2.1 above), it is agreed that (taking account of all the matters referred to in Clauses 2.1, 3.1 and 3.2) the adjusted Sub-Contract Sum (exclusive of Value Added Tax) shall be as specified in Schedule 1.5. The Sub-Contractor hereby warrants to the Contractor that it has discharged or will discharge all payment obligations to its sub-contractors and suppliers in respect of work performed and materials supplied up to and including 15 February 2004.6.1 In consideration of the above, the Contractor has paid to the Sub-Contractor prior to the date of this Agreement the sum of 4,000,000 (exclusive of Value Added Tax).6.2 In addition, the Contractor shall pay to the Sub-Contractor the sum of £1,250,000 (exclusive of Value Added Tax) within 14 days following completion of the lifting of the steel arch (forming part of the Sub-Contract Works) to the position referred to in Schedule 1, paragraph (e).7. The parties shall use reasonable endeavours to agree to re-programme the completion of the Sub-Contract Works and to agree a fixed lump sum and/or reimbursable Sub-Contract Sum for the completion of Sub-Contract Works (to incorporate the reimbursable cost items referred to in Schedule 1, paragraph (c), an additional lump sum payment of £500,000 and a 10% contribution to overheads and profit), and to enter into a further supplemental agreement, recording the agreement contemplated by this Clause 7, on or before 29 June 2004 (or other such extended date as agreed in writing between the Contractor and the Sub-Contractor). The said additional lump sum payment of £500,000 will be paid on execution of the further supplemental agreement described in this Clause 7.8. In the event that the parties fail to reach such agreement in accordance with Clause 7 on or before 29 June 2004 (or other such extended date as agreed in writing between the Contractor and the Sub-Contractor), the Contractor shall be entitled to give 28 days written notice (or other such extended notice period as agreed in writing between the Contractor and the Sub-Contractor) to the Sub-Contractor further varying the Sub-Contract Works to remove from the Sub-Contract the unperformed reimbursable cost items referred to in Schedule 1, paragraph (c). It is noted in this regard that the Sub-Contractor issued HR1 notices in respect of its Site employees on 30 April 2004.9. In the event that the unperformed reimbursable cost items (referred to in Schedule 1, paragraph (c)) are removed from the Sub-Contract Works in accordance with Clause 8, it is agreed that:9.1 the parties will liaise during the 28 day notice period with a view to securing alternative employment for as many of the Sub-Contractor's Site employees as possible and ensuring an orderly handover of the works with due respect for consultation and notice requirements; and9.2 there shall be no adjustment to the Sub-Contract Sum or other payment to the Sub-Contractor arising for such Variation other than the additional payment referred to in Clause 9.3; and9.3 the Contractor and/or his sub-contractors and/or his or their agents may enter upon the Sub-Contract Works and use for a consideration of £500,000 all temporary buildings, plant, tools, equipment and temporary works necessary for the carrying out and completion of the unperformed reimbursable cost items provided that where the aforesaid temporary buildings, plant, tools, equipment and temporary works are not owned by the Sub-Contractor, the Sub-Contractor shall use all reasonable endeavours to ensure that the benefits of all hire agreements and the like in respect of such temporary buildings, plant, tools, equipment and temporary works are fully assigned to the Contractor for the completion of the unperformed reimbursable cost items. The aforesaid consideration will be paid within 14 days of the Sub-Contractor complying with this Clause 9 and leaving the Site; and9.4 the adjusted period for the carrying out and completion of the whole of the Sub-Contract Works shall be 26 weeks commenting on 15 February 2004, as described in Schedule 4.10. The Sub-Contract shall be amended in accordance with the provisions of Schedule 2 and, save as amended by this Agreement, the Sub-Contract shall continue in full force and effect.11. The Guarantor hereby consents to the terms of this Agreement and confirms that the Guarantee will continue in full force and effect in relation to the Sub-Contract as varied by this Agreement.12. The parties hereto shall treat the existence and contents of this Agreement as strictly private and confidential between the parties and the parties to this Agreement shall not disclose to any other person the existence or contents of this Agreement, except as may be required by law or in connection with pursuing claims against third parties.13. Any Dispute arising under or in connection with this Agreement shall be dealt with in accordance with Articles 3 and 4 of the Articles of Agreement as if it was a Dispute under or in connection with the primary Sub-Contract save that the Mediation Period contemplated by the primary Sub-Contract need not apply.IN WITNESS whereof this Deed has been executed by the parties hereto and is intended to be and is hereby delivered the year first before written.
SCHEDULE 1 (Sub-Contract Sum) The adjusted Sub-Contract Sum shall comprise:-
(a) the gross valuation as a [sic] 15 February 2004 of work properly completed on Site and goods and materials brought onto the Site by the Sub-Contractor and Off-Site Materials in accordance with the provisions of the Sub-Contract, subject to the deduction of Retention and other deductions permitted under the Sub-Contract; and(b) a fixed, lump sum of £12,000,000 for the completion of all remaining works, services and other obligations under the Sub-Contract (save for those reimbursable cost items referred to in paragraphs (c) and (f) below and those lump sum items referred to in paragraphs (d) and (e) below) subject to the deduction of Retention and other deductions permitted under the Sub-Contract; and(c) all costs reasonably and properly incurred by the Sub-Contractor from 15 February 2004, in connection with the erection and site works (being site staff, direct labour, cranes and other site related costs), plus a fixed amount for off-site administration and overheads at a rate of £80,000 per month from 15 February 2004, subject to the deduction of Retention and other deductions permitted under the Sub-Contract; and(d) a fixed, lump sum of £4,000,000 previously paid as consideration for this Agreement (as referred to in Clause 6.1 above) not subject to the deduction of Retention;(e) a fixed, lump sum of £1,250,000 following completion of the rotation of the steel arch to its parked, temporarily restrained position prior to load transfer (as referred to in Clause 6.2 above) not subject to the deduction of Retention; and(f) the costs reasonably incurred by the Sub-Contractor in purchasing steel (as directed by the Contractor) that are not included in the gross valuation as at 15 February 2004, subject to the deduction of Retention and other deductions permitted under the Sub-Contract. The Contractor has, prior to the execution of this Agreement, directed that all steel required for these Works is purchased by the Sub-Contractor, but the Contractor reserves the right to alter this direction for subsequent purchases.Payment of the adjusted Sub-Contract Sum shall be made, monthly, in accordance with the payment provisions of the Sub-Contract save as to the items referred to at paragraph (c) above which shall be paid by the Contractor to the Sub-Contractor at two week intervals. An Application for Payment in respect of the items referred to at paragraph (c) above may be made in accordance with clause 21.3 of the Sub-Contract at two week intervals and clause 21 of the Sub-Contract shall be construed accordingly with the necessary changes made.
If the Contractor proposes to issue a Certificate of Payment for an amount that is less than the amount claimed by the Sub-Contractor in an Application for Payment, Mr M Stagg (or if unavailable, Mr B Sheppard) of the Contractor shall first consult with Mr R Grant (or if unavailable, Mr J Child) of the Sub-Contractor before such Certificate of Payment is issued.
(All costs associated with the painting for which a provisional sum was included in the Sub-Contract are deemed to be included in the lump sum referred to at paragraph (b) above. For the avoidance of doubt all costs associated with the expenditure of the Provisional Sum for Fire Protection is not included in the lump sum referred to at paragraph (b) above. Such expenditure will be recovered by the Sub-Contractor monthly and in addition to the draw down on the lump sum at paragraph (b)).
SCHEDULE 2 (Consequential amendments to the Sub-Contract)
The Sub-Contract Conditions shall be amended as follows:-
Articles of Agreement
Appendix - Part 4:
Remove programme referred to and replace with programme contained in Schedule 4 to this Agreement.
Sub-Contract Conditions
Clause 1.3:
The definition of Sub-Contract, after "the Appendix", insert "the Supplemental Agreement"
Clause 2.2
Before "1. Articles of Agreement" insert "1A. Supplemental Agreement"
Insert new definition after "Sub-Contractor Training Vacancies List" as follows:-
"Supplemental Agreement: The agreement dated 16th June 2004 made between the Contractor, the Sub-Contractor and the Guarantor, supplemental to the Sub-Contract."Clause 39.5: Delete and replace with:-
"In the event that the Sub-Contractor elects the option to provide to the Contractor a Retention Bond in lieu of the Retention, the Sub-Contractor shall procure and deliver to the Contractor a Retention Bond for an amount equivalent to 5% of the Sub-Contract Sum, reducing to 2.5% of the Sub-Contract Sum at Practical Completion, in the form attached in Appendix - Part 23 to the Articles of Agreement, to be issued by a bondsman previously approved by the Contractor and following receipt of the Retention Bond duly executed by the bondsman, the Retention deducted by the Contractor from payments shall be paid to the Sub-Contractor."SCHEDULE 3 VARIED SUB-CONTRACT WORKS Part A (Agreed omissions to the Sub-Contract Works) The Contractor will carry out the following Sub-Contract Works:
(i) Attached A4 Schedule (2 pages) entitled "Schedule 3 MPX Fabrication responsibility including MPX sublet, China steel returned unmade and 667T CBUK sublets";(ii) Attached A4 Schedule entitled "Schedule 3 varied Sub-Contract Works Part A - Document 2..."SCHEDULE 3 VARIED SUBCONTRACT WORKS PART A - DOCUMENT 2 Project Buyouts
Holding Yard Wembley
Shunting
Roof Expansion Joints
Site Electrodes
Cat Walks
Temp Works - Roof Props
M&E Package for moving roof
Cleats 18Te
Tube Trusses 45te
Cruciform 10te
Fire Protection
3500m² paint
Project Subcontracts
Site touch up - labour
Site touch up - Plant
Site touch up - Materials
In-situ machining
Strand Jacking Equipment
Strand Jacking Supervision
Part B (Responsibilities retained by Sub-Contractor) The responsibilities retained by the Sub-Contractor shall be as those arising from the primary Sub-Contract save as amended by this Agreement.
SCHEDULE 4 (Replacement Programme) The programmes are:
(i) Attached A3 Programme WS05-V1 Acceleration (Sub-Let fabrication listing), Rev. 0, 11-Feb-04;(ii) Attached A4 Projected CBUK Programme (incorporating CBUK Design & Fabrication Dates as at 06/02/04) Rev CBDP..."
"1. In breach of clause 4 and Schedule 1(a) of the Supplemental Agreement you have sought to revalue the agreed gross valuation of 15th February 2004 and purported to make deductions from that revaluation."2. In breach of clause 7 of the Supplemental Agreement you have failed to use reasonable endeavours to agree a new programme and price for the completion of the Sub-Contract Works. As set out in correspondence between us, this is most clearly evident from the fact that you had already engaged other contractors to take over our erection and site works before 29th June 2004.
"3. Consistently and without proper reason under certifying and/or making arbitrary deductions from our interim applications.
"4. Failure to make payment of £1.25 million within 14 days of the completion of the lifting of the steel arch pursuant to clause 6.2 of the Supplemental Agreement.
"5. A persistent failure to properly consult before issuing a Certificate of Payment for an amount that is less than the amount claimed in our application for payment pursuant to schedule 1 of the Supplemental Agreement."
(i) The completion of lifting the arch occurred on 29th June 2004. Therefore, Multiplex's withholding notice served on 6th July was valid.
(ii) The gross valuation of CB's works as at 15th February 2004 for the purpose of paragraph (a) of schedule 1 to the Supplemental Agreement was £32.66 million.
(iii) CB's reimbursable costs for the period after 15th February should be reduced by 15 per cent because the loss of tags from steel members caused disruption on site.
(iv) The concrete subcontractor was the effective cause of delay to the lifting of the arch. This delay was not a breach of contract by CB.
(v) Multiplex was entitled to recover contracharges totalling £293,516 in respect of the defects found in arch members.
(i) CB was in breach of contract or negligent by designing, fabricating and constructing the arch with defective members.
(ii) CB was in breach of contract by failing to raise the arch by 21st April 2004 as specified in clause 9 of the Heads of Agreement.
(iii) CB was in breach of contract or negligent by fabricating and erecting defective steelwork for the bowl.
(iv) CB was in breach of contract or negligent by producing defective drawings for the steelwork which was fabricated by Hollandia.
(v) CB was in breach of contract by causing the Bridon cable connections for the arch to be twisted.
(vi) By reason of those breaches of contract or negligence Multiplex is entitled (as an alternative to damages) to an abatement of the price payable to CB for the works. The claim for abatement is not subject to the £6 million cap imposed by clause 12.2 of the subcontract.
(vii) The Supplemental Agreement had retrospective effect as from 15th February 2004. It superseded any terms of the Heads of Agreement which were inconsistent with the Supplemental Agreement.
(viii) CB failed ever to propose a price or programme for completing the steelwork as envisaged by the Heads of Agreement and the Supplemental Agreement. Multiplex lawfully removed onsite erection from the scope of CB's works pursuant to clause 8 of the Supplemental Agreement.
(ix) The revaluation of CB's works and the deductions made in certificates 37 and 38 were lawful and in accordance with the subcontract and the Supplemental Agreement.
(x) CB was in breach of the Supplemental Agreement in that it failed to complete the design, drafting, fabrication and transport of steel in accordance with the programme contained in schedule 4 to the Supplemental Agreement.
(xi) CB was in breach of contract or negligent in that it failed to erect bowl steelwork in accordance with the programme attached to the Heads of Agreement and/or at the average rate of 400 tonnes per week.
(xii) CB repudiated the subcontract by its letter dated 2nd August 2004 and by ceasing work on that date.
(xiii) Multiplex is entitled to recover from CB the sums which it has overpaid and also damages for breach of contract.
(i) CB's entitlement to reimbursement of costs under the Heads of Agreement was not subject to those costs being reasonably or properly incurred. CB was not required to execute the works with such diligence and expedition as was required to meet the programme attached to the Heads of Agreement.
(ii) The Supplemental Agreement did not have retrospective effect or supersede the Heads of Agreement.
(iii) The programme attached to the Heads of Agreement did not have contractual effect.
(iv) Although CB replaced 24 arch members at the instigation of Mott, it is denied that those or any other arch members were out of tolerance. CB was not in breach of contract or negligent in designing or erecting the arch members.
(v) The delay in raising the arch from 21st April to 22nd June was not a breach of contract, because the Supplemental Agreement superseded clause 9 of the Heads of Agreement. Furthermore, the effective cause of delay to the arch was PCH using the wrong grade of concrete for the bases. Accordingly, CB was entitled to an extension of time for the arch on that and other grounds.
(vi) Any claim for defects in the arch members was compromised by clause 2.1 of the Supplemental Agreement.
(vii) The defects which are alleged in the bowl steelwork are denied. The problem with Bridon cables was resolved. The alleged defects in drawings for steelwork are denied. Multiplex cannot circumvent the £6 million limit set out in clause 12.2 of the subcontract by presenting these matters as claims for abatement.
(viii) In June 2004 Multiplex, in breach of the Supplemental Agreement, made no proper attempt to agree with CB a price and programme for completing the steelwork. CB did attempt to reach such agreement.
(ix) Certificates 37 and 38 were gross under-valuations. CB was entitled to receive the sums claimed in its valuations preceding those certificates.
(x) The Supplemental Agreement did not impose upon CB the obligation to complete sections of work in accordance with the programme contained in schedule 4.
(xi) CB's average steelwork erection rate between 15th February and 30th June 2004 was 202 tonnes per week. This was a proper rate in the circumstances and did not put CB in breach of any contractual obligation.
(xii) In any event, CB's liability to Multiplex is limited to £6 million by clause 12.2 of the subcontract.
(xiii) The gross valuation of CB's works as at 15th February for the purposes of the Supplemental Agreement was agreed in the sum of £32.66 million. Multiplex is estopped from contending otherwise.
(xiv) Multiplex was in breach of contract by reneging on the valuation agreement, failing to pay the arch bonus, grossly under-valuing CB's works in certificates 37 and 38, failing to consult before issuing those certificates, and implementing the Armageddon plan.
(xv) Multiplex's breaches of contract amounted to repudiation, which CB accepted.
(xvi) CB is entitled to the arch bonus of £1.25 million, the various sums claimed in CB's July 2004 applications and substantial damages.
"ISSUE NUMBER 1: Supplemental Agreement1. Is the Supplemental Agreement effective with retrospective effect from 15 February? If so, did clause 3.3 and/or 9.4 of the Supplemental Agreement supersede clause 9 of the Heads of Agreement with retrospective effect from 15 February 2004?
ISSUE NUMBER 2: Heads of Agreement
2. Does the Heads of Agreement, on a proper construction in the circumstances in which the Heads of Agreement was made, or as a matter of common intention or as matter of law provide that CBUK was obliged to execute the Sub-Contract Works with such diligence and expedition as were reasonably required in order to meet the dates of the projected CBUK programme which was attached? (APC §11C(ii); ADCC §11C(ii)).
ISSUE NUMBER 3: Programme
3. On a proper construction in the circumstances in which the Heads of Agreement was made did clause 9 of the Heads of Agreement:
(a) Oblige CBUK to complete the Sub-Contract Works in accordance with the Projected CBUK Programme (APC §65A)?(b) Require CBUK to carry out the Sub-Contract Works in the sequence set out in sequence set out in the Projected CBUK Programme but not to complete any particular activity by a particular date? (ADCC §65A.1(b))(c) Require CBUK to complete Phases 11 to 18 of the bowl steelwork by 26 July 2004? (APC §65A; ADCC §65A.1(d))(d) Permit CBUK to apply for an extension of time within which it was required to complete Phases 11 to 18 of the bowl steelwork (by 26 July 2004) and to raise the Arch (by 21 April 2004)?(e) Place CBUK under an obligation to achieve an average on-site steelwork erection rate between 15 February and 26 July 2004 of 400 tonnes/week? (APC §65B; ADCC §65B).ISSUE NUMBER 4: Settlement of Variations
4. Was the effect of the Supplemental Agreement in relation to pre-15 February variations:
(a) That insofar as such variations were disputed, the costs of carrying out the varied elements of the works after 15 February 2004, whether off site or on site, were compromised by the terms of the Supplemental Agreement? or(b) (i) The costs of the varied elements of such works on the off site before the 15 February 2004 were compromised by inclusion within the agreed sum of £32.66 million(ii) The cost of the varied elements of such works off site (drawing, design and fabrication) carried out post 15 February 2004 was included in the agreed sum of £12 million.(iii) The cost of the varied elements of such works on site carried out post 15 February 2004 were paid on a costs reimbursable basis.ISSUE NUMBER 5: Effect of Clause 2 of the Supplemental Agreement
5. Do clauses 2.1 and 2.2 of the Supplemental Agreement, on a proper construction in the circumstances in which the Supplemental Agreement was made, prevent Multiplex from making claims for design, workmanship or materials not being in accordance with the Sub-Contract in relation to matters which were known to it at 15 February 2004? (ADCC §35.1; ARDCC §16)
ISSUE NUMBER 6: Valuation Agreement
6. (a) Did Mr Matthew Stagg orally agree that the final valuation of the work undertaken by CBUK to 15 February 2004 would be £32.66 million? (the "Valuation Agreement")? (ADCC §85.1(4)(d); ARDCC §34(4)), if so
(b) Is the Valuation Agreement binding on Multiplex? (ARDCC §36A(2))ISSUE NUMBER 7: Entire agreement
7. (a) Was the effect of clause 4 and Schedule 1(a) of the Supplemental Agreement and the Valuation Agreement that the valuation to 15 February 2004 of £32.66 million became part of the adjusted sum payable under the Amended Sub-Contract? (ADCC §87; ARDCC §36)
(b) Is the effect of clause 1.8.1 of the Amended Sub-Contract that the Amended Sub-Contract sets out the entire agreement between the parties so that CBUK is not entitled to rely on the Valuation Agreement? (ADCC §87B; ARDCC §36(c) and 36B), if so(c) Is Multiplex estopped and precluded from contending that the alleged Valuation Agreement did not become a term of the Supplemental Agreement and from relying on clause 1.8.1 of the Sub-Contract? (ADCC §87A; ARDCC §36A)ISSUE NUMBER 8: Repudiation
8. Which party was in repudiatory breach of contract, in particular:
(a) Was Multiplex in repudiatory breach by:(i) Refusing to make payments of CBUK based on the agreed valuation of £32.656 million?(ii) Refusing to make the payment of £1.25 million within 14 days of the rotation of the Arch to its parked temporarily restrained position?(iii) Refusing to pay sums applied for by CBUK in respect of costs reimbursable to 2 July 2004?(iv) Failing and refusing to cooperate with CBUK in seeking to agree a new programme and price for completion of the Sub-Contract Works?(v) Failing to consult CBUK before issuing certificates of payment for amounts less than the amounts claimed in the application for payment? (ADCC §§93; ARDCC §48).If not,(b) Was CBUK in repudiatory breach by giving notice on 2 August that it would no longer carry out any further work under Sub-Contract? (APC §§68; ADCC §68).ISSUE NUMBER 9: Damages claim
9. Is CBUK's claim for damages for the loss of the sums which it would have made on the negotiation of the reprogramming of the completion of the Sub-Contract Works sustainable in law? (ADCC §97(3))
ISSUE NUMBER 10: Abatement
10. (a) Are the claims in Schedule 1A to 1E and item 16 of Schedule 3 claims for an abatement?
(b) If so, what is the proper measure of the abatement?"
The trial of the preliminary issues commenced on Tuesday, 25th April and lasted for a month. The senior management teams of both parties gave evidence about the history of events during 2003 and 2004. At the end of the hearing I said that I would consider the evidence and submissions over the vacation week and give judgment on Monday 5th June. This I now do.
ASHLEY MULDOON
• CB continue with erection and with the existing fabrication (i.e. that not outsourced pursuant to the Heads of Agreement).
• CB cease erection work, but continue with the existing fabrication.
• CB leave the job altogether.
• Revaluing CB's works as at 15th February to what Multiplex regarded as the proper figure;
• Withholding payment of the arch bonus by reason of CB's breaches of contract, if legal advice supported this course;
• Making a 50% deduction from payments for the costs reimbursable period, to reflect inefficiency and lack of productivity.
MATTHEW STAGG
• Give notice to CB removing on-site erection from their sub-contract after the arch had been lifted. Transfer on-site erection to Hollandia.
• Withhold payment of the arch bonus on the basis of a cross-claim.
• On 16th July issue a certificate reducing the 15th February valuation of CB's works to what Multiplex regarded as the proper figure.
• Reduce payments for the cost-plus period by about 50% on the grounds of CB's inefficiency.
• Bring in Hollandia to take over all the steelwork, in the event that CB withdrew altogether.
• Launch immediate adjudications in order to establish that Multiplex's various valuations and cross claims were valid.
DAVID WATKINS
2003
2004
RANALD McGREGOR
• CB's letter dated 5th December 2003, claiming a 50.5 week extension of time (this would delay the stadium by one year);
• CB's letter dated 23rd January 2004, threatening to delay raising the arch until November 2004.
"X Steel model must get it""GET X STEEL MODEL as it is today for entire roof. Absolutely critical! We need it so Hollandia can start preparing for future works and planning fab. MUST GET IT BY TOMORROW"
KEES VAN ROOIJEN
STUART CURSLEY
• Some of the variation work valued on 4th February was carried out after 15th February.
• A large part of the £2.8 million assessed on 4th February was in the nature of loss and expense and therefore compromised by clause 3 of the Heads of Agreement.
• The additional steel (which was part of the variations) should be picked up in the measured work or in the valuation of materials off site.
• A comparison between the predicted steelwork costs at 15th February and at 29th April;
• How substantial reductions might be made in the currently predicted costs if CB were removed from site and their works were revalued.
"The intent is that I meet with them tomorrow to execute. I will need the schedules, price, programme and a 15/2/04 valuation at £32.6 m (i.e. WT high valuation including items missed)."
• £1,833,732 needed to be added for materials off site, because the value of CB's bond had been increased.
• £354,726 needed to be added for steel which was off site. WT had correctly deducted this sum from the valuation of works on site, but had inadvertently failed to add it back as off site materials.
CHRISTOPHER ONG
"After negotiation with CBUK agreement was reached for a valuation of the works up to 15/2/2004 and this valuation included all materials and was a Final Account for all issues to the date of 15/2/2004."
MULTIPLEX WITNESSES WHO DID NOT GIVE ORAL EVIDENCE
STEPHEN BARON
ANDREW HALL
• Interface with concrete;
• Only 9 tower cranes instead of 10;
• Continuing design changes (although Mr Hall accepts that some of the 862 design changes referred to in his witness statement were completely irrelevant to the steelwork);
• Lack of sufficient lay down areas and poor site conditions.
MARK ALLISON
BRIAN ROGAN
"The strategy AN, Alan Carson and myself came up with in September last year … has worked. We have ended up on virtually all cost plus with no risk."
"It was noted that Multiplex is undertaking an IPO in Australia. As part of the Australian Stock Exchange requirements, all claims will be disclosed. It was RESOLVED that claims be maximised and submitted to assist in the company's commercial position."
RICHARD THOMAS
JAMES CHILD
"FEB 15 VALUATION
"Essential to have the figure referenced in S.A. as agreed, as well as the actual valuation document."
RODERICK GRANT
• carry on as before (which was not acceptable);
• walk off site and take a £6 million hit (this was a reference to the cap in clause 12.2 of the subcontract);
• work together to sort out a new plan.
"Schedule 1. we will give valuation cert, at execution. the subcontract, in total (i.e. as amended by variations and this SA)."
MR DONALD UNDERWOOD
• Strengthening works to the top of the core.
• Work relating to out of tolerance embedments.
• Welding work to arch bases.
• Fitting gutters and brackets to rakers.
• Ongoing variation and retrofit work.
"It appears to me that the result is that this case is an illustration of a broad principle of law which is perfectly well known and is constantly acted upon, namely, that where a preliminary contract of any description, whether verbal or written, is intended to be superseded by, and is in fact superseded by, one of a superior character, then the later contract -- the superior contract -- prevails, and the stipulations in the earlier one can no longer be relied upon. That proposition is laid down with great distinctness in the case of Leggott v Barrett, which really points to this, that as regards a preliminary contract which is naturally covered by the subsequent contract, the terms of the subsequent contract are to prevail."
1. Bowl phases 11 to 18 drafting.
5. Bowl phases 21 to 28 drafting.
7. Bowl phases 31 to 38 design.
9. Bowl phases 31 to 38 drafting.
19. PPT design.
20. PPT drafting.
300. North roof design.
312. South roof design.
322. East-west roof design.
(i) The subcontract itself does not contain any express term that CB shall execute the works with diligence and expedition. Instead, there are a series of express terms whereby Multiplex can regulate the progress of CB's works: see, for example, appendix part 4 and section 3 of the special conditions.
(ii) Clause 9 of the Heads of Agreement expressly provided that CB's activities, which were currently due for completion after 15th May, would be reprogrammed. I find it impossible to imply a term that CB would adhere to a programme which everybody knew was going to be changed.
(iii) The dates set out in the restraint schedule incorporated into the original subcontract were not binding. CB had no obligation to endeavour to achieve those dates. In those circumstances, it would be contrary to the scheme of the subcontract for the Heads of Agreement to require CB to direct its endeavours to a new set of programme dates extending 16 months into the future.
(iv) The parties specifically turned their minds to CB's obligation as to progress. They specified a date of 21st April 2004 for lifting the arch. They specified the precise extent of CB's obligations in relation to programme. If they had intended to supplement CB's duty to achieve the ten fixed dates specified with some further and more general obligation of diligence and expedition, they would have said so.
(v) Clause 9 of the Heads of Agreement makes perfectly good sense as it stands. The proposed implied term is not necessary to give business efficacy to the contract. It is certainly not obvious that this was or should have been intended by either party.
(vi) The reasoning in GLC v Cleveland Bridge and Engineering Company Limited [1986] 34 BLR 50, upon which Mr Stewart relies, is inapplicable to the circumstances of the present case. Furthermore, the general principles enunciated in Hudson's Building and Engineering Contracts (11th edition) at paragraphs 9-032 to 9-033, do not impact upon the Heads of Agreement, which was negotiated at a time of crisis for a specific purpose and for a limited period.
(a) Yes, but only in respect of activities 1, 5, 7, 9, 19, 20, 300, 312 and 322.
(b) No.
(c) No.
(d) No in respect of the bowl steelwork, but yes in respect of the arch.
(e) No.
(i) Clause 2.1 states that the provisions of the Supplemental Agreement are in full and final settlement of all disputes and claims existing on or before 15th February "whether for extension of time, direct loss and/or expense, variations, other adjustments to the subcontract sum, damages for breach of contract or otherwise". This is an all-encompassing list of the financial disputes between the parties. I find it impossible to read into this list some such phrase as "except the measured value of variations".
(ii) The sums totalling £5.25 million payable by Multiplex to CB under section 6 of the Supplemental Agreement are "in consideration of the above". That must be a reference to the preceding provisions, in particular clause 2.1.
(iii) Clause 4 of the Supplemental Agreement says that the adjusted contract sum shall be as specified in schedule 1. Clause 4 also includes the phrase "taking account of all the matters referred to in clauses 2.1, 3.1 and 3.2". In my view, this indicates that the computation exercises required by schedule 1 shall be performed without including those matters which have been settled by clause 2.1 or omitted from CB's scope of work by clause 3.1. Any alternative reading of clause 4 would lead to an absurd result.
(iv) CB's interpretation leads to the anomaly that the measured value of pre-15th February variations is included in paragraph (a) of schedule 1, excluded from paragraph (b) and included in paragraph (c). Such a reading of schedule 1 is bizarre. Furthermore, it would mean that CB could at whim increase its remuneration by shifting work from paragraph (b) to paragraph (c). This could be achieved by transferring fabrication work from Darlington to Wembley.
(v) Multiplex's interpretation of schedule 1, paragraph (c) fits with the language of that provision, once one takes into account the concession made by Mr Stewart in his closing speech at Day 16, page 141. On this interpretation, CB will recover all costs reasonably and properly incurred in connection with erection after 15th February. It can be seen from the structure of the Supplemental Agreement as a whole that onsite erection is the principal focus of schedule 1, paragraph (c).
(vi) On this interpretation of the Supplemental Agreement, CB recovers some £2.37 million in respect of variations which were not disputed as at 15th February, plus £5.25 million in respect of loss and expense, acceleration measures and disputed variations. These two figures total approximately £7.62 million. Having regard to the claims and issues which were being debated during the interregnum, I see nothing surprising or untoward in this figure. Neither party can say that those figures are so high or so low that this outcome cannot possibly have been intended.
"Subject to clause 2.2, the provisions of this agreement are in full and final settlement of all disputes between the contractor and the subcontractor and all and any claims by the subcontractor to the contractor and by the contractor to the subcontractor existing on or before 15th February 2004 under or in connection with the subcontract whether for extension of time, direct loss and/or expense, variations, other adjustments to the subcontract sum, damages for breach of contract or otherwise or howsoever arising. Neither the contractor nor the subcontractor shall be entitled or permitted to make or pursue any claims against the other for any matter arising from any event or circumstance occurring up to and including 15th February 2004 (whether or not known to the subcontractor)."
"Clause 2.1 shall not apply to any claim that the contractor might have for design workmanship or materials not being in accordance with the subcontract."
"A valuation will be compiled up to 15-2-04 (after which the arrangements described in the foregoing will apply) including £25K for overtime for week ending 15-2-04. This valuation will be checked by an independent [quantity surveyor]. Payment will be made on the basis of this valuation, less paid to date. The valuation will include an appropriate deduction for site office rent. Should CBUK dispute any deductions made by MPX in this valuation, then the value of the deductions, only, may be referred to dispute resolution."
"FEB 15 VALUATION.
- Essential to have the figure referenced in SA as agreed, as well as the actual valuation document."
(i) On this crucial issue, I find Mr Stagg to be an honest and reliable witness. If Mr Stagg had agreed £32.66 million as a final valuation for the purposes of schedule 1, paragraph (a), he could hardly (given the subsequent history of events) have forgotten that fact. I am quite satisfied that Mr Stagg was not deliberately lying in the witness box about this matter.
(ii) The figure of £32.66 million was not included in schedule 1, paragraph (a) of the Supplemental Agreement. Mr Grant pressed for the inclusion of this figure both at the meeting on 14th May and subsequently, but always without success. If the figure of £32.66 million had been agreed as the valuation for the purposes of schedule 1, paragraph (a), I believe that the figure would have been set out in that paragraph. It does not make sense for two major construction companies entering into a formal agreement, which was of grave importance to both companies, deliberately to omit a crucial term upon which they were agreed.
(iii) During the preceding one and a half years relations between CB and Multiplex were acrimonious to say the least. One of the many causes of acrimony was that Multiplex sometimes threatened to deduct from valuations or actually deducted from valuations monies previously certified as payable. CB did not trust Multiplex. If the directors of CB had negotiated the oral agreement which is alleged, they would have insisted that it be recorded in the supplemental agreement. Multiplex would have had no grounds to resist this. I do not accept that Mr Stagg had or put forward any internal or political reasons for not formally recording whatever was agreed between the parties.
(iv) The references in the evidence of Mr Rogan, Mr Child and Mr Grant to a "finally agreed number" are, in my view, reconstruction. I do not suggest that those witnesses are dishonest. In my view, their recollection of the crucial meeting has been coloured by what they were hoping to achieve.
(v) The notes made by participants during the meeting do not support the contention that £32.66 million was agreed as a final and binding valuation up to 15th February.
(vi) The letters and e-mails passing between the parties after 14th May are not, in my view, consistent with a final and binding valuation having been agreed on that date. On the contrary, CB was still pressing for this. Indeed, in his letter dated 17th May Mr Grant was pressing for a slightly higher figure.
(vii) The progress reports sent by CB to Multiplex for May and June 2004 do not refer to the valuation agreement. In my view, if such an important matter had been agreed it would have been recorded in the summary section of those reports. Mr Rogan was unable to explain this omission. The explanation given by Mr Thomas is unsatisfactory.
(viii) Whether the contact between the parties on 20th May was by telephone or at a meeting may not be important. What is striking, however, is that Mr Stagg, Mr Grant and Mr Child all recall Mr Stagg saying that Multiplex may want to claw the money back in a disaster or catastrophe situation. In previous discussions with CB, Mr Stagg had referred to the removal of CB from site as a disaster or Armageddon situation: see the evidence of Mr Stagg, Mr Child and Mr Grant.
"The subcontract comprises the conditions together with any special conditions annexed hereto (collectively referred to as the 'subcontract conditions'), the Appendix, the Supplemental Agreement and the Articles of Agreement..."
"If any conflict appears between the conditions and/or the appendix and/or the numbered documents and/or the special conditions the foregoing shall take precedence in the following order:-"1A. Supplemental Agreement."1. The Articles of Agreement."2. The Appendix."3. The Conditions."4. The Special Conditions."5. The Numbered Documents."
"The Sub-Contract constitutes the entire agreement between the parties and supersedes all prior negotiations, commitments, representations, communications and agreements relating to the Sub-Contract either oral or in writing except to the extent they are expressly incorporated herein. The Sub-Contractor confirms that it has not relied upon any representation inducing it to enter into the Sub-Contract (whether or not such representation has been incorporated as a term of the Sub-Contract) and agrees to waive any right which it might otherwise have to bring any action in respect of such representation. The Sub-Contractor further confirms that there is not in existence at the date of the Sub-Contract any collateral contract or warranty of which the subcontractor is the beneficiary which might impose upon the Contractor obligations which are in addition to or vary the obligations expressly contained in the subcontract and which relate in any way to the subject matter of the Sub-Contract. The Sub-Contractor's only rights arising out of, or in connection with, any act, matter or thing said, written or done, or omitted to be said, written or done, by or on behalf of the contractor (or any agent, employee or subcontractor of the Contractor) in negotiations leading up to the Sub-Contract or in the performance or purported performance of the Sub-Contract or otherwise in relation to the Sub-Contract are the rights to enforce the express obligations of the Contractor contained in the Sub-Contract and to bring an action for breach thereof. Nothing in this clause 1.8 is intended to exclude liability of the contractor for fraud or fraudulent misrepresentation."
"Unless the context otherwise requires, or this agreement specifically otherwise provides, words and phrases used in this agreement shall have the meanings (if any) given or ascribed to them by the subcontract."
"The subcontract is to be read as a whole and the effect or operation of any recital, article or clause in the subcontract must therefore unless otherwise specifically stated be read subject to any relevant qualification or modification in any other recital, article or clause in the subcontract."
(i) This issue does not arise on the facts.
(ii) Even if the alleged oral valuation agreement had been made, nevertheless the answers to questions (a), (b) and (c) are: no.
BREACH (i)
BREACH (ii)
BREACH (iii)
BREACH (iv)
BREACH (v)
"If the contractor proposes to issue a certificate of payment for an amount that is less than the amount claimed by the subcontractor in an application for payment, Mr M Stagg (or if unavailable Mr B Sheppard) of the contractor shall first consult with Mr R Grant (or if unavailable Mr J Child) of the subcontractor before such certificate of payment is issued."
"The parties shall use reasonable endeavours to agree to re-programme the completion of the subcontract works and to agree a fixed lump sum and/or reimbursable subcontract sum for the completion of subcontract works (to incorporate the reimbursable cost items referred to in schedule 1, paragraph (c), an additional lump sum payment of £500,000 and a 10 per cent contribution to overheads and profit), and to enter into a further supplemental agreement, recording the agreement contemplated by this clause 7, on or before 29th June 2004 (or other such extended date as agreed in writing between the contractor and the subcontractor). The said additional lump sum payment of £500,000 will be paid on execution of the further Supplemental Agreement described in this clause 7."
"An undertaking to use one's best endeavours to obtain planning permission or an export licence is sufficiently certain and is capable of being enforced: an undertaking to use one's best endeavours to agree, however, is no different from an undertaking to agree, to try to agree, or to negotiate with a view to reaching agreement; all are equally uncertain and incapable of giving rise to an enforceable legal obligation."
"The measure of that deduction is the sum which it would take to alter the work so as to make it correspond with the specification."
"It must however be considered, that in all these cases of goods sold and delivered with a warranty, and work and labour, as well as the case of goods agreed to be supplied according to a contract, the rule which has been found so convenient is established; and that it is competent for the defendant, in all of those, not to set off, by a proceeding in the nature of a cross action, the amount of damages which he has sustained by breach of the contract, but simply to defend himself by showing how much less the subject matter of the action was worth, by reason of the breach of contract; and to the extent that he obtains, or is capable of obtaining, an abatement of price on that account, he must be considered as having received satisfaction for the breach of contract, and is precluded from recovering in another action to that extent; but no more.
"The opinion, therefore, attributed on this record to the learned judge is, we think, incorrect, and not warranted by law; and all the plaintiff could by law be allowed in diminution of damages, on the former trial, was a deduction from the agreed price, according to the difference, at the time of delivery, between the ship as she was, and what she ought to have been according to the contract: but all claim for damages beyond that, on account of the subsequent necessity for more extensive repairs, could not have been allowed in the former action, and may now be recovered."
"Another inconvenience which would result from holding that the inferiority of the thing done to that contracted for must, if an action be commenced, be used by way of defence, is, that instead of furthering the object for which this defence was permitted, namely, the prevention of circuity of action, it would in many cases tend to complicate and increase litigation. The cases are, perhaps, rare in which the consequences of defective performance of work are limited to the depreciation of the value of the work done; they usually involve consequential damage by reason of the necessity of repairing the defective work; and for this the case of Mondel v Steel decides a separate action must be brought."
"A claim that the work had not been completed was not a matter of set-off; it was a pure defence to a claim for payment for work done. Similarly, though this point is more controversial, an assertion that work had not been properly executed was capable of being a matter of pure defence rather than of counterclaim or set-off."
"Subject to this, however, I see no reason why it should not be open to Dancon in the present case to complain that the work for which the claim for interim payment was demanded has not been properly executed, by way of defence in accordance with the principles recognised by Lord Diplock in Modern Engineering v Gilbert-Ash [1974] AC 689 at page 717. For the terms of the blue form contract themselves entitle Acsim to make a demand for interim payment only 'in respect of the total value of the subcontract works properly executed'."
(i) In a contract for the provision of labour and materials, where performance has been defective, the employer is entitled at common law to maintain a defence of abatement.
(ii) The measure of abatement is the amount by which the product of the contractor's endeavours has been diminished in value as a result of that defective performance.
(iii) The method of assessing diminution in value will depend upon the facts and circumstances of each case.
(iv) In some cases, diminution in value may be determined by comparing the current market value of that which has been constructed with the market value which it ought to have had. In other cases, diminution in value may be determined by reference to the cost of remedial works. In the latter situation, however, the cost of remedial works does not become the measure of abatement. It is merely a factor which may be used either in isolation or in conjunction with other factors for determining diminution in value.
(v) The measure of abatement can never exceed the sum which would otherwise be due to the contractor as payment.
(vi) Abatement is not available as a defence to a claim for payment in respect of professional services.
(vii) Claims for delay, disruption or damage caused to anything other than that which the contractor has constructed cannot feature in a defence of abatement.
(i) The partially completed steelwork of a national stadium which is under construction does not have a market value in the conventional sense. That steelwork only has a value to the main contractor who is under an obligation to produce a completed stadium.
(ii) From the point of view of the main contractor (who is the only interested party) the difference in value between the steelwork in its actual condition and the steelwork as it ought to be is the cost of remedial works.